SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP)...

30
SENGWA SENGWA POWER POWER STATION (PVT) LTD STATION (PVT) LTD SENGWA POWER STATION SENGWA POWER STATION (IPP) PROJECT [2 400MW] (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana Dr S Z Gata and Dr K J Moyana 1 1 GENERATION, TRANSMISSION AND RETAIL SUPPLY BUSINESS

Transcript of SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP)...

Page 1: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

SENGWA SENGWA POWERPOWER STATION (PVT) LTDSTATION (PVT) LTD

SENGWA POWER STATION SENGWA POWER STATION

(IPP) PROJECT [2 400MW](IPP) PROJECT [2 400MW]

Dr S Z Gata and Dr K J MoyanaDr S Z Gata and Dr K J Moyana

11GENERATION, TRANSMISSION AND RETAIL SUPPLY

BUSINESS

Page 2: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

22

(50%)(50%)

Page 3: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

33

RIOZIM(SH and Fuel

Supplier)

SPS (Gen, Trans,

RS)Business

ZESAGRID

(G, T, D)

SAPP(G&T)

ELECTRICITY MARKETS

(Zim. and SAPP)

EMO(Electricity Markets

Operator)

$$$

$

EMC(SH, Gen, Trans Infrastructure)

(EPC - O&M - T&T)

$

Page 4: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

ELECTRICITY MARKETSELECTRICITY MARKETS

�� Zimbabwe Zimbabwe ““PPA MarketPPA Market”” (1 200 MW)(1 200 MW)�� Commercial, Industrial and Mining ConsumersCommercial, Industrial and Mining Consumers ((��))

�� SAPP and EAPP Markets (1 200 MW)SAPP and EAPP Markets (1 200 MW)�� East African Power Pool (400 MW) East African Power Pool (400 MW) ((��))

�� Namibia (200 Namibia (200 -- 400 MW) 400 MW) ((��))

�� South Africa (400 South Africa (400 -- 600 MW)600 MW) ((��))

�� Katanga (150 Katanga (150 –– 200 MW) 200 MW) (?)(?)

�� Malawi (100 Malawi (100 –– 150 MW) 150 MW) (?)(?)

�� Mozambique (450 Mozambique (450 –– 600 MW) 600 MW) (?)(?)

�� SAPP Day Ahead Market (DAM) and SAPP Day Ahead Market (DAM) and

Other Bilateral Contract MarketsOther Bilateral Contract Markets 44

Page 5: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Zimbabwe Transmission Grid Zimbabwe Transmission Grid

(Eskom Northern

System)

Victoria Falls

Chertsey

Marvel

Triangle

Orange

Grove

Beitbridge

Bulawayo

Insukamini

Kariba

Alaska

DemaWarren

Bindura

Chakari

SherwoodKweKwe

Mutare

Gweru

Kariba North

SENGWA

(GOKWE NORTH)

(Songo, Cahora

Bassa)

Mozambique

Hwange

Botswana

(Polokwane)

Botswana Botswana

(Francistown)

Zambia

South Africa

Zimbabwe

Zizabona(System)

HARARE

Ngezi

South Africa

(Matimba)

Page 6: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

SAPP GRID SCHEMATIC/ SPS Potential Markets and Transfer Limits

ENE

ANGOLA

PD=535MW

BPC

BOTSWANA

PD=496MW

LECLESOTHO

PD= 109MW

SEBSWAZILAND

PD=196MW

ESCOM

MALAWI

PD=240MW

TANESCO

TANZANIA

PD=653MW

400MW

260MW

100MW

1 400MW

200 MW

300MW

1450MW

250MW

500MW

350MW

600MW

650MW150MW2000MW

250MW1450MW150MW

ESKOM

SOUTH AFRICA

PD=36 513MW

6

400 MW

850 MW

600 MW

200 MW

HCB/EDMMOZAMBIQUE

PD=365MW

200 MW

SNELDRC

PD=1 075MW

(EAPP)

NAMPOWER

NAMIBIA

PD=449MW

ZESA

ZIMBABWE

PD=1 758MW

200 MW

500MW

450 MW

ZESCOZAMBIA

PD=1 468MW

Page 7: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

NATIONAL POWER FEASIBILITY STUDY HIGHLIGHTS (1997)NATIONAL POWER FEASIBILITY STUDY HIGHLIGHTS (1997)

Commercial Parameters (USD Million)

Financial Plan

Total EPC Cost 1135 Capital Structure 70/30

Financing Cost 440 NP/ZESA Equity Share

80/20

Total CAPEX 1575 Import Duties on Capital Items

Nil

Installed Cost/kW 1125 Taxation Rate:

