Selection of Claycrete Projects from 1995 - 2004 Re-visited (2006)
-
Upload
claycrete -
Category
Technology
-
view
2.119 -
download
11
description
Transcript of Selection of Claycrete Projects from 1995 - 2004 Re-visited (2006)
Ionic Soil StabiliserStabilisation ofHigher P.I. ClayBased Material
Claycrete Constructed Projects Re-visited January 2006
• Corrigin - Narembeen Road – Constructed April 2002
• Spurr Road, Kondinin – Constructed 1995
• Carstairs Road, Varley – Constructed 1996
• East Hyden Road, Hyden – Constructed Nov. 2001
• East Kalgarin Road – Constructed December 2001
• Bridge wash-away – Road re-constructed 2002
• Hyden – Southern Cross – constructed Dec. 2004
Corrigin - Narembeen Rd.
Re-constructed with
CLAYCRETE
April 2002
Photo Taken Sept. 2003Photo Taken May 2002
Re-constructed with Claycrete April 2002 and sealed within 4 weeks
Photo taken Jan. 2006
Photo taken Jan. 2006
This area has a high clay material with high water retention. Major drainage required as
shown in photo.
When revisited the road looked as new, with the
shoulders and seal in un-marked condition
Travelling on this road at 110kph there was absolutely no undulations or suspension
vibrations
Photo taken Jan. 2006
Spurr Road Kondinin Re-constructed with
CLAYCRETE October 1995
Road re-constructed October 1995 Nuclear Density CBR test October 1996
Test results, taken after 12 months, show a significant CBR
increase
Spurr Road section re-constructed with Claycrete by Shire of Kondinin—October 1995
Picture taken September 2003. Inspection shows road in excellent shape. NO Shire records of
any maintenance grading since construction.
Photo taken Sept. 2003
September 2003
January 2006
Loose material is easily brushed off to reveal a firm
well bound and solid pavement
Regular on-site inspections confirm NO
deterioration in the pavement or any rutting
and corrugations. In recent week there was rain on this road as the next slide will illustrate
This first section of Spurr Rd. was never stabilised
with Claycrete and has been re-sheeted and re-
constructed twice since 1995. This area received a
large downpour from cyclonic rains
The truck that travelled on this section of Spurr road also travelled on the Claycrete
constructed section adjoining approx 800m away. Next slide shows a dramatic difference.
Photo taken Jan. 2006
Photo taken Jan. 2006
Spurr Road Both photo’s taken the same day and the vehicle
MUST have travelled on both sections. January 2006
Constructed with Claycrete in 1995
Un-stabilised section adjoining the
Claycrete section
Carstairs Rd. Lake Varley Forestania Nickel Mine
28 km Haul Road Re-constructed
with CLAYCRETE October 1996
Carstairs Road – Lake Varley Haul road for Forestania Nickel Mine 28km re-constructed with Claycrete 1996 Mine decommissioned 2000 now sheep &
wheat farming traffic
An excellent grading of gravel stone & clay re-constructed with Claycrete
resulting in a first class tight & well bound pavement
Carstairs Road re-visited Jan. 2006 This area received cyclonic rains and flooding 2 weeks prior. Road still in
excellent trafficable & Roadworthy condition
Forestania Nickel Mine – Lake Varley - Western Australia – 1996Project: The haul route from mine to highway was used by light vehicles and school buses. Several near accidents caused the Local Government Shire to close the haul road during rain. This 28km haul road was re-constructed with Claycrete providing an ‘all weather’ pavement, with a view to safety for local & school bus traffic. Work was performed & controlled by the Shire of Lake Grace.Problem:For safety reasons, due to main school bus route, the road was closed to mine traffic during wet weather. The road was badly corrugated with un-ravelling and creating excessive dust, needing constant maintenance, also very slippery in the wet due to high clay content. The local Government Shire required an ‘All Weather’ road to safely accommodate the heavy mine hauling trucks as well as local and school bus traffic. Solution: The in-situ material had a high clay content with high plasticity and good stone content. This in-situ material was re-constructed with Claycrete resulting in considerable savings, compared with the need to import 20cm of new material for a complete re-sheeting program. The crew finished mixing one section on a Friday afternoon and decided to trim and finish the section on the following Monday. When they returned to site the road had set up with truck tyre marks in the surface. The Shire grader was unable to cut the surface and was forced to leave the marks on the pavement surface.
The tight well bound surface achieved by the Claycrete method of construction resulted with a significant reduction in ‘billowing dust’, meaning that the ‘strength’ material of the road was not blown away and lost. In an un-stabilised situation the continual loss of road ‘strength’ materials in the billowing dust blowing off the road would result with requiring re-sheeting & re-construction of the road every 18 to 24 months.
This road DID NOT require any major re-sheeting during the life of the road, also what was noticeable was NO LOSS of surface pavement material.
Conclusion:The road was never closed during wet weather for the life of the mine once the road had been re-constructed with Claycrete, also maintenance was not required on the road.
A nuclear density test for CBR increase was taken 12 months after the road was re-constructed and showed a large increase.
This road was re-visited January 2006 and photo’s & movies taken. The road, today, is still a very good trafficable AND ‘all weather’ surface
with evidence the road had sustained cyclonic rains in the last 2 weeks.A major issue with this road is that should the Authorities decide to upgrade
the road and maybe even sealing it there is no need to re-stabilise the material, even tho it was stabilised in 1996.
