Session 42_2 Peter Fries-Hansen
-
Upload
transportforum-vti -
Category
Documents
-
view
228 -
download
2
Transcript of Session 42_2 Peter Fries-Hansen
Peter Friis-Hansen 12 January 2010
Introduction to risk analysis and risk acceptance setting
Transportforum, 2010, Jan. 13-14, Linköbing, Sweden
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
2
Risk analysis: a tool for decision making
Analysis of accidents Risk analysis
Others practise
Look backward Look forward
Look aside
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
3
Steps in a risk analysis
What might go wrong?
How likely is it and what are the consequences?
How can matters be improved?
How much will it cost and how much better will it be?
What actions are worthwhile to take?ActPlan
Improve Measure
$
Consequence
Probability
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
4
Phases in the risk analysis Phase 0
- Setting the purpose of the risk analysis and the boundaries of the analysis- Setting the acceptable level of risk ... or rather: defining what is unacceptable
Phase 1- Identification of what may go wrong – dangers, unwanted events- Coarse risk analysis for screening identified unwanted events
Phase 2- Detailed risk analysis
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
5
Risk-based design – questions
What is risk ? … the (annual) expected loss
How does the risk analysis enter the decision process of the owner ?
How large a risk does the operator impose on society by his activities ?
How large benefit does society gain form the activity … and how large should the benefit be to cover the loss of society ?
How safe is safe enough … or … how much are we willing to invest in safety ?
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Coarse Risk Analysis
Usage
More detailed hazard identification(from HAZOP or FMEA)
Classification of hazardous situations for identification and making priorities for risk-reducing actions
Basis for definition of detailed areas for analysis
Methodology
“Guesstimate” of frequency
Identification of barriers
Coarse estimates of consequences of hazards
Classification in risk matrix
Consequence
Probability
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
7
Frequency matrix: 10class
Frequency class Label More than X incidents per year
2 Daily -Monthly 101 Monthly-year 10 1-10 y 0,1-1 10-100 y 0,01-2 100-1000 y 0,001-3 1000-10.000 y 0,0001-4 10.000-100.000 y 0,00001-5 > 100.000 y 0,000001
Freq
uenc
y de
crea
ses b
y de
cade
s
5.010 Fcf
possible rare
unlikely
likely
remote
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
8
Consequence matrix: in €Label None Minor Significant Serious Critical Catastrophic
Consequence class Abbreviation 2 3 4 5 6 7
Crew PDBruises and minor injuries that do not
require hospitalization
Minor injuries that causes 1 week of
absence
Serious injuries that causes a month or
more in hospitalization
Several injuries that require hospitalization
/ invalidity at one or more.
1 - 2 fatalities More than 3 fatalities
ND Discomfort / malaiseBruises and minor injuries that do not
require hospitalization
Minor injuries that causes 1 week of
absence
Serious injuries that causes a month or
more in hospitalization
Several injuries that require
hospitalization / invalidity at one or
more.
1 - 2 fatalities
NF 500 person hours 5000 person hours 50000 person hours 1/2 mill person hours 5 mill person hours
50 mill person hours
Material MK
Negligible damages that may be
immediately repaired by the crew
Damages it takes days to repair
Damages it takes several weeks to repair and which
influences the functioning of the
system
Damages it takes several months to repair with several
follow-up consequences
Significant material damages
Significant parts of the plant destroyed
Environmental EMNegligible
environmental damages
Minor environmental damages
Significant environmental
damages
Serious environmental
damages
Critical environmental
damages
Catastrophic environmental
damages
Monetary value 100 1.000 10.000 100.000 1.000.000 10.000.000
Acceptability per year Negligible Tolerable Unwanted Unacceptable Unacceptable Unacceptable
Passengers
Com
para
ble
5.010 ClL
Consequences increases by decades
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
9
Scenario analysis Initiating failure unwanted consequences
Setting up a scenario
Identification of type of unwanted consequences
Identification of the chain of events
Identification of preventive controls (barriers)
Initiating event
Hazardouscondition
Unwanted consequences
Hazardouscondition
Barrier Barrier Barrier BarrierBarrierFc Cl
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
10
Risk: the annual monetary expected loss
ClFcClFcLfR 101010 5.05.0
i
ClFc PR Barrier10
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
11
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Consequence
Probability
What should we choose ?
What is best ?
Risk matrix and RCO’s
CFRNRank
6RN is too high andmust be reduced
11 CRN Alt 1:
A1
A2A322 CRN Alt 2:
33 CRN Alt 3:
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
13
Mitigation efficiency
Expense per unit reduction in risk
Used to rank different alternatives
May be used to identify limit for investments
lossin Reduction Expense
RiskCostefficiency Mitigation
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Prioritizing alternatives
1
1
RC
Alt 1 Alt 2 Alt 3
1
The RISK-rank RN is converted to €: R=10RN1 – 10RN2
Remember: a coarse analysis gives a coarse order of prioritiesConsequence
Probability
6A1A1
A2A2A3A3
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Use Results From Coarse Analysis to... To identify the most critical events in the
business
To evaluate the safety of production system
To evaluate the buildings / layout of the plant as regard to possible accidents
To set focus on possible accident scenarios for temporary activities
To calculate the risk levels of employees and 3. Parts
To establish a fundament for emergency plans and teams
To establish a fundament for plant inspection actions
To provide documentation - NOT JUST TO satisfy authorities
Note: No system effects taken into account.An event identified as being acceptable may become unacceptable due to system effects.