Local Content 25% First 5 years 10%

Price (Levelized) USc 4.63/kWh

-Thereafter 35%

Page 8: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL
Page 9: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Sengwa Colliery

Company

Riozim

THE DEVCO

(SPS)

Principal

Investor/Developer

/Operator

SPS Project

Rio Tinto Plc

EMC

THE GENCO

(SPC )

50% 50%

50%50%

Once the BFS is

completed – the

DEVCO is sold to

the SPC (the new

GENCO). Riozim

And EMC to have a

carried interest in

the IPP Company to

be determined via

an independent

valuation.

Public, Possibly

Listed to Enable

Raising of Capital -

Bonds, etc.

Schematic of SPS Investment StructureSPS is Established by

a Shareholders

Agreement, and a

Joint-Project

Development

Agreement Between

Riozim and EMC for

BFS and IP

SPS Project

Steering

Committee

To Produce

the (BFS + IP)

Funded by Nominal

Share Budget

Covering a

Feasibility Study,

EIA, SIA, Legal and

Regulatory Permits,

Consents,

Licenses: - Towards

a Bankable

Feasibility Study –

(BFS and IP)

Page 10: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

�� Legal and Regulatory Legal and Regulatory -- Electricity Act 2002Electricity Act 2002

�� Institutional Infrastructure Institutional Infrastructure -- ZERC ZERC

�� Electricity Pricing Principles Electricity Pricing Principles -- Tariff CodeTariff Code

�� SAPP Regional Markets SAPP Regional Markets -- Bilateral and DAMBilateral and DAM

�� Government Letter of Project Approval (***)Government Letter of Project Approval (***)

�� SPS: (IPP) Generation License (***) SPS: (IPP) Generation License (***)

�� SPS: Independent Transmission License (***)SPS: Independent Transmission License (***)

�� EMC: Retail Supply License / SAPP RegistrationEMC: Retail Supply License / SAPP Registration

�� Zimbabwe Grid Code / SAPP Book of RulesZimbabwe Grid Code / SAPP Book of Rules

Page 11: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

�� Sengwa Concession / 50 Year Mining TitleSengwa Concession / 50 Year Mining Title

�� 535 MMT Minable Reserves535 MMT Minable Reserves

�� Project Location and Market AccessProject Location and Market Access

�� Public Policy and Economic Reforms (***)Public Policy and Economic Reforms (***)

�� Improved Investment IncentivesImproved Investment Incentives

�� Economic Recovery and Power DemandEconomic Recovery and Power Demand

�� Direct Interest in both PPAs and Equity Direct Interest in both PPAs and Equity from Mining Houses and Industrial Firmsfrom Mining Houses and Industrial Firms

Page 12: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Name of Project Number of Units

In-service Date

Estimated Project CostUS$ Million

Hwange 7 & 8 Expansion 2x300 MW 2015 1080Kariba South Extension 2x150 MW 2015 400Lupane Gas Turbines 2x150 MW 2015 465Gokwe North Power Station(Sengwa Power Station)

1x320 MW1x320 MW1x320 MW1x320 MW

2017201820192022

3300

Batoka Gorge Hydro Electric Scheme (Zimbabwe-Zambia)

1x200 MW1x200 MW1x200 MW1x200 MW

2024202620282029

2700

Discounted Cost in US$ Million 4 385 Million

Page 13: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL
Page 14: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

ESKOMESKOM--NERSA (IPP) Cost Benchmarks for 2008 MidNERSA (IPP) Cost Benchmarks for 2008 Mid--Term Power Term Power

Purchase Program(ESKOM LRMC PRICE FOR NEXT BASEPurchase Program(ESKOM LRMC PRICE FOR NEXT BASE--LOAD PLANT)LOAD PLANT)

Project Parameters UnitsLow Range

Mid Range

High Range

CAPEX US$/kW 1400 1700 2000

Owners Development Cost %Capex 10% 12.5% 15%

Levelized Coal Price R/Ton 110 130 150

O&M Cost (+De-Sox) R/MWh 30 40 50

Discount Rate % 5% 7.5% 10%

Future Average Power Price [LRMC]

[NP=4.63USc/Unit(1997]Rc/Unit

Rc35 USc4.6

Rc42.5USc5.7

Rc50USc6.7

Page 15: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

�� Phase 1: SPS to Build 1 200 MW Capacity Phase 1: SPS to Build 1 200 MW Capacity

for the Local for the Local ““PPA MarketPPA Market”” by Endby End--2014;2014;

