Security Issues of Electric Power Supply in Japan May 2005 Hiroshi Iwano Agency for Natural...
-
Upload
veronica-bryant -
Category
Documents
-
view
215 -
download
3
Transcript of Security Issues of Electric Power Supply in Japan May 2005 Hiroshi Iwano Agency for Natural...
Security Issues of Electric Security Issues of Electric
Power Supply in JapanPower Supply in Japan
May 2005
Hiroshi Iwano
Agency for Natural Resources and Energy (ANRE),Ministry of Economy, Trade and Industry (METI),
JAPAN
2
Ⅰ. Introduction
Ⅱ. Energy Supply Structure and Portfolio of Power Supply Sources
Ⅲ. Transmission and Distribution System and the Governance of the System
Ⅳ. The Next Stage for the Establish- ment of Flexible and Robust Energy Supply System
3
ⅠⅠ. Introduction. Introduction1. Overview of the Japanese Electric Industry1. Overview of the Japanese Electric Industry
2. The Breakdown of Primary Energy Supply & Electric Power So2. The Breakdown of Primary Energy Supply & Electric Power Sources urces
3. The Current Balance of Electric Demand and Supply in Japan3. The Current Balance of Electric Demand and Supply in Japan
4. Introduction of the Bidding System for wholesale 4. Introduction of the Bidding System for wholesale SupplySupply
5. Partial Liberalization of Retail Supply5. Partial Liberalization of Retail Supply
6. Recent Regulatory Reforms in Japan 6. Recent Regulatory Reforms in Japan
7. The principle of the Regulatory Reform7. The principle of the Regulatory ReformⅡ. Energy Supply Structure and Portfolio of Power Supply Sources
Ⅲ. Transmission and Distribution System and the Governance of the System
Ⅳ. The Next Stage for the Establishment of Flexible and Robust Energy Supply System
4
1. Overview of the Japanese 1. Overview of the Japanese Electric IndustryElectric Industry
Alternating Current
50 Hz 0.6GW
Direct Current
60 Hz
0.6GW
2.8GW 1.3GW 4GW
0.3GW
1.2GW
0.3GW
0.9GW 1.4GW
1GW
Hokkaido
5.0GW
Tohoku
15GW
Tokyo
62GW
Kyushu
17GW
Chugoku
12GW
Shikoku
5.7GW
Kansai
30GW
Chubu
26GW
Hokuriku
5.4GW
2.5GW0.6GW
1.3GW 5GW
Alternating Current
Direct Current
Okinawa1.5GW
Okinawa1.5GW
10 General Power Utilities (GPUs), vertically-integrated generation, transmission and distribution segments, with their franchised areas under public service obligation.
Japanese network system does not form mesh network, and interconnection capabilities between GPUs are sometimes said to be weak.
Japanese network is isolated with no international connection.
Scarce indigenous resources brings about heavy independence on imported energy resources.
5
発電電力量シェアの推移(電気事業用)
2%13%
27% 30%
4%
4%
10%
22%
2%
13%
22%
26%
75%
54%
30%
12%1% 1%1% 1%15% 14% 11% 8%
0%
20%
40%
60%
80%
100%
1973 1979 1990 2002
再生可能・新エネルギー等揚水
石油等
LNG
石炭
原子力
一次エネルギー総供給シェアの推移
76%69%
54%47%
2%3%
4%3%
15%14%
16%20%
2%5%
10% 14%
1% 4%9% 12%
5% 6% 7% 6%
0%
20%
40%
60%
80%
100%
1973 1979 1990 2002
再生可能・新エネルギー等原子力
天然ガス
石炭
LPG
石油
(Source) Agency of Natural Resources and Energy
(Source) Agency of Natural Resources and Energy
(図1)(図1) (図2)(図2)
FY FY
2. The Breakdown of Primary Energy2. The Breakdown of Primary Energy Supply & Electric Power SourcesSupply & Electric Power Sources
Trends for Primary Energy Supply Trends for Electric Power Sources of GPU
Hydro,RenewableNuclear
Natural Gas
Coal
Oil
LPG
Hydro,RenewablePumped HydropowerOil
Coal
Nuclear
LNG
6
0
50000
100000
150000
200000
250000
Peak Demand Installed Capacity
Electric Demand and Installed Capacity (Summer, 2004)
Peak electric demand in summer 2004 was 175,820MW, and the installed capacity was 232,010MW. The reserve margin was 32%.Peak electric demand in summer 2004 was 175,820MW, and the installed capacity was 232,010MW. The reserve margin was 32%.
