September 10, 2001 1
Task Lead Due Dates
COS FSW Build 3.1 (Preparation for MEB Functional)
HW needs: fully functional Mechanism Simulator
1. Complete unit level testing– Linda K, Robert, Gavin, Allison
2. Complete build & EEPROM install – Justin, Robert
3. Update HW/SW I/F Document – Chris
This build completes code & unit test for the following 4 CSCs:,
- CS DCE, CS DIB, CS MCE, DIB CSCI
Chris Dorato
1. Sept 14
2. Sept 21
3. Sept 21
COS FSW Build 3.2
HW needs: nothing new
FSW support to MEB testing takes no more than 1 week
Complete code development:
1. Mechanisms part2 – Robert, Linda
2. Diagnostics – Linda
3. Start Target Acquisition - Robert
4. Complete code walkthrough
5. Complete unit level testing
6. Complete build & EEPROM install – Justin, Linda
This build completes code & unit test for the following 2 CSCs:
- Mechanisms & Lamps , Diagnostics
Chris Dorato
1. Oct 12
2. Oct 26
3. TBD
4. Nov 9
5. Dec 31
6. Jan 4, 2002
HST Software & Operations Task/Action Status
![Page 2: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/2.jpg)
September 10, 2001 2
Task Lead Due Dates
COS FSW Build 4
HW needs: nothing new
1. Complete code development
2. Complete code walkthrough
3. Complete unit level testing
4. Complete build & EEPROM install
5. Linkfile updates & general cleanup
This build completes code & unit test for the last CSC: Target Acquisition
Chris Dorato
1. Feb 15, 2002
2. Mar 1, 2002
3. Apr 3, 2002
4. Apr 5, 2002
5. Apr 30, 2002
HST Software & Operations Task/Action Status
![Page 3: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/3.jpg)
September 10, 2001 3
Task Lead Due Dates
COS FSW Component Testing – Build 3.1
1. Complete Memory Load & Copy – Steve
2. Complete CS DIB – Hugh
3. Complete NED – Adam
4. Complete Memory/Image Dump – Steve
5. Complete CS DCE – Adam, Gary
Denise Miller
1. Aug 22
2. Nov 30
3. Oct 5
4. TBD
5. Oct 15
COS FSW Component Testing – Build 3.2
1. Start Diagnostics – Denise
2. Complete Mechanism & Lamps – Tina
3. Complete CS MCE – Denise
4. Complete DIB CSCI – Hugh
Denise Miller
1. Aug 22
2. Aug 21
3. Nov 30
4. Oct 5
COS FSW Component Testing – Build 4
1. Complete Buffer Memory Management – Steve
2. Start Diagnostics – Denise
3. Start Target Acquisition – Hugh
4. Start System Init & Service Functions – Steve
Denise Miller
1. Aug 22
2. Aug 21
3. Nov 30
4. Oct 5
HST Software & Operations Task/Action Status
![Page 4: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/4.jpg)
September 10, 2001 4
Component Test Plan & Peer Review
Test Procedure & Peer Review
I&T w/FSW & Dry Run
Run for Record
Memory Load & Copy (SP)
CS DIB
(HM)
NED
(AT)
Memory/Image Dump
(SP)
CS DCE
(AT, GW)
Diagnostics
(DM)
Mechanisms & Lamps (TF)
CS MCE
(DM)
DIB CSCI
(HM)
Target Acquisition
(HM)
System Init & Service Functions (SP)
HST Software & Operations Task/Action Status
FSW Bld 3.1
FSW Bld 3.2
FSW Bld 4
![Page 5: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/5.jpg)
September 10, 2001 5
HST Software & Operations Task/Action Status
Sept Oct Nov Dec Jan Feb Mar Apr May Jun July Aug Sept
Mech & Lamp (Tina)
Mech & Lamp (Tina)
COS WFC3
2001 2002
![Page 6: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/6.jpg)
September 10, 2001 6
Task Lead Due Dates
COS Non-Flight Software
1. Get the FUV detector simulator working – Dina, Allison
- verify simulator responses for Door commands + 3 others
- review all needed Ops changes w/Linda R
2. Mechanism test software ready for Aperture testing – Jeff
3. CM control for non-flight software – Justin
Chris Dorato
1. August 29
2. November 1
3. August 31
COS MEB Functional Test
1. Mech Sim test and certify – Mike M
2. CEDER Training - Stephane
3. Test Set Equip. (Cables, LVPS loads, etc.) – Chuck Yanoski
4. FUV Detector Simulator ready – Dina, Allison
5. Test procedure development – Sue, Tina
6. Ops product development & database certification – Linda R
7. Flight Electronics Ready ************ - Virg
8. Flight database build complete – Chris B
9. Flight software build complete – Justin, Robert
10. Dry run test on SW/Ops Test Bench – Sue, Linda, Ken, Soraya
11. Test readiness review – Sue
12. Standalone backup – Adam
13. Rebuild flight software & database if necessary
14. Load Build 3.1x onto flight hardware – Justin, Robert, Soraya
Sue Ross
1. Aug 28
2. Aug 24
3. Aug 29
4. Aug 29
5. Aug 29
6. Sept 7
7. Aug 24
8. Sept 20
9. Sept 21
10. Oct 5
11. Oct 5
12. Oct 8
13. Oct 10
14. Oct 10
HST Software & Operations Task/Action Status
![Page 7: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/7.jpg)
