SESI LAB PEREKAYASAANPROJEK PEMODENAN LESEN
PERNIAGAAN PERINGKATNEGERI SARAWAK 2012
“Focus Group Business Process Re-engineering” (FGBPR)
PEREKAYASAANLEMBAGA PELABUHAN KUCHING :
APPLICATION FOR SUFFERANCE WHARF PERMIT
Project Title: To shorten the Sufferance Wharf Application Process
Business Case Opportunity StatementTo assist State Government to collectmore revenue through charging cargoesdischarged and loaded at private wharfwithin the port limit of the Port of Kuchingby simplifying and shortening the processflow.
Application much faster and convenient and approval will bedone in the shortest possible time.
Standardised form for the 6 months application permit.(Short term)
To review the tariff for the local cargoes. (Long term).
Goal statement Project scope• To better improve the process flow of
Sufferance Wharf’s daily application.• To shorten the period of approving the
application for “Sufferance Wharf’sPermit of 6 Months” from 5 workingdays to 2 working days.
Process: shorten the sufferance wharf application timeStart: Office openEnd: Office close
Project Plan New Team Line-upPhase Start End Leader : Matthew EdenDefine 21.09.2012 23.09.2012 Assistant Leader : Norman LigongMeasure 29.11.2012 30.11.2012 Secretary : Chin Soong ChoonAnalyze 19.12.2012 21.12.2012 Member : Chai Chin LinImprove Member : Chong Khai LingControl
Kuching Port Authority Team Charter
PEMETAAN PROSES ‘AS IS NOW’APPLICATION FOR SUFFERANCE WHARF PERMIT (DAILY)
- CHARGEABLE CARGO
Shipping Agent(Port User)
PenolongPegawai Tadbir(Costing Section)
Pembantu Tadbir(Costing Section)
Start (SubmitApplication)
CHECKING ONCOMPLETENESS OF
DOCUMENTCOMPLETE?
CLARIFYVESSEL
REGISTRATION
VERIFYCREDIT
SUFFICIENCY
CREATE &RECORD
Ship Call Numberon Application
Form
APPROVAL
YES
NO
Sufficient
1 minute : MP
3 minutes : MPNotSufficient
1 minute : MP
Registered Vessel
6 minutes : MP5 minutes : MP
1 minute : MP
LEGEND:MP = MASA MEMPROCESSMM = MASA MENUNGGU
NO
Top UpAccount
SupplyCompleteDocument
VesselRegistration
with CDP
CollectApprovedDocument
Total = MM + MPTotal = 0 + 17 = 17Total = 17 minutes / 1 day
# ActivityCustomer Value
Added(CVA)
Customer NonValue Added Masa
Proses (MP)
MasaMenunggu
(MM)
MasaDiambil
(MD)BVA NVA
A Start (Submit Application) /
B CHECKING ON COMPLETENESS OFDOCUMENT / 1 1
C COMPLETE? / 1 1D VESSEL REGISTERED? / 1 1E SUFFICIENT BALANCE? / 6 6F CREATE AND RECORD Ship Call Number
on Application Form / 5 5G APPROVAL / 3 3
2 5 0 17 0 17
Value Analysis of Process (DAILY - AS-IS NOW)
Rule of Thumb: CVA and BVA – Simplify, Combine and OptimizeNVA – Eliminate Interval – Eliminate or optimize
PEMETAAN PROSES ‘TO BE’APPLICATION FOR SUFFERANCE WHARF PERMIT (DAILY-IMPROVED PROCESS)
- CHARGEABLE CARGO
Shipping Agent(Port User)
PenolongPegawai Tadbir(Costing Section)
Pembantu Tadbir(Costing Section)
LEGEND:MP = MASA MEMPROCESSMM = MASA MENUNGGU
Start(Submit
Application)
CHECKING ONCOMPLETENESS OF
DOCUMENT &CREDIT LIMIT
BALANCE
COMPLETE /SUFFICIENTBALANCE ?
