SECTION F TECHNICAL SPECIFICATION

104
SECTION F – TECHNICAL SPECIFICATION Page F1 SECTION F TECHNICAL SPECIFICATION TABLE OF CONTENTS TECHNICAL SPECIFICATION 1 1 PRELIMINARIES 2 2 DEMOLITION 6 3 ASBESTOS REMOVAL & DISPOSAL 8 4 SITE PREPARATION & EXCAVATION 12 5 PLUMBER: SANITARY, SEWERAGE, WATER SUPPLY AND DRAINAGE 18 6 ELECTRICAL INSTALLATION 24 7 MINOR CONCRETE WORKS 29 8 BLOCKWORK 34 9 BRICKWORK 40 10 COLD FORMED METAL FRAMING 45 11 STRUCTURAL STEEL 47 12 METALWORK 50 13 CARPENTRY 54 14 METAL ROOFING, SIDING, PLUMBING & RAINWATER TANK 57 15 FIBRE CEMENT PRODUCTS 60 16 PLASTERBOARD 62 17 DOORS & DOOR FRAMES 64 18 METAL WINDOWS & GLAZING 66 19 INSULATION (THERMAL AND ACOUSTIC) 71 20 JOINERY 73 21 UNIT KITCHEN 76 22 PACKAGED AIR CONDITIONING UNIT 80 23 AIR DISTRIBUTION DUCTWORK 82 24 ROOM AIR CONDITIONING UNIT 85 25 CERAMIC TILES 87 26 TANKING 91 27 RESILIENT FLOORING 93 28 PAINTING 95 29 MIRRORS 99 30 METAL FINISHES 101 31 FENCES AND GATES 103

Transcript of SECTION F TECHNICAL SPECIFICATION

Page 1: SECTION F TECHNICAL SPECIFICATION

SECTION F – TECHNICAL SPECIFICATION Page F1

SECTION F

TECHNICAL SPECIFICATION

TABLE OF CONTENTS

TECHNICAL SPECIFICATION 1

1 PRELIMINARIES 2

2 DEMOLITION 6

3 ASBESTOS REMOVAL & DISPOSAL 8

4 SITE PREPARATION & EXCAVATION 12

5 PLUMBER: SANITARY, SEWERAGE, WATER SUPPLY AND DRAINAGE 18

6 ELECTRICAL INSTALLATION 24

7 MINOR CONCRETE WORKS 29

8 BLOCKWORK 34

9 BRICKWORK 40

10 COLD FORMED METAL FRAMING 45

11 STRUCTURAL STEEL 47

12 METALWORK 50

13 CARPENTRY 54

14 METAL ROOFING, SIDING, PLUMBING & RAINWATER TANK 57

15 FIBRE CEMENT PRODUCTS 60

16 PLASTERBOARD 62

17 DOORS & DOOR FRAMES 64

18 METAL WINDOWS & GLAZING 66

19 INSULATION (THERMAL AND ACOUSTIC) 71

20 JOINERY 73

21 UNIT KITCHEN 76

22 PACKAGED AIR CONDITIONING UNIT 80

23 AIR DISTRIBUTION DUCTWORK 82

24 ROOM AIR CONDITIONING UNIT 85

25 CERAMIC TILES 87

26 TANKING 91

27 RESILIENT FLOORING 93

28 PAINTING 95

29 MIRRORS 99

30 METAL FINISHES 101

31 FENCES AND GATES 103

Page 2: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Preliminaries Page F2

1 Preliminaries

PART I GENERAL

1.101 Interpretation

(a) Supply means purchase and transport to site or nominated depot.

(b) Provide means supply and install.

(c) Repair means to make good.

(d) Retain means take out, reinstall and repair or leave in place.

(e) Remove means demolish and dispose of materials and repair.

(f) Replace means to remove and then to provide equal material or material as nominated.

(g) Relocate means move into a new location/position, reinstall and repair.

(h) N/A means Not Applicable.

(i) Wet Areas means laundry, toilet, bathroom and shower room.

(j) Renew means replace with equal new item or item as nominated.

(k) Perform means to test and report.

(l) Principal means Principal’s Representative

1.102 Project Description

Transport and installation of fire water tank stands for eight communities including site preparation,

footings, tank stand assembly installation, plumbing installation and various minor items for the

satisfactory completion of the works. Refer to Schedules for full scope of work.

1.103 Location

Refer to tender documents for location of work.

1.104 Scope of Work

Refer to Drawings & Schedules for extent of work.

The Contractor shall supply and install all necessary materials, labour, plant, equipment (including hire)

and cartage necessary for the proper completion of the works.

Any works described in the drawings but not mentioned in the specification and schedules and vice

versa shall be included in the Contract.

The Contractor shall be deemed to have inspected the sites before tendering and to have made sufficient

allowance for the nature and requirements of the works to be done, conditions of access for building

purposes, access to services, and shall allow for and undertake all incidental and minor work not

particularly mentioned but that are necessary for the satisfactory completion of the Contract.

1.105 Materials and Work Supplied by the Principal

No materials and work shall be supplied by the Principal except where scheduled.

1.106 Proprietary Items

The use of trade and brand names in the specification may indicate performance characteristics of the

item. Equal products, as approved by the Principal, may be used.

Upon request by the Principal, the Contractor shall provide evidence of manufacture.

1.107 Care & Protection of Property & Persons

The contractor shall provide adequate protection of all work against damage from subsequent trades,

against damage from the weather, and against damage by other persons.

The Contractor shall provide adequate protection of all adjacent property from damage caused as a

result of undertaking works under the Contract. Any damage so caused shall be made good at the

Contractor’s expense.

The Contractor shall provide adequate protection to persons by erecting barricades, fencing, markers,

signs or any other measure around or upon works so as to reduce risk and to prevent injury.

1.108 Warranties, Guarantees, Certificates and Rebates

All warranties on goods and/or materials shall be taken out in the name of the Principal.

Page 3: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Preliminaries Page F3

Any certificates, warranties or guarantees given by sub-contractors or suppliers of materials and

equipment shall be delivered by the Contractor to the Principal prior to Practical Completion.

Warranties, guarantees and certificates shall be delivered to the Principal prior to the acceptance of

Practical Completion.

Any rebates that can be claimed by the Principal or on behalf of the Principal may be claimed by

Contractor and are deemed to be incorporated in the Contract Sum.

1.109 On-Site Storage and Site Control

The Contractor shall:

a) Arrange for or provide adequate storage for materials, equipment and machinery on-site or

elsewhere for the duration of the works in a manner that will prevent damage, deterioration,

and loss including theft. Control delivery schedules to minimise long-term storage of products

at sites.

b) Be responsible for activities on the site including providing access for authorised persons and

restricting access by unauthorised persons and shall take the necessary precautions to secure

the assets of the Principal.

c) Not store waste building materials and flammable liquids in the building.

d) Maintain the site in a clean, tidy and safe condition. Provide and erect barriers, bunting etc. as

appropriate to protect and isolate persons and materials from injury and damage.

e) Take proper precautions to keep poisons, solvents and other injurious substances in places

secured against access by unauthorised persons.

f) During the handling and installation of work as the project proceeds, clean the site and protect

work in progress and adjoining work on a basis of perpetual maintenance. Apply suitable

protective covering on newly installed work where required to ensure freedom from damage or

deterioration until Practical Completion; otherwise clean and perform maintenance on newly

installed work as frequently as necessary throughout the remainder of the construction period.

1.110 Site Amenities and Meetings

The Contractor shall provide statutory and necessary amenities and sanitary facilities for site workers

where such are not already available in suitable locations. These shall be maintained in clean and

working condition.

The Contractor shall provide accommodation on the site of sufficient size to hold site meetings between

the Contractor and Principal or arrange for the use of a suitable facility on site for such meetings.

The Contractor shall be available for site meetings which are to occur at regular intervals throughout the

contract period and shall liaise with the Principal or Principal’s representative on suitable meeting

times.

1.111 Site Telephone & Fax

The Contractor shall provide either a satellite telephone, mobile telephone or a telephone service on site

or elsewhere to allow for effective communication with the Principal and pay the relevant installation,

rental, calls and removal costs.

1.112 Light & Power

The Contractor shall make arrangements, if required, for a temporary electric light and power supply

during construction. The Contractor shall provide sufficient supplies of each as required for execution

of work specified.

Where construction occurs on an Outstation serviced by a wind, solar or hybrid power generation

system the Contractor shall provide independent power generation equipment.

1.113 Water

The Contractor shall make arrangements through the Shire Service Manager or PowerWater, if

required, for the provision of and maintain a temporary water supply sufficient for executing the work

under the contract. The Contractor shall disconnect and clear away same on completion and may be

required to pay costs and charges in connection therewith.

1.114 General Product Compliance

The Contractor shall:

a) Provide products which comply with requirements, and which are undamaged and unused at

time of installation, and which are complete with accessories, trim, finish, features required by

Page 4: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Preliminaries Page F4

regulation, and other devices and details needed for a complete installation and for intended

use and effect.

b) Where they are available provide standard products of types that have been produced and used

previously and successfully on other projects and in similar applications.

c) Provide continued availability of the product, wherever possible, for the Principal. The

Contractor shall where additional amounts of a product, by its application, are likely to be

needed by Principal at a later date for maintenance and repair or replacement work, provide a

standard, domestically produced product which is likely to be available to Principal at such

later date.

d) Comply with Manufacturer’s recommendations: Where installations include manufactured

products, the Contractor shall comply with manufacturer’s current and applicable

recommendations for installation, to whatever extent these are more explicit or more stringent

than applicable requirements indicated in the Technical Specification or other parts of the

Tender Documents.

e) At completion of the project, provide to the Principal a copy of each set of Manufacturer’s

recommendations that have been used in the work of each trade.

f) Manufacturer’s Data Sheets: Where the Technical Specification requires, obtain two copies of

the current data sheets issued by the manufacturer of the specified component. Retain one copy

for use on site and submit the other to the Principal as a record of instructions followed on the

site.

1.115 Waste Disposal

The Contractor shall dispose of all solid and inert builder’s waste by removal from site to a suitable

waste disposal facility.

Where an existing Community land-fill disposal pit is sought to be used, prior approval shall be

obtained from the Shire Service Manager. Any fees that apply shall be paid by the Contractor.

Where an existing Community land-fill site is used, waste shall be compacted and a light soil cover

shall be provided to prevent windblown distribution and vermin access. Cost of disposal shall be based

on volumetric measure at current and applicable rates. Steel, non ferrous metals and other recyclable

materials shall be segregated from waste to landfill and stockpiled in an approved location. Where

inadequate deposition and separation of waste occurs the cost of reinstatement shall be borne by the

Contractor.

Restricted and prohibited waste including chemical and non-inert products (including paints, solvents,

cleaners, acids, adhesives, asbestos etc.) are to be removed from the Community and disposed of in

accordance with Environmental Protection Authority guidelines.

1.116 Key Labelling

The Contractor shall label keys for locks by embossing or engraving the individual keys with the lock

code and provide these in triplicate to the Principal, as required or at Practical Completion. Each set of

keys is to be attached to a key ring and key tag labelled with the site number.

1.117 Contractor’s Accommodation

The Contractor shall be responsible for arranging their own accommodation and food requirements.

The Contractor shall obtain approval for the location of the accommodation and other related

arrangement through the Shire Service Manager.

1.118 Final Cleaning

The Contractor is responsible for ‘Final Cleaning’ of the works and the site area. The Contractor shall,

prior to Practical Completion, provide final cleaning of the works and site area that are specified in the

Technical Specification or elsewhere in the Tender Documents. The cleaning standard required will be

the cleaning of each surface or unit of work to a normal 'clean' condition expected from a first class

building cleaning and maintenance program.

Examples of the required cleaning are:

(a) Remove labels, which are not, required as permanent labels.

(b) Clean transparent materials, including mirrors and window/door glass, to a polished condition,

removing substances which are noticeable as vision-obscuring materials. Replace broken glass

and damaged transparent materials.

Page 5: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Preliminaries Page F5

(c) Clean exposed exterior and interior hard surfaces finished, to a dirt free condition, free of dust,

stains, fingermarks, films and similar noticeable distracting substances. Except as otherwise

indicated, avoid disturbance of natural weathering of exterior surfaces. Restore reflective

surfaces to original reflective condition.

(d) Wipe clean surface of mechanical and electrical equipment, remove excess lubrication and

other substances.

(e) Remove debris and surface dust from limited access spaces.

(f) Clean concrete floors broom clean.

(g) Sweep and mop resilient flooring and tiled surfaces.

(h) Clean plumbing fixtures to a sanitary and polished condition, and free of stains including those

resulting from water exposure.

(i) Clean light fixtures and lamps so as to function with full efficiency.

(j) If permanent lighting fixtures have been used for works purposes replace globes with new.

(k) Clean project site, including planted sections and footpaths where applicable, of litter and

foreign substances. Sweep paved areas to a broom clean condition; remove stains, petro-

chemical spills and other foreign deposits.

(l) Be responsible for maintaining clean roads and access. Remove and clean away mud and

building debris from footpaths, gutters, drains, walls etc. when such occurs.

1.119 As Constructed Record of Work

The Contractor shall provide the As Constructed Record of Installation to the Principal at Practical

Completion. This shall consist of ‘as constructed’ drawings on marked up site plans showing the in-

ground installation. The contractor shall record on the drawing the invert levels of drains and the

alignment of other underground services.

1.120 Entry Permits

For work performed at locations under the jurisdiction of Central Land Council permit requirements all

contractors, sub-contractors and employees shall obtain and hold a valid entry permit.

Permit holders shall abide by the relevant entry conditions while at such locations.

Page 6: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F – TECHNICAL SPECIFICATION - Demolition Page F6

2 Demolition

PART I GENERAL

2.101 Scope

Refer to Drawings and Schedules for items to be demolished and for requirements which may affect

demolition.

2.102 Related Work

Co-ordinate and Co-operate with the following trades:

Site Preparation – Excavation

Sanitary Plumbing

Sewerage & Drainage

Electrical

2.103 Quality

This work is to be done by specialists with experience in the work.

Where requested by the Principal provide substantiating evidence before starting work.

2.104 References

Comply with applicable portions of the following Australian Standards:

AS 2436 1981 Guide to noise control ... and demolition sites

AS 2601 1991 The demolition of structures

Comply also with the requirements of applicable building regulations, local council requirements or the

requirements of other relevant Statutory or Regulatory authorities having jurisdiction.

2.105 Public and Property Protection

Provide measures required by municipal and state ordinances, laws, and regulations for the protection

of surrounding property, footpaths, streets, kerbs, the public, occupants and workers during demolition

operations. Comply with the above ordinances, laws etc. in carrying out measures including barricades,

fences, warning lights and signs, rubbish chutes, etc.

No blasting for demolition purposes will be permitted.

Exercise due care in executing this work.

Make good to original condition, damage to structures to be retained and to adjacent property that

results from demolition operations.

Perform restoration work without expense to the Principal.

2.106 Fees

Pay fees due to authority requiring same in connection with the work of this section.

2.107 Services

Before demolishing and removing parts of building having electrical wiring, gas and water pipes,

conduit or similar items embedded in them, notify the Principal and authorities having jurisdiction, and

make sure that these items are out of service so that they can be removed without danger.

PART II MATERIALS

2.201 Demolished Materials

Material required to be demolished becomes the property of the Contractor (except items specifically

referred to in the schedules). Remove from the site and dispose of in accordance with EPA guidelines.

Where indicated on Drawings or Schedules that materials are to be salvaged for re-use. Materials for

salvage are to be removed to a local storage site to the approval of the Principal and Shire Service

Manager.

2.202 Equipment

Supply equipment required to perform the work of sufficient capacity to meet the stated completion

date.

Provide disposal containers for disposal required.

Page 7: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F – TECHNICAL SPECIFICATION - Demolition Page F7

No containers may be located on public streets or pavements without obtaining approval of the

Principal, Local Authorities and Shire Service Manager. Co-operate with Sub-Contractors doing work

in or near container locations to prevent disruption of their work.

PART III EXECUTION

2.301 Examine the Site Conditions

Examine carefully the site conditions before starting work and confirm that they are as specified and as

indicated on drawings. Start of work means total acceptance of conditions.

2.302 Existing Reinforced Concrete

Neatly cut back or trim to new alignment with a clean true face on material to be retained. Cut with

diamond saw where necessary.

2.303 Shoring

Provide necessary shoring in accordance with industry standards.

Alter, adapt, and maintain temporary works as necessary, and strike or withdraw them progressively as

the work proceeds. Obtain the written consent of the Principal if such works are to be left in position at

the completion of the work.

2.304 Exposed Excavations

Leave excavations open after removal of work below ground level until completion of inspection by

Principal.

2.305 Methods and Operations

Demolish and remove completely those parts of the structure listed and/or drawn for demolition. The

methods of cutting and removal of floors, walls, and other items to be removed are to be approved by

authorities having jurisdiction.

Furnish flame-cutting required to dismantle sections of equipment too large to be otherwise removed.

Flame-cutting is to be performed only by experienced and qualified mechanics. Protect combustible

surfaces during flame cutting. Maintain fire extinguishers, required by the Fire Authority at hand during

flame-cutting operations.

Do not drop or throw material more than 5 metres. Lower by means of hoists or rubbish chutes. Wet

down thoroughly during demolition to prevent nuisance of dirt and dust. Equip trucks used in hauling

debris with tarpaulins to cover the loads. Do not load so excessively as to spill debris on streets.

Except when placed in approved disposal containers, do not allow combustible material and rubbish to

accumulate on the site. Remove daily, or as directed. Burn no debris on site.

Upon completion of wrecking and demolition and the removal of rubbish and debris, remove equipment

used for this work.

2.306 Reinstatement

Restore to original condition, without expense to the Principal any damage to remaining construction

resulting from failure to provide adequate protection. Backfill and grade hollows, holes or inundations.

2.307 Completion

Complete contracted work and leave the site in an entirely clean condition, ready for the work of other

trades.

Page 8: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Asbestos Removal & Disposal Page F8

3 Asbestos Removal & Disposal

PART I GENERAL

3.101 Scope

Refer to the Schedules for the identification of asbestos removal and disposal as work under contract.

Where such work has not been identified this Section applies to Variation Orders or incidental work.

The work of this Section includes but is not limited to:

Identification, removal and safe disposal of materials found on the site containing asbestos fibres. Refer

to Drawings and Schedules supplied as part of the contract documents. Non-friable asbestos containing

products generally, but not limited to asbestos-cement products. Examine relevant documents for

requirements which will affect the work of this Section.

Disposal of materials containing asbestos is to be at a licensed asbestos cement disposal site as detailed

in the Schedule or alternative as approved by the Principal.

3.102 Related Work

A. Co-ordination: Co-ordinate with other trades affecting or affected by the work of this Section.

Co-operate as necessary to ensure steady and satisfactory progress of the work.

B. Unit prices: Submit with tender a Schedule of rates for work required to be done not identified

at time of tender. The Schedule of rates is required to reflect costs on a square metre rate for

sheets or panels to be removed and on a metre run basis for other work. Such costs are to cover

work referred to in Clause 3.101 above.

3.103 Quality Assurance

A. Registration of Asbestos Removalists. Comply with Part 10 of ‘ASBESTOS: GUIDE TO

THE CONTROL OF ASBESTOS HAZARD IN BUILDINGS AND STRUCTURES.’

B. Submit evidence, in Section C Tender Response Forms Item F of the training and experience

of those who will be performing the required work.

C. Comply with CODE OF PRACTICE Parts 1.4 and 1.5.

D. Supply names of contacts, with telephone numbers, who can verify performance quality.

3.104 References

Perform asbestos removal in accordance with:

A. CODE OF PRACTICE for the SAFE REMOVAL OF ASBESTOS, AUGUST 1988, which is

part of Clause 3.104B.

B. ASBESTOS: CODE OF PRACTICE and GUIDANCE NOTES produced for WORK SAFE

AUSTRALIA (National Occupational Health and Safety Commission), published by

Australian Government Publishing Service, Canberra. Web Address:

www.nohsc.gov.au/OHSInformation/NOHSCPublications/

C. Relevant State Government Department or State Statutory Authority, which has jurisdiction

over the work of this Section, and which is in force at the time of tendering.

• Occupational Health, Safety & Welfare Act 1986

• Occupational Health, Safety & Welfare Regulations 1995

• Code of Practice for the Safe Removal of Asbestos

• Code of Practice for Asbestos Removal Work (Excluding Removal)

• Environmental Protection Agency Technical Bulletin No.1 March 2000

• Dangerous Substances Act 1975

• Dangerous Substances Regulations 1998

• Health Act 1935

• Waste Management Commission Act 1979

• (Construction Safety) Regulations 1987

• Australian Standards AS1716 Respirators for Asbestos Work

• Australian Standards AS1319 Safety Signs for the Occupational Environment

Page 9: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Asbestos Removal & Disposal Page F9

• Australian Standards AS3544 Industrial Vacuum Cleaners for Particulates Hazardous

to Health

• Australian Standards AS1324 High Efficiency Particulate Air (HEPA)

• EPA Guidelines ‘Waste containing asbestos – removal, transport and disposal’

October 2002.

3.105 Submissions

A. Submit as and when required all of the reports and submissions required by the Statutory

Authorities referred to in Clause 3.104 above.

B. Submit the data required in CODE OF PRACTICE Part 1.2 as detailed in Tender Response

Forms.

C. Submit tenders conforming with documents referred to in Clause 3.104.

3.106 Planning and Programming

A. Comply with CODE OF PRACTICE Clause 1.3.

B. Arrange for and attend a Pre-demolition Conference. Abide by decisions and Schedules

established at such conference.

C. Obtain approvals prior to commencement

3.107 Documents Required on Site (as applicable)

A. Copy of Asbestos Removal Application

B. Copy of Asbestos Removal Approval

C. Copy of Air Monitoring Program

D. Safe Work Procedures/ Work plans/ Job Safety Analysis

3.108 Project Site Control

Unrestricted access to the site shall be available for the duration of the work under contract. Secure the

site using temporary fencing, barricades or the like to prevent entry of persons other than those engaged

in the removal of asbestos containing products. Demolition and removal of existing structures and

materials including roofing, external claddings, internal linings, fittings and fixtures may be undertaken

to facilitate removal of asbestos containing products. Fittings and supports may be removed and

disposed of with asbestos containing waste. Control vehicle access and mechanical operations that may

disturb asbestos containing products.

3.109 Notices and Fees

Provide notices to Statutory Authority which needs data relating to asbestos removal. Pay fees due to

any Statutory Authority which require, by law, fees to be paid.

3.110 Signage

Provide approved signage and labels as necessary, conforming to AS1319, warning of the presence of

asbestos and so placed as to be clearly visible.

PART II EQUIPMENT

3.201 Decontamination Facilities

Where required by regulations of the controlling Statutory Authority, provide appropriate

decontamination facilities as described in CODE OF PRACTICE (ASBESTOS) Part 2.3 OR Part 2.4.

3.202 General Hygiene Requirements

Where required by regulation of the controlling Statutory Authority, comply with General Hygiene

Requirements, CODE OF PRACTICE Part 5.

3.203 Protective Clothing and Equipment

Where required by regulations of the controlling Statutory Authority, comply with Protective Clothing

and Equipment, CODE OF PRACTICE Part 6.

NOTE: The use of glove-bags is described and should be used where necessary in accordance with

CODE OF PRACTICE Part 4.

Page 10: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Asbestos Removal & Disposal Page F10

3.204 Labelling and Warning Signs

Provide necessary labels and warning signs in accordance with the requirements of Part 12 of ‘GUIDE

TO THE CONTROL OF ASBESTOS HAZARDS IN BUILDINGS AND STRUCTURES.’

3.205 Tools and Equipment

Provide tools and equipment necessary for the work. Refer to Part 3 and Clauses 3.1, 3.2, 3.3, 3.4, 3.5

and 3.6 of the CODE OF PRACTICE (ASBESTOS).

PART III EXECUTION

3.301 Examination

A. Inspect relevant site conditions.

B. Establish conditions which may be discovered relevant to asbestos removal without disturbing

material containing asbestos.

