CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.1/10
Act [ Section- 40 ]
Session: M1-7
Advertisement
Rules [Rule-90]
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.2/10
IFPQ IFE REOI IFTAny other
PROCUREMENT OPPORTUNITIES
Advertisement
Rule- 90PE directly advertises for all Invitations
Follow FORMATS in Schedule X
CONDITION: Procurements included in the APP
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.3/10
ONE ENGLISH LANGUAGE
ONE BANGLA LANGUAGE
Choosing News Paper
Rule- 90(2)
Avoid controversy in choice
Choosing National Level Newspapers of wide daily circulation commonly known and ubiquitously accepted; carefully applying sound judgment
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.4/10Choosing News Paper
Follow-up publication
May advertise in maximum 2 local or regional newspapers for a maximum of 2 days;
when estimated cost is less than Tk. 5 lakh and PEs are outside Dhaka, in addition to national daily
reduce the size of the advertisement when cost is a factor and higher the number of newspapers
ensure publication in each copy of every edition of the day if more than ONE edition on that particular day
Rule- 90(2)
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.5/10Posting in Website
all invitations be posted in the PE’s websites, if any
subsequent changes or amendments relating to invitations be re-advertised preferably in the same newspapers and websites
all kinds of procurement documents be ready for issuance on the date of publication
Keep track on corresponding events
Rule- 90(2)
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.6/10
Certain procurement opportunities
be sent to CPTU for posting in their website
CPTUwebsite
GOODS10 M
ABOVE
SERVICES5 M
ABOVE
WORKS10 M
ABOVE
Posting in Website
Default may lead to rejection of Tenders
Rule- 90(2) Particularly
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.7/10
INTERNATIONAL
PROCUREMENT OPPORTUNITIES
ENGLISH NEWSPAPER or PUBLICATION OF WIDE
INTERNATIONAL CIRCULATION;
or UN DEVELOPMENT
GATEWAY MARKET (dgMarket);
and if necessary FOREIGN TRADE
MISSIONS IN BD or BD TRADE MISSIONS ABROAD
Advertisement
Visit: www.dgmarket.com, www.devbusiness.com
Rule- 90(2)
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.8/10
International Procurement
One Option
www.dgmarket.com
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.9/10
International Procurement
Another Option
www.devbusiness.com
CPTU-IMED (PPRP II) Three-Week Training on Procurement of Goods, Works & Services Fineurop
Session: M1-7Slide N0.10/10Advertisement
See Schedule II
PE FOLLOWS TIME-FRAME IN PUBLISHING ADVERTISEMENTS AS
SPECIFIED IN SCHEDULE II
DISCUSSED IN MORE DETAILS UNDER DIFFERENT PROCUREMENT METHODS
Rule- 90(2)