�� Target Debt to Equity Ratio 70:30; Target Debt to Equity Ratio 70:30; (85:15)(85:15)

�� Estimated Capex: US$ 2.04Billion;Estimated Capex: US$ 2.04Billion;

�� Required Equity: US$ 612Million; Required Equity: US$ 612Million; (US$306M)(US$306M)

�� IPP Syndicate to Fund Project Equity;IPP Syndicate to Fund Project Equity;

�� DFIs and ECAs to fund Project Debt DFIs and ECAs to fund Project Debt (*)(*)

1515

Page 16: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Contract Types % Local% Base

Contract Price

Mechanical 24.9 56.4Electrical + C&I 45.2 7.1Civil & Structural 90.1 22.1Transmission 71.0 14.4% Base (EPC) Contract Price

47.4

% Project Total 30.4 100

Page 17: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

SPS Project“Base Case”Scenario

Africa Power Industry

“Best Practice”Thresholds

Shareholder Equity Return (IRR%)

23.69% >18%

Shareholder Equity Payback Period (Years)

6.13 <10

Debt Service Coverage Ratio (Minimum)

1.58 >1.25

Page 18: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Capital Investment = 1 700 US$/kW Tariff (Current) =Capital Investment = 1 700 US$/kW Tariff (Current) = 6 USc/kWh6 USc/kWh

Plant Capacity = 1 200 MWPlant Capacity = 1 200 MW Grace Period = 3 yearsGrace Period = 3 years

Plant Load Factor = 85%Plant Load Factor = 85% Term of Debt = +12 yearsTerm of Debt = +12 years

Debt/Equity Ratio = 80/20Debt/Equity Ratio = 80/20 Scenario 2 is the Base CaseScenario 2 is the Base Case

Scenario 1 Scenario 2 Scenario 3

KEY VARIABLES

Fuel Price (US$/Ton) 10 15 20

Availability (%) 90 90 90

Interest Rate (%) 6 6 6

KEY RESULTS

IRR (%) 25.01% 23.69% 22.35%

Debt Service Cover Ratio 1.64 1.58 1.53

Equity Payback Period (Years)

5.83 6.13 6.46

Page 19: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Capital Investment = 1 700 US$/kW Tariff (Current) =Capital Investment = 1 700 US$/kW Tariff (Current) = 6 USc/kWh6 USc/kWh

Plant Capacity = 1 200 MWPlant Capacity = 1 200 MW Grace Period = 3 yearsGrace Period = 3 years

Plant Load Factor = 85%Plant Load Factor = 85% Term of Debt = +12 yearsTerm of Debt = +12 years

Debt/Equity Ratio = 80/20Debt/Equity Ratio = 80/20 Scenario 5 is the Base Case Scenario 5 is the Base Case

Scenario 4 Scenario 5 Scenario 6

KEY VARIABLES

Fuel Price (US$/Ton) 15 15 15

Availability (%) 85.7 90 94.5

Interest Rate (%) 6 6 6

KEY RESULTS

Shareholder IRR (%) 20.41% 23.39% 27.26%

Debt Service Cover Ratio 1.43 1.58 1.75

Equity Payback Period (Years)

7.02 6.13 5.41

Page 20: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

2020

Page 21: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

2121

Page 22: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

2222

Page 23: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Risk

Matrix

Risk

MatrixProject-Quality &

Performance

Permitting

Consents and

Approvals

Construction Cost

Over-run Risk

Completion Risk

Program Over-run Risk

Industry

Restructuring

Trading System

Force Majeure

Change in law

Inflation and

Monetary Policy

Interest Rate

Currency Exchange

and Repatriation

Policy

Market Demand

And Power Price

Operation and

Maintenance Cost

Fuel Supply

Reliability

Fuel Price

Escalation

Interest Rates

and Exchange

Rates

Transition and

Trading

Permits and

Licences

Political Force

Majeure Events

Environmental

And Emissions

Compliance

O&M Costs

Escalation

O&M

Performance

Plant and

Equipment

Breakdown

Load Factor

Page 24: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

LegalLegal--RegulatoryRegulatory--Environmental Risk Environmental Risk

(Investor(Investor--Lender Perceptions)Lender Perceptions)

““Africa Country RiskAfrica Country Risk””

�� Changes in Law (As and When)Changes in Law (As and When)

�� Changes in Policy (Frequently Retrogressive)Changes in Policy (Frequently Retrogressive)

�� Integrity of Administration of Public Policy (Rule of Law)Integrity of Administration of Public Policy (Rule of Law)