CREATE &RECORD
Ship Call Numberon Application
Form
APPROVAL
YES
NO
4 minutes : MP
3 minutes : MP
5 minutes : MP
1 minute: MP
VESSELREGISTER
ED?
2 minutes : MP
NO
YES
SUPPLY COMPLETEDOCUMENT / TOP-
UP ACCOUNT
COLLECTAPPROVEDDOCUMENT
Total = MM + MPTotal = 0 + 15 = 15Total = 15 minutes / 1 day
VESSELREGISTRATION
WITH CDPCall for verificationon account balance
# ActivityCustomer Value
Added(CVA)
Customer NonValue Added Masa
Proses (MP)
MasaMenunggu
(MM)
MasaDiambil
(MD)BVA NVA
A Start (Submit Application)/
B VESSEL REGISTERED?/ 2 2
C CHECKING ON COMPLETENESS OF DOCUMENT &CREDIT LIMIT BALANCE / 4 4
D COMPLETE / SUFFICIENT BALANCE?/ 1 1
E CREATE & RECORD Ship Ccall Number on ApplicationForm / 5 5
F APPROVAL/ 3 3
2 4 0 15 0 15
Value Analysis of Process (DAILY-TO BE PROCESS)
Rule of Thumb: CVA and BVA – Simplify, Combine and OptimizeNVA – Eliminate Interval – Eliminate or optimize
PEMETAAN PROSES ‘AS IS NOW’APPLICATION FOR SUFFERANCE WHARF PERMIT (6 MONTHS) –
NON CHARGEABLE CARGO
Shipping Agent(Port User)
PenolongPegawai Tadbir(Registry Section)-Finance
General Manager
Assistant GeneralManager(Finance)
Chief SecurityOfficer
Sufferance WharfEnforcement(Security)
LEGEND:MP = MASA MEMPROCESS MM = MASA MENUNGGU
Start(Submit
Application)Letter)
CHECKING ONCOMPLETENESS OF
DOCUMENTCOMPLETE?
INSTRUCTION TOVERIFY
4 minutes : MP
420 minutes : MM
2 minutes : MP
INSTRUCTION TOPROCESS
420 minutes : MM
5 minutes : MP
VERIFICATION TOCHECK
5 minutes : MP
CHECK VESSEL PAST 6MONTHS
MOVEMENTS
PREPARE ‘Applicationfor Use of A Sufferance
Wharf’ FORM (pervessel)-Article 4
SIGN FORAPPROVAL
INFORMAGENT
NO
YES
5 minutes : MP
120 minutes : MM
10 minutes : MP
120 minutes : MM
1 minute: MP
Total = MM + MPTotal = 1160 + 154 = 1314Total = 22 hours / 3 workingdays
20 minutes : MM20 minutes : MM
1 minute : MP
10 minutes : MM
INFORMAGENT
PROVIDEINFORMATION
YES
NO
COLLECTAPPORVEDDOCUMENT
1 minute: MP
SUPPLYCOMPLETE
DOCUMENTS
118 minutes : MP
SUBMITRECOMMENDATION
APPROVE ?
