SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In...

59
SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE WEST VIRGINIA MINE DRAINAGE TASK FORCE SYMPOSIUM March 27, 2012 Conestoga-Rovers & Associates Arch Coal, Inc.

Transcript of SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In...

Page 1: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

SELENIUM TREATMENT

ARCH-EASTERN, BIRCH MINE

WEST VIRGINIA MINE DRAINAGE TASK FORCE SYMPOSIUM

March 27, 2012

Conestoga-Rovers & Associates

Arch Coal, Inc.

Page 2: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Conestoga-Rovers & Associates (CRA)

• Al Meek

Arch Coal, Inc.

• Keith Odell

Bratton Farm

• Ben Faulkner

Page 3: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Birch Mine

In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to comply with Selenium standard (i.e., 4.7 µg/l (average) and 8.2 µg/l (maximum )) at 10 discharge points on the Knight Ink surface mine.

A corrective action plan developed by Arch and CRA to establish the following:

• Establish design criteria for treatment of waters associated with discharge points identified in the Consent Decree

• Determine applicability of new and existing selenium treatment technologies

• Complete alternatives analysis of selenium treatment system options.

• Select Treatment Alternative

• Design and construct system

• Initial compliance by August 2012

Page 4: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Birch Mine Overview

Page 5: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Knight Ink Permit S-2019-88

Page 6: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Establishing Design Criteria

• Design Flow Rates • Hydrologic Modeling of Surface Runoff, Infiltration,

Evapotranspiration and Shallow Ground Water (pit floor discharge) — Developed Base Model (calibrated with weir data)

— Applied Base Model to 2010 rainfall

— Inserted 10yr, 24 hr. rain event in 2010 model year

• Design Selenium Concentration • Historical review of NPDES outfall monitoring

• Surface water runoff analysis

• Surface runoff and seep flow components of outfall concentrations

Page 7: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling-Conceptual Model

Page 8: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling

Consisted of Three Separate Models

• Surface Runoff

• Infiltration/Evapotranspiration

• Pit Floor (Seepage flow)

Utilized the EPA developed Storm Water Management

Model (PCSWMM)

Conducted on-site flow monitoring to calibrate model.

Utilized 2010 rainfall data and inserted a 10 yr, 24 hour

event.

Page 9: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling-Surface Runoff

Page 10: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling-Pit Floor Drainage Area

Page 11: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling-Infiltration

Page 12: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling- Model Calibration

Page 13: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Modeling- Model Calibration

Input Parameters

90 deg. V-NotchV-Notch Rectangular Weir

Formula Q=4.28 C Tan (v-angle deg./2) (H + K)5/2Q=C(L-0.2H)H3/2

Q= Flow in CFS Q= Flow in CFS

K= Head correction Factor= 0.002903 C= Reference MSHA 3.33

Design ManualManual

H= head (ft)above bottom of V-Notch H= head (ft)

Tan (90/2) = 1 L= width rect.weir(FT) 4

C= Discharge Coeficient=0.5779

Head adjustment Factor (ft)0.49791

Weir Id-- Discharge 006 V-notch Rect Notch Total Total

Date Time Flow Flow Flow Flow

H (head ft) CFS CFS CFS GPM

2/13/2012 2:51:26 PM 0.242 0.073 0.000 0.073 32.9

2/13/2012 3:21:26 PM 0.237 0.070 0.000 0.070 31.4

2/13/2012 3:51:26 PM 0.246 0.076 0.000 0.076 34.3

2/14/2012 4:21:26 PM 0.247 0.077 0.000 0.077 34.8

2/14/2012 4:51:26 PM 0.245 0.076 0.000 0.076 34.1

2/14/2012 5:21:26 PM 0.251 0.080 0.000 0.080 36.1

2/15/2012 5:51:26 PM 0.250 0.079 0.000 0.079 35.6

2/15/2012 6:21:26 PM 0.255 0.084 0.000 0.084 37.5

2/15/2012 6:51:26 PM 0.256 0.084 0.000 0.084 37.9

2/16/2012 7:21:26 PM 0.252 0.082 0.000 0.082 36.6

2/16/2012 7:51:26 PM 0.253 0.082 0.000 0.082 36.8

2/16/2012 8:21:26 PM 0.254 0.083 0.000 0.083 37.0

Page 14: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Hydrologic Model- Model Calibration