C. Start of work means total acceptance of conditions.

3.302 Preparation

A. Prepare for asbestos removal in full accordance with the requirements of Part 2 ‘Preparation of

the Removal Site for a major removal program’ of the CODE OF PRACTICE (ASBESTOS).

Note and comply particularly with Clauses 2.1, 2.2 and 2.2.1.

B. Install Decontamination Facilities in a location agreed upon with the Principal and other

relevant Parties.

C. Install required Labelling and Warning signs. Refer Clause 3.204 above.

D. Remove from the work area items which may be damaged by the work of this Section. Items

identified for salvage as identified in the relevant Schedule are to be transported to the

nominated local depot within the community.

E. Protect item of furniture, surface, equipment or plant which may be damaged or soiled during

the preparation for and action of asbestos removal. Be responsible for damage resulting from

asbestos removal actions, processes and other works.

3.303 Asbestos Removal

A. Advise the Principal in advance of proposed removal methods.

B. Comply with the requirements of CODE OF PRACTICE (ASBESTOS) and with the

instructions of the authorised Principal of the work.

C. Removal techniques. Comply with Part 4 and/or Part 9 of CODE OF PRACTICE

(ASBESTOS). Note requirements that sheet materials to be wetted to reduce dust. Note

requirement that sheet materials be removed with minimal breakage, and be lowered to ground

not dropped.

3.304 Monitoring of Airborne Asbestos

Comply with Part 7 of CODE OF PRACTICE (ASBESTOS).

3.305 Field Quality Control

Work will be performed under the supervision of an authorised Supervisor. Comply with his

requirements which are in accordance with the CODE OF PRACTICE, and other requirements to which

parties have agreed.

3.306 Dismantling of Asbestos Removal Area

Comply with Part 8 of CODE OF PRACTICE (ASBESTOS).

3.307 Removal of Asbestos Material From Site

Remove all asbestos materials from the demolition site to the disposal approved by the Principal.

Comply with requirements of the Authorities.

Remove such materials to the approved location.

3.308 Reinstallation

Reinstall all items to be retained or relocated. No items containing asbestos are to be reinstalled.

3.309 Cleaning

Thoroughly clean areas in which work has been performed and those adjacent to the work area.

Page 11: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Asbestos Removal & Disposal Page F11

Remove and dispose of traces of the asbestos removal process, protective materials, etc.

Pick up all pieces of asbestos cement sheeting found within the site boundary and within the immediate

vicinity.

3.310 Completion

Complete contracted work in accordance with contract documents and written variation orders issued

by the Principal. Leave the site in a condition suitable for the work of other trades, in co-operation with

the Principal and Contractor.

3.311 Certification

Provide receipts and certification of disposal to the Principal on completion.

Page 12: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Site Preparation & Excavation Page F12

4 Site Preparation & Excavation

PART I GENERAL

4.101 Scope

Refer to Drawings & Schedules for extent of work related to this section.

The work of this section comprises but is not limited to excavation, disposal of surplus excavated

material both on and off the site, supply of compaction and filling material and the preparation

necessary to bring the areas to correct shape and level prior to building construction, and including the

supply and installation of waterproofing membrane.

4.102 Related Work

Co-ordinate and co-operate with the following trades:

Concrete

Sanitary Plumbing

Electrical

4.103 Quality

This work is to be done by specialists with experience in the work.

Where requested by the Principal provide substantiating evidence before starting work.

4.104 References

A. Comply with applicable portions of the following Australian Standards:

AS 1289 Methods of testing soils for engineering purposes. There are 40 sections

additional to this standard; each refers to a specific application.

AS 2187 Explosives - storage, transport and use.

AS 2187.2 1993 Use of explosives.

AS 3798 1996 Guidelines on earthworks for commercial and residential developments.

AS/NZS 4200 1994 Pliable building membranes and underlays. This standard has two additional

parts.

Comply with particular specifications in Building Regulations and/or Local Council publications.

B. Definitions

Rock: natural or artificial material encountered in the excavation which cannot be removed with a 75

kw backhoe of good working condition and operated by an experienced competent operator until

broken up by mechanical means such as rippers, jack-hammers or percussion drills.

Rippable Rock: massive pieces of rock equal to or exceeding 0.5 cubic metres with a smallest

dimension that exceeds 0.75m and that cannot be excavated at a rate exceeding 4.0m3 (bank) per hour

with a 75 kw backhoe of good working condition and operated by an experienced competent operator.

Non-Rippable Rock: Means all other rock.

Other than Rock: Other material encountered in excavation.

Sub-Grade: The natural ground below the excavations.

Filling: A general term for material spread and compacted over the sub-grade to make up finished

levels or levels to the under-side of the base.

Sub-Base: Selected filling spread and compacted over the sub-grade to make up levels to the underside

of the base.

Base: A selected filling layer spread and compacted to form an acceptable working surface directly

under the building.

4.105 Approval for Variations

Before starting excavation work which may involve a variation (whether addition or deduction) because

of the nature of the material to be excavated, obtain a determination as to the nature of the material from

the Principal. The variation is derived from the determination. If no prior determination has been

obtained, the variation, if any, is to be made only at the discretion of the Principal. The Contractor shall

measure and record the volumes, locations and horizon depths of rock that are encountered. Where the

Principal is unable to attend on site at the time rock is encountered to quantify volumes, the excavated

Page 13: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Site Preparation & Excavation Page F13

rock is to be stockpiled adjacent to the site for a period negotiated between the Contractor and the

Principal to enable the Principal to determine the nature of the material and the volumes.

4.106 Site Clearing

Remove from site progressively any debris or growth which may constitute a fire hazard.

4.107 Use of Explosives

Do not use Explosives.

4.108 Protection of trees

Do not remove any tree unless it is located within 1 metre of the construction footprint or it is identified

in the Documents or prior approval is given by the Principal.

Protect from damage the trees and shrubs that are to be retained including those beyond the site area,

both above and below ground.

Give notice to the Principal and obtain instruction before repair of trees damaged during the work.

4.109 Work Near Trees

Take necessary precautions to protect trees specified or shown to be retained from damage by

groundworks, including the following:

A. Do not store, stockpile, dump, or otherwise place under or near trees, bulk and harmful

materials including oil, paint, waste concrete, boulders and the like. Do not place spoil from

excavations against tree trunks, even for short periods. Prevent wind-blown materials such as

cement from harming trees and plants.

B. Prevent damage to tree bark. Do not attach stays, guys and the like to trees.

C. Do not remove topsoil from within the foliage line of trees specified. If it is necessary to

excavate within the foliage line, use hand methods so that root systems are preserved intact and

undamaged. Open up excavations under tree foliage for as short a period as possible.

D. Do not cut tree roots exceeding 50 mm diameter unless necessary. Where it is necessary to cut

tree roots, use an axe or chain saw or similar means such that the cutting does not unduly

disturb or rock the remaining root system. Immediately after cutting, apply an approved

bituminous fungicidal sealant to the cut surface to prevent the incursion of rot or disease.

E. Avoid compaction of the ground under trees. If the ground under trees has been unduly

compacted during the work under Contract, for example for the operation of heavy

constructional plant, loosen the soil by coring.

F. Carry out coring by forming 75 mm diameter, 300 mm deep core holes at 900 mm centres for

the whole of the area affected and backfilling the core holes with sand watered in.

4.110 Site Investigation

The information given in the any attached report, or shown on the Drawings, or both, is information on

the nature of the ground at each tested part. It is not a complete description of conditions existing below

the surface. The accuracy of the information is not guaranteed and will not be a basis for cost variation.

4.111 Provisional Depths

The footing or strip depths shown in any attached Engineer’s Report or on the Drawings are the

minimum requirements. Approval of the Engineer and Principal is required for any variation to these

depths. If there have been variations to the Contract levels or dimensions of excavations, do not

commence back-filling or place permanent work in excavations until the Principal has given approval.

4.112 Site Management

Inspection: Give the Principal the prescribed notice that the following are ready for inspection:

A. rock encountered in the excavations

B. excavation completed to Contract levels

C. filling completed to Contract levels

D. completed placement of waterproof membrane.

4.113 Grading of Site

Grade soil away from the structure at a minimum grade of 2% for a minimum distance of 3 metres.

Page 14: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Site Preparation & Excavation Page F14

PART II MATERIALS

4.201 Filling

Provide suitable compactable fill as required.

Where suitable fill is available at the Community the Contractor shall obtain and forward to the

Principal written approval from the Shire Service Manager for the use of local materials. A Contract

price variation may be applied following an assessment by the Principal. Following removal of fill the

site will be reinstated and all cuts battered to a slope not exceeding one vertical unit to three horizontal

units.

The Contractor shall bear the cost of transporting the fill to each site.

4.202 Water-proof Membrane

Approved flexible polymeric film 0.3mm thick conforming to AS/NZS 4200 shall be used. Deliver

underlays to the site in suitable protective packaging, bearing the name of the manufacturer. Handle and

store the underlay so that it is not punctured, torn or otherwise damaged. Comply with AS/NZS 4200

PART III EXECUTION

4.301 Examine all Conditions

Start of work means total acceptance of conditions.

4.302 Excavations Generally

Suspend ground works during inclement weather which would result in unsatisfactory work.

Excavate accurately to shape and profile and keep free from loose earth and stones.

Excavate generally as required or as shown on the Drawings, including but not necessarily limited to

the following:

A. Cutting back of plant roots at the face of the trench and treating with an approved bituminous

fungicide.

B. Removal of footings and unnatural items to 900mm below grade.

C. Preparation of sub-grade as necessary.

D. Trim the sub-grade surface evenly to the profiles shown on the Drawings.

E. Make allowance for settlement and compaction.

F. Allow for falls in slabs on grade to streets, lanes and outlets.

G. Prepare for underground services, referred to in other Sections of the Specification.

H. Prepare for strip footings, footing beams, pad footings, ducts and pits, to depths shown.

Carry out additional excavation where necessary to permit full use of suitable mechanical equipment

(eg. rippers) and back-fill with appropriate material as specified in this Section.

Where excavation exceeds the required depth, fill back to correct depth with material as follows:

I. below slabs on ground: Filling

J. below footings, beams and other structural elements: Concrete of strength equal to the

structural element, minimum 20MPa.

K. In service trenches: approved compacted pipe bedding material.

L. below septic tanks on sub-grade: Filling

M. below drains: Base.

4.303 Design Levels

Unless otherwise specified graded soil levels shall be 300mm below finished floor level.

4.304 Dog Proofing

Where identified in Drawings or Schedules all external perimeters to concrete slabs and paving shall be

dog-proofed.

Excavations for strip footings shall be a minimum of 300mm below adjacent finished ground levels.

Alternatively include provision for a lean-mix dog proof beam 200mm wide and a minimum of 300mm

below finished ground level and located under or immediately adjacent edges of concrete floors.

Page 15: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Site Preparation & Excavation Page F15

Include provision for a dog proof beam 200mm wide and a minimum of 300mm below finished ground

level and located under edges of concrete paving and concrete pads.

Where the fall of the ground requires steps in strip footings excavate additionally to accommodate the

minimum depth.

Suspended floors also require the provision of dog proofing.

4.305 Pier Excavations

All pier bores shall be poured within 24 hours of being drilled unless otherwise approved by the

Principal.

On completion of boring provide timber or steel cover plates and leave in position until concrete pour

commences.

Grade around bore holes to prevent entry of surface water.

4.306 Services Excavations

Excavations shall be as narrow as practicable but generally with a bedding width not less than 200mm

plus the diameter of pipe.

Trenches shall be at the required service grade and levels. Clean sand bedding material shall generally

be not less than 75mm. Backfill with and compact with clean sand.

4.307 Adjacent Areas

Restore disturbed areas outside the limit of the Works to their original condition and levels, without

subsidence or cracking at junctions with existing surfaces.

Obtain approval of appropriate owner prior to commencing work beyond the site boundary.

4.308 Bad Ground

Should unsuitable material be encountered at the prescribed depths of excavation, or soft, wet and

unstable areas develop during excavation, obtain instructions from the Principal before carrying out

additional excavations. Back-fill and compact to the correct levels as directed.

4.309 Existing Services

Remove existing services and seal adjacent to the service main. Where sealing adjacent to the service

main is not practical seal beyond the site boundaries.

Before demolishing and removing parts of building having electrical wiring, gas and water pipes,

conduit or similar items embedded in them, notify the Principal and Authorities having jurisdiction, and

make sure that these items are out of service so that they can be removed without danger.

4.310 De-Watering

Maintain excavations, levelled and filled areas free of water by temporary catch drains, sumps,

pumping, bailing or whatever means are suitable and effective.

Immediately before placing concrete or masonry on ground remove free water and foreign matter.

Prevent water flow over freshly laid work.

4.311 Shoring

Provide shoring, planking and strutting necessary to retain the sides of the excavations and to ensure

safe working. Provide safety covers over holes. Provide necessary needling, shoring and strutting to

adjacent buildings.

Guard against the formation of voids outside sheeting or sheet piling if used and should voids form, fill

and consolidate them to approval.

4.312 Filling Schedule

Fill generally as required or as shown on the Drawings, and as follows:

Under concrete floor slabs cast on ground:

First 25mm below slab: clean sand blinding.

Base: appropriate selected excavated material, maximum aggregate size DN40,

compacted in layers not exceeding 150mm to required depth for non-

suspended slab.

Sub-base: appropriate excavated material compacted in layers not exceeding 150mm

over sub-grade for non-suspended slabs.

Back-fill: appropriate excavated material compacted in layers not exceeding 150mm

Page 16: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Site Preparation & Excavation Page F16

over sub-grade for non-suspended slabs as required.

To retaining walls or

walls below grade:

free draining granular material.

Under Septic Tank

Above Sub-grade: Compacted filling, depth as required.

First 50mm below tank: Compacted sand base.

To Top of tank: Compacted sand base.

Backfill: Compacted clean excavated material from site maximum aggregate size

DN40 or filling maximum aggregate size DN40.

Under Septic Tank Coverslab (Large sized 2400mm x 1500mm)

Above Backfill: Compacted sand base 30mm.

Above Sand Base to

Splay on Coverslab

(ground level):

Clean excavated material from site maximum aggregate size DN20 or

filling maximum aggregate size DN20.

Drains:

Above Sub-grade: Compacted clean sand base 75mm.

Side Support: Compacted clean sand base 100mm min.

Pipe Overlay: Compacted clean sand base.

Backfill: Clean excavated material from site maximum aggregate size DN20 or

filling maximum aggregate size DN20 or clean sand base.

4.313 Bearing Surfaces in Rock

Where structural loads bear on rock, unless otherwise specified, scabble the rock face to give even

plane bearing surfaces, level unless required to be sloping or stepped.

Bored pier holes are to be taken a minimum of 150mm below the rock surface and the bottoms cleaned

of loose matter.

4.314 Compaction

Place filling in layers not exceeding 150mm deep when measured loose.

Mechanical compaction or hand tamp against ground or perimeter beams or walls.

Compact each layer of filling to obtain a uniform density of not less than 95% of the standard dry

density at optimum moisture content as determined by the Dry Density/Moisture Content tests set out in

AS 1289.

Finish the base to the following tolerances:

Variation from designed level: 5mm

Variation from 3000mm straight edge: 5mm

4.315 Waterproof Membrane

Lay on approved sand blinding - Refer Clause 4.202 herein. Where necessary, cut sheets to maximum

practical width, to suit the layout, and arrange laps to face away from the direction of the pour.

Provide laps as recommended by the manufacturer, but not less than 300mm. Seal laps with ‘Scribal

330’ 48mm wide PVC tape or equal approved and as recommended by the manufacturer of the underlay

and ensure that the adhered surface of the underlay is dry and clean.

Take the underlay up walls to level of top of future concrete slab or as otherwise instructed. Seal service

pipes and similar elements when they penetrate the underlay. Allow ample slack to avoid pulling at tape

junctions.

Cover vertical or inclined surfaces in an unbroken sheet where possible. Otherwise arrange laps

vertically to avoid pulling at joints. Fix at the top with tape or other recommended fixing.

Inspect membrane after laying and before concrete is poured. Patch and seal punctures.

4.316 Maintenance of Membranes and Underlays

Maintain the membrane or underlays in their best possible condition throughout the construction period.

Repair immediately any damage which does occur.

Page 17: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Site Preparation & Excavation Page F17

4.317 Clean Up

On completion of work specified above, remove surplus materials imported to the site to a location

approved by the Principal and Shire Service Manager. Level off surplus excavated material, or pile such

material on the site as directed by the Principal.

Page 18: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Plumber: Sanitary, Sewerage & Drainage Page F18

5 Plumber: Sanitary, Sewerage, Water Supply and Drainage

PART I GENERAL

5.101 Scope

Refer to Drawings & Schedules for extent of work related to this section.

The work of this section includes but is not limited to, supplying and fixing of complete septic tank and

sanitary systems and dry pit toilets plus the reticulation of cold and hot water and LP gas including

associated isolating valves, stop taps and outlets and fittings.

5.102 Related Work

Co-ordinate and co-operate with the following trades:

Site Preparation – Excavation

Sewerage and drainage

Schedule of Sanitary Items

Ceramic tile

Electrical

Finishing trades

Except where otherwise specified ensure that all required penetration openings are provided and that all

pipes, vents, fixings and fittings are installed progressively as the work proceeds.

5.103 Quality

Perform the work of this section using tradesmen whose experience and skills meet the requirements of

controlling statutory authorities and in accordance with the site-specific approval of the Department of

Health and Families - Environmental Health as applicable.

5.104 Special Requirements

Not applicable.

5.105 References

Comply with applicable portions of the following Australian Standards:

AS/NZS 1260 1996 PVC Pipes and fittings for wastes and vents applications

AS 2031 – 1977 Installation of UPVC pipe systems

AS/NZS 2030: 2008 Installation of polyethylene pipe systems

AS 1357 Water supply – Valves for use with un-vented water heaters

1357.1 1992 Protection valves

AS 1432 1996 Copper tubing for plumbing gas fitting and drainage applications

AS/NZS 1730 1996 Wash basins

AS 3500 National Plumbing and Drainage Code

3500.0 1995 Glossary of terms

3500.1 1992 Water supply

3500.2 1990 Sanitary plumbing and sanitary drainage

3500.3 1990 Stormwater drainage

3500.4 1994 Hot water supply systems. Two new parts issued 1997

Comply with requirements of statutory authorities having jurisdiction.

Gas installation shall comply with the current code AG601 of the Australian Gas Association

Waste Control System shall comply with the Department of Health and Families – Environmental

Health’s CODE OF PRACTICE FOR SMALL ON-SITE SEWAGE AND SULLAGE TREATMENT

SYSTEMS AND THE DISPOSAL OR REUSE OF SEWAGE EFFLUENT .

5.106 Precedence

Work shall be carried out in accordance with all relevant codes except that this specification shall take

precedence where it requires a higher standard than that required by the Code.

Page 19: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Plumber: Sanitary, Sewerage & Drainage Page F19

5.107 Submissions

Before ordering scheduled material, submit required product data to the Principal, specifically where

the specified material is not available and alternatives are offered.

5.108 Fees & Notices

Pay fees to the relevant statutory authorities. Provide Certificate of Compliance prior to Practical

Completion.

5.109 As Built Drawings

Provide marked up copies of site and or floor plans showing as constructed details. Comply with special

conditions of contract as applicable.

PART II MATERIALS

5.201 Acceptable Manufacturers

Refer to Schedule for Sanitary Items and materials for water supply.

Ensure that items to be installed are approved for installation by local authorities before ordering.

5.202 Materials

Water Supply:

A. Material: Polyethylene (PE) DN25 PN16

B. Jointing: Butt thermal fusion, electrofusion couplings, or with compression fittings

Tubing for Cold Water:

A. Material: Copper Type A to AS 1432; uPVC DN25 Class 12.

B. Jointing:Capillary, brazed or compression fittings for copper; solvent cement joints for uPVC.

Tubing for Hot Water:

A. Material: Copper Type A to AS 1432

B. Jointing: Capillary, brazed or compression fittings

C. Insulation: Through concrete with hair felt or as approved. Bradflex or Polylag to all exposed

sections.

Tubing for Drainage from Fittings:

A. Material: uPVC

B. Jointing: Solvent-welded

Tubing for Gas Service:

A. Material: Copper

B. Jointing: Capillary, brazed or threaded

Do not use Kingcos. All terminal fittings shall be brass.

Breeching pieces for tap sets and connectors for pillar and bibcocks to be included.

5.203 Equipment

Provide necessary equipment to effect a complete installation of each part of this section, including

seals, jointing materials, flanges, etc.

5.204 Fabrication

Fabricate components in a manner approved by the local authority and the Principal. Comply with

requirements of relevant Australian Standards where applicable.

PART III EXECUTION

5.301 Examination

Visit the site before delivery of materials, and compare conditions with those shown on drawings.

Start of work means total acceptance of conditions.

5.302 Connections to Supply

Provide connection to supply at PowerWater meter.

Page 20: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Plumber: Sanitary, Sewerage & Drainage Page F20

Where indicated in the Schedule or on site plans that there is no existing service connection commission

PowerWater to provide a service connection.

On outstations not subject to PowerWater services provide connection to mainwater in equivalent

pipework, minimum size NB25. Provide isolation valve at 600mm above ground to building adjacent to

wet areas. All pipework above ground to saddled to supports and to be either copper or galvanised steel.

Provide compression or barrel unions prior to the isolation valve.

5.303 Water Supply Piping Installation

Polyethylene Pipes:

All underground pipework except for pipes laid under a building shall be laid at a depth of no less than

600mm from the existing ground level and not more than 1200mm. If this requirement cannot be made,

then the Principal should be notified.

The pipe shall be bedded and covered in sand to protect it from being penetrated by sharp objects.

Where sand or other non-cohesive material is not readily available, Crusher screening shall be used

with the prior approval of the Principal.

Irrespective of foundation, the material to be used for pipe bedding underlay a minimum of 100mm

below the underside of the pipe barrel and socket, side support and overlay to a depth of 150mm above

the pipe as shown in figure 5.1 in AS2032.

On completion, backfill with approved material shall be carefully placed so as not to disturb or damage

the pipe, and shall be brought up evenly on both sides in layers not more than 200mm in depth before

compaction at or near optimum moisture content. Minimum density index shall be 95%.

Copper Pipes:

Support copper pipes at 1200mm centres and secure to the building structure using approved saddles or

straps of compatible material.

Completely isolate copper piping from contact with galvanised metal framing.

Conceal pipes wherever practicable in wall cavity or chases. Where unavoidably exposed provide

chromium plated pipes and fittings.

Pipework to outlets occurring on internal masonry walls shall be chased or built horizontally into

masonry at the required height on the wall side opposite the outlet. Hollow masonry shall not be chased

vertically.

Generally do not embed pipes in concrete floors. Where unavoidably embedded protect pipework with

an inverted galvanised pressed steel angle or other approved means.

Where under floor pipes will be in contact with concrete make provision for expansion by wrapping

hair felt or other approved means.

Outlets shall be set level, firm and square. Outlets and breeching pieces shall have brazed on lugs to

ensure rigid wall fixing.

Bending of pipes shall be in easy sweeps without any restriction that may be caused by bending,

cutting, jointing or securing.

5.304 Cold Water Supply Service

Where indicated on Drawings or in Schedules connect to main water supply through an isolation valve.

Isolation Valve: Isolate water service with DN20 ball type valve fixed externally to wet area at 600mm

above floor level. Refer to drawing detail.

Standpipe: Provide a 20mm dia. galvanised standpipe with 2 x brass 20mm bibcocks fixed to 75mm

dia. galvanised steel post. Provide 900mm diameter and 300mm high concrete ring filled with DN20

aggregate at base of standpipe. Posts are to be capped and shall extend 900mm above ground level and

be embedded in concrete and as indicated on drawings. Refer to site plans for locations.

Cold Water Branches (minimum):

A. Bathroom or Shower Room including WC N18 (15.9mm)

B. Individual fixtures N15 (12.7mm)

C. Kitchen N18

D. Laundry N18

E. HWS stopcock N18

F. Airconditioner N15

Page 21: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Plumber: Sanitary, Sewerage & Drainage Page F21

HWS Supply: Install isolating stopcocks adjacent the cold water inlet of the unit.