30 minutes : MM
# ActivityCustomer Value
Added(CVA)
Customer NonValue Added Masa
Proses (MP)
MasaMenunggu
(MM)
MasaDiambil
(MD)BVA NVA
A Start (Submit Application)/
B CHECKING ON COMPLETENESS OFDOCUMENT / 4 4
C COMPLETE? / 1 10 11
D INSTRUCTION TO PROCESS / 5 420 425
E INSTRUCTION TO VERIFY / 2 420 422
F VERIFICATION TO CHECK / 5 20 25
G CHECK VESSEL PAST 6 MONTHSMOVEMENTS / 118 20 138
H PROVIDE INFORMATION /
I SUBMIT COMMENTS / 5 30 35
J APPROVE ? / 1 120 121
K PREPARE THE 6 MONTHS APPLICATIONFORM / 10 120 130
L SIGN FOR APPROVAL / 1 1
M INFORM AGENT / 2 2
3 9 1 154 1160 1314
Value Analysis of Process (6 Months- AS IS NOW)
Rule of Thumb: CVA and BVA – Simplify, Combine and OptimizeNVA – Eliminate Interval – Eliminate or optimize
PEMETAAN PROSES ‘TO BE’APPLICATION FOR SUFFERANCE WHARF PERMIT (6 MONTHS)
- NON CHARGEABLE CARGO
Shipping Agent(Port User)
PenolongPegawai Tadbir(Registry Section)- Finance
Assistant GeneralManager(Finance)
Chief SecurityOfficer
Sufferance WharfEnforcement(Security) /Costing Section
LEGEND:MP = MASA MEMPROCESS MM = MASA MENUNGGU
Start(Submit
ApplicationForm)
CHECKING ONCOMPLETENESS OF
DOCUMENTCOMPLETE ?
4 minutes : MP
30 minutes : MM
VERIFICATION TOCHECK
5 minutes : MP
CHECK VESSEL PAST 6MONTHS
MOVEMENTS
PREPARE ‘Applicationfor Use of A Sufferance
Wharf’ FORM (pervessel)-Article 4
SIGN FORAPPROVAL
INFORMAGENT
NO
YES
5 minutes : MP
120 minutes : MM
10 minutes : MP120 minutes : MM
1 minute: MP
Total = MM + MPTotal = 360 + 269 = 629Total = 11 hours / 2 days
30 minutes : MM
20 minutes : MM
1 minute : MP
INFORMAGENT
PROVIDE SECURITY &COSTING
INFORMATION
YESNO
COLLECTAPPORVEDDOCUMENT
1 minute: MP
SUPPLYCOMPLETE
DOCUMENTS
240 minutes : MP
SUBMIT COMMENTS
APPROVE ?
30 minutes : MM
2 minutes : MP 2 minutes : MP
5 minutes : MP
5 minutes : MM
# ActivityCustomer Value
Added(CVA)
Customer NonValue Added Masa
Proses (MP)
MasaMenunggu
(MM)
MasaDiambil
(MD)BVA NVA
A Start (Submit Application)/
B CHECKING ON COMPLETENESS OFDOCUMENT / 4 4
C COMPLETE? / 1 30 31
D VERIFICATION TO CHECK / 5 30 35
E CHECK VESSEL PAST 6 MONTHSMOVEMENTS / 240 20 260
F PROVIDE SECURITY AND COSTINGINFORMATION / 5 5 10
G SUBMIT COMMENTS / 5 30 35
H APPROVE ? / 1 120 121
I PREPARE THE 6 MONTHS APPLICATIONFORM / 10 120 130
J SIGN FOR APPROVAL / 1 1
K INFORM AGENT / 2 2
3 7 1 274 355 629
Value Analysis of Process (6 Months TO BE PROCESS)
Rule of Thumb: CVA and BVA – Simplify, Combine and OptimizeNVA – Eliminate Interval – Eliminate or optimize
No. Perkara Sebelum Selepas
1. Kecekapan Kerja 100 % 100 %
2. Jumlah aktiviti 7 6
3. Masa keseluruhan proses 17 minutes 15 minutes
Perbandingan Sebelum dan Selepas ProjekAPPLICATION FOR SUFFERANCE WHARF (DAILY)
* Kecekapan Kerja = Jumlah Masa Memproses / Jumlah Masa Diambil x 100%
No. Perkara Sebelum Selepas
1. Kecekapan Kerja 11.7% 43.6%
2. Jumlah aktiviti 13 11
3. Masa keseluruhan proses 22 Hours 11 Hours
Perbandingan Sebelum dan Selepas ProjekAPPLICATION FOR SUFFERANCE WHARF (6 MONTHS)
* Kecekapan Kerja = Jumlah Masa Memproses / Jumlah Masa Diambil x 100%
DAILY SUFFERANCE WHARF PERMIT APPLICATIONItem / Perkara Sebelum Projek Selepas Projek Catatan / Isu
1. Asas Undang-undang (nyatakanakta/peraturan)
“The Port AuthoritiesOrdinance, 1961 on KuchingPort Authority (Places forDischarge and Loading ofCargo) Order, 2002”.