ICG-Eastern- Weir Data

Blue-007, Yellow 021

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

20-A

pr

21-A

pr

22-A

pr

23-A

pr

24-A

pr

25-A

pr

26-A

pr

27-A

pr

28-A

pr

29-A

pr

30-A

pr

1-May

2-May

3-May

4-May

5-May

6-May

7-May

8-May

9-May

10-M

ay

11-M

ay

12-M

ay

13-M

ay

14-M

ay

15-M

ay

16-M

ay

17-M

ay

18-M

ay

19-M

ay

20-M

ay

21-M

ay

22-M

ay

23-M

ay

24-M

ay

25-M

ay

26-M

ay

27-M

ay

28-M

ay

29-M

ay

30-M

ay

31-M

ay

1-Ju

n

2-Ju

n

3-Ju

n

4-Ju

n

5-Ju

n

6-Ju

n

7-Ju

n

8-Ju

n

9-Ju

n

10-Jun

11-Jun

12-Jun

13-Jun

14-Jun

15-Jun

16-Jun

17-Jun

18-Jun

19-Jun

20-Jun

21-Jun

22-Jun

23-Jun

24-Jun

25-Jun

26-Jun

27-Jun

28-Jun

29-Jun

30-Jun

1-Ju

l

2-Ju

l

3-Ju

l

4-Ju

l

5-Ju

l

Date/time

Rain

fall

(in

ch

es)

0.0

100.0

200.0

300.0

400.0

500.0

600.0

700.0

800.0

900.0

1000.0

Flo

w (

GP

M)

Page 15: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Model Calibration

Page 16: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Model Output- surface/seep flow (2010 rainfall)

by discharge

Date/Time Precipitation W002 W002 W002

Runoff Seep Flow Total Flow T. Acre Ft % runoff

M/d/yyyy (in) gpm gpm gpm per day of T. Flow

5/8/2010 0.28 0.0 43.9 43.9 0.19 0.00%

5/9/2010 0 20.4 84.2 104.5 0.46 19.47%

5/10/2010 0 0.0 57.2 57.2 0.25 0.00%

5/11/2010 0 0.0 39.8 39.8 0.18 0.00%

5/12/2010 0.22 0.0 29.0 29.0 0.13 0.00%

5/13/2010 1.66 14.2 53.7 67.9 0.30 20.91%

5/14/2010 0 2460.7 150.0 2610.8 11.54 94.25%

5/15/2010 0.47 0.0 145.4 145.4 0.64 0.00%

5/16/2010 0 60.9 217.2 278.2 1.23 21.90%

Page 17: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Modeling Summary by Discharge

10 yr 24 hr storm

Discharge Average Average Average Peak runoff Peak seep flow Total Peak

I.D. runoff (gpm) seep flow (gpm) total flow (gpm) gpm gpm gpm

001 77.5 86.8 164.3 5462.0 1041.5 6503.5

002 88.1 72.7 160.8 6810.7 167.6 6978.3

005 41.6 67.1 108.8 3602.7 225.5 3828.2

006 13.4 192.4 205.8 1032.9 429.3 1462.2

007 31.1 97.4 128.5 3582.1 472.9 4055.0

014 14.0 26.6 40.6 1057.3 102.4 1159.7

021 22.7 68.4 91.0 1525.4 168.9 1694.3

031 22.6 77.7 100.3 1281.1 894.7 2175.8

034**

036 19.3 23.6 42.9 719.6 239.5 959.2

Totals 330.3 712.7 1,043.0 25,073.9 3,742.4 28,816.3

** Discharges into 001, flow included in 001

Page 18: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Modeling Summary of Contributing Precipitation

Rainfall (2010)

Total inches

Runoff

Inches (%)

Seepage

Inches (%)

Evapotrans.

Inches (%)

45.87 10.10 (22%) 26.47(58%) 9.30 (20%)

Surface Runoff Pit Floor Total

Average

Gal/min./a

cre 0.5 1.4 1.9

Page 19: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Modeling Summary of Contributing Precipitation

Page 20: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Determining Design Se Concentrations

From 2010 DMR Data

Discharge Average Se Conc. 95th Percentile Se Conc. Maximum. Se Conc.

I.D. ug/l ug/l ug/l

001 4.59 11.13 17.50

002 8.38 20.03 34.90

005 6.97 10.40 11.60

006 2.10 5.95 15.10

007 6.21 13.34 20.50

014 2.47 6.80 9.00

021 9.66 16.34 32.90

031 6.72 15.94 21.00

034 3.82 9.50 10.60

036 13.25 20.45 21.20

µg/l µg/l µg/l

Page 21: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Basis-- 2010 rainfall Modeled (W. 10yr-24hr) and DMR Selenium Conc.Average Average Selenium (2010)

Average Flow Surface Runoff Seepage Flow Design Conc.