5.305 Gas Service

Gas installations shall comply with Installation Code AG601 of the Australian Gas Association for Gas

Burning Appliances and Equipment.

The gas service shall be LP bottled gas complete with all regulators, fittings and the like installed by a

qualified gas fitter. The bottle shall be secured by a chain arrangement. A compliance plate shall be

fixed to the wall above gas bottles.

Ensure that electrical connection is made prior to gas connection.

5.306 Below Ground Installation

Prepare trenches or openings and lay pipes at approved depth on clean creek sand. On completion,

back-fill with approved material and consolidate as required by the statutory authority and the Principal.

Maintain required distances between pipes of different sorts and between pipes and the structure.

Minimum Cover to pipework:

Copper 450mm

Polyethylene 600mm

UPVC Pressure 600mm

UPVC Drain 300mm at head

5.307 Fabrication and Jointing

Fabricate and join components in accordance with the manufacturer’s instructions and with the

applicable Australian Standards.

Square cut uPVC, deburr, clean with priming fluid, apply solvent cement Type P for pressure

applications, Type N for non-pressure applications, bed spigot to full depth of socket.

Tapping saddles to have a maximum hole size of 1/3 pipe diameter and to be located not less than

300mm from a spigot end, no closer than 450mm to another hole and where there is no significant

bending stress applied to the pipe.

5.308 Installation

Install components in accordance with the manufacturer’s instructions and with the applicable

Australian Standards.

Connect drained fittings and installations to the drain inlets and ensure that interfaces are of appropriate

size and type and are properly sealed. Ensure the drainage of water emanating from appliances to

approved outside locations.

Seal penetrations as needed to achieve a watertight installation.

5.309 Hot Water Service

Carry out the work corresponding to the Hot Water Unit scheduled.

Electric Service:

Provide Quantum Systems P/L Standard Eyre Fan Coil Model No. 340T2EC hot water units including

hot and cold relief valves as recommended by the manufacturer. Provide 100mm thick concrete pad for

external installation. Provide hardwood stringers beneath unit.

Solar Hot Water (bobbin element):

Provide a Solarhart 302J with over temperature protection, set at roof pitch brackets set at 20-30

degrees from horizontal, stone guards and 2400W bobbin element with one shot contactor switch

without LED display connected to thermostat located beside consumer switch board, or other

appropriate location, and with on/off switch in consumer switch board. Orient to unit to north, locate

unit on south side of ridge. Confirm alternative positioning with the Principal.

Solar Hot Water (no element):

Provide a Solarhart 302J with heat dissipator, set at roof pitch brackets set at 20-30 degrees from

horizontal, stone guards. Orient to unit to north, locate unit on south side of ridge. Confirm alternative

positioning with the Principal.

Installation:

Provide discharge of overflows from unit to floor drain, tundish or gully. Provide pressure release

valves, isolation valve and non-return valve. Where required Provide a pressure reduction valve suited

to the unit supplied.

Page 22: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Plumber: Sanitary, Sewerage & Drainage Page F22

Completion:

Ensure the Hot Water Unit is completely filled with water before connection to power supply. Test for

leaks and provide additional strutting if vibration of cold water supply line is apparent. Test water

temperature and adjust thermostat to a maximum of 50 degrees.

5.310 Appliances

Refer to Schedule for type and extent of work. Confirm if gas supply is via mains or bottled LPG.

Gas Stoves:

Provide for the installation and connection of gas stoves where nominated in the Schedule. Install to

manufacturer’s specification. Provide restraining device and anti-tilt brackets. Make good and vermin

proof any penetrations.

Gas Heaters:

Provide for the installation and connection of gas heaters where nominated in the Schedule. Install to

manufacturer’s specification. Make good and vermin proof any penetrations.

5.311 Sanitary Fixtures

Refer to Schedule for type.

General: Supply all relevant items complete with plugs and washers to approved installation.

Sink and Drainer: Fit to sink cupboard and seal to cupboard top with an approved sealant.

Wash Trough: Fix supporting brackets with self tapping screws through studs or noggings (or

alternative fixings as applicable) to wall and fit stainless steel trough. Connect suds-saver into 40mm

wash trough waste outlet.

WC Suite: Bed pan firmly in cement mortar after floor tiling or topping has been completed and seal

fixing holes to approval. Fix cistern to wall and fit flush pipe.

5.312 Cocks and Fittings

Refer to Schedule for type.

Water cocks shall be of approved solid brass construction high pressure types stamped by the water

supply authority. Breeching pieces shall either be cast in dezincification resistant brass or if fabricated

the cock bodies shall be of that material and the tubes of 60/40 brass all fully brazed. Install stainless

steel seats and hydro seal washers to taps, cocks and breeching pieces.

5.313 Sanitary Drainage

Pipes built into or passing through concrete or masonry shall be lagged with an approved flexible

material. Pipes rising above concrete floors shall be capped prior to pouring floor slabs.

Provide inspection shafts to surface at all changes in direction in main run and at not more than 30m

intervals. Provide inspection shafts to all DN100 branches except where an ORG is specified.

Provide a minimum of one ORG to each drainage system. Locate as indicated in drawings.

Terra tape to be laid 150-200mm above drain.

Floor wastes shall be fitted with a 150mm polypropylene grate connected to a 100mm waste pipe

draining to an approved septic waste disposal system.

Minimum Grades:

DN100 Drain 2%min or reduced grade only with the Principal’s approval

DN100 Effluent Drain 1.66%min or reduced grade only with the Principal’s approval

Venting of Drains:

DN50 vent to be installed at the upstream end of the drain between the first and second fixture or to the

upstream end of a branch drain containing a fixture or floor waste gully where the distance between the

weir of the trap and the vented drain exceeds 10 metres.

5.314 Septic Tank

General:

Provide septic tank and effluent disposal system for all dwellings that are not connected to a sewage

system. All work to be completely installed, tested, inspected under water test and passed in accordance

with the installation approval of the Department of Health and Families - Environmental Health and the

approval of the Principal.

Septic Tank:

Unless otherwise identified in Drawings or Schedules, the septic tank shall be an approved precast

concrete type of not less than 3000 litre capacity and 60mm wall thickness. Check tanks and pre-cast

Page 23: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Plumber: Sanitary, Sewerage & Drainage Page F23

concrete products fully for damage on delivery. Reject all damaged items. Provide saddle risers and

increments (as required) to raise to surface. Fix saddle risers to 3000 litre septic tanks and increments to

saddle risers (if required) with construction adhesive conforming to AS2329 (Fosroc Construction

Adhesive or equivalent approved). Provide an approved pre-cast septic coverslab with 600mm diameter

Gatic opening, seal coverslab to riser. Ensure the top of the coverslab is between 100 and 150mm above

natural ground. Backfill to coverslab with slight grade away to prevent stormwater ponding.

Soakage Trench:

Connect each system to common effluent or provide distribution box and soakage trenches in

accordance with the requirements of the Code of practice for small on-site sewage and sullage

treatment systems and the disposal or reuse of sewage effluent. Where impractical to test soil LTAR

provide either: 40 metres of soakage trench 1200mm wide including poly tunnel in 2 x 20 metre runs

(or as indicated on site plans) with the base of soakage trench to be establish according to required

grades and backfilled with DN40 durable aggregate covered with geotextile; or 60 metres of soakage

trench 600mm wide (nom) including Altantis drainage cells in 3 x 20 metre runs wrapped in geotextile.

Provide a precast concrete cover to an inspection shaft to surface at the induct of each soakage trench.

Distribution Box:

Raise distribution box above natural ground level with increments. Set lid on 5mm spacers and seal lid

to increment with silicone sealant to prevent influx of stormwater. Cap unused outlets to distribution

box. Where 3 (or more) soakage trenches are used half cap the third outlet to enable the third soakage

trench to operate as an overflow trench.

5.315 Inspection Shafts to Surface

Provide pre-cast concrete covers with cast iron cover to all inspection shafts. Set all such covers in

concrete bed 600mm x 600mm x 150mm thick. Box out with 200mm diameter collar to uPVC

inspection shaft. Back fill with clean sand.

5.316 Overflow Relief Gullies

Bed ORGs in concrete 150mm minimum depth. Provide pre-cast concrete covers with cast iron grate to

all ORGs. Set all such covers in concrete bed 600mm x 600mm x 150mm thick. Box out with 200mm

diameter collar to uPVC inspection shaft. Back fill with clean sand. Top of ORG to be 75mm min

above finished ground level. Top of ORG to be 150mm min below lowest fixture connected to the

drain. Provide finishing collar.

5.317 Storm Water Installation

Provide site cast stormwater pads beneath down pipes at locations indicated on site plans. Ensure

stormwater is directed away from the building a minimum of 1.2m. Form trenches and bedding to

provide constant falls to outfall or as indicated on drawings. Connect pipes in accordance with the

manufacturer’s instructions. Provide inspection openings, bends, junctions and pits all as indicated on

drawings.

5.318 Testing

Cover no pipes, joints or connections until tested and passed by the relevant authority, and approved by

the Principal.

Submit copies of certificates issued by relevant authorities.

5.319 Protection

Protect work of this section from damage and vehicle traffic until Practical Completion is achieved.

5.320 Completion

On completion, remove debris and clean visible work to the satisfaction of the Principal.

Page 24: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Electrical Installation Page F24

6 Electrical Installation

PART I GENERAL

6.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

The work of this Section includes but is not limited to the design, supply and installation of electrical

transmission and reticulation materials from the mains supply to metered positions and final sub-circuit

installation for power and lighting, requirements to each living unit.

Refer to Drawings and Schedule for installed fittings, items of equipment and work under this section.

6.102 Related Work

Co-ordinate and co-operate with the following trades:

Site Preparation – Excavation

Floor Construction

Wall Construction

Ceiling Construction

Carpenter

Fibre Cement

Air Distribution Ductwork

6.103 Quality

Electrical technicians must be licensed and experienced in the requirements of the project and as

approved by the Principal. Licences are those issued by the State Authority having direct control or

interest in the work.

Perform the entire installation in accordance with the requirements of the Statutory Authority having

jurisdiction.

6.104 References

Comply with applicable portions of the following Australian Standards:

AS 1680 Interior lighting. There are 8 parts to this standard

AS/NZS 2053 Conduits and fittings for electrical installation. There are 8 parts in

this standard

AS/NZS 3000.2000 SAA Wiring Rules. This standard is in constant revision

AS 3786 1993 Smoke alarms

6.105 Submissions

On request of the Principal, submit for approval any item related to the installation, including data

sheets on materials; wiring diagrams - plans; samples of products; licence certificates and obtain written

approval of each item so requested.

6.106 Inspections

Provide notification to the Principal according to the notification schedule before the installation of

trench cabling, the backfilling or concealment of conduits, and at the completion of installation ready

for inspection.

6.107 Confirmation of Supply

Upon taking possession of the site confirm availability of service supply fuse. Notify the Principal

immediately if supply is not available.

6.108 Delivery, Handling and Storage

Deliver, unload and store in a secure area, in accordance with manufacturer's instructions where

applicable, to prevent damage, deterioration and loss.

6.109 Fees and Notices

Pay fees where scheduled. Provide Certificate of Compliance prior to Practical Completion.

6.110 Maximum Peak Load

Provide calculation of maximum peak load to Principal. Where required provide calculation to Power

and Water.

Page 25: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Electrical Installation Page F25

PART II MATERIALS

6.201 General

Supply only products which bear the required indication of approval of the Statutory Authority having

jurisdiction.

At the request of the Principal supply a list of proposed materials, showing the name of manufacturer

where not nominated in the Schedule.

6.202 Cables

Unless otherwise nominated use multi-strand copper conductors.

Minimum size of cables shall be 1.5mm2 for lighting and remote push buttons and 2.5mm

2 for power,

6mm2 for cooker, 16mm

2 for supply otherwise to AS/NZS 3000.2000.

For fixed wiring colour the conductor insulation at the termination points as follows:

Active Single Phase: Red

A Phase: Red

B Phase: White

C Phase: Blue

Switched Active to Fittings: White

Sheathing colour – Flat TPS: White

Circular: Orange

Identify multi-core cables and trefoil groups at each end and at crowded intermediate points with

stamped, non-ferrous tags.

6.203 Conduits

All conduits shall be a minimum of 20mm diameter.

Galvanised water pipe to comply with AS 1074

Use screwed steel conduit and fittings unless otherwise nominated.

Use heavy-duty non-metallic conduits and fittings

6.204 Power Points and Switches

Power points and switches shall be heavy-duty external weatherproof fittings Clipsal WS Series,

installed 1400mm above floor except where other height is identified or where alternative fitting type is

scheduled. Refer to Drawings for locations.

Where details are not provided on Drawings or Schedules provide power points as follows:

Bedrooms 2 x Double 240V

Kitchen 3 x Double 240V (refrigerator/freezer as separate circuit)

Living 2 x Double 240V

Meals 1 x Double 240V

Laundry 1 x Double 240V

External 1 x Double 240V

6.205 Wet Area Light Fittings

Light fittings to wet areas to be waterproof and vandal proof 18W fluorescent Phillips or equal.

Laundry, bathroom and toilet room light fittings shall be on a separate circuit.

6.206 Light Fittings

Refer to Drawings and Schedules for type of fitting. Where no fitting is scheduled install 36W bare

batten fluorescent.

Locate light fittings and switches at 1400mm minimum above floor level or as per the drawings.

Coordinate light fittings with the locations of ducted air conditioner ceiling registers, flues vents or fans.

Coordinate light switches with GPOs, and other electrical controllers. Locate light switches adjacent to

latch side of door jambs.

Light fittings to verandah soffits adjacent to external doors to be 36W fluorescent

In combined living /kitchen area provide light fittings with 2-way switching.

Laundry, shower room and toilet room light fittings shall be on a separate circuit.

Page 26: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Electrical Installation Page F26

6.207 Meter Boxes / Main Switchboard

Except where alternative units are scheduled all meter boxes shall be a B&R 1DIN24S fitted with the

following;

1 x Email M3 meter.

1 x 80 amp Main Switch

1 x Active Meter Link suitable for 35mm2 cables, (Clipsal L4T35R or equivalent)

1 x Neutral Meter Link suitable for 35mm2 cables (Clipsal L4T35 or equivalent)

1 x Neutral Link suitable for 16mm2 cables & MEN point connection. (Clipsal L5 or equivalent)

Note: MEN point must be located at Main Switchboard / Meter Box

6.208 Load Centre

The Load Centre shall be recessed into the wall to provide a flush finish / profile in reference to the wall

sheeting.

Heger 24 module capacity flush mount (VT24F) except where alternative is scheduled.

Provide an 80A Isolation Switch at load centre

Provide an individual MCB / RDC unit to each final sub-circuit. Minimum rating 4.5kA. Circuit

breakers and labelling for load centres will be as follows:

Isolator 80A

Light 1: 10A

Light 2 (if applicable) 10A

Power 1: 16A

Power 2: 16A

HW Service: 16A

Fridge / Freezer: 16A

Cooker (if applicable): 32A

Air Conditioner: 20A

6.209 Electric Cookers

Provide unit as scheduled. Installation in accordance with the Manufacturer’s instructions. Provide anti-

tilt bracket.

6.210 Cabling for Remote Timer Push Buttons

Not applicable.

6.211 Cooker Timer

Where a 240V electric cooker is provided fit a 2 hour timed cut off switch as Clipsal 31VETR through a

6C12/10/240 cut off switch in the circuit. Locate adjacent to cooker at 1600mm.

6.212 Coaxial Cabling

Provide television antenna connection point where scheduled and/or indicated on drawings.

Extend cable to gable end of dwelling units and coil 4 metres for others to fit antenna.

6.213 Telephone Service

Where indicated on Drawings or in Schedules locate telephone junction box on external wall adjacent

service point. Co-ordinate with floor construction for placement of telephone conduit from perimeter of

slab to telephone connection point, with draw wires and capped. Wire internally with 2 pair to identified

telephone point.

6.214 Fabrication

Components manufactured off-site are to be compatible with the requirements of the project and to

approval of the Principal. Refer to Principal for approval of finishes of components where item will be

exposed to view after installation.

6.215 Source Quality Control

Where Supply Authority or Principal requires, submit data relating to manufactured components in the

form of:

Page 27: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Electrical Installation Page F27

Test Reports

Certificates issued following inspection of products.

Verification of Performance Statement.

6.216 Earthing System

The installation shall be earthed as a MEN system in accordance with the SAA Wiring Rules and as

directed by power authority.

All exposed earth wiring to be protected from possible damage using metal conduits or by enclosure

within verandah posts. Earth stake shall be contained within a metal enclosure with hinged lid, (Earth

Pit). The enclosure shall be surrounded by formed concrete minimum 300mm x 300mm x 500mm deep.

The concrete shall be formed via a permanent surround / box to prevent concrete cracking / damage.

Ensure earth clamp is painted in an approved manner after completion of electrical tests.

Provide separate earthing to steel frames during erection.

Where electrodes are to be installed in rock, fill the gap between the rock and electrode with a bentonite

clay or resin compound or as otherwise approved.

Where corrosive soil install each copper electrode in a 200 mm bore hole, backfill with a conductive

metallic grouting compound and compact with a vibrator.

6.217 Smoke Alarms

Provide Brookes PFS-100TY or Clipsal 755DCL smoke alarms located according to BCA

requirements. Provide additional smoke alarms where indicated on drawing sheets.

PART III EXECUTION

6.301 Examination

Request rectification of existing work or preparation of additional or new work where necessary to

facilitate electrical installations.

Start of work means total acceptance of conditions.

6.302 Preparation

Provide necessary safety or security controls where required to ensure safe practices and installations.

Slab penetrations

Chasing and making good for conduit access for skirting

Chasing and wiring duct, GPOs switches etc.

Supply and installation for access opening where required.

Provision of electrical riser.

Provision of signwriting to Main Switchboard & Load Centre.

Forming, trimming, patching and making good of openings for luminaries to sizes required.

Provision of concrete

Making good.

6.303 Installation

Comply with Regulatory requirements relating to installation methods and systems.

Ensure that installations are within the Regulatory maximum loads and tolerances.

Chases:

Form chases where necessary in structural items within limits set by the Principal.

Cable:

Secure cable, using materials specified above, at centres recommended by Regulations and/or

manufacturer. Suspend all cables in roof space beneath rafters to prevent vermin access.

Conceal wiring and cable equipment. Conduit cable where necessary or required in approved material.

6.304 Field Quality Control

Where requested by Supply Authority supply test data obtainable from component manufacturer.

Arrange for inspections by component manufacturer's representative to ensure correct application, use

and installation.

Page 28: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Electrical Installation Page F28

6.305 Adjust and Clean

Adjust installations of components to ensure proper fit and alignment.

Remedy items of inefficient operation or of doubtful performance.

Clean visible items to original condition.

Remove debris from installation in concealed spaces.

6.306 Protection

Protect installed items from damage from any source until Practical Completion.

6.307 Completion

Complete contracted work in accordance with contract documents.

Page 29: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Concrete Small Works Page F29

7 Minor Concrete Works

PART I GENERAL

7.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section. This section includes the

supply of materials, equipment, labour and services necessary for the construction of minor concrete

structures including footings, pits, manholes, anchor blocks, minor walls, footpaths, pavements and

vehicular crossings, kerbs, channels and post bases, including but not limited to edge trim, vibrating,

float screeding and curing.

7.102 References

Comply with applicable portions of the following Australian Standards:

AS 1012 Methods of testing concrete. There are about 20 parts to this standard

AS 1302 1991 Steel reinforcing bars for concrete

AS 1303 1991 Steel reinforcing wire for concrete

AS 1304 1991 Welded wire reinforcing fabric for concrete

AS 1379 1997 The specification and supply of concrete

AS 1478 1992 Chemical Admixtures concrete, mortar and grout – Admixtures for concrete

AS 3600 2001 Concrete structures with Supplements 1, 2 and 3 Supplement 1 - Commentary

AS 3610 1995 Formwork for concrete

AS 3972 1997 Portland and blended cements

Comply with the requirements of any Building Regulations applicable to the project and to the

recommendations of appropriate bulletins issued by the Cement and Concrete Association of Australia.

7.103 Quality

This work shall be carried out by a specialist trades-person with experience appropriate to the work

required and supervised by a foreman with proven background in this trade. Sampling and testing of

concrete shall be as requested by the Principal. Sample, test and assess shall be carried out in

accordance with AS 1379 Section 5 using a NATA registered testing authority.

Where requested by Principal, present substantiating evidence.

7.104 Delivery and Handling

Where available deliver concrete materials to the site in ready-mix trucks in accordance with AS 1379.

Arrange and provide for concrete pumping equipment as needed.

7.105 Hot Weather Placing

Do not mix concrete where ambient shade temperature is >38oC

Before and during placing maintain formwork and reinforcement at < 32oC using protection, cold water

spraying, or other effective means.

7.106 Cold Weather Placing

Prevent concrete from freezing at any time during the curing process.

Ensure that the temperature of the concrete does not fall below 5oC until the end of the 7 day curing

period.

7.107 Tolerances

Finished concrete surfaces shall not vary by greater than +

5mm when measured with a 3.0m straight

edge.

7.108 Warranty

Forward to the Principal a statement guaranteeing that the concrete complies with the approved mix

design and that concrete has attained required strength at 28 days.

Page 30: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Concrete Small Works Page F30

PART II MATERIALS

7.201 Formwork

A. Provide formwork required to meet the requirements of both drawings and this Specification.

Comply with AS 3610. Formwork for concrete.

B. Unless otherwise specified all formwork shall be Class 4

Formwork for special off-form finishes such as exposed edges of slabs, faces of beams, lintels

etc and as indicated on drawings shall be Class 2.

Soffits to suspended structural slabs shall be Class 3 and shall require submission and approval

of formply layout prior to commencement.

Materials: timber or steel

Be responsible for inspections of structural adequacy of any formwork as required under

AS3610.

7.202 Steel Reinforcement

A. Provide required steel reinforcement for concrete in accordance with drawings and details

thereon. Comply with relevant Australian Standards.

B. Ensure reinforcing is free from loose mill scale, rust, mud, oil, grease or other non-metallic

coatings which would reduce the bond between the concrete and steel and is free from kinks or

other defects, at the time of placing concrete.

7.203 Materials for Concrete

Comply with AS 1379 or AS 3600, AS 2870.

Cement: Shall be Type GP Portland Cement complying with AS 3972 and all cement shall be

transported in watertight containers, and shall be protected from moisture until used. Caked or lumpy

cement shall not be used.

Water: Shall be free from injuries amounts of materials harmful to concrete and to its reinforcement

and neither salty nor brackish.

Fine Aggregate: shall consist of clean, hard, tough, durable uncoated grains, uniform in quality, and

shall confirm to the requirements of AS 2758.1 in respect of bulk density, water absorption (maximum

5 per cent) material finer than 2 micrometres, impurities and reactive materials.

Coarse Aggregate: shall consist of clean, hard, durable, crushed stone, crushed river gravel, screened

river gravel or metallurgical furnace slag and shall confirm to the requirements of AS 2758.1 in respect

of particle density, bulk density, water absorption (maximum 2.5 per cent), materials finer tham 75

micrometres, weak particles, light particles, impurities and reactive materials, iron unsoundness and

falling or dusting unsoundness.

Admixtures: None, except at the approval of the Principal. Chemical admixtures and their use shall

comply with AS 1478.1. Admixtures shall not contain calcium chloride, calcium formate, or

triethanolamine or any other accelerator. During the warm season, a lignin or lignin-based set-retarding

admixture (Type Re or Type WRRe) approved by the Principal shall be used to control slump within

the limits stated in this specification. Duing the cool season, only a lignin based set-retarding admixture

containing not more than 6 per cent reducing sugars (Type WRRe complying with AS 1478.1) may be

used in the mix.

7.204 Pre Mixed Concrete Premix concrete shall comply with the requirements of Australian Standard AS1379 – 1997. All

concrete used in the works shall develop a minimum compressive strength of 20MPa at 28 days and

shall be composed of a mixture of screenings, sand and cement to give the strength specified with a

maximum slump of 80mm.

Addition of water on site is not permitted.