September 10, 2001 7
HST Software & Operations Task/Action StatusTask Lead Due Dates
COS FUV ETU HW/SW Integration Test
1. Receive ETU from Berkeley – Ken
2. FSW Bld 3.02 (CS DIB) load & checkout on bench – Chris D.
3. Generate test plan – Ken
4. Complete Test #2 with new DCE & CS DCE code
5. Update both benches with DCE code - Justin
6. Send image data to STScI – Ken
Ken Brownsberger 1. Aug 15
2. Aug 13
3. Aug 17
4. Aug 24
5. Sept 3
6. Sept 3
COS OSM2 I/F Test
AI: GB – resolve schedule/resource conflict
AI: TF – contact cleanroom people for flow bench certification
AI: TF – coordinate w/Chuck Y. on cable needs
HW needs: Ops test bench w/ new mech sim, Flow bench, OSM2, cable, scope (in cal) w/prob
1. OSM2 available for test (binding problem)
2. Complete test procedure and conduct peer review – Tina, Jeff
3. FSW Build 3.1 image ready – Chris D.
4. Dry run procedure
5. Run test bench certification procedure – Tina, Jeff
6. Test Readiness Review – Tina, Jeff
7. Perform test – Tina, Jeff
Tina Fredo
1. Sept 20
2. Sept 7
3. Sept 21
4. Sept 24
5. Sept 27
6. Oct 1
7. Oct 1
![Page 8: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/8.jpg)
September 10, 2001 8
HST Software & Operations Task/Action Status
Task Lead Due Dates
COS Software & Mechanism I/F Testing
1. OSM1 – Tina, Jeff
2. Aperture – Tina, Jeff
Tina Fredo
1. October 26
2. November 22
COS Documentation
1. DM-01 SI Commands List – Chris B
2. DM-02 Engineering Data List – Chris B
3. DM-03 FSW Everything Document – Chris D
- Update requirements, hold CCB & re-release
4. DM-04 GSE Software – Dina
5. DM-05 Command Definition – Linda R
6. DM-06 Science Data Format – Linda K
7. DM-08 FSW Test Procedure – Denise
8. DM-14 Telemetry Calibration List – Chris B
9. OP-04 Constraints And Restrictions Document (CARD) – Hugh
10. OP-04 Operations Limitations Document (OLD) – Hugh
Grant Blue
1. Sept 2002
2. Sept 2002
3. Sept 2002
Sept 2001
4. Sept 2002
5. Oct 31, 2001
6. Sept 2002
7. Dec. 15, 2001
8. Sept 2002
9. TBD
10.TBD
SI Delivery Date: Sept 29, 2002
![Page 9: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/9.jpg)
September 10, 2001 9
COS Action Item List1. GB – Remind Electronics group that the Test Bench MEB must stay current