Discharge ID. gpm gpm gpm ug/l **

001 164.29 77.5 86.8 11.1

002 160.82 88.1 72.7 20

005 108.79 41.6 67.1 10.4

007 128.48 31.1 97.4 13.3

021 91.03 22.7 68.4 16.3

031 100.31 22.6 77.7 15.9

036 42.88 19.3 23.6 20.5

Totals 796.59 302.88 493.71

Weight Average 14.88

** 95 th Perentile Se concentrations

Treatment Design Basis

µg/l**

Page 22: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Birch Mine

In March of 2011 a Consent Decree was entered by WVDEP

requiring corrective action to comply with Selenium standard at 10

discharge points on the Knight Ink surface mine.

A corrective action plan developed by Arch and CRA to establish

the following:

• Design criteria for discharge points identified in the Consent Decree

• Determine applicability of new and existing selenium treatment

technologies

• Complete alternatives analysis of selenium treatment system options.

• Select Treatment Alternative

• Design and construct system

• Initial compliance by August 2012

Page 23: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Alternative Treatment Analysis

New and Existing Technologies

Page 24: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Treatment Design Considerations, Centralized

vs. Independent

Property access, permitting time requirements and jurisdictional

wetlands immediately downstream of discharges, dictated that a

centralized treatment approach be employed.

Centralized Collection and Transfer System

• Water level in ponds will be kept low via level controlled pump.

• Pumps will deliver water to a centralized location for treatment

Benefits of Centralized Collection and Treatment

• Flow equalization is achieved in existing ponds

• Treatment system can be constructed in most favorable location

• Combining of flow allows for a lower Se. design concentration i.e., 95th

percentile vs. max concentration

Page 25: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Centralized Collection and Transfer System

Page 26: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Centralized Collection and Transfer System

(20,000 ft. Pipeline Transfer System)

Page 27: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Centralized Collection and Transfer System

Key System Details

• 2200 GPM pumping capacity via seven pumps

• Surface Runoff Selenium concentrations found to

be low, during precipitation events

• Pump capacity nearly three times avg. flow,

equivalent to 9.7 acre-ft./day

• Level Controlled Automatic pump operation

• 60 acre feet of storm water storage and flow

equalization volume

• System Owning and Operating cost is estimated

at $0.48/1000 Gallons 10 yr. period, 8% NPV

Page 28: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Selenium Treatment Alternatives Evaluation

Completed Bench Scale Testing of the Following Technologies

• Electro-Coagulation

• Adsorbent Media

• Iron Co-Precipitation

Completed Pilot or Demonstration Scale Testing of the Following Technologies

• Phyto -Remediation

• Bio-Augmentation -in-situ pond treatment

• Zero-Valent Iron Treatment

• Ion-Exchange

• Biological Reactor (Anaerobic Wetland) Treatment

— With and Without Bio-Augmentation

Page 29: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Selenium Treatment Alternatives Evaluation

Bench Scale Results • Electro-Coagulation- Bench scale tests had favorable results, equipment

issues prevented further investigation of the technology

• Adsorbent Media- Removal rates were insufficient to warrant further evaluation

• Iron Co-Precipitation- Iron addition requirements were very high, did not move to pilot testing of the technology

Pilot Scale Results • Phyto -Remediation – Some removal during active growing season, not

effective for higher Se loading

• Bio-Augmentation (in pond) –Effective during low load, summer months, Not effective during winter months

• Zero-Valent Iron Treatment- Effective Selenium Removal, High Iron generation

• Ion-Exchange-Effective Selenium Removal, Large Brine disposal requirement

• Biological Reactor (Anaerobic Wetland) Treatment-Effective Selenium removal, No Apparent Issues.

Page 30: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Results of Focused Feasibility of Selected

Technologies

Estimated O&O Cost Pro's Con's

Treatment Technology $/1000 Gal. 10yr

Semi-Passive Biological Reactor $0.38 Low Maintenance, No Residual Large footprint required, initial

Material Handling Issues, Self startup equilibrium period,

Sustaining, Low Cost Operation Reaction to higher Se concentration

Have installed simular systems is time consuming

that have shown long term

success

Ion Exchange $3.90 Small Footprint required, Labor intensive, Residual Brine

Reaction period for higher Se handling issue, Active mechanical

Concentrations short. maintenance issues. High Cost

Operation, Treatment materials

require storage, spill control

Zero Valent Iron $3.00-$5.00 Small Footprint required, Labor intensive, Residual Iron

Reaction period for higher Se handling issue, Active mechanical

Concentrations short. maintenance issues. High Cost

Operation, Treatment materials

require storage, spill control

Iron sludge handling and cost

Page 31: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Determination of Treatment

In November, 2011 ARCH-Eastern Indicated to WVDEP

that Centralized Collection & Transfer and Biological

Reactor Treatment Would be Implemented in Accordance

with the Site Consent Decree

• Final sizing of the biological treatment system would occur after

winter operation of the demonstration project.