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
16
Integrating risk into the decision process and risk acceptance setting
Time
$
g
AccidentsFrequency : Consequence:
ciExpected loss = T
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
17
Design with respect to optimal monetary gain
T
tTN
n
Tn dtetGeXc gnl
0
)(
0
)(),(
Initial costs
Loss
Income
)1()1(),(][ T
g
T
l
gl egecLE
Expected loss
Owner will minimise his loss
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
18
Design with respect to optimal monetary gain
ci(,)
T
design
loss
Best design
Owners optimisation
)1()1(),(][ T
g
T
l
gl egecLE
)1(),();1(),( T
l
T
l
ll ecec
Optimality condition
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
19
Optimality at the limit
No solution for l = 0 if T is infinite
Optimal solution depends on T
Decision model with finite T and zero interest rate is equivalent to a decision model with infinite T and l = 1/T
Tl ;0
0;),(;),(
lTcTc
Tcc
ll
;),(;),(
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
20
Interest rate on human life value
”It is unethical to use an interest rate on human life value”
T=1 year for the acceptance related to casualties
T= entire reference period related to other values
For T=1 year the equivalent interest rate is l = 1/T. Interest capitalization factor becomes e 1 ~ 2.27
A reasonable interest capitalization factor is e 0.05 ~ 1.05. The equivalent decision theoretic time horizon without capitalization is therefore 1/l = 20 years lower adverse event frequency
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
21
Risk acceptance
Owners net gain: 0 og
The societal gain should at least cover the public loss
po rg
How large a risk should society be willing to accept ?
Society gain: rg o )(
is related to the wealth of the society, i.e. GDPp
Corporate social responsibility is to cover ALL the losses the activity imposes on society
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
22
A rational acceptance criteria
111
o
po
rg
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
23
Safeguarding life, property and the environment
www.dnv.com
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
24
HAZARDIDENTIFICATION
Identify all "risk agents" and the conditions under which they may produce adverse impacts.
Describe and quantify the risk by evaluation of all scenarios that lead to the adverse events.
RISKASSESSMENT
Compare the risk to acceptable standards and judge the significance of risk mitigation.
RISKEVALUATION
RISK ANALYSIS
Identify solutions for managing risk during the lifetime. Evaluate cost and compare alternatives.
OPTIONEVALUATION
RISK CONTROL
Select one or more of the solution alternatives for implementation.
OPTIONSELECTION
Implementing, monitoring, and enforcing solution alternatives.
IMPLEMENTATION& ENFORCEMENT
SAFETY PHILOSOPHY
The safety philosophy should define goals for the future, the fundament for priorities, and standards.
SAFETY GOALS
Reflects the willingness of people and society to accept risk. Normally the cost of fulfilling the criteria is not considered.
ACCEPTANCECRITERIA
Risk information (of accident scenarios, demands to emergency teams, operation, and modifications).
General information(technical, political, economical, performed risk studies, etc.).
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Frequency Classes
Definition of frequency classes
Frequency class
Description Frequent
(F4)
Moderate
(F3)
Rare
(F2)
Very rare
(F1)
Extremely rare
(F0)
Frequency More than 1 incident per year
May happen with 1 to 10 years of interval
May happen with 10 to 100 years of interval
May happen with 100 to 1000 years of interval
Happens more rarely than once each 1000 year
Frequency decreases by decades
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Consequence Categories
Consequence type
None / negligible
(0)
Small
(1)
Significant
(2)
Serious
(3)
Very serious
(4) Personnel risk (P)
None / small injuries < 1 week of absence
Minor injuries causing 1 week to 1 month of absence
Serious injuries causing 1 month of absence
Possibility of death
Possibility of several death
Risk for 3. Party (N)
Malaise (discomfort)
None / small injuries
Minor injuries Serious injuries Possibility of death
Environmental risk (E)
No / negligible environmental damages
Minor environmental damages
Significant environmental damages
Serious and long restoration time
Very serious / very long restoration time
Materiel damage (M)
None / negligible damage to equipment
Minor damage to equipment
Significant damages to equipment / spreading to other equipment
Large damage to equipment / spreading to other fire cell / building
Major parts of the plant is destroyed
Consequences increases by decades
Com
para
ble
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
Frequency/consequence Matrix
Matrix for•Personnel•3. party•Environment•Materiel
None /negligible
consequences(0)
Minorconsequences
(1)
Significantconsequences
(2)
Seriousconsequences
(3)
Very seriousconsequences
(4)Frequent
(4)ALARP
Moderate(3)
ALARP
Rare(2)
ALARP
Very rare(1)
ALARP
Extremely rare(0)
ALARP
Not acceptable
Acceptable
Consequence
Probability
© Det Norske Veritas AS. All rights reserved.
Introduction to risk analysis and risk acceptance setting
12 January 2010
28
RISK Risk is the expected loss
Log10(Risk) = Frequency class + Consequence class
Cost-benefit analysis becomes straight forward