SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work...

17
PARK EAST CONSTRUCTION Prepared by Shawez Idrees SEPTEMBER 2020 Construction Report

Transcript of SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work...

Page 1: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

PARK EAST CONSTRUCTION Prepared by Shawez Idrees

SEPTEMBER 2020 Construction Report

Page 2: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Table of Contents

Section I - Work Progress through the month of September

Greenacres Elementary School (Addition and Alterations)

Heathcote, Quaker Ridge, & MS (Capital Improvements Project)

Edgewood (HVAC and Interior Alterations)

Fox Meadow (HVAC and Interior Alterations)

High School (Phase 7 Capital Improvements)

Section II – Planned work for the month of October

Section III – Progress Photos

Section IV – Summary of Daily Reports

September 2020

Scarsdale Union Free School District

2

Page 3: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Report – Section I

Greenacres Elementary School

Work Progress – Greenacres Elementary School Addition (Phase – 1)

Exterior sitework - Complete

Work Progress – Greenacres Elementary School Existing Bldg. (Phase – 2)

Installation of new casework - Complete

Installation of new ceiling grid and finishes - Complete

Installation of new light fixtures - Complete

Installation of new flooring finishes - Complete

Installation of new ceramic wall / floor tiles - Complete

Installation of new plumbing fixtures - Complete

Startup of new boilers - Complete

September 2020 3

Page 4: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Report – Section I

HC, QR, MS – Capitol Improvements Project

Work Progress – Quaker Ridge Elementary School

Punchlist

Work Progress – Quaker Ridge Elementary School

Punchlist

Work Progress – Quaker Ridge Elementary School

Punchlist

September 2020 4

Page 5: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Report – Section I

Edgewood & Fox Meadow – HVAC & Interior Alterations Project

Work Progress – Edgewood Elementary School

Startup of new boilers - Complete

Electrical service upgrades - 95% Complete

Installation / connection of new ERV units - Complete

Work Progress – Fox Meadow Elementary School

Installation of new ductwork within attic - Complete

Startup of new boilers - Complete

Electrical service upgrades - 95% Complete

Installation / connection of new ERV units - Complete

September 2020 5

Page 6: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Report – Section I

High School – Phase 7 Capital Improvements at HS Project

Work Progress – Scarsdale High School

GC Work Scope

Rebuilding portion of existing stone wall - Complete

Masonry repairs / repointing - Complete

Foundation drainage / waterproofing - Complete

Backfilling and site restoration - Complete

Asphalt paving - Complete

Roof Work Scope

Roofing replacement - Complete

Detail / metal capping work - 90% Complete

Dean Field Work Scope

Removal of existing trees - Complete

Striping of existing field / soil - Complete

Installation of field drainage - 90% Complete

Grading and spreading of fill / topsoil - 80% Complete

September 2020 6

Page 7: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Planned Work – Section II

District Wide

September 2020

Planned Work for October

Greenacres Elementary School Addition (Phase – I & II)

Address punch list items

Heathcote, Quaker Ridge, Middle School

Address punch list items

Edgewood Elementary School

Complete electrical upgrades

Begin creating punch list

Fox Meadow Elementary School

Complete electrical upgrades

Begin creating punch list

Scarsdale High School

GC Work Scope

Continue fabrication of existing stair handrails

Roof Work Scope

Complete all detail metal capping work

Dean Field Work Scope

Continue grading and prepping field for new natural turf.

7

Page 8: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Greenacres Elementary School

September 2020

Corner of Sage / Huntington Sage Terrace Elevation

8

Page 9: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Greenacres Elementary School

September 2020

Learning Commons 146 Typical New Addition Classroom

9

Page 10: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Greenacres Elementary School

September 2020

Interior of staircase 163 Library

10

Page 11: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Scarsdale High School

September 2020

Roof Replacement

11

Page 12: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Scarsdale High School

September 2020

Dean Field Renovation

12

Page 13: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Scarsdale High School

September 2020

Walkway Replacement / Waterproofing

13

Page 14: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Progress Pictures – Section III

Scarsdale High School

September 2020

Masonry Repairs Floor Joist / Flooring Tile

Replacement

14

Page 15: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Summary of Daily Reports – Section IV

Greenacres Elementary School – Additions & Alterations

September 2020 15

Page 16: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

Scarsdale Union Free School District

Summary of Daily Reports – Section IV

Edgewood & Fox Meadow – HVAC & Interior Alterations

September 2020 16

Page 17: SEPTEMBER 2020 Construction Report...Installation / connection of new ERV units - Complete Work Progress –Fox Meadow Elementary School Installation of new ductwork within attic -

September 2020

Scarsdale Union Free School District

Summary of Daily Reports – Section IV

Phase 7 Capital Improvements at High School

17