• Construction of the collection and transfer system would occur

beginning in December 2011 (and it has)

Page 32: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Chemistry of Selenium Treatment

Page 33: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Chemistry of Selenium Treatment

Most Treatment Strategies (except Ion exchange

& Reverse Osmosis) Reduce Selenate (+6) to

Selenite (+4) Elemental (0) or Selenide (-2) form.

Reducing Condition can be created either

chemically or biologically.

Chemically by a reducing agent (e.g., -ZVI),

biologically through decomposing organic matter

and/or microbial respiration processes

Page 34: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Chemistry of Selenium Treatment in Bio-Reactor

4CH3C0- + 3SeO2 Se°+ 8CO2 +4H20 + 4H+

Selenium (Selenate/Selenite) is reduced to its elemental state, where it precipitates out of solution and remains in the bio-reactor substrate.

Key Factors to Removal • Form of Selenium, Arch-Eastern waters are > 95% Selenate

• Eh (oxidation/Reduction) potential of the system

— Affected by Temperature, Biological Activity, Flow Rate

• Hydraulic Retention Time (detention time in the system)

— Affected by Theoretical HRT (volume of the Bio-Reactor)

— Affected by Actual HRT (Flow patterns within the system).

Page 35: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Chemistry of Selenium Treatment in Bio-Reactor

Key Components of Bio-reactor Design • Gravel Sub-Drain- Acts as a Biological Media and Principle

Flow Path.

• Hay Substrate- Acts as a Biological Media and Carbon Source for microbial activity. Reduces Eh of the System through decomposition

• Mushroom Compost- Serves as a source of Nutrients to Microbes. Serves as growth media for cattails.

• Cattails- Provides cover. Dying cattails replaces decomposing hay.

• Microbes- Consumes available Oxygen, creates reducing conditions. (Some forms consume Oxygen associated with Selenate and Selenite ions)

Page 36: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Bio-reactor Demonstration Project

Page 37: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Demonstration Bioreactor, Construction

Page 39: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Cattails . Cattails

Page 43: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Bioreactor Demonstration Project-Key Features

Lined System

Fixed Bed-Plug Flow Biological Reactor

Horizontal and Downward Flow

Volume and Theoretical Hydraulic Retention Time (HRT) measured upon initial filling of the system

Pumped, Measured inflow to the system

Ability to increase Se concentrations to the influent

Weekly analysis of daily composite samples

Daily field reading of flow, pH, eH, Temp. and DO

Continual operation from Mid-August thru February

Page 44: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Demonstration Bio-reactor Results

Page 45: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Bioreactor # 1

05

1015202530

8/29

/2011

9/1/20

11

9/8/20

11

9/15

/2011

9/22

/2011

9/29

/2011

10/6/2011

10/13/201

1

10/20/201

1

10/27/201

1

11/3/2011

11/10/201

1

11/17/201

1

12/1/2011

12/8/2011

12/15/201

1

12/22/201

1

12/29/201

1

1/5/20

12

1/12

/2012

1/19

/2012

1/26

/2012

2/2/20

12

2/9/20

12

2/16

/2012

2/23

/2012

Date

Sele

niu

m C

on

c.

(ug

/l)

Bio #1 influentBio #1 Effluent SeDischarge Criteria

Page 46: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Bioreactor #1

Dementration Project

0.0000

0.0500

0.1000

0.1500

0.2000

0.2500

0.3000

0.0 500.0 1000.0 1500.0 2000.0 2500.0

Influent Se, mg/day

Se r

em

oval,

mg

/day/c

ub

ic f

t.

Y=. 0 0 0 13 5 X+. 0 0 9 6 7

r 2 = . 9 8

I n f l e c t i o n P o i n t i n

r e mo v a l r a t e @

. 2 2 mg / d a y / f t3

r2

= . 9 4 5

Arch-Eastern, Bioreactor #1

Demonstration Project

Page 47: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Bioreactor #1

0.0000

0.0500

0.1000

0.1500

0.2000

0.2500

0.0000 0.0500 0.1000 0.1500 0.2000 0.2500 0.3000

Influent Se, (mg/day/cub.ft.)

Se R

em

oval,

(mg

/day/c

ub

.ft.