3. The Current Balance of Electric 3. The Current Balance of Electric Demand and Supply in JapanDemand and Supply in Japan
GPU
Wholesale
New Entrants (PPS)
MW
7
After 1995 【 Introduction of IPP bidding system】
Special Electric Company
Special Electric Company
Small to medium buildings, etc
Supply by its own transmission
Power Plants
Power Plants
Transmission Lines
General Power Utilities
Before 1995
Department Store, Large Hospital, Large Office Building, etc.
Large Factory
etc.
Household Small to Medium Factory, etc.
Office, Bldg,Shopping Arcade, etc.
Regulated Rate
Power Plants
General Power Utilities
Department Store, Large Hospital, Large Office Building, etc.
Large Factory
etc.
Household Small to Medium Factory, etc.
Office, Bldg,Shopping Arcade, etc.
Regulated Rate
Independent Power Producers (IPP)
Independent Power Producers (IPP)
BiddingBidding
4. Introduction of the Bidding System 4. Introduction of the Bidding System for Wholesale Supplyfor Wholesale Supply
8
After Partial liberalization (current system)
【 Starting March 21, 2000 】 Electric Power Company
General Power UtilitiesGeneral Power Utilities
Rate Control
Power Plants
Household Small to Medium Factory, etc.
Office Bld., Shopping Arcade, etc.
Introduction of Notification System when lowering Rates. Deregulation of Option Menu
Introduction of Notification System when lowering Rates. Deregulation of Option Menu
Before Partial Deregulation
General Power UtilitiesGeneral Power Utilities
Regulated Rate
Power Plants
Transmission Lines
Department Store, Large Hospital, Large Office Building, etc.
Large Factory, etc.
Household Small to Medium Factory, etc.
Office, Bld.,Shopping Arcade, etc.
Electric Power
Company’s Transmissio
n Lines
New EntrantsNew Entrants
Power Plants
( Companies outside the supply area included)
Electric Power Company reports the wheeling rates to METI
Electric Power Company reports the wheeling rates to METI
Department Store, Large Hospital, Large Office Building, etc.
Large Factory, etc.
Free Rates (competitive
)
“Guideline for Fair Electricity Trade” compiled jointly by METI and the Fair Trade Commission
“Guideline for Fair Electricity Trade” compiled jointly by METI and the Fair Trade Commission
Large Consumers (about 30% of the total From April, 2005 60%)
Large Consumers (about 30% of the total From April, 2005 60%)
5. Partial Liberalization of Retail Supply5. Partial Liberalization of Retail Supply
9
generation
transmission and
distribution
Wholesale electric power
enterprises
Retail ( liberalized)Retail (regulated)
General Power Utilities
NewEntrants
(PPS)Wholesale
Power Exchange
I. Maintaining vertical coordination between generation and transmission
In order to secure a stable supply of electric power as well as to promote nuclear power generation, integrated operation and facility planning of electric power generation and transmission is needed.
Ⅱ. Securing the fairness and transparency of the network function
Implementation of the behavioral regulation
Establishment of neutral organization
Securing competitive neutrality under an integrated structure
6. Recent Regulatory Reforms in Japan6. Recent Regulatory Reforms in Japan
GPUs operate both power generators and the network system, offer ancillary service, and are still the last resort suppliers. Securing the fairness and transparency of the network is a key issue for the regulatory reforms in Japan.
GPUs operate both power generators and the network system, offer ancillary service, and are still the last resort suppliers. Securing the fairness and transparency of the network is a key issue for the regulatory reforms in Japan.