7.205 Site Mixed Concrete

Where pre-mixed concrete is not available or where only small quantities are required site mixing may

be permitted. In all other respects the concrete will conform to the requirements of this specification.

Local creek sands are not to be used except for dogproofing as detailed below.

Mix proportions are to be 1:2:3 for cement, sand and aggregate with cement content not less than 325kg

per cubic metre.

Maximum aggregate size shall be 20mm.

Page 31: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Concrete Small Works Page F31

Mix for a minimum of 1.5 minutes after all ingredients are added.

Discard any concrete not poured within 20 min. of adding water.

Concrete for dogproof edge beams beneath ground level where such dogproofing does not form part of

a structural beam, may be lean mix concrete in proportions of 1:8 cement and sand using local creek

sand.

7.206 Testing of Materials

When requested by the Principal, the contractor shall submit to the Principal a copy of a NATA

Certified Laboratory Test Report on the quality and gradings of the aggregates proposed to be used in

the work.

PART III EXECUTION

7.301 Examination

Inspect the site and relevant conditions before installing work. Ensure conditions are satisfactory for

installation. Start of work means total acceptance of conditions.

7.302 Preparation

Ensure that preparatory work of other trades is complete, including site preparation, sub-base placement

and compaction to a minimum of 95% maximum dry density, plumbing and other fittings are in place

and secured, membrane and other materials are secure and complete

7.303 Formwork

Place and secure formwork complying with AS 3610. Forms shall be of approved material, rigid,

securely braced and supported to produce mortar tight joints and smooth even surfaces. Interior surfaces

of forms thoroughly cleaned and oiled before erection.

7.304 Fixing Reinforcement

Place and secure in correct location, reinforcement in accordance with structural drawings.

Unless otherwise shown on the drawings or directed by the Principal, measurements made in placing

the reinforcement are to be to the centre-lines of the reinforcement.

Support and wire together reinforcement with a 0.5mm soft wire ties or clips, or tack weld in

accordance with AS 1554.3, to prevent displacement by construction loads.

Use plastic-tipped metal chairs, metal hangers, metal spacers and other plastic, metal or concrete

accessories as required for supporting reinforcement in accordance with the following:

Where the concrete surface is off form and exposed to view, internally or externally, provide

accessories in which the portions in contact with the formwork are of plastic matching in colour the

concreted paste.

Where the concrete surfaces are to be sandblasted, internally or externally, use only plastic or concrete

accessories, matched in colour with the concrete paste, where in contact with the formwork.

Weld, tie, clip or otherwise secure mesh reinforcement together by approved means at alternate

intersections and at such other points as may be required. Minimum lapping of sheets to be 2 transverse

wires plus 25mm unless alternative according to Engineer’s Specification.

If necessary, support footing reinforcement on concrete blocks of adequate strength and size not to split

under the loads they are required to carry.

Take particular care to ensure that wall and column steel is properly fixed in position by the use of

plastic chairs clipped on to the steel and by steel spacers for wall reinforcement. Place such spacers in

position prior to erecting the last shutter.

Splices on Reinforcement: Splice only at locations according to Engineer’s Specification with minimum

lap lengths as shown on the drawings or welded to develop the full strength of the small bar in

accordance with AS 1554.3. Generally allow 500mm min for Y12 and 750mm min for Y16 bars.

Splices to be staggered.

Corner bars: Provide corner bars at external corners top and bottom, 45 bar diameters to each leg, tied

to the outermost bar.

7.305 Minimum Cover

Unprotected by membrane on ground or external surfaces: 50mm

Protected by membrane on ground: 40mm

Page 32: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Concrete Small Works Page F32

Internal surfaces: 30mm

Footings: 65mm

Aggressive soil or salty environment: 100mm

7.306 Build In

Install and build in items required including:

Damp proof membrane

Construction joints

Conduits and piping

Bolts, lugs and anchors and plates

Threshold Strips

Waterstops

and other items so required.

Comply with structural and other trades requirements. Secure such items to prevent displacement

during concrete pouring.

7.307 Pouring Concrete

Concrete shall not be placed until all formwork, installation of reinforcement and preparations of all

surfaces have been approved by the Principal. Arrange an inspection of preparatory work according to

the schedule of notification for approval by the Principal. No concrete shall be poured, following receipt

of notification by the Principal, prior to the period identified in the schedule of notification or until

approval is issued.

Concrete shall be placed so as to avoid segregation and in layers not exceeding 300mm depth and shall

be thoroughly compacted during and immediately after placing by means of continuing tamping,

spading or use of vibrators, as directed by the Principal. Under no circumstances shall concrete be

shaken, displaced or disturbed after the initial set of the concrete.

Transport concrete from the mixer to the place of final position without delay and by means that will

prevent segregation and loss of materials. Where necessary, transport concrete on substantial gangways

or barrow runs supported on stools clear of reinforcement. Remove hardened concrete and foreign

materials from the inner surfaces of the conveying equipment.

Place concrete in accordance with AS 3600.

7.308 Concrete Quality

Obtain certification from the supplier of the concrete that it complies with AS2870 and AS3600.

7.309 Compaction of Concrete

Compact concrete by mechanical vibration to the maximum practicable density, free of air or stone

pockets. Concrete not vibrated will be rejected.

Have on site sufficient vibrators of an approved pattern and keep one spare vibrator to every two active

vibrators.

Concrete shall be placed so as to avoid segregation and in layers not exceeding 300mm depth and shall

be thoroughly compacted during and immediately after placing by means of continuing tamping,

spading or use of vibrators, as directed by the Principal. ‘Travelling’ concrete by use of vibrators is

likely to produce segregation and is not permitted. Under no circumstances shall concrete be shaken,

displaced or disturbed after the initial set of the concrete.

Operate immersion type vibrators in a near-vertical position and insert and withdraw them slowly.

Allow them to penetrate and revibrate the concrete in the upper portion of the underlying layer.

Do not leave vibrators, when in action, lying unattended on formwork, reinforcing or in concrete. Keep

vibrator heads clean and free of mud or other deleterious matter when inserted into the concrete.

Avoid contact of the vibrating head with surfaces of the forms.

7.310 Curing Concrete

After placement of concrete, exposed surfaces shall be kept continuously wet for a minimum period of

seven (7) days by covering with water saturated material. Protect freshly cast concrete from premature

drying and excessively hot or cold temperatures. Erect windbreaks in windy conditions to shield the

concrete surface during and after placing. Maintain the concrete at a reasonably constant temperature

with minimum moisture loss for the curing period.

Page 33: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Concrete Small Works Page F33

Curing and Protecting Concrete: Cure as soon as the surface of the concrete has hardened sufficiently to

prevent damage but in no case later than two hours after the finishing operation has been completed.

Keep continuously moist by:

The use of waterproof paper or

The use of an approved polyethylene building film, or

The use of other approved moisture retaining covering.

Secure the covering material firmly against the concrete for the full length of edges and laps and at

frequent intervals between to prevent air circulation at the concrete surfaces.

Period of Curing: Continue for seven days for normal Portland cement concrete. For high early

strength concrete, continue for three days.

Prevent rapid drying out at the end of the curing period.

Spray strip footings, pads and similar finished items with ‘CalcureD’ or similar as recommended by the

manufacturer.

Chemical curing agents shall not be applied to any floor slabs that are scheduled for tiling or application

of any floor covering with adhesive.

7.311 Stripping off Formwork

Strip formwork in accordance with the recommendations of AS 3610, Table: ‘Recommended Minimum

Stripping Times’. If construction loads greater than the live load shown on the drawings are placed on

the structure, fix emergency shoring and tomming to the satisfaction of the Principal.

7.312 Screed Finishes Generally

Finish in one operation wherever practical and within 3 hours of pouring floor slab.

Where topping is delayed for more than three hours after pouring, brush or scabble surface to remove

laitance and to expose aggregate and clean thoroughly.

Apply a dusting of 1 cement: 3 sand while the concrete is still moist and workable and screed to a firm

and dense finish.

Where scheduled add pigment to screed mix as instructed by manufacturer, to colour approved by the

Principal. Add coloured dusting in two successive applications, worked into the surface by trowelling to

a smooth dense finish.

Refer to Finishes Schedule and use a steel trowel to finish the surface to a uniform and smooth finish

suitable to receive resilient flooring materials.

Where tiles are to be laid allow for the thickness of the scheduled tiles and a minimum topping of

20mm. Screed to falls as required using a wood float.

7.313 Rainwater Tank Stand

Provide a nominal 100mm thick ground slab with edge beams as detailed. Provide edge beams that

extend 200mm below ground level.

Reinforce with F62 fabric finish off neat and level with a wood float.

Provide 4 x 8mm diameter hot dipped galvanised tying down eyelets hooked and set 150mm into

concrete. Coordinate all work with roof plumber.

7.314 Concrete Paving

Provide 80mm minimum thick concrete paving with edge beams to areas where indicated on drawings.

Reinforce with F62 fabric finish neat and level with a wood float. For verandah paving protected from

weather use a steel trowel to provide an easy to sweep non-slip finish. Form so that it is entirely free

draining on completion.

7.315 Pit Toilet Slab

Provide a nominal 100mm thick ground slab with edge beams as detailed. Provide dog proof beams that

extend 300mm below ground level

Reinforce with F62 fabric finish of neat and to falls with a wood float.

Coordinate all work with sanitary plumber.

7.316 Completion

Complete work in accordance with contract documents.

Page 34: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Blockwork Page F34

8 Blockwork

PART I GENERAL

8.101 Scope

Refer to Drawings & Schedules for the extent of work relating to this section.

General: Supply and build the blockwork shown on the Drawings or needed to complete the blockwork

including, but not limited to the following:

A. Labour and materials.

B. Building in of miscellaneous items provided by others.

C. Staging and scaffolding.

D. Cleaning.

8.102 Related Work

Co-ordinate and co-operate with the following trades:

Concrete

Structural Steel

Carpentry and Joinery

Metal door frames and Fire doors

Plumbing

Electrical

8.103 Quality Assurance

Provide manufacturer's certification that blocks supplied are of the specified type and strength and were

manufactured in accordance with AS 2733.

Approved Samples: At the start of blocklaying, arrange with the Principal to designate a beginning

section of each type of facework not less than 6 courses high x 1200 long as the Control Sample/s.

When approved by the Principal, the Sample/s will become the control standard/s for blockwork and

remain part of work.

8.104 References

Comply with applicable portions of the following Australian Standards:

AS 2699 1984 Wall ties for masonry construction (incorporating Amendment 1)

AS 2701 Methods of sampling and testing mortar for masonry construction. There are

10 parts to this standard

AS 2733 1984 Concrete masonry units, amended 1988

AS/NZS 2904 1995 Damp-proof courses and flashings

AS 3700 1988 SAA Masonry Code

There are 4 supplements to this code

8.105 Submissions

A. Name of proposed block manufacturer.

B. Prior to ordering:

1. Product data: showing the following information where appropriate:

(a) Manufacturer's name and product details including a designation of proposed

types and sizes.

(b) Schedule of lintels.

(c) Other.

2. Samples: Submit if requested by the Principal.

C. Submissions required prior to delivery:

Two (2) of each type of unit described below.

Page 35: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Blockwork Page F35

8.106 Delivery, Handling and Storage

Co-ordination: Reach agreement with the Principal about site provisions for storage of sand, cement and

other materials and for the mixing of mortar.

Deliver, handle and store products in accordance with manufacturer's recommendations and prevent

damage, deterioration or loss.

PART II MATERIALS

8.201 Blocks

Machine made precast concrete units with sharp arrises, free from distortion, cracks and other defects,

uniform in colour and texture.

Supply hollow blocks except where otherwise specified or required.

Supply solid blocks where core holes would otherwise be visible or where required for fire rating or

other purposes. Match colour and texture of solid and hollow blocks in facework.

Supply matching half-blocks, half-height blocks, closers and lintel and bond beam blocks as required.

A. Strength Grade: 12

B. Colour: Refer to Schedules or seek approval of Principal

C. Sizes and types: 390 (l) x 190 (w) x 190 (h) or other size as per Schedule.

8.102 Mortar and Grout Materials and Types

A. Materials: Comply with AS 3700 as follows:

1. Mortar: Restrict the amount of fine aggregate passing a 75 micron test sieve to 5%

maximum.

2. Grout: Clause 2.4.

3. Pigment: Powdered metallic oxides used in accordance with the manufacturer's

instructions.

B. Types: Comply with AS 3700, Clauses 2.2.3.1, 2.4 and 8.4 and Table 2.1, providing materials

in the proportions described below:

1. Mortar:

Classification Mix proportions (by volume)

Type A Portland cement Building lime Sand

M1 0 1 3

M2 1 2 9

1 3 12

M3 1 1 6

1 0 5 + water thickener*

M4 1 0 to 0.5 3

1 0 4.5

1 0 4+ water thickener*

*Methyl cellulose as recommended by the manufacturer of the block with which it is used.

Mortar for loadbearing blockwork: M3 (M4 or M2 with the approval of the Principal).

Mortar for grouted and reinforced blockwork: M3 (M4 with the approval of the Principal).

Mortar for non-loadbearing blockwork: M3 (M4 or M2 with the approval of the Principal).

Mortar for bagging:

2. Grout: f’c not less than 12 MPa (AS 3700, clause 2.4)

8.202 Miscellaneous Materials

Comply with AS 3700 as follows:

A. Wall ties and accessories: Clause 2.7. Where building is to be located within 10

kilometres of the coast wall ties: stainless steel.

B. Reinforcement: Clause 2.8

C. Lintels and other steel in Clause 2.9

Page 36: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Blockwork Page F36

blockwork:

D. Caulking: Elastomeric sealing compound coloured to match mortar; for

general caulking including movement control joints

Liquid polysulphide polymer equal to Thioseal 5000.

Neutral silicone equal to Dow Corning 790.

E. Head restraint: 100 x 100 x 6 mild 450 long steel angle masonry anchored to

concrete soffit on either side of wall.

Proprietary anchor equal to Brunswick Sales Pty. Ltd., Fax No.

(03) 9870 7712, MFA4/1 or MFA4/M/B at 1000 maximum

centres.

F. Damp-proof Courses comply with AS 2904

G. Flashings comply with AS 2904.

H. Expansion joint material: Closed cell polyethylene foam

I. Control joint material: Closed cell polyethylene foam

8.203 Source Quality Control

A. Tests.

Have the following tests performed in a laboratory NATA registered for the particular test.

Supply copies of the resulting test certificates to the Principal.

TEST: TEST METHOD:

Transverse strength AS 2733 Appendix C

Compressive strength AS 2733 Appendix E

B. Test frequency.

1 in every 10,000 blocks.

8.204 Steel Lintels

A. Where blockwork is to be supported over openings and no special lintels are detailed, build in

mild steel lintels, in accordance with the following schedule:

1. To each 100mm and 150mm thickness of blockwork, support over openings not

otherwise specified:

OPENING NUMBER PROFILE SIZE

Up to 950mm wide 1 MS flat 76 x 10mm

950 to 1200mm 1 MS angle 76 x 76 x 10mm

1200 to 1650mm 1 MS angle 102 x 76 x 10mm

1650 to 2400mm 1 MS angle 127 x 76 x 10mm

2400 to 3000mm 1 MS angle 152 x 89 x 10mm

2. To each 100mm and 150mm thickness of blockwork supported over internal door

openings only:

OPENING NUMBER PROFILE SIZE

Up to 950mm wide 1 MS flat 76 x 10mm

950 to 1050mm 1 MS flat 76 x 12mm

1050 to 1200mm 1 MS angle 76 x 76 x 10mm

1200 to 1650mm 1 MS angle 102 x 76 x 10mm

1650 to 2400mm 1 MS angle 127 x 76 x 10mm

2400 to 3000mm 1 MS angle 152 x 89 x 10mm

B. Set angles with the first dimension vertical.

C. Hot dip galvanise steel lintels in exterior openings.

D. Fix angles to concrete columns or beams with the bearing leg cut and bent to the height of the

vertical leg and bolted to concrete with 2 no. 16mm masonry anchors.

Page 37: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Blockwork Page F37

PART III EXECUTION

8.301 Mortar Mixing

Measure materials to ensure that the specified mix proportions are maintained (AS 3700, Clause

2.2.3.1).

Mix in a suitable mixing machine until a uniform blending of the components is achieved.

Add water to create a mix that is as wet as can be conveniently used by the blocklayer.

Except for the previously specified methyl cellulose water thickener, use no chemical to affect the

plastic or other properties of mortar or as a substitute for lime without the Principal's permission.

8.302 Mortar Life

Re-tempering to replace water lost by evaporation is encouraged until initial set begins. Reject mortar

which has begun its initial set and do not re-temper.

8.303 Preparation

Review the project with other trades in relation to ducts, piping, conduits, thimbles, sleeves, etc. or

other item penetrating or to be built into blockwork and co-ordinate their installation.

Obtain built-in items from their suppliers prior to starting blockwork.

Clean the surface of concrete before laying blocks thereon.

Set up pressed metal door frames plumb and level and brace as required. Maintain bracing until walls

are at least 1000 high and frame grouting has set.

8.304 Laying

General: Comply with applicable provisions of AS 3700. Set out blockwork so as to reduce cutting to

a minimum and, in facework, to avoid irregular or broken bond.

Make cuts in facework with a masonry saw.

Carefully position openings for other trades to eliminate cutting.

Build in accordance with the dimensions, thicknesses and heights shown on drawings, plumb, level and

in the designated position within the tolerances of AS 3700, Clause 8.8.

Allow no part to rise more than 1000mm above adjacent unfinished work. Rake back advanced work,

build blockwork in bond and avoid toothing wherever possible.

Build in as necessary reinforcements, arch bars, lintels, frames, straps, bolts, lugs, wall ties, metalwork,

damp-proof courses and flashings, etc.

Re-lay, in fresh mortar, blocks moved after initial laying.

Keep mortar stains to a minimum and protect horizontal ledges, finished sills and the like from mortar

droppings as work proceeds.

Before mortar sets hard remove excess mortar. Scrub blockwork within 24 hours of laying using a

bristle brush plus detergent if necessary.

Protect new and incomplete blockwork with coverings, temporary bracing or the like - AS 3700,

Clause 8.13.

8.305 Jointing and Finishing

Joint thickness: 10mm within the tolerances given in AS 3700:

Joint finish Blockwork for plaster: cut off flush

Face blockwork

Bagged finish: Spread the mortar on exposed external/internal surfaces with a brush, sponge float,

rough cloth or other suitable device and then rub to achieve a uniform texture approved by the

Principal.

Protect adjacent surfaces as necessary and promptly remove bagging mortar spilt, splashed or otherwise

lodged on them.

Carry out bagging as the work proceeds.

Carry out bagging as a separate operation after blocklaying has been completed.

8.306 Bond Beams

Provide bond beams to block walls.

Page 38: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Blockwork Page F38

Where possible, form bond beams continuous with lintels. Reinforce with mild steel rods bent as

required to follow wall pattern. Lap a minimum of 400mm at joints and corners and tie with 18 swg

wire.

Provide clear space between rods and block shell and fill block with concrete as specified, compacted

into the block and finished flush at top. Where block cavity leaves insufficient space for concrete

infilling, grout with 1:2.5 cement: sand mortar.

8.307 Lintels, General

Lintels may be of steel or reinforced masonry units, subject to approval of Principal.

Build in steel lintels: Refer to specification in Part II Clause 203.

8.308 Lintels, Concrete Masonry

Build block lintels occurring to heads of openings in block walls. Form with standard bond beam

blocks of a thickness to suit the leaf and extend a minimum of one full block on either side of jamb or

further as required to suit bonding. Allow for cutting of blocks needed to suit height of openings.

Reinforcement: Reinforce with structural grade mild steel bar in accordance with the following

schedule:

Width of Bond Beam/Lintel Span Reinforcing

90mm Maximum 1000mm 1/12mm bar

90mm Maximum 1800mm 1/16mm bar

Bond beam grout: fill with 30MPa concrete.

Where block lintels abut walls or columns, support on mild steel angle bracket, welded or bolted to wall

or column.

8.309 Bonding and Tying

Build work in stretcher bond.

Space wall ties in accordance with AS 3700, Clause 3.8

Keep cavities clean and free from mortar droppings.

Fix to concrete or steel columns and at junction with concrete walls with frame ties built at least 250mm

into block joint and fix to the structure as close as possible to the course line.

8.310 Door Frames

Build in door frames as the work proceeds. Generally allow for lugs at 400 to 450mm centres except

FU door frames which have lugs to sizes and centres required by the fire test report pertaining to the

particular type of door. Grout solid cavities behind frames.

8.311 Incidental Work

Chases: Refer to AS 3700, Clause 3.12 and, as far as possible, provide for chases to be made as the

work rises. No horizontal chase may exceed 1200mm in length and no vertical chase may be closer

than 600mm to an element providing lateral support. No chase may be more than 1/3 of the thickness of

the wall.

Perform miscellaneous incidental blockwork as required throughout and for other trades. Make good

after other trades.

8.312 Field Quality Control

A. Tests.

Have the following tests performed in a laboratory NATA registered for the particular test.

Supply copies of the resulting test certificates to the Principal.

TEST: TEST METHOD:

For Mortar: Sampling method AS 2701.1

Chemical Composition AS 2701.10

For Blockwork:

Compressive strength AS 3700 Appendix A

Bond strength

Characteristic strength AS 3700 Appendix B

B. Test frequency.

Page 39: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Blockwork Page F39

For Mortar: One for every 10,000 blocks laid

For Special Masonry: Every 5,000 blocks laid where work exceeds one storey

For other Masonry: One for every 10,000 blocks laid

8.313 Cleaning of Facework

Take care to keep walls clean at times. Should further cleaning be necessary, use hydrochloric acid not

stronger than 5%, treating only a small area at one time. Wet the wall prior to applying the acid, work

from the top down and thoroughly wash off after brushing. Do not leave acid solution on wall at

stoppage of work.

8.314 Completion

Complete contracted work in accordance with contract documents and written variation orders issued

by the Principal.

On completion clean up mortar droppings, debris, etc., remove scaffolding, make good put-log holes

and blemishes and leave work in a first class condition.

Protect facework surfaces where necessary to avoid damage during other building operations.

Page 40: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Brickwork Page F40

9 Brickwork

PART I GENERAL

9.101 Scope

Refer to Drawings & Schedules for the extent of work relating to this section.

General: Supply and build the brickwork shown on the Drawings or needed to complete the brickwork,

including but not limited to the following:

A. Labour and materials.

B. Building in of miscellaneous items provided by others.

C. Staging and scaffolding.

D. Cleaning.

9.102 Related Work

Co-operate and co-ordinate with the following trades:

Concrete

Structural Steel

Carpenter and Joiner

Metal door frames and Fire doors

9.103 Quality Assurance

Provide manufacturer's certification that bricks supplied are of the specified type and strength, and were

manufactured in accordance with AS 1225 or AS 1653.

Approved Samples: At the start of brick laying, arrange with the Principal to designate a beginning

section of each type of face brickwork not less than 6 courses high x 1200 long as the Control Sample.

When approved by the Principal, the Section/s become the control standard/s for brickwork and remain

part of work.

9.104 References

Comply with applicable portions of the following Australian Standards:

AS/NZS 2904 1995 Damp-proof courses and flashings

AS 3700 1988 SAA Masonry Code. There are 5 Supplements to this code

9.105 Submissions

A. Submissions required:

Where manufacturer has not been scheduled, name of proposed manufacturer of bricks.

B. Submissions required prior to ordering:

1. Product Data: Showing the following information where appropriate:

(a) Manufacturer's name and product details including a designation of proposed

types and sizes.

2. Samples: Submit if requested by the Principal.

C. Submissions required prior to delivery:

1. Four of each type of face brick to represent the range of colours, textures and surface,

arris and shape irregularities.

9.106 Delivery, Handling and Storage

Co-ordination: Provide adequate site provision for storage of sand, cement and other materials and for

mixing of mortar.

Deliver, handle and store products in accordance with manufacturer's recommendations and prevent

damage, deterioration or loss.

PART II MATERIALS

9.201 Bricks

Refer to Schedules for Manufacturer and type.