All that would be required is to rip the road and re-waterbind with ONLY 10% Claycrete added.
Still A Good Well Bound Surface with
Signs of only Minimal Wear, as in loose
material.
Photo’s January 2006
Re-constructed with Claycrete in 1996
East Hyden Bin Road Kondinin Western Australia
Re-constructed with
CLAYCRETE
Project Completed November 2001
Road was starting to deform and pothole with
the asphalt deteriorating. The road was ripped and the in-situ high clay gravel material was re-constructed using Claycrete. Project
completed November 2001
East Hyden Bin Road Section of Pavement Failure Across A Salt PanThe road Pavement was extensively rutted and undulating, with evidence of considerable movement under the seal. It was evident that the material was plastic and holding water. The decision was to re-work the section and stabilise with Claycrete. The existing seal was chopped & mixed into the re-worked in-situ material thus saving cost of disposal and cartage away.This photo is of the re-constructed and sealed Claycrete Pavement
Construction was undertaken by Manager of Works Shire of Kondinin, November 2001This Picture Taken September 2003.Details From CBH Show 2002-2003 Grain Haulage On This Road was 27,339 Tonnes In 365 (each way)Triple Road Train Movements Hauling An Average Of 75 Tonnes Per Load, Over & Above Local Farming Traffic Also Tourist Traffic To Wave RockThis Section of Road Is Now One Of The Main Connecting Routes To The Eastern States and used by heavy haulage interstate vehicles.
Photo taken Sept. 2003
Project re-visited October 2004 Road in first class condition with NO
Deformations or sign of damage
Photo taken Oct. 2004
Project re-visited January 2006
Crossed the road at 110kmh and there was NO sign of deformations or faults in the pavement. The asphalt is now showing
signs of ‘bleeding’ due to the current heavy haulage use
Photo taken Jan. 2006
East Kalgarin Crossing re-constructed with
CLAYCRETE December 2001
East Kalgarin access roadSection of flood crossing re-constructed
with Claycrete by Manager of
WorksShire of Kondinin—December 2001
Project re-visited Sept. 2003 & Jan. 2006Inspection shows road in excellent shape.
Every year prior to the Claycrete re-construction this crossing was washed away & totally lost after every overflow
during a wet season.Pic taken after a flow over the crossing.
NO Maintenance has been required since re-constructed in December 2001
Evidence of Water Flow Over Road Is Clearly Seen
Photo taken Sept. 2003 and water flow from right to left clearly visible
September 2003 January 2006
Both photo’s show evidence of water flow over the crossing. The latest shows considerable silt
deposited on the road
January 2006
This photo clearly shows the heavy scouring caused by the large volume of water flowing
over the crossing
Bridge washaway - Kondinin
Cyclonic Rains January 2006
CLAYCRETE re-constructed
2002
Water reached here
The water flowed over this road to width of the arrow mark and a depth of 40cm over the
asphalt. The current was sufficient to wash away the bridge section
Water reached knee cap height
January 2006 Cyclone Clare dumped a record 223mm (in 24 hours) of rain on and
around Lake Grace & districts.
Reported as - A ‘once in 500 year event’
Lake Grace is located approx 200km South East of Kondinin.
The large volume of water dumped on Lake Grace has flowed to many
surrounding areas via the lake system & thus also caused flooding, even as far as
Kondinin.
This damage at Kondinin was caused by the water flow from Lake Grace’s deluge,
rather than directly from the cyclone.
Extract from West Australian newspaper Sat. 28th Jan. 2006
Extract from West Australian newspaper Sat. 28th Jan. 2006
3 weeks after the cyclonic
rains roads and rail still remain submerged by the flooding.
Article from West
Australian newspaper 1st February
2006
The base course was a high clay gravel
material with good stone and
re-constructed with Claycrete. This photo
clearly shows the Claycrete material to
the right of the yellow line. When inspected the Claycrete section was dry, firm & well
bound with no scouring marks even tho water to 40cm deep washed
over this road. Material left of the line was
holding moisture. The flow of water started to
lift the asphalt seal. The area was totally
submerged for several days
Note
Next Slide
This photo shows the Claycrete clay gravel material still attached to the asphalt seal. This material has not broken down or washed away under the worst conditions of flooding & complete submersion for
several days.
Photo taken Jan. 2006
Hyden – Southern Cross Road Re-
constructed with CLAYCRETE
December 2004
Photo taken January 2006
3km section of road re-constructed with Claycrete. Driving on this road at 110kpm was extremely
smooth with no vibrations thru the shock absorbers or steering wheel. This area received cyclonic rains
2 weeks prior to my visit.
The road is well constructed with excellent drainage and constructed with Claycrete from
shoulder to shoulder. Thus if a vehicle's tyres leave the asphalt they will not damage the un-
sealed areas nor the asphalt edge
Photo taken Jan. 2006
16/100 Briggs Street16/100 Briggs StreetWelshpool 6106Welshpool 6106
Western AustraliaWestern Australia
Email : [email protected] [email protected]
TEL : +61(8) 9470 9117FAX : +61(8) 9472 4366