SAMA
2. Piagam Pelanggan(Masa Kelulusan) 17 minutes 15 minutes
Kelulusan diperolehi selepassemua dokumen lengkap, creditbalance mencukupi, vesseldidaftarkan dan Ship Call Numberdikeluarkanserta diluluskan olehPegawai Kewangan (Costing)
3. Caj/bayaran• Borang• Proses• Kelulusan
Borang Percuma.Proses Percuma.Kelulusan-RM2 per tonne or
part thereof
SAMA
4. Nama Borang• Komposit• Contoh
SCHEDULE (Article 4)APPLICATION FOR USEOF A SUFFERANCEWHARF
SAMA
Ringkasan Penemuan dan Cadangan Penambahbaikan
DAILY SUFFERANCE WHARF PERMIT APPLICATIONItem / Perkara Sebelum Projek Selepas Projek Catatan / Isu
5. Tempoh sahlaku 1 VESSEL TRIP 1 VESSEL TRIP
6. Pembaharuan 1 VESSEL TRIP 1 VESSEL TRIP
7. Agensi yangdirujuk NIL NIL
8. KeperluanDokumen sokongan
VESSEL MANIFEST orCARGO SHIPPINGDOCUMENT
VESSEL MANIFEST orCARGO SHIPPINGDOCUMENT
9. KaedahPermohonan MANUAL MANUAL
Ringkasan Penemuan dan Cadangan Penambahbaikan
6 MONTHS SUFFERANCE WHARF PERMIT APPLICATIONItem / Perkara Sebelum Projek Selepas Projek Catatan / Isu
1. Asas Undang-undang (nyatakanakta/peraturan)
“The Port AuthoritiesOrdinance, 1961 on KuchingPort Authority (Places forDischarge and Loading ofCargo) Order, 2002”.
SAMA
2. Piagam Pelanggan(Masa Kelulusan) 5 WORKING DAYS 2 WORKING
DAYS
Kelulusan diperolehi selepas semuadokumen lengkap, credit balancemencukupi, vessel didaftarkan danShip Call Number dikeluarkan sertadiluluskan oleh Assistant GeneralManager (Finance)(Follow-up in the KFA Project)
3. Caj/bayaran• Borang• Proses• Kelulusan
Borang Percuma.Proses Percuma.Kelulusan-NON CHARGEABLE
SAMA
4. Nama Borang• Komposit• Contoh
SCHEDULE (Article 4)APPLICATION FOR USEOF A SUFFERANCEWHARF
SAMA
Ringkasan Penemuan dan Cadangan Penambahbaikan
6 MONTHS SUFFERANCE WHARF PERMIT APPLICATIONItem / Perkara Sebelum Projek Selepas Projek Catatan / Isu
5. Tempoh sahlaku 6 months /regardless on thevessel movement
6 months /regardless on thevessel movement
6. Pembaharuan
After 6 months withattachment of the vesselmovement record period of 6months.
After 6 months withattachment of the vesselmovement record period of 6months.
7. Agensi yangdirujuk NIL NIL
8. KeperluanDokumen sokongan
Company official letter,Cargo Tonnage and VesselMovement Record for Last6 Months, Vessel License,Company License,Company Owner I.C. All. 1set.
Standard Application Form,Cargo Tonnage and VesselMovement Record for Last6 Months, Vessel License,Company License,Company Owner I.C. All. 1set.
9. KaedahPermohonan MANUAL MANUAL
Ringkasan Penemuan dan Cadangan Penambahbaikan