Page 41: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Brickwork Page F41

9.202 Mortar and Grout Materials and Types

A. Materials: Comply with AS 3700 as follows:

1. Mortar: Restrict the amount of fine aggregate passing a 75 micron test sieve to 5%

maximum.

2. Grout: Clause 2.4

3. Pigment: Powdered metallic oxides used in accordance with the manufacturer's

instructions.

4. Refractory Mortar: Approved refractory mortar, treated as recommended by the

manufacturer.

B. Types: Comply with AS 3700; Clauses 2.23.1, 2.4 and 8.4 and Table 2.1, providing materials

in the proportions described below:

1. Mortar:

Classification Mix proportions (by volume)

Type A Portland

cement

Building lime Sand

M1 0 1 3

M2 1 2 9

1 3 12

M3 1 1 6

1 0 5 + water thickener*

M4 1 0 to 0.5 3

1 0 4.5

1 0 4+ water thickener*

*Methyl cellulose as recommended by the manufacturer of the block with which it is used.

Mortar for Load Bearing Brickwork: M3

Mortar for Grouted and Reinforced Brickwork: M3

Mortar for Non-Load Bearing Brickwork: M3

Mortar for Repair of Lime Mortar Brickwork: M1

Mortar for bagging:

Use same mortar as used for laying when the work is to be bagged as bricklaying proceeds.

Use M3 mortar when the whole of the bagging is to be carried out as a separate operation.

Use M3 mortar, with powdered metallic oxide pigment added to achieve a dry colour approved

by the Principal where the whole of the bagging is to be carried out as a separate operation and

a uniform textured coloured mortar is to be the permanent finish

2. Grout: f'c not less than 12 MPa (AS 3700, Clause 2.4).

9.203 Miscellaneous Materials

Comply with AS 3700 as follows:

A. Wall ties and accessories: Clause 2.7. Where building is to be located within 10

kilometres of the coast wall ties: stainless steel.

B. Reinforcement: Clause 2.8

C. Lintels and other steel in

blockwork:

Clause 2.9 Extend lintels 230mm minimum past each jamb of

openings.

D. Caulking: Elastomeric sealing compound coloured to match mortar; for

general caulking including movement control joints

Liquid polysulphide polymer equal to Thioseal 5000.

Neutral silicone equal to Dow Corning 790.

E. Head restraint: 100 x 100 x 6 450 long mild steel angle masonry anchored to

concrete soffit on either side of wall.

Page 42: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Brickwork Page F42

Proprietary anchor equal to Brunswick Sales Pty. Ltd., Fax No.

(03) 9870 7712, MFA4/1 or MFA4/M/B at 1000 maximum

centres.

F. Damp-proof Courses 0.5mm embossed polyethylene film, comply with AS 2904

G. Flashings colorbond to match roofing, folded steel profile to exposed

openings and intersection of roofing with walling, comply with

AS 2904.

H. Expansion joint material: Closed cell polyethylene foam

I. Control joint material: Closed cell polyethylene foam

9.206 Source Quality Control

A. Tests.

Have the following tests performed in a laboratory NATA registered for the particular test.

Supply copies of the resulting test certificates to the Principal.

TEST TEST METHOD

Dimensions: ST0 AS 1226.2

Transverse strength AS 1226.3

Compressive strength AS 1226.4

Characteristic expansion AS 1226.5

For silica lime bricks:

Transverse strength AS 1653 Appendix B

For clay bricks: sampling method AS 1226.1

Compressive strength AS 1653 Appendix C

For concrete bricks: AS 2733 Appendix C

Transverse strength AS 2733 Appendix E

B. Test frequency. of one test per 20,000

9.207 Steel Lintels

A. Where brickwork is to be supported over openings and no special lintels are detailed, build in

mild steel lintels, in accordance with the following schedule:

1. To each 110mm (or 76mm) thickness of brickwork, support over openings not

otherwise specified:

OPENING NUMBER PROFILE SIZE

Up to 950mm wide 1 MS flat 76 x 10mm

950 to 1200mm 1 MS angle 76 x 76 x 10mm

1200 to 1650mm 1 MS angle 102 x 76 x 10mm

1650 to 2400mm 1 MS angle 127 x 76 x 10mm

2400 to 3000mm 1 MS angle 152 x 89 x 10mm

2. To each 110mm (or 76mm) thickness of brickwork supported over internal door

openings only:

OPENING NUMBER PROFILE SIZE

Up to 950mm wide 1 MS flat 76 x 10mm

950 to 1050mm 1 MS flat 76 x 12mm

1050 to 1200mm 1 MS angle 76 x 76 x 10mm

1200 to 1650mm 1 MS angle 102 x 76 x 10mm

1650 to 2400mm 1 MS angle 127 x 76 x 10mm

2400 to 3000mm 1 MS angle 152 x 89 x 10mm

Page 43: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Brickwork Page F43

B. Set angles with the first dimension vertical.

C. Hot dip galvanise steel lintels in exterior openings.

D. Fix angles to concrete columns or beams with the bearing leg cut and bent to the height of the

vertical leg and bolted to concrete with 2 no. 16mm masonry anchors.

PART III EXECUTION

9.301 Mortar Mixing

Measure materials to ensure that the specified mix proportions are maintained (AS 3700, Clause

2.2.3.1).

Mix in a suitable mixing machine until a uniform blending of the components is achieved.

Add water to create a mix that is as wet as can be conveniently used by the bricklayer.

Except for the previously specified methyl cellulose water thickener, use no chemical to affect the

plastic or other properties of mortar or as a substitute for lime without the Principal's permission.

9.302 Mortar Life

Re-tempering to replace water lost by evaporation is encouraged until initial set begins. Reject mortar

which has begun its initial set and do not re-temper.

9.303 Preparation

Review the project with other trades in relation to ducts, piping, conduits, thimbles, sleeves, etc. or

other item penetrating or to be built into brickwork and co-ordinate their installation.

Obtain built-in items from their suppliers prior to starting brickwork.

Clean the surface of concrete before laying bricks thereon.

Set up pressed metal door frames plumb and level and brace as required. Maintain bracing until walls

are at least 1000 high and frame grouting has set.

9.304 Laying

General: Comply with applicable provisions of AS 3700. Set out brickwork so as to reduce cutting to a

minimum and, in facework, to avoid irregular or broken bond.

Make cuts in facework with a masonry saw.

Carefully position openings for other trades to eliminate cutting.

Build in accordance with the dimensions, thicknesses and heights shown on Drawings, plumb, level and

in the designated position within the tolerances of AS 3700, Clause 8.8.

Allow no part to rise more than 1000mm above adjacent unfinished work. Rake back advanced work,

build brickwork in bond and avoid toothing wherever possible.

Build in as necessary reinforcements, arch bars, lintels, frames, straps, bolts, lugs, wall ties, metalwork,

damp-proof courses and flashings, etc.

Provide weepholes 1200 mm apart over damp proof course and flashings where these span across

cavaties.

Re-lay, in fresh mortar, bricks accidentally moved after initial laying.

Keep mortar stains to a minimum and protect horizontal ledges, finished sills and the like from mortar

droppings as work proceeds.

Before mortar sets hard, remove excess mortar. Scrub brickwork within 24 hours of laying using a

bristle brush plus detergent if necessary.

Protect new and incomplete brickwork with coverings, temporary bracing or the like - AS 3700, Clause

8.13.

9.305 Jointing and Finishing

Joint thickness: 10mm within the tolerances given in AS 3700:

Joint finish Brickwork for plaster: cut off flush

Face brickwork: concave tooling except where alternative is scheduled or detailed in drawings.

Bagged finish: applicable only when identified in the Schedule or drawings Spread the mortar on

exposed external/internal surfaces with a brush, sponge float, rough cloth or other suitable device and

then rub to achieve a uniform texture approved by the Principal.

Page 44: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Brickwork Page F44

Protect adjacent surfaces as necessary and promptly remove bagging mortar spilt, splashed or otherwise

lodged on them.

Carry out bagging as a separate operation after bricklaying has been completed.

9.306 Bonding and Tying

Build work in stretcher bond.

Space wall ties in accordance with AS 3700, Clause 3.8

Keep cavities clean and free from mortar droppings.

Fix to concrete or steel columns and at junction with concrete walls with frame ties built at least 250mm

into brick joint and fix to the structure as close as possible to the course line.

9.307 Door Frames

Build in door frames as the work proceeds. Generally allow for lugs at 400 to 450mm centres except

FU door frames which have lugs to sizes and centres required by the fire test report pertaining to the

particular type of door. Grout solid cavities behind frames.

9.308 Incidental Work

Chases: Refer to AS 3700, Clause 3.12 and, as far as possible, provide for chases to be made as the

work rises. No horizontal chase may exceed 1200mm in length and no vertical chase may be closer

than 600mm to an element providing lateral support. No chase may be more than 1/3 of the thickness of

the wall.

Perform miscellaneous incidental brickwork as required throughout and for other trades. Make good

after other trades.

9.309 Field Quality Control

A. Tests.

Have the following tests performed in a laboratory NATA registered for the particular test.

Supply copies of the resulting test certificates to the Principal.

TEST: TEST METHOD:

For mortar: Sampling method AS 2701.1

Chemical Composition AS 2701.10

For brickwork: Compressive strength AS 3700 Appendix A

Bond strength AS 1653 Appendix A

Characteristic strength AS 3700 Appendix B

B. Test frequency.

For Mortar: one test per 20,000 bricks laid.

For Special Masonry: where construction exceeds one storey, one test per 10,000

bricks laid or one test per storey whichever is the greater

For other Masonry: one test per 20,000 bricks laid.

9.310 Cleaning of Facework

Take care to keep walls clean at times. Should further cleaning be necessary, use hydrochloric acid not

stronger than 5%, treating only a small area at one time. Wet the wall prior to applying the acid, work

from the top down and thoroughly wash off after brushing. Do not leave acid solution on wall at

stoppage of work.

9.311 Completion

Complete contracted work in accordance with contract documents and written variation orders issued

by the Principal.

On completion clean up mortar droppings, debris, etc., remove scaffolding, make good put-log holes

and blemishes and leave work in a first class condition.

Protect facework surfaces where necessary to avoid damage during other building operations.

Page 45: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Cold Formed Metal Framing Page F45

10 Cold Formed Metal Framing

PART I GENERAL

10.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Supply and erect cold formed metal framework including but not limited to:

Load bearing wall framing

Non-load bearing wall framing

Load bearing roof framing

10.102 Related Work

Co-ordinate and Co-operate with the trades preparing floors, installing windows and doors and

weatherproofing material, including casting in of anchors where required.

10.103 Quality

All work shall be of the highest standard and carried out by specialists experienced in the particular type

of work.

10.104 References

Comply with applicable portions of the following Australian Standards:

AS 1170 SAA Loading Code

1170.1 1989 Dead and live loads and load combinations

1170.2 1989 Wind loads (Amended 1993)

1170.3 1990 Snow loads

AS 4600 1996 Cold formed steel structures code

AS 3623 1993 Domestic metal framing

Comply with relevant Authority’s requirement for fire-rated installation

10.105 Submissions

Submit details of Manufacturer’s framing system and Engineer’s calculations to the Principal prior to

commencement where required.

Make application and obtain Building Rules Consent where required. Submit approvals to the Principal

prior to commencement.

10.105 Special requirements

Not applicable.

8.106 Delivery, Handling and Storage

Handle materials with care. Install directly in place as instructed by manufacturer. Provide adequate

storage of materials on site.

PART II MATERIALS

10.201 Materials

Wall, floor and roof framing components manufactured from corrosion resistant steel materials

Match components detailed on Drawings.

10.202 Structural Criteria

Adopt Terrain Category N3 41m/s (Refer AS 1170).

Wind Loading: Design: Frame assemblies to suit the static and dynamic wind forces as indicated on the

tables in the Australian Standard AS1170.

Structural members of units of such strength that when tested at the specified design wind values they

do not deflect by an amount greater than span/240 and do not cause permanent deflection.

Fix members so that the above loading is generated in the members without stress causing failure or

movement becoming evident at any joint.

Page 46: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Cold Formed Metal Framing Page F46

Movement: Permit free and noiseless movement of the components due to thermal effects, structural

effect, wind pressure, effect of dead loads, without strain to the frames, without buckling of components

and without excessive stress to members or assemblies.

Contact with Other Materials: Coat metal surfaces in contact with mortar, concrete, plaster, masonry,

wet-application of fire-proofing and absorbent materials with an anti-galvanic, moisture barrier

material. Isolate, with inert material, dissimilar metals for the prevention of electrolytic action and

corrosion.

Distortion: Design the assembly to minimise visual distortion.

10.203 Detail Design Provisions

General: The Contract Drawings are to be considered essentially schematic except for profiles of

exposed surfaces and panel arrangement where indicated. If, in the opinion of the Contractor a change

of profile is required in order to meet the specification, arrange through the Principal for a review of the

condition. Design the assembly, reinforcing and anchorage to suit each specified condition in an

acceptable manner complying with the requirements specified herein.

Tolerances: Frames are to accommodate building tolerances, and when completed, within the following

tolerances:

Deviation from plumb, level or dimensioned angle within 3mm per 3.5m of length of member, or 6mm

in total run in line.

Deviation from theoretical position on plan or elevation, including deviation from plumb, level or

dimensioned angle not to exceed 9mm total at location.

Change in deviation not to exceed 3mm for 3.5m run in direction.

10.204 Fabrication

Form junctions so that no fixings, such as pins, screws, pressure indentations and the like are visible on

exposed faces.Cut edges, drill holes, rivet joints and clean flat sheets, neat, free from burrs and

indentations. Remove sharp edges without excessive deformation. Fit mitred joints accurately to a fine

hairline.

Pre-assemble and match mark before delivery.

PART III EXECUTION

10.301 Examination

Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are

satisfactory for installation.

Perform rectification required before delivery of materials.

Start of work means total acceptance of conditions.

10.302 Preparation

Prepare surfaces affected by the installation in accordance with material manufacturer’s instructions.

10.303 Frame Anchorage

Provide anchorage devices to the Engineer’s specificationfor building in and check that devices are

located as required to suit the requirements of the fabrication for positive and permanent fixing.

Insulation: Isolate dissimilar metals at interfaces with bitumen based or nylon shim materials to prevent

galvanic action.

Steel wall framing shall be separately and permanently earthed on completion.

Make good concrete or masonry damaged during the installation of masonry anchors at no cost to the

Principal.

10.304 Damp Proof Membrane

Provide 0.5mm embossed polyethylene membrane beneath all wall frames.

10.305 Cleaning

Debris: Remove rubbish and debris resulting from the fabrication and erection operations, each day.

10.306 Completion

Complete contracted work in accordance with contract documents.

Page 47: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Structural Steel Page F47

11 Structural Steel

PART I GENERAL

11.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Supply, fabricate and install a complete structural steel system including but not limited to:

A. Steelwork shown on Drawings specified herein and includes surface treatment, storage,

delivery to the site, steel to steel connections and their fastenings, steel to concrete and their

fastenings, miscellaneous attachments and anchor bolts.

B. Erection of the steelwork shown on the Drawings and includes off-loading, erection, field

welding, making steel to steel connections, connection to anchor bolts, permanent grouting and

repairs to surface treatment.

11.102 Related Work

Co-ordinate and Co-operate with the following trades:

Concrete

Metal Framing

Metalwork

Roof Plumber

11.103 Quality

All structural steelwork shall be done in accordance with the Drawings and Specifications by

appropriately experienced trades-persons and installed under the direct supervision of a capable

foreman experienced in the class of work under construction.

11.104 References

Conform to the latest edition, including amendments, of the following Australian Standards (except

where varied by this Specification or the Contract Drawings):

AS 1538 1988 Cold-formed Steel Structures Code

AS/NZS 1554 Structural Steel Welding There are 3 parts to this code (1554.2 Amended 1994

and 1995)

1554.1: 1995 Welding of steel structures

AS 1627 Metal finishing - Preparation and pre-treatment of surfaces There are 10 parts to

this standard

AS 1650 1989 Hot-dipped galvanised coatings on ferrous articles

AS 4100 1998 Steel structures and amendments

SAA HB48 - 1993 Steel Structure Design Handbook.

11.105 Delivery, Handling and Storage

Handle and store materials by methods and appliances that will not over-stress or deform the members.

Separate materials on site from surface of ground.

Members bent or buckled from handling or storing will be liable to rejection.

Supply bolts, nuts and washers in grit-free containers and stored in water-tight premises. Reject burred,

damaged, corroded or otherwise unserviceable bolts.

PART II MATERIALS

11.201 Materials

General:

The Contractor shall supply materials required to complete the works under this Section in accordance

with the contract documents. Materials which do not comply will be rejected.

Steel supply:

Unless otherwise shown on the drawings, comply with AS3678 and AS3679. Do not use other types

and grades of steel without written approval of the Principal.

Page 48: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Structural Steel Page F48

11.202 Fabrication

Fabricate finish in accordance with AS 4100.

Do not exceed the end clearances shown on the Drawings. Where these are not shown, ascertain the

clearances used in the design of the connections.

11.203 Connections

A. General:

Supply end cleats, brackets and other connections, not specifically detailed on the Drawings, to

suit the location and forces shown thereon with gauge and edge distances in accordance with

AS 4100.

B. Bolting General:

Supply bolts in bearing of such lengths that no threaded portion crosses the interface of the

parts joined. Place at least one washer under the bolt head or nut, whichever is to be rotated.

Provide taper washers where the part under the bolt head or nut is not perpendicular to the

centre-line of the bolt.

C. Welding:

Do manual welding in accordance with AS 1554

Do semi-automatic welding in accordance with AS 1554.

D. Miscellaneous Attachments:

Allow for the drillings, cleat and other fitments indicated on the Contract Drawings or shown

on other relevant Drawings and required by other trades.

Be entirely responsible for supply of necessary information to the Steel Fabricator.

11.204 Hot Dip Galvanising

Where scheduled or specified galvanised steel after chemical descaling in accordance with AS 1627 and

AS 1650, so that rust, mill scale, oil grease and other foreign matter is removed leaving a clean surface

of metal.

Then immerse steel in a bath of molten zinc so that when withdrawn, the zinc coating solidifies to a dry

film thickness of 100 microns. Allow a 48 hour curing period before transporting steelwork.

Reinstate transport and erection abrasions, site welds, etc., by thoroughly wire brushing affected areas

to achieve a clean sound substrate and patch coating with an Zinc rich paint with a film thickness of 100

microns.

11.205 Surface Treatment of Steel

Clean steelwork free from loose rust, loose mill scale, dirt, oil and grease or by sand-blasting - Class

2.5. Apply a coat of inorganic zinc silicate, 100 microns thick. Refer AS 1627.4

11.206 Inspection Before Delivery

Material and work is subject to inspection before painting and delivery. Provide the necessary access

and facilities.

Where steel has been inspected at the shop before being delivered to the site, such inspection does not

relieve the Contractor of his responsibility to carry out the work in accordance with the Drawings and

this Specification.

PART III EXECUTION

11.301 Examination

Inspect site conditions both before fabrication and delivery of steel.

Ensure that on delivery, materials can be directly installed.

Report discrepancies immediately they are found and instruction obtained before continuing with the

affected portion of the work.

Start of work means total acceptance of conditions.

11.302 Erection

Comply with the requirements of the Drawings and Engineer’s report and those of AS 4100.

Adopt an erection procedure such that members can be placed and fixed in position without distortion.

Make safe, during erection, against wind and erection stresses and loading conditions, including those

due to erection equipment.

Page 49: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Structural Steel Page F49

Allow for the cost of temporary erection bracing required and for the requirements of the Principal in

connection with such bracing.

11.303 Inspection on Site

Advise Principal when erected steel is ready for inspection.

11.304 Adjustments

Following erection, adjust the installation as required by Principal.

Touch up abraded or missing paint areas.

11.305 Cleaning

Clean the installed steelwork and touch up with zinc rich primer paint of matching colour.

Ensure that the touch up paint is compatible with the factory applied material.

11.306 Pit Toilet

Provide structural framing for pit toilets as indicated on drawings and nominally 50mm RHS bolted to

floor slab. Door framed in 25 x 25 x 2mm Durugal SHS.

11.307 Completion

Complete contracted work in accordance with contract documents.

Page 50: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Metalwork Page F50

12 Metalwork

PART I GENERAL

12.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide required metalwork including cupboards, shelves, benches and tops and support framing for

kitchens and wet areas generally, and as indicated on drawings or specified.

12.102 Related Work

Co-ordinate and co-operate with other trades and as follows:

Concrete, Structural, Electrical

Plumber

Fences and Gates

Joinery

Electrical

Packaged Air Conditioning

12.103 Quality

Work of this Section will be performed by experienced craftsmen familiar with the quality required in

this class of work. Comply throughout with manufacturer's instructions.

12.104 References

Comply with applicable portions of the following Australian Standards:

AS/NZS 1554 SAA Structural Steel Welding. There are 3 parts to this code (1554.2

Amended 1994, 1995)

AS 1627 Metal finishing - Preparation and pre-treatment of surfaces. There are 10

additional parts to this standard

1627.6 1994 Chemical conversion treatment of metals. (1627.8 has been deleted)

AS 1650 1989 Hot-dipped galvanised coatings on ferrous articles

AS/NZS 1664 Aluminium structures

AS/NZS 1734 1997 Aluminium and aluminium alloys - flat sheet, coiled sheet & plate

AS/NZS 1866 1997 Aluminium and aluminium alloys

AS 4100 2001 Domestic solid fuel burning appliances - installation

AS 4100 1990 Steel Structures

Comply with requirements of statutory and local authorities.

PART II MATERIALS

12.201 Materials

Items of metalwork shall be as specified or indicated on Drawings and as nominated in the Schedules

12.202 Finish

Materials exposed to weather may be either:

Mild steel - hot dipped galvanised after fabrication or chromate pre-treated followed by polyester

powder coating.

Finish internal steel after fabrication with zinc rich organic primer, or with inorganic zinc silicate paint.

All welds to be painted with cold galv paint.

Comply with relevant codes of practice or Manufacturers' recommendations.

12.203 Welding of Steel

General: Details of joints, the techniques of welding employed, the appearance and quality of welds

made and the methods used to correct defective work; conform to requirements of AS/NZS 1554, Part

1.

Welds exposed to view: grind smooth to approval of Principal.

Page 51: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Metalwork Page F51

Concealed welds: grind smooth before galvanising.

Tack or skip welding: at regular intervals, very neat; not permitted if material is to be hot dip

galvanised.

Remove weld spatter, slag and slag inclusions.

Certification: Only welders who have previously been qualified by tests may weld.

Weld continuously, to form joints and connections to exclude water and to permit draining during

galvanising.

12.204 Connection Design

General: Design fabricated items so that all possible work is done before delivery. Fully protect for

shipment. Take all possible care to prevent damage.

Welding External Items: conform to the recommendations of AS/NZS 1554, noting particularly the

design criteria.

Flanges: Concealed where possible. Sleeve connecting railings inside railing sections and secure with

flush or set screws. Except where access is impossible, connection screws and bolts will be on the

underside of joints.

Fasteners on the top of railing sections will not be permitted.

Weld shop connections for steel fabrications, and bolt field connections.

Provide smooth finishes to exposed surfaces with sharp well-defined lines and arrises. Mill to a close fit

or provide machined joints. Design necessary lugs, brackets and similar items so that work can be

assembled and installed in a neat, substantial manner.

Provide ample strength and stiffness by using appropriate metal thickness of assembly and supports.

Provide holes and connections as required to accommodate the work of other trades and for site

assembly of metalwork. Drill or punch and ream in the shop.

12.205 Miscellaneous

Fasteners: Provide required bolts, screws, inserts, fasteners, templates and other accessories required for

a complete installation of the work.

Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the

item is to be secured.

Fasten galvanised items with galvanised fasteners.

PART III EXECUTION

12.301 Examination

Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure

conditions are satisfactory for installation. Arrange for rectification required.

Start of work means total acceptance of relevant conditions.

12.302 Preparation

Field measurements: Do not delay job progress. Allow for adjustments and fitting of the work in the

field where taking of measurements might cause delay.

Co-ordination with work of others: Furnish to each relevant trade foreman anchorages and setting

Drawings, diagrams, templates and instructions for installation of items having integral anchors which

are to be embedded in concrete or masonry construction. Co-ordinate delivery of such items to the

project site.