�� Ad Hoc Pricing Interventions (Arbitrary Criteria & Measures)Ad Hoc Pricing Interventions (Arbitrary Criteria & Measures)

�� Weak Regulatory Infrastructure & Systems (Permitting Risk)Weak Regulatory Infrastructure & Systems (Permitting Risk)

�� Security of Property Rights (A Huge Concern)Security of Property Rights (A Huge Concern)

�� An Overhang of Expropriation and NationalizationAn Overhang of Expropriation and Nationalization

�� Skewed Dispute Resolution and Compensation SystemsSkewed Dispute Resolution and Compensation Systems

�� Currency, Monetary and Exchange Policies Currency, Monetary and Exchange Policies 2424

Page 25: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Legal, Regulatory and Environmental Legal, Regulatory and Environmental

Risk (LRE) (Mitigation)Risk (LRE) (Mitigation)

�� ““Africa Country RiskAfrica Country Risk””

�� It is possible to It is possible to RingRing--fencefence and and QuarantineQuarantine IPP Projects from IPP Projects from

the primary elements of legal and regulatory risk through a the primary elements of legal and regulatory risk through a

Special Special ““IPPIPP”” Statutory InstrumentStatutory Instrument that has the that has the ““Authority of Authority of

ParliamentParliament””

�� It is possible to design and develop a It is possible to design and develop a Dispute Resolution Dispute Resolution

Process and ProcedureProcess and Procedure that has clear provisions for realistic that has clear provisions for realistic

compensation, and that can be executed through a compensation, and that can be executed through a ““Neutral Neutral

JurisdictionJurisdiction”” We can agree on We can agree on Allocation & Pricing Allocation & Pricing of LRE Risk?of LRE Risk?

�� There is a There is a ONE STOP ONE STOP Investment Centre: It is possible to have Investment Centre: It is possible to have

a a ””ONE STEPONE STEP”” Statutory Instrument for IPP Investments?Statutory Instrument for IPP Investments?2525

Page 26: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

↑ EPC Cost↑ EPC Cost

↑ O&M Cost↑ O&M Cost

SPSSPS

↑ Cost↑ Cost ↓ Revenue↓ Revenue

PROJECT RISK

InvestorInvestor

LendersLenders

Equity Dividends

Debt Loan

Repayments

Project Risk OriginationProject Risk Origination

↓ Production↓ Production

↓ Receipts (*)↓ Receipts (*)

Page 27: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

Market Risk: Customer Usage Market Risk: Customer Usage

Load Factor and PPA Payment Load Factor and PPA Payment

Risk MitigationRisk Mitigation

�� Mitigation Measures for Load Factor Risk:Mitigation Measures for Load Factor Risk:

�� A Diligent Market Survey with an Independent A Diligent Market Survey with an Independent

PPA Risk PPA Risk Review (Identify Review (Identify ““DerivativeDerivative”” Risks)Risks)

�� EnforceableEnforceable TakeTake--oror--Pay Clause in the PPAPay Clause in the PPA

�� Arrange to Sell Unused Arrange to Sell Unused ““EnergyEnergy”” to ZESAto ZESA

�� Trade Excess Trade Excess ““CapacityCapacity”” on SAPP DAM Marketon SAPP DAM Market

�� Customer Customer DSMDSM and Energy and Energy EfficiencyEfficiency Services Services

�� Procure PPA Procure PPA ““Payment Risk InsurancePayment Risk Insurance”” CoverCover2727

Page 28: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL

PPA TPC

PPA Payment Risk

Insurance Guarantee

SPC: (GENCO)Generates andSells Electricity to the Electricity Market Operator (“EMO”)

Power

EMO: (TRADECO)is the Bulk Power Purchaser; Transmission and Trading Company for Both the SPC Generation and the SAPP Imports.

Power

Primary Markets: Large Commercial, Mining and Industrial Companies

Secondary Markets:“SAPP Markets and ZESA Capacity Deficit Market”

Gen Tariff

Retail Tariff

PPA Risk Prem-ium

Insurance Underwriters

RISK (ii): Customer Usage

Load Factor and PPA Risk Mitigation

3 x Months Cash Cover

Prime Bank

Guarantees

Page 29: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL
Page 30: SENGWA POWER STATION (IPP) PROJECT [2 …SENGWA POWERSTATION (PVT) LTDSENGWA POWER STATION (IPP) PROJECT [2 400MW] Dr S Z Gata and Dr K J Moyana 1 GENERATION, TRANSMISSION AND RETAIL