)

Data Linear Regression Line

Y=.818 X -.0029

r2 =.985

.22 mg/ day/ f t3

.26 mg/ day/ f t3

Page 48: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Bioreactor #1

0

0.05

0.1

0.15

0.2

0.25

0.3

0 5 10 15 20 25 30

Temperature (C)

Se R

em

oval

(mg

/day/c

ub

ic f

t.) R e mo v a l r a t e d u r i n g

l o w e s t e f f l u e n t

t e mp s . t h r o u g h o u t

t h e e x p e c t e d r a n g e ,

d o n o t a p p e a r t o b e

e f f e c t e d b y t e mp s .

d o w n t o 5 d e g r e e s CHi gher temper atur e ef f l uents al so

coor esponds to l ower i nf l uent Se

l oadi ng

Page 49: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Bio-reactor #1

0.0000

0.0500

0.1000

0.1500

0.2000

0.2500

0.3000

0 10 20 30 40 50 60 70 80 90 100

Theoretical HRT (Hours)

Se R

em

oval, (

mg

/day/c

ub

ic f

t

Effective Removal seen at

Theoretical HRT as low as

eleven hours

Removal more dependent on incoming

load than HRT

)

Page 50: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Bio-Reactor #1

0

0.05

0.1

0.15

0.2

0.25

0.3

-350 -300 -250 -200 -150 -100 -50 0

Efflluent Eh (mv)

Se

Rem

ov

al,

mg

/da

y/c

ub

ic f

t.

Eh varied between minus 155 and minus

340. Variation appears to be dependent

on system flow and effluent temperature.

Acceptable Selenium removal throughout

the range of effluent Eh.

Initial start up period

Page 51: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Full Scale Implementation

Full Scale Design Criteria (Established earlier in the project). • Flow 800 gpm

• 95th Percentile Se concentration- 14.88

• Effluent Concentration -2.35 µg/l (1/2 discharge criteria)

• Yields a required Se removal of - 54635 mg Se/day

Selenium removal rates of bio-reactor treatment established during demonstration testing • 0.22 mg/day/ft3

Full Scale Bio-Reactor Size

• 54635 mg/day / .22 mg/day/ft3 = 248,340 ft3

Page 52: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Full Scale Bio-Reactor

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

0 200 400 600 800 1000 1200 1400 1600

Influent Flow (GPM)

Th

eo

reti

cal H

RT

(h

ou

rs)

Page 53: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Arch-Eastern, Full Scale Bio-reactor

250,000 cubic foot, of Media

Design Se Removal Rate= .022 mg/day/ft3

0.0000

0.0500

0.1000

0.1500

0.2000

0.2500

0.3000

0.0000 0.0500 0.1000 0.1500 0.2000 0.2500 0.3000 0.3500 0.4000 0.4500

Influent Se, mg/day/cub.ft.

Se

Rem

ov

al, m

g/d

ay

/cu

b.f

t

Data

Linear Equation

Y=.818 X - .0029

r2 = .985

Linear Equation

Design Removal

rate=.22 mg/day/ft3

95th percentile

Influent load.=.26

Avg. Removal

Avg. influent

Average operational

Range

Page 54: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Quality Predictive Tool

The linear equation developed during the demonstration

projects allows us to model expected effluent concentrations at

various incoming loads

• Incoming Concentration 14.88 µg/l (95th percentile) at 800 gpm =

effluent concentration of 2.35 µg/l

• Incoming Concentration 7.24 µg/l (average conc.) at 800 gpm =

effluent concentration of 1.5 µg/l

• Incoming Concentration 19.7 µg/l at 800 gpm=

effluent concentration of 3.7 µg/l

• Incoming Concentration 7.24 µg/l (average conc.) at 1150* gpm =

effluent concentration of 1.45 µg/l

* HRT at 10 hr.

Page 55: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Full scale Bio-reactor Design, Plan View

Page 56: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Full scale Bio-reactor Design, Inlet section

Page 57: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Full scale Bio-reactor Design, Outlet section

Page 58: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Full scale Bio-reactor Design

Page 59: SELENIUM TREATMENT ARCH-EASTERN, BIRCH MINE€¦ · 12/01/2016  · Arch-Eastern, Birch Mine In March of 2011 a Consent Decree was entered by WVDEP requiring corrective action to

Conclusions, Completed Objectives

• Establish design criteria for treatment of waters associated with

discharge points identified in the Consent Decree- 800 GPM, 14.88

mg/l

• Determine applicability of new and existing selenium treatment

technologies – Bench and/or Pilot testing of 8 technologies

• Complete alternatives analysis of selenium treatment system

options. -Three Technologies Analyzed

• Select Treatment Alternative- Collection and Transfer to Central

Bio-reactor Treatment

• Design and construct system- Design Completed, Construction

underway

• Initial compliance by August 2012