12.303 Inspection and Reinstatement

Check pre-fabrications as they are unloaded at the project site for evidence of physical damage.

Treat damaged pre-fabrications as follows:

Damage to galvanising: Perform immediate inorganic zinc silicate paint or cold-galvanising repair. Do

not install until reinstated.

Architectural metalwork: Returned to shop for repair or replacement.

Verify anchors, bolts and other required anchorage items for proper size and accurate location prior to

erection.

Page 52: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Metalwork Page F52

12.304 Installation

Anchorage: Except for anchorages furnished herein but placed by other trades, set and secure necessary

anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as

needed. Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper

positioning of completed work.

Fit: During installation and assembly, form tight joints with exposed connections accurately fitted, and

reveals uniform. Finish work accurately, plumb, level, square and true in reference to adjacent

construction. Make tolerances conform to Australian Standards.

Finish: Do not cut or abrade shop finishes which cannot be completely restored in the field.

The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted under any

conditions. Fabrications may be cut shorter with power hacksaws on site.

Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on completion

of installation.

12.305 Fireplaces

Provide fireplace as scheduled in accordance with the Manufacturer’s specification. Provide

Manufacturers’ minimum clearances. Fit Dektite and seal to ensure that it is fully waterproof.

Refer to Schedule for selected unit. Where a fire place is required but no unit is specified the fireplace is

to be Nectre Mark 1 including stainless steel flue kits with steel glazing panel and flat top plate as

manufactured by Pecan Engineering (13 Acorn Rd Dry Creek, phone Adelaide 8349 8332).

12.306 Wet Area Fixtures

Provide laundry troughs and supports, hand basin stands, and seat and shelf brackets as detailed on

drawings and scheduled, all manufactured from ‘DuraGal’ (or equal) 30mm x 30mm x 2.0mm SHS

securely fixed with approved fasteners through horizontal rails to wall framing.

Provide towel rails, rings, toilet roll holders and soap holders as detailed or scheduled. Fix securely with

appropriate fasteners to wall framing.

Provide shower curtain rails as detailed or scheduled. Fix securely with approved fasteners to wall

framing or ceiling battens as required. Where no rail is scheduled provide chrome plated rail with brace

to ceiling for corner instalations.

Provide additional wall framing or noggings as required for mounting.

Co-ordinate with joiner for fixing of 19mm reeded hardwood decking with arrised edges to seat

brackets and for fixing 15mm thick exterior grade plywood with arrised edges to shelf brackets.

12.307 Kitchen Cupboards

Install steel framed kitchen sink and bench cupboards as detailed or scheduled. Screw fix frames to

floor and to wall framing as required. Co-ordinate installation with Joiner.

12.308 Cupboards & Benches

Install cupboards, shelves and benches to laundry, pantry, bedrooms and other locations as detailed or

scheduled.

Where stainless steel bench tops are required these are to have safety folds andintegral 100mm

splashback bonded to 32mm water-resistant particleboard and screw fixed to frames. Stainless steel to

be 304 grade minimum with satin finish.

Where laminate bench tops are required bond to 32mm water resistant particleboard and provide 2mm

PVC bonded edging. Seal all exposed edges and provide tile splashback with 3mm minimum colour

matched silicone bead to bench top junction and colour matched grout.

Co-ordinate installation with Joiner, Tiler and Sanitary Plumber for installation of cupboard units and

sink.

12.309 Cupboards & Bench Framing

Provide cupboard and benches frames fabricated from 25mm x 25mm x 2mm SHS ‘DuraGal’ or other

profile as detailed in drawings. Provide fixing tabs, feet and stops as required. Refer to Schedule for

finish.

Co-ordinate with Joiner for installation of cupboard units and tops.

12.310 Clothes Line

Provide clothes line as per Drawings or Schedules.

Page 53: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION - Metalwork Page F53

Where type has not been scheduled provide a post and rail clothes line at least 4.0 metres in length with

a minimum of 6 lines.

Posts shall be 32mm nominal bore galvanised steel tube with Y shaped arms 500mm per arm, 150

degree included angle with 25mm nominal bore bracing in same material as posts and anchored in

concrete.

Set posts on hard base 600mm into ground positioned in a 300mm diameter hole filled with concrete.

The average height of lines from surrounding pavement level shall be 1800mm.

12.311 Air Conditioner Stand

Where scheduled provide an air-conditioner stand manufactured of ‘DuraGal’ 40 x 40 x 2.0mm SHS.

Set frame uprights on hard base 400mm into ground positioned in 300mm dia holes filled with concrete.

12.312 Conditioner & LPG Safety Cage

Where scheduled provide safety cages fabricated from 40 x 40 x 2.0 SHS ‘DuraGal’ with 25 x 25 x

3mm galvanised woven steel mesh. Secure to concrete base and wall with expansion bolts and Tek

screws (as appropriate) to enable removal for servicing. Provide hinged door (matching RHS & mesh)

with lockable hasp and staple or padbolt to LPG cylinders. Refer to Schedule for finish.

12.313 Curtain Rails

Provide curtain rails to bedrooms and living room windows where scheduled. Refer to Schedule or

Drawings for type. Fix securely with approved fasteners to wall framing.

12.314 Field Quality Control

Where considered necessary by the Principal, arrange for the manufacturer of products to instruct

installers regarding correct installation.

12.315 Protection

Cover Work: Immediately following installation, wrap or cover architectural metalwork to avoid wear

and tear of finish during subsequent construction.

12.316 Cleaning

Clean materials installed to the satisfaction of the Principal.

Remove temporary protective coatings.

12.317 Completion

Complete contracted work in accordance with contract documents.

Page 54: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Carpentry Page F54

13 Carpentry

PART I GENERAL

13.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide materials and labour, equipment and services and perform operations necessary to complete the

carpentry as indicated and specified. Include nailers, blocking, furring, grounds, hardware, framing,

shoring, bracing, scaffolding and barriers as required for construction and/or defined in the Drawings

and construction.

13.102 Related Work

Co-operate and co-ordinate with the following trades:

Timber Framing

Joinery

Metal Framing

Metalwork

Doors and Windows

Fibre Cement

Insulation

Electrical

13.103 References

Comply with applicable portions of the following and other relevant Australian Standards:

AS/NZS 1859 Reconstituted wood - based panels

1859.1 Particle-board

1859.2 Medium Density fibreboard

1859.3 1996 Decorative overlaid wood panels

AS/NZS 2271 Plywood and blockboard for exterior use

AS 2796 – 1985 Timber – Seasoned hardwood – Milled Products: in 3 parts

AS 1604 – 1997 Preservative treatment for sawn timber, veneer and plywood

13.104 Special requirements

Not applicable.

13.105 Delivery, Handling and Storage

Deliver, handle and store products so that damage, deterioration and loss will be prevented.

Control delivery schedules to minimise long-term storage at site.

Store timber on site indoors, or above ground and cover with secure impervious material.

PART II MATERIALS

Note: these abbreviations are used when appropriate:

HWD hardwood RAD radiata pine

S seasoned CYP cypress pine

US unseasoned DAR dressed all round

PRES copper, chrome-

arsenate preservative

RG red gum

WR light organic solvent

preservative

M moulded

13.201 Timber and Related Items

Provide materials of type, size and grade as scheduled or indicated on drawings.

If items not scheduled the following is to apply:

Item Size or Type

Page 55: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Carpentry Page F55

Window reveal linings ex.100mm x 25mm HWD DAR

Window architraves ex. 75mm x 25mm HWD M

Skirtings ex. 75mm x 25mm HWD M

Cornices ex. 50mm x 25mm HWD M

Wall & ceiling linings Exterior grade Plywood 9.0mm, B Grade face veneer,

C grade back veneer, A bond

13.202 Timber Generally

Timber:

Where special provisions in regard to type and application have not been included in the Schedules, the

timber types shall be as follows:

Window linings, architraves, mouldings etc: Select seasoned hardwood

Seat slats: select seasoned reeded hardwood

Timber Skirtings: hardwood

Door frames: select seasoned hardwood

Plywood: 9mm Paint grade B/C ply with A bond (exterior) glue line.

Heads of fasteners shall be driven below the timber surface ready for stopping by Painter.

Do not use rainforest timber species unless plantation grown. Provide source certification if requested.

Provide timber that is straight and free from faults such as shakes, splitting, cupping and warping.

Use selected timber, free from weakening or unsightly defects and conditioned to finish at a moisture

content of 12% - 15%. Timber used for temporary purposes shall not be incorporated in the permanent

structure unless specifically approved.

Knots and gum veins shall not be sufficiently extensive as to reduce the strength of the timber at its

weakest point below 75% of the strength of defect free timber, unless a grading standard is specified

which permits otherwise.

Timbers showing any trace of borers, termite attack or decay of any kind will not be accepted and shall

be removed from the site to an agreed location.

Metal Fastenings:

Connectors used in fixing timber, such as framing anchors, brackets, cleats, metal soldiers and plates

shall be manufactured either from ‘Galvabond’ steel or from steel that is hot dip galvanised after

manufacturing.

Bolts shall not be less than 10 mm diameter unless shown otherwise. All bolts shall be hot dip

galvanised and fitted with matching washers and nuts.

Heads of fasteners shall be driven below the timber surface ready for stopping by Painter.

PART III EXECUTION

13.301 Examination

Visit site and inspect conditions, comparing conditions to Drawings before delivery of materials to site.

Start of work means total acceptance of conditions.

13.302 Installation

Perform operations as necessary to carry out the works. Use timber in single lengths whenever possible.

If joins are necessary, make them over supports unless otherwise shown or specified.

Arris visible edges in sawn work and in dressed work arris with abrasive paper to 1.5mm radius unless

otherwise shown or specified.

Take appropriate measures where necessary to resist warping, e.g. Back plough (groove) boards liable

to warping (for example, if exposed on one face). Make the width, depth number and distribution of

ploughs appropriate to the dimensions of the board and the degree of its exposure.

Provide necessary templates, linings, blocks, stops, ironwork and hardware, screws, bolts, plugs and

fixings generally.

Trim framing where necessary for openings, including those required by other trades.

Page 56: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Carpentry Page F56

13.303 Plywood Installation

Provide cold-formed galvanised steel framing or furring channels to suit arrangement and alignment of

sheets. Joint wall sheets vertically over studs to ensure full support to long edges. Where jointing over

studs is impractical fully back joints with timber strips 75 x 25 (nom). Joint ceiling sheets long edge

across battens. Fully back end joints with timber strips 75 x 25 (nom) where joints do not align with

battens.

Generally run wall sheets vertically and ceiling sheets across battens. Screw fix or twist nail and

combine with adhesive. Where sheets do not extend to the ceiling provide timber moulding to cover

horizontal joint. Screw heads and nails to be finished below surface ready for stopping by Painter.

Joints to be close butted with consistent use of either V-joint or square edged with uPVC joining

sections.

Frame and trim ceiling battens to suit screw fixed access hatch. Leave screw heads exposed.

Frame and trim ceiling battens for installation of airconditioner registers.

13.304 Completion

Complete contracted work in accordance with contract documents

.

Page 57: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Metal Roofing, Siding, Plumbing & Rain Water Tank Page F57

14 Metal Roofing, Siding, Plumbing & Rainwater Tank

PART I GENERAL

14.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide roofing and siding installation as shown on the Drawings including but not limited to zincalume

or Colorbond roof sheeting and Colorbond wall cladding, including accessories, fastening clips,

flashings, cappings, trims, gutters, sumps, downpipes, roof penetrations and sealing thereof and

including cladding and roof sheeting to pit toilets.

14.102 Related Work

Co-ordinate and Co-operate with the following trades:

Insulation

Structural Framing/Metal Work

Carpentry

Fibre Cement

Plumber

Electrician

14.103 Quality

Installers are required to be widely experienced in relevant aspects of the work and with the

requirements of the Australian Standards appropriate to the work.

14.104 References

Comply with applicable portions of the following Australian Standards:

AS 1170 SAA Loading Code. There are 4 supplements to this standard

AS 1562 Design and installation of sheet roof and wall cladding

1562.1 1992 Metal (Amended 1995)

AS/NZS 2179 Specifications for rain water goods, accessories & fasteners

2179.1: 1994 Metal shape or sheet rainwater goods and metal accessories.

AS 2918:2001 Domestic solid fuel burning appliances – Installation.

AS 3500 1998 National Plumbing & Drainage Part 3.2 Acceptable Solutions.

AS 3566 1988 Screws self-drilling for the building and construction industries

SAA HB 39 - 1997 Installation code for metal roof and wall cladding.

14.105 Delivery, Handling and Storage

Deliver to site, unload and stack in a location away from potential damage, preferably on appropriate

supports directly on to installed roof framing. Inspect on arrival and reject bent or damaged material.

PART II MATERIALS

14.201 Materials

Sheet materials of Australian manufacture:

Roof Sheeting: Refer to Schedule or Drawings for material, finish and profile. Where not specified use

corrugated 0.42 mm minimum AZ150 Zincalume G550 steel.

Wall Cladding: Refer to Schedule or Drawings for material, finish and profile. Where not specified use

corrugated 0.42 mm minimum Colorbond G550 steel.

Gutters: Refer to Schedule or Drawings for material, finish and profile. Where not specified use

nominal 150mm half round gutters, 0.6mm Colorbond G300 steel.

Downpipes: Refer to Schedule or Drawings for material, finish & profile. Where not specified use

100mm x 50mm x 0.48mm Zincalume.

Cappings: Refer to Schedule or Drawings for material, finish and profile. Where not specified use

0.6mm AZ150 Zincalume G300 steel.

Flashings: Refer to Schedule or Drawings for material, finish and profile. Where not specified use

Page 58: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Metal Roofing, Siding, Plumbing & Rain Water Tank Page F58

0.42mm AZ150 Zincalume or Colorbond G300 steel to match sheeting type and colour. Refer to detail

sheets for finishing thickness. Defined flashing thickness to apply.

14.202 Fabrication

Form and fabricate components in accordance with AS 1562, AS 2179 and AS 3500.3.2, and other

relevant standards.

Self-drilling screws are to conform to Class 3 as described in AS 3566.

Wire bird proofing: Refer to Schedule or Drawings for material, finish and profile. Where not specified

use WGA 002-16-1220 Galvanised wowen wire with 11.2mm aperture, 1.6mm wire diam. And 77%

open area.

PART III EXECUTION

14.301 Examination

Inspect site conditions before installation. Ensure framing is entirely satisfactory.

Ensure that delivery and installation will not be impeded by on-site condition at time of delivery.

Start of work means total acceptance of conditions.

14.302 Terrain Category

Refer to Engineer’s report. Where no wind terrain category is specified adopt the site as zoned N3:

Wind speed 41m/s.

14.303 Preparation

Prepare framing and surfaces for installation.

14.304 Installation

Install work in accordance with manufacturer's instruction and Australian Standards.

14.305 Flashing

Lap flashing at least 150mm at junctions, and over flashings neatly dressed and finished. Where

necessary to follow a roof slope, step flashings in even overlapping widths. Finish top corners to a line

parallel to the roof slope.

Fabricate flashings in materials which are compatible with, and same finish as gutter, roofing and

cladding materials as specified. Complete work and leave an entirely watertight installation.

14.306 Penetrations

Form penetration flashings neatly with material matching roofing and/or cladding materials. Form

flanged tubular collars 0.70mm sheet zinc not less than 150mm high and 12mm wider than penetrating

item, or use EPDM collars.

Where the width of a penetration is wider than a roofing trough or extends across several troughs, form

a back gutter, using sheet material similar to the roofing material, well lapped under the roofing, double

riveted and sealed with silicone sealant. Close and seal ends of cut ribs. Form back gutters not less than

100mm wide with falls towards the sides of the penetration collars.

Form over-flashings of penetration collars neatly in material matching the roofing material but not less

than 0.5mm thick, securely clipped and sealed to the penetrating items and dressed well down over the

collars to finish at a straight line level with the tops of the ribs.

Do not use lead or copper for over-flashings.

Vent, flue pipes and chimney flashings to be heat resistant Dektite Orange Flashing.

14.307 Gutters

Support gutters using 19mm x 2mm external gutter brackets at 900mm maximum centres.

Form 100mm downpipe penetrations (pops) and properly rivet and seal joint.

14.308 Downpipes

Location of downpipes shall be according to site plans. Where not defined, a minimum of two

downpipes are to be installed at opposed corners of the roof.

Install in accordance with AS 2179 and comply also with manufacturer's instructions.

Secure to building at least twice and at maximum 1500mm with 50mm x 0.8mm galvanised steel straps.

Page 59: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Metal Roofing, Siding, Plumbing & Rain Water Tank Page F59

Fixings to steel columns shall be with approved one-operation screws to AS 3566 Class 3, drilled and

tapped to column.

Install site cast 500mm x 500mm x 100mm thick splash pad to base of downpipes.

14.309 Fasteners

Fasteners to be according to SA 3566 – 1988 Class 3.

Roofing Buildex Metal Teks Hex-head, EPDM seal, 12-14 x 35 HiTeks, crest 4 fix 2:3:3:2

pattern mid span, crest 5 fix 2:2:2:2:2 pattern to end span.

Siding Buildex Metal Teks Hex-head, colour matched painted, EPDM seal, 10-16 x 16

HiTeks, valley 4 fix 3:2:2:3 pattern, max spacing 900mm.

Rivets for Galvabond, Zincalume & Colorbond steels use aluminium rivets

Washers EPDM washers to roofing, siding, ridge caps, barge caps etc.

14.310 Bird Proofing

Provide and install all bird proofing accessories deemed necessary to leave roof completely proofed

against bird entry.

14.311 Vermin Proofing

End cap or seal flashings, corner cappings and all other trims to prevent vermin access to the wall

frames, roof spaces and internal areas of the house.

14.312 Rainwater Tank

Refer to Schedule and Drawings for size, type, finish and location of rainwater tank.

Co-ordinate with concretor and carpenter.

The tank is to sit on a base or stand 300mm minimum above ground level.

Fit 19mm range cock with lever head and rough nickel body (to allow for tank drainage).

Plumb to kitchen sink.

Where polyethylene tanks are specified provide polyethylene rainwater tanks with DN50 threaded

polyethylene outlet as per detail.

Connect roof gutter to tank with a downpipe before installation of roof sheeting.

14.313 Wood Heaters

Provide wood heater as per schedule.

Install according to manufacturer’s recommendations and in accordance with AS 2918.

Cut neat penetrations of ceiling and roofing. Ensure adequate clearance between flue and trusses.

Adjust location of roof purlins or battens or provide additional purlins or battens to allow adequate

clearance to the flue. Seal roof penetrations according to clause 14.306 above.

14.314 Cleaning

To prevent contamination and corrosion keep metal roofing and rainwater goods clean at all times

during the progress of the works.

At the end of work each day, and immediately before each occurrence of rain, sweep the metal surfaces

thoroughly to remove metal filings, swarf, off-cuts, dust, and other materials which could cause

corrosion or blockages. Prevent waste materials from entering downpipes, rainwater heads, or drains.

Remove unsecured nails, rivets, screws, bolts and similar fixing devices and loose guttering, etc at the

end of work each day and at the completion of roofing installation.

14.315 Testing

On completion, test the entire installation to the satisfaction of the Principal.

14.316 Completion

Complete contracted work in accordance with contract documents.

Page 60: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Fibre Cement Products Page F60

15 Fibre Cement Products

PART I GENERAL

15.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide fibre cement products and associated equipment and fixings including but not limited to:

Wet area wall lining

Exterior wall linings

Ceilings & Soffits

Flooring

Tiled wall panels

15.102 Related Work

Co-ordinate and co-operate with the following trades:

Wall framing

Structural Framing

Minor Steelwork

Ceiling framing

Tiling

Insulation

Plumber

Electrician

15.103 Quality

The work of this section shall be performed by a tradesperson with wide experience and knowledge in

this class of work.

15.104 References

Comply with applicable portions of the following Australian Standards:

AS 2329 1980 Mastic adhesives for fixing wallboards

AS 2908 1992 Cellulose - cement products

2908.2 - 1992 Flat sheets

15.105 Special Requirements

Not applicable.

15.106 Delivery, Handling and Storage

Deliver materials in bundles or packages with care. Stack on edge or lay flat under cover and keep dry

until installed. Protect edges and covers from chipping.

PART II MATERIALS

15.201 Materials

Villaboard Thickness 6mm Heater wall lining (over ply)

Villaboard Thickness 9mm Wet area wall linings

Fibrous Cement Sheet Thickness 15mm Flooring

Fibrous Cement Sheet Thickness 9mm Internal wall linings

Hardie Plank weather boards External claddings

15.202 Equipment

Supply equipment required for the erection and installation of the specified materials as recommended

by the manufacturer.

Page 61: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Fibre Cement Products Page F61

PART III EXECUTION

15.301 Examination

Visit site and inspect conditions, comparing conditions to the Drawings before delivery of materials to

site. Rectify any discrepancy or unsuitability of substrate.

Start of work means total acceptance of conditions.

15.302 Preparation

Co-ordinate with and ensure preparatory work by other trades is done prior to commencement of work

and arrange for fixing grounds required for satisfactory execution of the work of this trade including

penetrations through cement sheet for services.

15.303 Installation

Comply with the manufacturer's installation instructions. Anchor and fasten materials and components

to comply with ratings and performance requirements, and to comply with governing local regulations.

Comply with appropriate Australian Standard.

Use screws only to areas where substrate is used for tiling, per stud 200mm max centres, 12mm min

offset from sheet edge, 50mm min offset from corners.

Provide perimeter insitu flashing membrane to floor wall junctions, ABA Superflex 1 with bond

breaker, or equivalent approved. Provide vertical corner flashing, fibre cement PVC angle 50 x 50.

Provide flexible sealant to tap penetrations, vertical corners to shower recess, and expansion joints.

Take care of and protect surrounding work, including other finishes, equipment and components, during

installation. Provide protective covering where necessary.

15.304 Installation Particulars

Comply in all respects with manufacturers recommendations contained in technical bulletins.

Screws: Self-embedding head drill point for steel framing 0.8 to 1.2mm, No8 x 20mm.

Glue (for non tiled areas if applicable): Plasterboard acrylic stud ashesive.

Flexible Sealant: Dow or Selleys Corning Brick & Concrete crack sealant.

15.305 Finishing Details

Finish joints and secure fasteners. Flush joints to wet areas with fibre cement wet area base coat and

paper tape. Remove surface defects to achieve uniform appearance of each type of installation.

15.306 Protection

Protect finished work. Make good damage in every respect.

15.307 Cleaning

Clean exposed surfaces including trim, edge mouldings, and comply with manufacturer's instructions

for cleaning and touch-up of minor finish damage.

Remove spatterings, droppings and surplus material.

15.308 Completion

Complete contracted work in accordance with contract documents.

Page 62: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Plasterboard Page F62

16 Plasterboard

PART I GENERAL

16. 101 Scope

Refer to Drawings & Schedules for the extent of work relating to this section.

Supply and install a complete installation of plasterboard including but not limited to:

Plasterboard

Plasterglass

Flexible plasterboard, 6.5mm thick in 2 layers

Lining of concrete and masonry walls

Lining of steel stud walls

Lining with water-resistant plasterboard

Ceilings, drop walls, bulkheads

Fire-rated plasterboard walls/ceilings

Cornices

16. 102 Related Work

Co-ordinate and co-operate with the following trades:

Masonry Walls

Electrical

Stud Walls

Suspended Ceilings

16. 103 Quality Assurance

Where requested by the Principal and at a location selected by the Principal, construct a complete

prototypical installation of plasterboard on each different substrate.

Each sample, full height by 3600 wide includes elements required by this Specification and finish in

every respect. When approved by the Principal, this sample will remain part of the work and becomes

the standard for the remaining work.

16.104 References

Comply with applicable portions of the following Australian Standards:

AS/NZS 2589.1 1997 Gypsum linings in residential & commercial construction - Application and

finishing

2589.2 1997 Fibre reinforced gypsum plaster

AS 2753 1985 Adhesives, mastic for bonding gypsum plaster to framing members.