with the flight MEB ** COMPLETE **
2. GB – Get Mike Malone to update both COS Mechanism simulators.
3. JS – Learn how to modify the Mechanism simulator for future changes
4. GB – Update the plan for COS component test activities.
HST Software & Operations Task/Action Status
![Page 10: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/10.jpg)
September 10, 2001 10
HST Software & Operations Task/Action Status
Task Lead Due Dates
WFC3 Flight Software Build 2.1 (finish on WFC3 Test Bench)
HW needs: MEB CS (in place)
1. Execute performance testing on Operate code
2. Complete unit test documentation
3. Operate 2.1 Build, EEPROM load & verification
4. Database build & SITS install – Mike
This build completes code & unit test for the following 7 CSCs:
- Command, Telemetry, Error, Limits,
- Memory/Image Dump, Memory Load & Copy,
- Buffer Memory Management
Chris Dorato
1. Aug 29
2. Aug 31
3. Aug 31
4. Aug 31
BOOT Code Development & Test
HW needs: MEB CS (in place), SES1 (10/29)
1. Complete code walkthrough – Dominic
2. Complete I&T on test bench – Dominic
3. Burn PROM, install on benches and verify– Dominic, Jason
This effort completes code & unit test for the BOOT CSC
Chris Dorato
1. Oct 15
2. Nov 12
3. Nov 16
![Page 11: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/11.jpg)
September 10, 2001 11
HST Software & Operations Task/Action StatusTask Lead Due Dates
WFC3 Flight Software Build 2.2
HW needs: SES2 (10/19), SES3 (9/14), SES4(9/7), MecSim1 (10/1)
1. Complete code development:
- Mechanisms (SOFA, Shutter, Correctors) – TBD, TBD
- Service Functions - TBD
2. Complete code walkthrough – Jason, Dominic
3. Complete unit level testing – J, D, G
4. Complete build & EEPROM install – Gavin, Jason, Dominic
This build completes code & unit test for the Service Functions CSC
Chris Dorato
1. Oct 1
2. Oct 15
3. Nov 15
4. Nov 17
WFC3 Flight Software Build 2.3
HW needs: SES1 (10/29), SES2 (10/19), MecSim2 (11/15)
1. Complete code development:
- Mechanisms (CSM, IR, FSM, Lamps) – TBD
- NED – TBD
- Diagnostics - TBD
2. Complete code walkthrough – J, D, G
3. Complete unit level testing – J, D, G
4. Complete build & EEPROM install – Gavin, Jason, Dominic
This build completes code & unit test for the following 3 CSCs:
- Mechanisms & Lamps, NED, Diagnostics
Chris Dorato
1. Nov 30
2. Dec 15
3. Jan 15, 2002
4. Jan 17, 2002
![Page 12: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/12.jpg)
September 10, 2001 12
HST Software & Operations Task/Action Status
Task Lead Due Dates
WFC3 Flight Software Build 3
HW needs: complete test bench (December)
GSE SW needs: Detector Simulator, Science Data Generator
1. Complete code development:
- UVIS Detector (BOE: ACS MCE/MIE) – TBD
- IR Detector – TBD
2. Complete code walkthrough – J, D, G
3. Complete unit level testing – J, D, G
4. Complete build & EEPROM install – Gavin, Jason, Dominic
This build completes code & unit test for the last CSCs:
- UVIS Detector, IR Detector
Chris Dorato
1. Dec 31
2. Jan 15, 2002
3. Mar 15, 2002
4. Mar 30, 2002
IR: 100 days Start: 11/1/01 BOE: ACS MCE & MIE
UVIS: 40 days
![Page 13: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/13.jpg)
September 10, 2001 13
Component Test Plan & Peer Review
Test Procedure & Peer Review
I&T w/FSW & Dry Run
Run for Record
Command August 22
Steve & Chris
Telemetry August 22
Steve & Chris
Error November 30
Hugh & Jeff
Limits November 30
Hugh & Jeff
Memory/Image Dump
November 30
Hugh & Jeff
Memory Load & Copy
November 30
Hugh & Jeff
Buffer Memory Mgt
October 5
Adam & TBD
Boot October 5
Adam & TBD
HST Software & Operations Task/Action Status
FSW Bld 2.1
![Page 14: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/14.jpg)
September 10, 2001 14
Component Test Plan & CCL Development
Peer Review Procedure Testing
Run for Record
Service Functions August 22
Steve & Chris
NED August 22
Steve & Chris
Diagnostics November 30
Hugh & Jeff
Mechanisms & Lamps
October 5
Adam & TBD
IR Detector TBD
Steve
UVIS Detector October 15
Gary & Allison
HST Software & Operations Task/Action Status
FSW Bld 2.3
FSW Bld 4
FSW Bld 2.2
![Page 15: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/15.jpg)
September 10, 2001 15
HST Software & Operations Task/Action Status
Task Lead Due Dates
WFC3 FSW Component Test – Build 2.1
1. Start Telemetry – Adam
2. Start Buffer Memory Management – Gary
3. Start Limit Checking – Denise
4. Start Memory/Image Dump – Steve