10
7. The Principle of the 7. The Principle of the Regulatory ReformRegulatory Reform
(1) Conditions of Japanese Electric IndustryIsolated location with no international connectionScarce indigenous resources and heavy
dependence on imported energy resources
(2) Basic Philosophy of Regulatory ReformEnsuring the stable electric power supplyBalance the regulatory reform and the policies such as
energy security and environmental protectionHarmonizing free business activities with the system
securing stability and fairness based on the nature of electricity
Expanding retail choice
11
ⅠⅠ. Introduction. Introduction
ⅡⅡ. Energy Supply Structure and . Energy Supply Structure and Portfolio of Power Supply SourcesPortfolio of Power Supply Sources
8. Regulations imposed on GPUs8. Regulations imposed on GPUs
9. Notification of the Plan for Power Supply & 9. Notification of the Plan for Power Supply & DemandDemand
10. Future Prospect of Japanese Electric 10. Future Prospect of Japanese Electric Industry Industry
11. Directions of Japanese Electric Industry11. Directions of Japanese Electric IndustryⅢ. Transmission and Distribution System and the Governance
of the System
Ⅳ. The Next Stage for the Establishment of Flexible and Robust Energy Supply System
12
8. Regulations Imposed on GPUs8. Regulations Imposed on GPUs
Business license, Construction plan approval,
Public service obligation,
Approval of terms and conditions for wheeling services, Supplier of last resort,
Behavioral regulation on wheeling,
Obligation on quality assurance of electricity,
Coordination among electric networks, and
Notification of the plan for power supply and demand.
The regulations imposed on GPUs are as follows;
13
Each GPU submits its individual 10-year plan for power supply & demand by the end of every fiscal year.
The plans show power construction projects, transmission network investments, etc.
The Japanese government (ANRE, METI) checks the plans to ensure they meet requirements.
9. Notification of the Plan for 9. Notification of the Plan for Power Supply & DemandPower Supply & Demand
The Japanese government checks the GPUs’ long term investment plan to ensure adequate investment on electric facilities.
14
10. Future Prospect of Japanese 10. Future Prospect of Japanese Electric IndustryElectric Industry
0
50000
100000
150000
200000
250000
300000
2004FY 2014FY
Peak DemandInstalled Capacity
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2004FY 2014FY
HydroThermal (Oil)Thermal (LNG)Thermal (Coal)Nuclear
Outlook for Electric Demand and Supply Balance Outlook for the Share of Electric Power Sources
According to the plans for electric power supply and demand of GPUs, electric demand and balance in 2014, will still keep over 30% level as reserve margin.
Share of Nuclear power plants and LNG fired power plants in 2014 will increase from the current level.
15
11. 11. Directions of Japanese Directions of Japanese Electric IndustryElectric Industry
The appropriate portfolio in terms of power supply sources, including hydro, thermal and nuclear power, should be pursued continuously.
Nuclear power will keep its significant role in the future.
The effort to conduct conditions for Natural gas utilization should be initiated.
The incentive for load-leveling should be enhanced through covenant of electricity rate.
Energy conservation will be the ultimate and effective tool for rapid increase of energy demand in Asia and environmental protection.
Demand Side;
Supply Side;
16
Ⅰ. Introduction
Ⅱ. Energy Supply Structure and Portfolio of Power Supply Sources
ⅢⅢ. Transmission and Distribution . Transmission and Distribution System and the Governance of the System and the Governance of the SystemSystem
12. The Role of NSO12. The Role of NSO
13. Outline of NSO’s Rule13. Outline of NSO’s Rule
14. Reliability Issues in NSO’s Rule14. Reliability Issues in NSO’s Rule
15. Monitoring of Inter-connection Lines15. Monitoring of Inter-connection Lines
16. The Mechanism to Expand 16. The Mechanism to Expand Interconnection LinesInterconnection Lines
17. To Ensure Reliability17. To Ensure ReliabilityⅣ. The Next Stage for the Establishment of Flexible and
Robust Energy Supply System
17
12. The Role of NSO12. The Role of NSOJapanese regulatory reform has maintain vertical coordination between generation and transmission.
Ensuring fairness and transparency in the transmission and distribution sector is one of the essential concept of it.
1. Designation Electric Power System Council of Japan (ESCJ) as Neutral System Organization (NSO), which formulates network rules and monitors their implementation, etc.
2. Implementation of the behavioral regulation.
Information firewalls, Prevention of cross-subsidizing and Prohibition of discriminatory treatments are enforced as legal obligations.
18
13. Outline of NSO’s Rule13. Outline of NSO’s Rule
NSO’s (Neutral System Organization) main functions are; (a) Rulemaking (not regulation, but organization rules) :
-Construction of network facilities-Network access-System operation-Disclosure of network information
(b) Arbitration and dispute settlements between network users and the transmission/distribution segments of GPUs
(c) Providing a central dispatching liaison office(d) Operating OASIS
NSO is not a governmental organization, but a specified organization by the law. It consists of incumbent utilities, new entrants, other network users and academic experts.