16.105 Delivery, Handling and Storage

Deliver manufactured materials in bundles and packages bearing the name of the manufacturer, and the

brand. Handle with care. Remove damaged materials from the site. Protect stored materials from

damage and damp, or materials which may cause deterioration.

16.106 Warranty

Provide Warranty covering the work against defective materials and workmanship for a period of five

(5) years from the date of Practical Completion. The Warranty includes a statement that the whole of

the work has been carried out in accordance with relevant Australian Standards and Codes and

manufacturer's instructions in effect at the time of installation.

PART II MATERIALS

16.201 Acceptable Manufacturers

Boral

CSR

Page 63: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Plasterboard Page F63

16.202 Materials

Supply materials in accordance with material supplier's recommendations for each application.

LOCATION PRODUCT THICKNESS

Ceilings Gyprock Supaceil 10mm

Walling Gyprock Impactchek 10mm

Cornice Coved plasterboard 55mm

PART III EXECUTION

16.301 Examination

Acceptance: Visit site and inspect conditions, comparing conditions to Drawings before delivery of

materials to site. Rectify any discrepancy or unsuitability of substrate.

Start of work means total acceptance of conditions.

16.302 Preparation

A. Co-ordinate with and ensure preparatory work by other trades is done prior to commencement

of work; failure to do so will involve removal of plasterboard and immediate rectification.

B. Arrange for provision of additional stud, nogging, trimmed openings, boxed studs, fixing

grounds, etc., required for satisfactory execution of the work of this trade including

penetrations through plasterboard for services. Co-operate in installation of frames, duct

openings, etc.

C. Space Enclosure: Do not install materials until space is enclosed and weatherproof, and until

wet-work in space is completed and nominally dry.

16.303 Layout and Tolerances

A. Check dimensions of areas and surfaces to which material is applied before installation begins.

B. Measure each area and establish layout pattern.

C. All finished work is to be within + 2mm of the sizes shown on the relevant Drawings.

16.304 Installation - General

A. Comply with manufacturer's installation instructions. Anchor and fasten materials and

components to comply with ratings and performance requirements, and to comply with

governing local regulations. Comply with appropriate Australian Standard.

B. Take care of and protect surrounding work, including other finishes, equipment and

components, during installation. Provide protective covering where necessary.

16.305 Finishing Details

General: Apply treatment at board joints (both directions), flanges of trim accessories, penetration,

fasteners, heads, surface defects and elsewhere as required to prepare work for decoration. Pre-fill open

joints and rounded or bevelled edges, using type of compound recommended by manufacturer.

A. Apply fibreglass joint tape at joints between boards, where a trim accessory is indicated, or

where extra strength is required.

16.306 Protection

Protect finished work. Make good damage in every respect at no additional cost to the Proprietor, and

without delay to job progress.

16.307 Cleaning

A. Adjust and Clean: Clean exposed surfaces including trim, edge moldings, and comply with

manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and

replace work which cannot be successfully cleaned and repaired to permanently eliminate

damage.

B. Remove spatterings and droppings resulting from work. Remove daily surplus materials and

rubbish from the work area.

C. Leave floors broom clean at completion.

16.308 Completion

Complete contracted work in accordance with contract documents and written variation orders issued

by the Principal.

Page 64: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Doors & Door Frames Page F64

17 Doors & Door Frames

PART I GENERAL

17.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide doors and steel door frames including but not limited to:

External solid core doors:

Security and insect screen (steel) doors

Internal solid core doors.

17.102 Related Work

Co-ordinate and Co-operate with the following trades:

Metalwork

Painting

17.103 Quality

This work is to be done by specialists with experience in the work.

17.104 References

Comply with applicable portions of the following Australian Standards:

AS/NZS 1859 1997 Re-constituted wood-based panels. Includes particleboard and medium

density fibreboard

1859.1 Particleboard

1859.2 MDF

1859.3 Decorative overlaid wood panels

1859.4 Hardboard

1859.5 Fibre insulating board

AS 2272 Marine plywood

AS 2688 1984 Timber doors

AS 2689 1984 Timber Door sets

AS/NZS 2803 Doors - security screen

2803.1 1994 Hinged

2803.2 1995 Sliding

AS/NZS 2804 Installation of security screen doors

2804.1 1995 Hinged

2804.2 1996 Sliding

AS 4145 Lock sets. There are 2 parts to this standard

17.105 Delivery Handling & Storage

Deliver specified items shortly before installation is due to occur.

Prevent damage and deterioration during transport and handling.

Store carefully at site in a secure area. Prevent twisting and warping of doors.

PART II MATERIALS

17.201 Doors Generally

Provide doors and hardware as scheduled. If not otherwise nominated doors shall be as External timber

doors:

Size: 820 x 2040

Thickness: 35mm

Material: solid-core with 4.8mm tempered hardboard both sides with edge strips and dust seals.

External steel frames:

Pressed ZF100 Zincanneal steel 1.6mm thick double-rebated fully welded frames with floor spreader

Page 65: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Doors & Door Frames Page F65

and three pre-fitted 100mm hinges.

Provide 75mm x 1.2mm galvanised or zincanneal steel straps projecting 150mm from frame and two

black stops on closing side.

Supply steel frames with shop applied rust inhibitive primer paint.

Security screen doors:

Refer to Schedule for type. Where no type specified the following applies:

Steel-Type as available from Hyland & Sons, 17 Bennet St, Dandenong, Victoria 3175. Telephone (03)

9706 9938.

Internal timber doors:

Size: 820 x 2040

Thickness: 35mm

Material: solid-core with 4.8mm tempered hardboard both sides with edge strips.

Internal steel frames:

As above for external steel frames.

Pit Toilet doors (where applicable):

Duragal 25 x 25 x 2mm SHS frame, welded hinges, Panelrib clad one side.

PART III EXECUTION

17.301 Examination

Inspect site conditions. Ensure conditions are satisfactory for installation. Start of work means total

acceptance of conditions.

17.302 Preparation

Prepare openings in walls or other structures before installation. Install fixing grounds and inserts as

required to secure frames.

17.303 Installation of door frames

Erect frames plumb and true. Brace as required until surrounding structure is complete. Comply with AS

2689.

17.304 Installation of Doors

Comply with manufacturers instructions and AS 2689. Reject doors which do not comply with AS 2688

Appendix A. Condition doors to average humidity in area prior to hanging.

Align doors to frame for proper fit and uniform clearance at edge and machine for hardware. Seal cut

surfaces after machining.

Provide clearance of 3mm at jambs and heads; 3mm at meeting stiles at pairs of door; 12mm from

bottom of door to top of floor finishing or covering. At thresholds provide 6mm clearance.

Provide 3 x 100mm loose pin zinc plated hinges per door.

17.305 Installation of Hardware

Refer to Schedule of door furniture and hardware. Check deliveries on arrival. Keep items locked until

needed. Assume responsibility for delivered items. In general and unless otherwise specified fit handles at

900mm, locks at 1100mm. Fit cover plate to all locks. Fit accurately and at correct heights, protect with

heavy cloth until completion of project.

Master key locks as per schedule.

Label keys according to the code in the schedule.

Hand over 3 copies of each key at Practical Completion.

17.306 Adjustment and Cleaning

Adjust each door in its frame and ensure silent operation. Oil locks and hinges. Clean all surfaces

marked during the installation of door frames, doors and hardware.

17.307 Completion

Complete contracted work in accordance with contract documents.

Page 66: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F66

18 Metal Windows & Glazing

PART I GENERAL

18.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide a complete glazed system of aluminium windows and screens.

18.102 Related Work

Co-ordinate and Co-operate with tradesmen preparing walls and frames to accept windows.

18.103 Quality

This work shall be carried out by a specialist fabricator with suitable experience in the work.

18.104 References

Comply with applicable portions of the following Australian Standards:

AS 1170 SAA Loading Code

1170.1 1989 Dead and live loads and load combinations

1170.2 1989 Wind loads (Amended 1993)

AS 1231 1985 Aluminium and aluminium alloys - Anodised coatings for architectural

applications

AS 1288 1994 Glass in buildings - Selection and installation. Amended 1997

AS 2047 1977 Aluminium windows in buildings

2047.1 - 1996 Specification for materials & performance

2047.2 - 1996 Construction, installation and maintenance,

AS 3715 1989 Metal finishing - Thermoset powder coatings for architectural applications

18.105 Special requirements

Not applicable.

18.106 Delivery, Handling and Storage

Handle materials with care. Do not store on site. Install directly in place. Store sealants as instructed by

manufacturer.

PART II MATERIALS

18.201 Materials

Window Frames: Extruded aluminium components manufactured from aluminium alloy 6063, temper T5 or

T6. Match to components detailed on Drawings.

18.202 Structural Criteria

Terrain Category

N3 41m/sec Refer AS 1170.

Wind Loading Design:

Glazing and frame assemblies to suit the static and dynamic wind forces as indicated on the tables in the

Australian Standard 1170.

Structural members of glazed units of such strength that when tested at the specified design wind values they

do not deflect by an amount greater than span/240 and do not cause permanent deflection.

Fix members so that the above loading is generated in the members without stress causing failure or

movement becoming evident at any joint.

Movement: Permit free and noiseless movement of the components due to thermal effects, structural effect,

wind pressure, effect of dead loads, without strain to glazing, without buckling of components and without

excessive stress to members or assemblies.

Contact with Other Materials: Coat metal surfaces in contact with mortar, concrete, plaster, masonry, wet-

application of fire-proofing and absorbent materials with an anti-galvanic, moisture barrier material. Isolate,

with inert material, dissimilar metals for the prevention of electrolytic action and corrosion.

Distortion: Design the glazed assembly to minimise visual distortion of reflected images.

Page 67: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F67

18.203 Detail Design Provisions

General: The Drawings are to be considered essentially schematic except for profiles of exposed surfaces and

panel arrangement where indicated. If, in the opinion of the Contractor a change of profile is required in order

to meet the specification, arrange through the Principal for a review of the condition. Design the assembly,

reinforcing and anchorage to suit each specified condition in an acceptable manner complying with the

requirements specified herein.

Tolerances: Design frames to accommodate building tolerances, and when completed, within the following

tolerances:

Deviation from plumb, level or dimensioned angle within 3mm per 3.5m of length of member, or 6mm in total

run in line.

Deviation from theoretical position on plan or elevation, including deviation from plumb, level or

dimensioned angle not to exceed 9mm total at location.

Change in deviation not to exceed 3mm for 3.5m run in direction.

18.204 Finish

Refer to Schedule

Polyester powder coat:

Minimum coating thickness of 50 microns subjected to random testing after installation. Non-conforming

material shall be removed and made good by the Contractor.

Comply with requirements of AS 3715.

18.205 Glazing Material

In Communities and Outstations glazing materials shall be polycarbonate. Refer to table below for approved

thickness. For wind category 41m/s the maximum short length for 4.5mm polycarbonate is 980mm.

In all other locations glass shall apply unless otherwise scheduled.

Generally, and unless otherwise indicated on Drawings, or nominated in the Schedule, windows shall be

glazed as follows.

Top pane: Clear

Sash: Clear.

Toilet: Opaque

Bathroom: Opaque

Laundry: Clear

18.206 Window Glass

Glass to Bathroom, utility and W.C. areas and any internal borrowed lights, shall be decorative glass,

‘Satinlite’ or equal approved.

Except where otherwise indicated, the remaining window glass is to be clear.

The minimum thickness and type of glass shall be as indicated in the following tables.

Areas in m² of ordinary annealed framed glass for differing design wind speeds;

Design Wind Speed

Thickness 28m/s 33m/s 41m/s 45m/s

3mm 2 1.4 1.0 0.8

4mm 3.5 2.4 1.7 1.4

5mm 5.2 3.6 2.6 2.1

6mm 7.4 5.2 3.6 2.9

8mm 11.0 7.9 5.4 4.4

Areas in M² of ordinary annealed patterned glass for differing design wind speeds;

Design Wind Speed

Thickness 28m/s 33m/s 41m/s 45m/s

3mm 1.7 1.1 0.8 0.6

4mm 3.0 2.1 1.5 1.2

5mm 4.8 3.3 2.4 1.8

6mm 6.6 4.8 3.5 2.6

Page 68: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F68

Where Grade A safety glass is required in framed glazing for doors and sidelights and windows next to doors,

the following applies:

Minimum Glass thickness for toughened glass;

Max. Area of Pane Min. Thickness

1.0m² 3mm

2.0m² 4mm

3.0m² 5mm

4.0m² 6mm

Unless otherwise detailed the minimum glass thickness for panels starting less than 500mm above floor shall

be as follows;

Max. Area of Pane Min. Thickness

0.3m² 4mm

2.0m² 5mm

Glass to Doors

Glaze full and half glass doors in clear glass, unless directed otherwise.

Where a sidelight adjoins a glass door the glazing shall be in decorative glass.

18.206 Sealants and Accessory Materials

Sealants shall be appropriate to their application and as approved Principal and by the manufacturers of the

framing, glazing and sealant components of the installation.

Do not use PVC gaskets, amine or benzamide curing silicone sealants when glazing with polycarbonate sheet.

Provide non-structural external weatherproofing sealants of low modulus neutral curing silicone rubber

compounds by approved manufacture.

Generally comply with AS 1288, Part 2, Section 6 or 8. Supply spacer gaskets, glazing tapes and setting

blocks compatible with sealants, which do not contribute to sealant colour change or affect the sealants

adhesion to substrates when exposed to ultraviolet light.

Prior to application, samples of materials receiving the silicone, including elastomeric sealants are to be

evaluated by the silicone sealant manufacturer for compatibility and primer selection. Clearly identify the

submitted materials as to manufacturer and product number.

Interior Sealers: Acrylic-emulsion or latex-rubber-modified acrylic emulsion sealant compound, permanently

flexible, non-staining and non-bleeding; recommended by manufacturer for protected exterior exposure and

general interior exposure.

Joint Primer/Sealer: Provide type of joint primer/sealer as recommended by sealant manufacturer to suit each

surface.

Bond Breaker Tape: Polyethylene tape or other plastic as recommended by sealant manufacturer to be applied

to sealant-contact surfaces where bond to substrate or joint filler is to be avoided for proper performance of

sealant. Provide self-adhesive tape where applicable.

Sealant Backer Rod: Compressible rod stock of polyethylene foam, polyethylene jacketed polyurethane foam,

butyl rubber foam, neoprene foam or other flexible permanent, durable non-absorbent material as

recommended by sealant manufacturer for compatibility with sealant.

Glazing Tape: Polyisobutylene tape of type, thickness and width as recommended by glass manufacturer and

Principal.

Exposed screws: countersunk type, anodised aluminium or non-magnetic stainless steel evenly and neatly

located in an approved manner. Exposed fasteners: finished to match aluminium.

18.207 Fabrication

Comply with AS 2047.

Framing System: Fabricate from extrusions as approved.

Form junctions so that no fixings, such as pins, screws, pressure indentations and the like are visible on

exposed faces. Cut edges, drill holes, rivet joints and clean flat sheets, neat, free from burrs and indentations.

Remove sharp edges without excessive deformation. Fit mitred joints accurately to a fine hairline.

Pre-assemble and match mark before delivery.

Page 69: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F69

Generally, and unless otherwise nominated opening sash windows shall be vertical sliding type

PART III EXECUTION

18.301 Examination

Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are

satisfactory for installation.

Perform rectification required before delivery of materials.

Start of work means total acceptance of conditions.

18.302 Preparation

Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.

18.303 Frame Anchorage

Provide the anchorage devices for building in and check that devices are located as required to suit the

requirements of window frame fabrication for positive and permanent fixing, complying with, for example,

AS 2048.

Insulation: Isolate dissimilar metals at interfaces with bitumen based or nylon shim materials to prevent

galvanic action.

18.304 Frame Installation

Comply with AS 2048, Code of Practice for Installation and Maintenance of Aluminium Window Frames.

18.305 Glazing

Secure glazing material in accordance with manufacturer's recommendations. Allow for thermal expansion of

glazing material, the metal framing and spandrels.

14.306 Preparation for Sealants

Joint Preparation Sealants: Clean joint surfaces immediately before installation of sealant or caulking

compound. Remove dirt, insecure coatings, moisture and other substances which could interfere with bond of

sealant or caulking compound. Etch concrete and masonry joint surfaces as recommended by sealant

manufacturer. Roughen vitreous and glazed joint surfaces if recommended by sealant manufacturer.

Prime or seal joint surfaces where indicated, and where recommended by sealant manufacturer. Do not allow

primer/sealer to spill or migrate on to adjoining surfaces.

18.307 Installation of Sealants

Install bond breaker tape where required by manufacturer's recommendations to ensure that elastomeric

sealants will perform properly.

Employ only proven installation techniques, which will ensure that sealants are deposited in uniform

continuous ribbons without gaps or air pockets, with complete ‘wetting’ of joint bond surfaces equally on

opposite sides. Except as otherwise indicated, fill sealant rabbet to a slightly concave surface slightly below

adjoining surfaces.

Install sealant to depths as recommended by sealant manufacturer.

Cure sealants and caulking compounds in compliance with manufacturer's instructions and recommendations,

to obtain high early bond strength internal cohesive strength and surface durability.

Maintain procedures required for the curing and protection of joint sealers during construction period, so that

they will be without deterioration or damage (other than normal wear and weathering) at time of Practical

Completion.

Remove excess caulking compound and sealant and leave surfaces neat, smooth and clean, without smears on

surrounding work. Tool joints where recommended by manufacturer or where required. Remove cartons and

debris from site as the work progresses.

18.308 Security Screens

Fit approved security insect screens to all windows. Fit one opening security screen hinged at top to open

outwards, with two bottom catches per bedroom, located opposite to the door where possible.

18.309 Protection

Framing System: Protect metal surfaces as necessary during erection. Finish surfaces free from mechanical

imperfections such as scratches, scrapes, dents, spots, stains and streaks.

Glazing: Protect glazing from damage immediately upon installation and until Practical Completion. Remove

and replace glazing and metal panels which are in any way damaged before, during or after installation.

Page 70: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F70

18.310 Cleaning

Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass, frames, hardware

and other finished surfaces immediately upon installation of glazing for each light.

Debris: Remove rubbish and debris resulting from glazing operations, each day.

18.311 Completion

Complete contracted work in accordance with contract documents.

Page 71: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F71

19 Insulation (Thermal and Acoustic)

PART I GENERAL

19.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

The scope of work includes but is not limited to, the supply and installation of thermal insulation.

19.102 Related Work

Wall & Roof Framing

Metal Roofing, Siding & Plumbing

Carpentry

Fibre Cement

19.103 Quality

Installers are required to be widely experienced in relevant aspects of the work and with the requirements of

the Australian Standards appropriate to the work.

19.104 References

Comply with the applicable portions of the Australian Standards.

AS 2627 Thermal Insulation of dwellings.

2627.1 1993 Thermal Insulation of roof/ceilings and walls in dwellings.

AS 3999 1992 Thermal insulation of dwellings - Bulk insulation - Installation requirements

AS/NZS 4200 Pliable building membranes and underlays

4200.1 1994 Materials

4200.2 1994 Installation requirements

19.105 Delivery, Handling and Storage

Deliver, handle and store products so that damage, deterioration and loss will be prevented. Control delivery

schedules to minimise long-term storage at the site.

Store under cover and above ground with secure impervious material.

PART II MATERIALS

19.201 Materials

Refer to Drawings or Schedule. Where materials are not defined the following shall apply.

Roof: R3.3 mineral fibre insulation with R0.5 Medium weight reflective foil sarking flammability index less

than 5.

External walls: R2.0 mineral fibre insulation with medium weight perforated sarking to external face of studs

Vapour barriers - with and without reflective facings - paper/foil, high density polyethylene breather

membranes, aluminium foil reinforced or folded as batts.

Comply with manufacturers recommendations and AS/NZS 4200.1 Materials

Thermal insulation - in sealed batts semi-rigid glasswool, rockwool or polyester, with or without facing.

Comply with manufacturer’s recommendations the applicable Australian Standards.

PART III EXECUTION

19.301 Examination

Visit the site and inspect conditions, comparing conditions to Drawings before delivery of materials to site.

Start of work means total acceptance of conditions.

19.302 Preparation

Prepare surfaces and or framing material and ensure that no obstructions will prevent rapid and effective

installation.

19.303 Installation General

Comply with manufacturer’s current written recommendations and the relevant Australian Standards.

Page 72: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F72

To all framed external walls, ceilings and roofs install, insulation and perforated sarking under external linings

material and insulation and vapour proof sarking to roofs to achieve required insulation ratings.

19.304 Cleaning

Remove surplus material from the site on completion and arrange for inspection by Principal.

19.305 Completion

Complete contracted work in accordance with the contract document.

Page 73: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F73

20 Joinery

PART I GENERAL

20.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

The work of this Section covers the supply and installation of site built joinery items and manufactured

casework. It includes, but is not limited to:

Wardrobes

Cupboards

Benches

Shelves

Trim, architraves, skirtings, pelmets etc.

Hardware

20.102 Related Work

Co-ordinate and co-operate with the following trades:

Carpentry

Floors

Walls

Ceilings

Doors and windows trades

Plumbing

Electrical installations

20.103 Quality

This work shall be carried out by specialists trade-persons approved by the Principal.

20.104 References

Comply with applicable portions of the Australian Standards listed in Section 13 CARPENTRY, plus the

current editions of the following:

4AS/NZS 1859 Reconstituted wood-based panels

AS 2754 1991 Adhesives for timber and timber products

2754.2 1991 Polymer emulsion adhesives

2754.3 1988 Adhesives for non-structural applications

AS 2131 1987 Adhesives – for bonding decorative thermoset laminates (contact adhesives)

AS 2924 Decorative thermosetting laminated sheet

AS/NZS 4386 Domestic Kitchen Assemblies

20.105 Delivery, Handling and Storage

Do not deliver until completion, anything which could soil, damage or deteriorate joinery. Prevent soiling,

damage or deterioration during delivery, storage and handling.

Keep site storage to a minimum. If circumstances make storage necessary in areas other than the final

location, store only in those that meet the requirements specified for installation areas.

PART II MATERIALS

20.201 Materials

Materials are to be of the type, size and grade specified or indicated on the Schedules or Drawings. Where

details are not defined the following shall apply.

Carcasses:

Cupboards, pantry, wardrobes:

Ends, vertical divisions, floors, shelves, doors: 18mm High Moisture Resistant MDF

Steel frame 25 x 25 x 2 SHS, paint finish

Drawers:

Fronts: 18mm High Moisture Resistant MDF

Drawer carcass: 15mm Exterior Grade Ply, all painted

Page 74: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F74

Kitchen Bench Tops: 32mm High Moisture Resistant MDF

Stainless steel bonded top

Robes:

Shelves, sides & doors: 18mm High Moisture Resistant MDF

Backs, 16mm High Moisture Resistant MDF

Paint finish

Bathroom Seats: 19mm Reeded Hardwood slats

Paint finish, steel frame

Bathroom / Laundry Shelves: 15mm Exterior Grade Plywood Paint finish, steel frame

20.202 Hardware

Handles: 75mm satin chrome D handles

Hinges: Concealed snap-on, self-closing with dome head bolts through door

Note: ‘Bolts through door’ applies only to work specifically identified.

Slides: Single extension with fixing to drawer bottom

PART III EXECUTION

20.301 Examination

Visit the site and inspect conditions. Check dimensions and compare aspects with the Drawings and

Specification. Resolve differences before ordering materials or starting work.

Start of work means total acceptance of conditions.

20.302 Preparation for Joinery Installation

Prior to installing, condition joinery to the average humidity conditions prevailing in the installation areas.

Deliver anchoring devices and similar inserts required to be built into substrates well in advance of the fixing

of fittings and provide full details when they are to be fixed by others.

Prior to installation, examine shop-fabricated work for completeness and remedy deficiencies. Include back

priming and the removal of packing.

Thoroughly clean floors and walls that will be permanently concealed by joinery.

20.303 Installation of Joinery

Use concealed shims as required to install the work plumb, level, straight and distortion free within the

following tolerances:

1mm in 800mm for plumb and level (including bench tops),

0.5mm maximum offsets in flush adjoining surfaces,

2mm maximum offsets in revealed adjoining surfaces.

