FNR 66 Final Labs and Schedule: Week 9: Seismic Hazard Week 10: Flood Hazard or Bathymetry Lab
Seismic and External Flood Hazard Risk Insights
Transcript of Seismic and External Flood Hazard Risk Insights
Seismic and External Flood Hazard Risk Insights
Milton Valentín, P.E.NRC Risk and
Reliability Analyst
Timeline of NRC Efforts
1990 2000 2010 2020
1991: NUREG-1407, Submittal and Guidance for IPEEE
1995: GL 88-20 Supplement 5 (IPEEE Modified Seismic Requirements)
2002: NUREG-1742, Perspectives Gained from IPEEE
2005: GI-199Seismic Hazard Estimates
2009: External Event PRA Standard Endorsed in RG 1.200
2010: GI-204 Upstream Dam Failure
2011: PRE-11 Downstream Dam Failure
2012: 10 CFR 50.54(f) Request for Information on Fukushima Reevaluations
1992: NUREG/CR-4839, External Event Screening
1987-89: NUREG/CR-5042,Evaluation of External Hazards
2017: POANHI
2015: PFHA Workshops
Post-Fukushima ActionsHow did we do it?• Applied a safety-first
mentality
• Used latest methods and information
• Supported improvement of the state of knowledge
• Endorsed industry guidance
What did we do with it?• Confirmed safety for
licensing basis events
• Enhanced protection and mitigation for beyond-design-basis events
• Improved the state of knowledge
Reevaluated Flooding Hazards
Annual Exceedance Probability (AEP):
AEP ≥ 1x10-3 + Margin or 1x10-4
High Likelihood—Protection
AEP < 1x10-3 + Margin or 1x10-4
Low Likelihood—Mitigation
NEI 16-05, Revision 1, “External Flooding Assessment Guidelines,” June 2016
Prot
ectio
n (H
igh
Like
lihoo
d)M
itiga
tion
(Low
Lik
elih
ood)
Floo
ding
Wat
er E
leva
tion
Seismic Risk Can Be Nontrivial
Frequent Seismic Risk Contributors
Estimated Risk Reduction from SPRA-Based Plant Modifications
Safety Enhancements ΔSCDF ΔSLERFOperator actions and training to prevent relay chatter
17% 6%
Alternate letdown isolation ~ 92%Alternate power to hydrogen ignition system
~ 50%
Emergency supply transformer anchorage
16.5% ~
Diverse and robust auxiliary feedwater supply
40% 60%
Conclusion• U.S. plants are better prepared against external hazards as
the understanding of the hazards and the tools to quantify risk have evolved.
• U.S. plants have improved their mitigation and protection capabilities commensurate with the improved understanding of the risk.
• The NRC staff continues to enhance the state of knowledge:– POAHNI– PFHA workshops– PRA standard/guidance/tools development and updates
Acronyms10 CFR – Title 10 of the Code of Federal Regulations10 CFR 50.54(f) – Regulation stating that licensees shall, upon the Commission’s request, submit written statements to enable the Commission to determine whether a license should be modified, suspended, or revoked.AC and DC – Alternate Current and Direct CurrentAEP – Annual Exceedance ProbabilityCDF – Core Damage FrequencyFLEX – Diverse and Flexible Coping Mitigation Strategies GI – Generic IssueGL – Generic LetterIPEEE – Independent Plant Examination for External EventsLIP – Local Intense Precipitation
LOCA – Loss-of-Coolant AccidentLOSP – Loss of Offsite PowerNEI – Nuclear Energy InstituteNUREG – NRC ReportsNRC – U.S. Nuclear Regulatory CommissionPFHA – Probabilistic Flooding Hazard AnalysisPOAHNI – Process for Ongoing Assessment of Natural Hazard InformationPRA – Probabilistic Risk AssessmentPRE – Pre-Generic Issue SummaryRG – Regulatory GuideSCDF – Seismic Core Damage FrequencySLERF – Seismic Large Early Release FrequencySPRA – Seismic Probabilistic Risk AssessmentΔSCDF – Delta Seismic Core Damage FrequencyΔSLERF – Delta Large Early Release Frequency