19
14. Reliability Issues in NSO’s Rule14. Reliability Issues in NSO’s Rule
Analysis is made on the condition of assumed severe contingency corresponding to each case.
Analysis is made on the condition of assumed severe contingency corresponding to each case.
NSO’s rule covers; - thermal limit, - voltage stability, - system stability, - system frequency maintenance, etc.
20
15. Monitoring of Inter-connection 15. Monitoring of Inter-connection LinesLines
• NSO manages and posts the available transmission capability on interconnection lines between system operators each other.
• NSO determines the availability of inter-connection lines for each request of transaction through interconnection lines.
NSO manages the available transmission capability on interconnection lines.
21
16. The Mechanism to Expand 16. The Mechanism to Expand Interconnection LinesInterconnection Lines
The mechanism to plan to expand and/or construct interconnection lines is supposed to be implemented by NSO in case the power flow on interconnection lines increases and the remaining capabilities become insufficient due to construction of new generators, increase of long-distance power trade, etc.
However, the interconnection lines will be constructed by GPUs, because they still possess transmission assets, and are responsible for reliability of the network systems.
22
17. To Ensure Reliability17. To Ensure Reliability
NSO prepares the reliability assessment of the network system twice a year. NSO carries out the 1st assessment this spring.
The assessment could contribute to maintaining or even improving the current level of reliability.
NSO will assess the reliability of power network system in Japan twice a year.
NSO will assess the reliability of power network system in Japan twice a year.
23
Ⅰ. Introduction
Ⅱ. Energy Supply Structure and Portfolio of Power Supply Sources
Ⅲ. Transmission and Distribution System and the Governance of the System
ⅣⅣ. The Next Stage for the . The Next Stage for the Establishment of Flexible and Robust Establishment of Flexible and Robust Energy Supply SystemEnergy Supply System
18. Conditions of Japanese Energy Sector18. Conditions of Japanese Energy Sector
19. Outlook for the Future19. Outlook for the Future
20. The Next Stage20. The Next Stage
21. Future Energy Strategies Based on the 21. Future Energy Strategies Based on the Energy OutlookEnergy Outlook
24
18. Conditions of Japanese 18. Conditions of Japanese Energy SectorEnergy Sector
Limited gas pipeline network Limitation of thermal power
generators Location (Only along coast line)
Construction of new transmission lines
is difficult.
Most fuels for generators are imported in Japan, because Japan does not have significant gas or coal reserves.
NIMBY, Small & mountainous country
25
19. Outlook for the Future19. Outlook for the Future
レファレンスケース
低成長ケース
高成長ケース
0
2
4
6
8
10
12
14
16
1955 1965 1975 1985 1995 2005 2015 2025年度
千億
kW
h
On the other hand, electric power demand in Japan is expected to increase moderately over the next 20-30 years.
26
20. The Next Stage20. The Next Stage
The study on full liberalization will start in 2007.
Our goal is the harmonization of ensuring energy security, environment protection and economic efficiency. The role of nuclear powers will remain significant. Investment of transmission/distribution lines and other necessary investment should be sustained. Effective use of distributed generations is also a key issue.
The study on full liberalization will start in 2007.
Our goal is the harmonization of ensuring energy security, environment protection and economic efficiency. The role of nuclear powers will remain significant. Investment of transmission/distribution lines and other necessary investment should be sustained. Effective use of distributed generations is also a key issue.
27
Development of international strategy focused on the increase of energy demand in Asia
Realization of the virtuous circle of energy conservation and environmental protection among the civil society and industrial circles
Strengthen the ability to adapt to any change by dispersion and diversification of energy supply
Establishment of the flexible and robust energy supply system
21. Future Energy Strategies Based on the Energy Outlook
28
Thank you.Thank you.Hiroshi Iwano
Director, Office of Electric Transmission and Distribution,
Electricity and Gas Industry Department,Agency for Natural Resources and Energy (ANRE),Ministry of Economy, Trade and Industry (METI),
Hiroshi Iwano
Director, Office of Electric Transmission and Distribution,
Electricity and Gas Industry Department,Agency for Natural Resources and Energy (ANRE),Ministry of Economy, Trade and Industry (METI),