5. Complete Command – Todd, Denise
6. Complete Memory Load & Copy – Steve
7. Complete Telemetry – Adam
8. Complete Buffer Memory Management – Gary
9. Complete Limit Checking – Denise
10. Complete Error Handling – Gary
11. Complete Memory/Image Dump – Steve
Denise Miller
1. TBD
2. TBD
3. TBD
4. TBD
5. October
6. October
7. October
8. October
9. October
10. October
11. October
WFC3 FSW Component Test – Boot
1. Complete Boot – Denise, Todd
Denise Miller
1. Dec 15
![Page 16: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/16.jpg)
September 10, 2001 16
HST Software & Operations Task/Action Status
Task Lead Dates
WFC3 FSW Component Test – Build 2.2
1. Start Mechanisms & Lamps (Part 1) – Gary
2. Start Sys Init & Service Functions – Adam, Steve
3. Complete Mechanisms & Lamps (Part 1) – Gary
4. Complete Sys Init & Service Functions – Adam, Steve
Denise Miller
1. TBD
2. TBD
3. January
4. January
WFC3 FSW Component Test – Build 2.3
1. Start NED – Adam
2. Start Diagnostics – Denise
3. Start Mechanisms & Lamps (Part 2) – Gary
4. Complete NED – Adam
5. Complete Diagnostics – Denise
6. Complete Mechanisms & Lamps (Part 2) – Gary
Denise Miller
1. December
2. December
3. December
4. February
5. February
6. March
WFC3 FSW Component Test – Build 3
1. Start IR Detector – Gary
2. Start UVIS Detector – Steve
3. Complete IR Detector – Gary
4. Complete UVIS Detector – Steve
Denise Miller
1. TBD2. TBD 3. September
4. September
![Page 17: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/17.jpg)
September 10, 2001 17
Task Lead Due Dates
WFC3 Non-Flight Software
1. MEB sim CEB/DEB cmds (MEB Com board testing w/ Proto)
2. UVIS & IR Detector Sim (runs on PC in SW Test Bench)
- supports HW Detector Simulator & FSW testing
3. MEB sim UVIS & IR image cmd & data capture
- supports HW Detector Simulator testing using Proto
4. UVIS/IR Science Data Generator
- supports FSW testing
5. Det Sim HW checkout with SES1 board (Proto sw update)
6. [DEB/CEB] Test Controller (MEB sim) – Dina
- need direction from I&T to start (Mark B: “Hold off”)
7. Mech test software: UVIS Corrector – Jeff
8. Mech test software: IR Filter Wheel – Jeff
9. Mech test software: Channel Select – Jeff
10. Mech test software: UVIS Shutter – Jeff
11. Mech test software: IR Corrector – Jeff
Chris Dorato
1. Aug 31
2. Sept 21
3. Sept 21
4. Dec 1
5. TBD
6. Sept 13
7. Oct 17
8. Oct 19
9. Nov 19
10. Oct 17
11. Oct 17
HST Software & Operations Task/Action Status
Dates driven by Mech hw & test set development
Current date: Oct 17
![Page 18: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/18.jpg)
September 10, 2001 18
HST Software & Operations Task/Action Status
Task Lead Due Dates
WFC3 Documentation
1. DM-01 SI Commands List (IR: 3/27/01) – Mike
2. DM-02 Engineering Data List – Mike
3. DM-03 FSW Design Document – Chris D
4. DM-04 GSE Software – Dina
5. DM-05 Command Definition (IR: 5/17/01) – Mike
6. DM-06 Science Data Format (IR SER: 6/29/01) – Mike
7. DM-08 FSW Test Procedure – Denise
8. DM-14 Telemetry Calibration List – Mike
9. OP-04 Constraints & Restrictions Doc (CARD) – Tim, Todd
10.OP-04 Operations Limitations Document (OLD) – Tim, Todd
Grant Blue
1. Aug 15, 2002
2. Sept 10, 2001
3. Aug 29, 2001
4. Aug 15, 2002
5. Sept 30, 2001
6. Oct 15, 2001
7. TBD
8. Nov 30, 2001
9. TBD
10.TBD
SI Delivery Date: Aug 15, 2002
![Page 19: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/19.jpg)
September 10, 2001 19
Task Lead Due Dates
Schedules
1. Update Master Schedule – Grant
Grant Blue
1. Aug 24
COS/WFC3 Transition Plan
1. COS/WFC3 Transition Plan: Generate Initial Release
2. STScI Memo of Understanding (COS images)
Grant Blue
1. Aug 31
2. Aug 31
WFC3 Descope List:
Need 6 ideas for each IPT
- Cost: Low <$250, Med, >$1M High
- Schedule: Low <5 days, Med, >25 days High
1. Send data to Mike Davis
Grant Blue
1. Aug 30
HST Software & Operations Task/Action Status
![Page 20: September 10, 20011 TaskLeadDue Dates COS FSW Build 3.1 (Preparation for MEB Functional) HW needs: fully functional Mechanism Simulator 1.Complete unit.](https://reader036.fdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a5bd/html5/thumbnails/20.jpg)
September 10, 2001 20
WFC3 Action Item List1. GB – Resolve date conflict: Build 2.3 and 3.0
2. GB/JP replan the Mechanism test schedule
3. GB present COS/WFC3 Risk list at next staff meeting (9-10-01)
4. GB define date for DM-08 & OP-04
HST Software & Operations Task/Action Status