Scribe and cut to fit adjoining work. Refinish cut surfaces or repair damaged finishes at cuts.

Secure joinery with anchors or blocking built-in or directly attached to substrates. Secure to grounds, stripping

and blocking with countersunk, concealed fasteners and blind nailing as required to complete the installation.

Except where pre-finished matching fastener heads are required, use fine finishing nails, countersunk and

filled flush. Use a matching filler where a transparent finish is required.

Install joinery items without distortion so that doors will fit openings properly and be accurately aligned.

Unless otherwise indicated on Drawings:

A. Mouldings:

Mouldings shall be mitred or scribed at angles, and edges shot true and straight before fixing. Scribe

as necessary to fit straight and tight against adjacent surfaces, after wall linings are flush jointed and

completed.

B. Architraves:

Provide architraves around all windows frames, at junctions of built in cupboards with walls, and

where detailed, of the profile indicated.

Rebate architraves to neatly cover junctions with wall tiles. Fixings shall be at 250 mm maximum

centres.

For architrave requirements refer to details and notes included in the detail drawings.

C. Skirtings:

Except where otherwise specified, provide timber skirtings along floors to all exposed wall surfaces.

Fit skirtings neatly against wall faces and flooring and screw fix to wall frames. Alternatively patent

Page 75: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Joinery Page F75

steel pin fastenings may be used with the approval of the Principal. All fixings shall be at 600 mm

maximum centres. Caulk all gaps. Fix skirtings over resilient flooring.

D. Cover Beads:

Provide 19 x 19 mm or as indicated cover beads with one arris removed and pencil rounded, to cover

junctions with adjacent surfaces of cupboards and other built in items where shown and as required.

E. Cupboards Generally:

Build in and firmly fix units in position to finish in relation to adjacent surfaces.

Secure wall units at 600mm maximum centres through fixing rails with recommended fasteners to

suit the type of wall to which the unit is to be fixed (eg. wood screws, dyna bolts, coach bolts). For

all bench units seal between the underside of the tiles and the bench top with an approved neutral,

mould resisting, self curing flexible sealant.

F. Hardware Generally:

Unless otherwise stated exposed metal items shall be chromium plated or be stainless steel. Screws

shall match the item to be fixed, ie chrome plated on brass or stainless steel.

Obtain instructions from the Principal for exact positioning of hardware, check hanging of doors, etc

before fixing.

Note that hardware is to be removed before painting backgrounds to which it is fixed. Replace after

completion of paint work.

Test all moving parts and ensure that locks, latches and other operative items are in sound working

condition at time of Practical Completion.

20.304 Hardware

Install joinery hardware as scheduled, listed and required in full compliance with the manufacturer's

recommendations.

Adjust as needed to centre doors in openings.

20.305 Adjustments, Cleaning, Finishing and Protection

Finish the work specified in this Section and remedy anything not finished at the shop or other stage prior to

completion.

Adjust joinery to achieve a uniform appearance.

Lubricate and clean hardware making final adjustments needed for proper operation.

Remove handling marks from visible joinery surfaces.

Protection: Do everything needed to ensure that work is without damage or deterioration at Practical

Completion.

20.306 Completion

Complete contracted work in accordance with contract documents.

Page 76: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Unit Kitchen Page F76

21 Unit Kitchen

PART I GENERAL

21.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

The work of this Section covers the supply and installation of manufactured unit kitchen items.

It includes but is not limited to:

Kitchen cabinets and cupboards

Pantry & shelves

Shelving

Robes

21.102 Related Work

Co-ordinate and co-operate with the following trades:

Carpentry

Wall Finishes

Floor Finishes

Ceiling Finishes

Plumbing

Electrical Installation

21.103 Quality Assurance

Manufacturers and installers are required to be widely experienced in the relevant aspects and class of

work required for this section.

21.104 References

Comply with applicable portions of the Australian Standards:

AS/NZS 1859 Re-constituted wood-based panels. .Includes particleboard & medium density

fibreboard. There are 5 parts of this standard, dated 1996 and 1997

AS 2131 1987 Adhesives - for bonding decorative thermoset laminates (contact adhesives)

AS 2924 1987 Decorative thermosetting laminated sheet

AS/NZS 4386 Domestic Kitchen Assemblies

4386.1 1996 Kitchen Units

4386.2 1996 Installation

21.105 Submissions

Submit the following prior to fabrication:

Product literature on all proposed hardware items including components.

21.106 Delivery, Handling and Storage

Do not delivery work to the site until after completion of other trade activities which could soil, damage

or cause deterioration of manufactured joinery items l.

Prevent soiling, damage or deterioration during delivery, storage and handling.

Keep site storage to a minimum. Install directly in place, but refer to Clause 302.

If circumstances make storage necessary in areas other than the final location, store only in those that

meet the requirements specified for installation areas.

PART II MATERIALS

21.201 Materials

Refer to Schedule and Drawings for materials specified. Where details are not defined the following

shall apply.

Carcase Material Thickness Finish

Page 77: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Unit Kitchen Page F77

Ends and vertical divisions Moisture Resistant MDF 18mm Melamine

Floors and tops Moisture Resistant MDF 18mm Melamine

Shelves Moisture Resistant MDF 18mm Melamine

Doors Moisture Resistant MDF 18mm Melamine

Back Moisture Resistant MDF 16mm Melamine

Edge strips Protected 0.4mm Melamine

Edge strips Exposed 2.0mm PVC

Laminates As Scheduled

Bench Tops Moisture Resistant particle

board

32mm Laminate or SS

refer Schedule

21.203 Fasteners and Adhesives

A. Metal fasteners:

Manufacturer: Buildex

Type: Contersunk rib head 8-10 x 40mm (6-241-0103-2) (Carcase members)

Type: Contersunk rib head 8-10 x 18mm (6-241-0099-5) (Hinges)

Type: Coach head bolt with dome nut M5 (Hinges to door) (Designated Aboriginal Lands

only)

Type: Wafer head 10-16 x 30mm (6-311-0535-7MP) (Carcase to RHS frame)

B. PVA adhesives: Comply with AS 2754.

C. Contact adhesives: Comply with AS 2131.

21.204 Hardware

A. Hinges

Manufacturer: Submit data for approval prior to manufacture.

Type: Fully metal bodied concealed snap-on self closing

Number per door Max width Max height

2 450 800

3 600 1200

4 600 1800

B. Catches

Manufacturer: Submit data for approval prior to manufacture.

Type: NA

C. Door handles

Manufacturer: Submit data for approval prior to manufacture.

Type: 75mm x 6mm Satin Chrome

D. Drawer handles:

Manufacturer: Submit data for approval prior to manufacture.

Type: 75mm x 6mm Satin Chrome

E. Drawer Tracks:

Manufacturer: Submit data for approval prior to manufacture.

Type: Single extension, nylon rollers with drawer bottom fixing

21.205 Fabrication

Refer Clause 301 below.

Construct by screwing and gluing or other approved method. A dry stapled assembly will not be

approved.

Fabricate bench tops as indicated in a manner recommended by the material's manufacturer. Fabricate

units without joints unless counter length exceeds maximum available length of materials.

Seal joints between counter and splash back with matching colour silicone. Wherever possible, per-cut

openings to receive hardware, appliances, plumbing fixtures, electrical work and similar items.

Page 78: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Unit Kitchen Page F78

Locate openings accurately using templates or roughing-in diagrams for proper size and shape. Smooth

edges of cut-outs and, where located in bench tops and similar exposures, seal edges of cut-outs with a

water resistant coating.

Back prime all concealed solid timber surfaces prior to installation.

Install fasteners, hinges etc in accordance with manufacturer’s instructions. When in doubt about

suitability, consult with manufacturer of the items specified or selected.

21.206 Inspection Before Delivery

Advise Principal when the first of any group of items is ready for inspection not less than four days

before delivery is due at the site. Where work is found not to comply with documentation, the Principal

will order rectification. The Principal will be the sole decision-maker regarding compliance or non-

compliance.

PART III EXECUTION

21.309 Examination

Visit the site and inspect conditions. Check dimensions and compare all aspects with the drawings and

specification. Resolve differences before ordering materials or starting work.

Start of work means total acceptance of all conditions.

21.310 Preparation for Installation

Prior to installing, condition joinery to the average humidity conditions prevailing in the installation

areas.

Delivery anchoring devices and similar inserts required to be built into substrates well in advance of the

fixing of fittings and provide full details when they are to be fixed by others.

Prior to installation, examine shop-fabricated work for completeness and remedy and deficiencies.

Include back priming . Remove packing where not required.

Thoroughly clean all floors and walls that will be permanently concealed by joinery.

21.311 Installation

Use concealed shims as required to install the work plumb, level, straight and distortion free within the

following tolerances:

- 1mm in 800mm for plumb and level (including bench tops),

- 0.5mm maximum offsets in flush adjoining surfaces,

- 2mm maximum offsets in revealed adjoining surfaces.

Scribe and cut to fit adjoining work; refinish cut surfaces or repair damaged finishes at cuts.

Secure joinery with anchors of blocking built-in or directly attached to substrates. Secure to grounds,

stripping and blocking with countersunk, concealed fasteners and blind nailing as required to complete

the installation.

Except where pre-finished matching fastener heads are required, use fine finishing nails, countersunk

and filled flush. Use a matching filler where a transparent finish is required.

Install casework without distortion so that doors will fit openings properly and be accurately aligned.

21.312 Hardware

Install all door and joinery hardware as scheduled, listed and required in full compliance with the

manufacturer's recommendations.

Adjust as needed to centre doors in openings.

21.313 Adjustments, Cleaning, Finishing and Protection

A. Finish the work specified in this Section and remedy anything not finished at the shop or any

other stage prior to completion.

B. Adjust joinery to achieve a uniform appearance.

C. Lubricate and clean hardware making any final adjustments needed for proper operation.

Remove all handling marks from visible joinery surfaces.

D. Protection: Do everything needed to ensure that all work is without damage or deterioration at

completion.

Page 79: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Unit Kitchen Page F79

21.314 Completion

Complete all contracted work in accordance with contract documents and written variation orders

issued by the Principal

Page 80: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Packaged Air Conditioning Unit Page F80

22 Packaged Air Conditioning Unit

PART I GENERAL

22.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Supply, install and commission a complete evaporative air conditioning system consisting of but not

limited to the following items:

Evaporative cooling units complete and housed in single cabinets.

Ducting and ceiling registers.

Wall penetrations, under-flashings, over-flashings and trimming members.

Support frame.

Disposal of bleed-off water or condensate.

22.102 Related Work

Co-ordinate and co-operate with the following trades:

Plumber

Metal Decking and Roof Plumbing

Metalwork

Air Distribution Ductwork

Electrical Installation

22.103 Quality

Provide written evidence to the Principal of required experience and skills of personnel proposed for

this project.

Ensure electrical and plumbing work is performed only by electricians and plumbers with

qualifications. Submit evidence of these qualifications.

22.104 References

Comply with applicable portions of the following Australian Standards:

AS 1324 Air filters for use in air conditioning and general ventilation (in 2 parts, dated

1996)

AS 2913 1987 Evaporative air-conditioning equipment

AS/NZS 3666 1989 Air-handling and water systems of buildings - Microbial Control

3666.1 1995 Design installation and commissioning

3666.2 1995 Operation and maintenance

Comply also with the requirements of Environmental and Statutory Authorities having jurisdictions.

22.105 Submissions

Submit to the Principal operation and maintenance instructions for units and other items.

22.106 Delivery Handling and Storage

Arrange and co-ordinate delivery and installation of units and associated components, cranage or

handling to installed position, and maintenance arrangements.

Where possible, install materials directly in place. Store other materials in a secure location on site as

directed by Contractor.

PART II MATERIALS

22.201 Equipment

Unit shall be as defined on the drawing sheet or as scheduled.

Pump and fan to be activated by a remote timer through the consumer’s on/off switch.

22.202 Fans

Provide supply air fans of forward-curved centrifugal type, balanced to prevent vibration.

22.203 Motors and Drive Units

Fans to are to be provided with v-belt driven continuously rated induction motors.

Page 81: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Packaged Air Conditioning Unit Page F81

Supply all fan motors sized for duty, plus 20%.

Supply with bearings of permanently lubricated ball type.

22.204 Controls

Provide units with a control panel containing all controls needed to operate and protect the components

of the units. Locate according to drawings.

Ensure all protective devices automatically reset.

Use only low voltage thermostats and control wiring.

22.205 Brackets Sleeves, etc

Hot dip - Galvanised steel, as required for secure installation.

PART III EXECUTION

22.301 Examination

Inspect drawings and visit site. Check aspects of required work such as plant platforms, refer any

discrepancy to the Principal for decision and correction.

Start of work on site means total acceptance of conditions.

22.302 Mounting

Fix unit to stand with anti-vibration mounts. Provide flexible ductwork between unit and supply air

fixed ducts

Co-operate with other trades to ensure watertight installation.

22.303 Bleed-off Drains

Refer to Drawings for disposal of bleed-off.

Where no details are provided collect bleed-off via DN20 copper pipe saddled to stand with cranked

end 200mm above ground level. Attach DN20 polyethylene pipe to copper and run 300mm below

ground for a minimum of 6 metres from the perimeter of the house. Tee polyethylene pipe and extend a

minimum of 3m to each tail. Raise to surface.

22.304 Connection

Connect direct to main switchboard to space allocated for mechanical services and for future

equipment.

Provide weatherproof coverings over connections to external units. Provide sun protection to flexible

connection.

22.305 Commissioning

Operate the system for two days. Rectify any faults.

22.306 Completion

Complete the contracted work in accordance with contract documents.

Page 82: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Air Distribution Ductwork Page F82

23 Air Distribution Ductwork

PART I GENERAL

23.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Design, fabricate, supply, install and test a complete air distribution system consisting of but not limited

to:

Ductwork and fittings

Insulation to ductwork

Supply grilles

Painting of all exposed ductwork

Testing

23.102 Related Work

Co-ordinate and co-operate with the following trades:

Metal Decking and Roof Plumbing

Metalwork

Packaged Air Conditioning Units

Electrical Installation

23.103 Quality

Provide written evidence to the Principal of required experience and skills of personnel proposed for

this project.

23.104 References

Comply, as a minimum requirement, with the applicable parts for supply and installation of the

following publication:

‘Low Pressure Duct Construction Standards’, (latest edition) as published by the SMACNA

Association. (American Sheet Metal & Air Conditioning Contractor's Association)

Comply with applicable portions of the following Australian Standards:

AS 1668 The use of mechanical ventilation and air-conditioning in buildings. There are 2

parts to this standard issued in 1991.

AS 2107 1987 Acoustics - Recommended design sound levels and reverberation times for

building interiors

AS/NZS 3666 Air-handling and water systems of buildings - Microbial Control

3666.1 1995 Design installation and commissioning

3666.2 1995 Operation and maintenance

AS 4254 1995 Ductwork for air handling systems in buildings

23.105 Delivery Handling and Storage

Co-ordinate dates of delivery and installation of ductwork and associated fittings, cranage or handling

to installed position and handling arrangements.

Where possible, install materials directly in place. Store other materials in a secure location on site as

directed by the Contractor.

23.106 Project Conditions

Inspect drawings and visit site. Check aspects of required work and refer any discrepancy to the

Principal for decision.

Determine final locations and dimensions from site measurements prior to fabrication.

PART II MATERIALS

23.201 Rectangular Ductwork

Galvanised steel sheet specifically manufactured for roll forming such as ‘Galvabond’ or other,

approved by the Principal.

Page 83: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Air Distribution Ductwork Page F83

23.202 Flexible Ductwork

Patent aluminium spiral wound type

PVC is not to be used.

23.203 Insulation

Comply with AS 1530, Part 3: Test for early fire hazard properties of materials and have the following

results certified:

Ignitability Index 0

Spread of Flame Index 0

Heat Evolved Index 0

Smoke Developed Index 0

R rating: R1.0

23.204 Diffusers

Aluminium louvre, powder coat/enamel finished:

Type: Ceiling Multi-directional

Type: Wall Double reflection (if applicable)

Colour: To match ceiling

Air deflection is required to be adjustable horizontally & vertically.

PART III EXECUTION

23.301 Examination

Inspect site conditions.

Ensure that conditions will permit installation.

Arrange for correction of unsatisfactory conditions.

Start of work means total acceptance of conditions.

23.302 Preparation

Provide for the Mechanical Services Contractors, a clear opening, access opening, cutting patching.

Check associated Air Conditioning Units and equipment are of the correct type and able to be

operational Report any discrepancy to the Principal, and request correction.

23.303 Installation

Install ductwork complete with transitions, bends, tees, supports, dampers, off-sets, flexible

connections, take-offs and similar fittings necessary for the balancing and full operation of the system.

Form bends in flexible ductwork to manufacturer's recommendations. Bends to remain at full cross

section.

Ensure galvanising remains unbroken after fabrication and installation.

Adequately stiffen to prevent 'drumming'.

Adequately support ductwork with cushioned hanging straps, located to prevent sagging.

23.304 Duct Supports

Hanging and supporting systems to SMACNA Standards and of the trapeze type of hanging system.

Install hot dip galvanised steel supports.

Fix supports for ductwork to the building structure at recommended spacing and at each change of

direction.

23.305 Insulation

Install insulation as required, over entire surface of ductwork fixed with adhesive, adhesive tape or

bands avoiding any damage to insulation blanket or foil.

23.306 Flexible Connections

Use to prevent transmission of vibration from moving equipment to adjacent ducting. Also use between

main ducts and unit casings and to prevent excessive movement of long ducts and where ducts cross

building expansion joints.

Page 84: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Air Distribution Ductwork Page F84

23.307 Balancing Dampers

Fit to branches and where a branch serves more than one outlet.

Control air volumes by means of dampers in branches, opposed blade dampers in necks, behind grilles,

or stream splitter dampers as appropriate. Ensure that factory manufactured opposed blade dampers are

fitted at the air outlet to balance and straighten the air flow across the face of the grille. Do not use

plastic cogs.

23.308 Air Outlets

Install supply and return air outlets as indicated on the drawings or arrange with Contractor to have

other trades install.

Ensure diffusers have provision for air pattern adjustment, both horizontally and vertically.

23.309 Testing

Balance air quantities at air grilles to within + 10% of specified quantity.

Measure air quantities in air ducts. Include a N.E.B.B. or N.A.T.A. certification for air and water

balancing.

Perform final balancing under the supervision of the Principal, and complete to his satisfaction.

23.310 Completion

Complete the contracted work in accordance with contract documents.

Page 85: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Room Air Conditioning Unit Page F85

24 Room Air Conditioning Unit

PART I GENERAL

24.101 Scope

Refer to Drawings & Schedules for the extent of work relating to this section.

Supply, install, and commission electrically operated, air conditioning units of a capacity to air

condition the nominated room volume, including but not limited to:

Reverse cycle

Installation

Commissioning

24.102 Related Work

Co-ordinate and co-operate with trades in the following other sections:

Plumber

Metal Decking and Roof Plumbing

Metalwork

Air Distribution Ductwork

Electrical Installation

24.103 Quality Assurance

A. Provide written evidence to the Principal of required experience and skills of personnel

proposed for this project.

B. Ensure electrical and plumbing work is performed only by electricians and plumbers with

qualifications. Submit evidence to the Principal of these qualifications.

24.104 References

Comply with applicable portions of the following Australian Standards:

AS 1324 1973 Air filters for use in air conditioning and general ventilation

1324.1 1996 Application performance and construction

1324.2 1996 Methods of test

AS 1668 The use of mechanical ventilation and air conditioning in buildings.

1668.1 1991 Fire and smoke control

1668.2 1991 Mechanical ventilation for acceptable indoor-air quality

AS 3179 1993 Approval and test specification-Refrigerated room air conditioners.

AS 3666 1989 Air-handling and water systems of buildings - Microbial Control

Comply also with the requirements of Environmental and Statutory Authorities having jurisdictions.

24.105 Submissions

Submit data on units and other components.

Submit to Principal maintenance and operating instructions for units.

24.106 Delivery, Handling and Storage

Arrange with Builder for dates of delivery and installation of units and associated components, cranage

or handling to installed position and maintenance arrangements.

Where possible, install units directly in place. Store other materials in a secure location on site as

directed by Builder.

24.107 Project Conditions

Inspect drawings and visit site. Check aspects of required work and refer any discrepancy Principal, for

decision.

24.108 Warranty

Provide a warranty to the Proprietor via the Principal that units will remain operational for a period of

five years from the date of Practical Completion and that the equipment will be repaired or replaced

Page 86: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Room Air Conditioning Unit Page F86

without cost providing maintenance is carried out as contracted, where maintenance is not performed by

this Contractor.

PART II MATERIALS

24.201 Manufacturer & Unit

Refer to Drawings and Schedules for Manufacturer and specified unit.

24.202 Split System Units

Supply units equipped with hermetically sealed compressor motor, condenser, evaporator using a

capillary tube refrigerant, and adjustable thermostat either remotely mounted or fixed to control panel.

On reverse cycle units, ensure the refrigeration circuit includes reversing valve, accumulator and check

valve, plus additional refrigeration pipework to bypass the drier on reverse cycle operation.

Supply split units with refrigeration pipework, sized and installed to equipment manufacturer's

recommendations.

24.203 External Units

Provide concrete pad in nominated or suitable location for external unit.

Mount unit with waffle pad in accordance with manufacturer’s instructions.

Provide folded steel mechanical protection to all exposed pipework.

Provide 25 x 25 x 3mm woven wire mesh protective cage with 40 x 40 SHS frame to external unit. Fix

cage securely with fasteners which allow removal for servicing.

24.204 Internal Units

Mount units in indicated locations. High mount units to be 1800mm minimum above floor level.

PART III EXECUTION24.301 Examination

Inspect site conditions

Ensure that conditions will permit installation.

Arrange with Builder for correction of unsatisfactory conditions.

Start of work means total acceptance of conditions.

24.302 Manufacturer's Instructions/Recommendations

Comply with manufacturer's printed instructions

24.303 Installation

Install window units with outside tilted down for condensate drain. Seal edges to prevent air

infiltration.

Install console units fixed in place, levelled and restrained.

Make plumbing and electrical connections in conformity to the local codes.

Test units. Check and record for future reference air temperature, inside and out, electrical load and

operating pressures.

24.304 Condensate Drains

Drain wall mounted units to the nearest garden bed, downpipe or gutter.

24.305 Connection

Provide electrical connection direct to main switchboard to pre-designated space allocated for air

conditioning units.

Provide weather-proof connections to external units.

24.306 Completion

Complete the contracted work in accordance with contract documents and written variation orders

issued by the Principal.

Page 87: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Ceramic Tiles Page F87

25 Ceramic Tiles

PART I GENERAL

25.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide Ceramic Tile work including but not limited to:

Preparation of surfaces before tiling or bedding

Bedding screeds where required

Wall tiles

Floor tiles

Cleaning of finished tiled surfaces.

25.102 Related Work

Co-ordinate and co-operate with the following trades:

Wall Construction and Cladding

Plumbing (re floor wastes)

Floor Construction

Concrete Screeds

Mortar and Grout

25.103 Quality

Samples: Provide samples of tiles specified, not less than 4 units of each.

25.104 References

Comply with applicable portions of the following Australian Standards:

AS 2358 1990 Adhesives for fixing ceramic tiles (amended 1994).

AS/NZS 3661 Slip resistance of pedestrian surfaces

3661.1 1993 Requirements

3661.2 1994 Guide to the reduction of slip hazards

AS 3958 Ceramic tiles

3958.1 1991 Guide to the installation of ceramic tiles

3958.2 1992 Guide to the selection of a ceramic tiling system

25.105 Special Requirements

Not applicable.

25.106 Delivery, Handling and Storage

Deliver to the site in original, unopened containers with grade, type and quality indicated on the labels.

Provide secure and dry storage.

PART II MATERIALS

25.201 General

Glazed ceramic tiles as per schedule. Wall tiles 150 x 150 Johnson white or equal approved.

25.202 Screed and Setting Bed Materials Concrete Floors

Cement: Portland Cement, comply with AS 3972, Type A.

Sand: Clean, washed, sharp, sieved and graded, complying with the following limits:

Sand Grade: No. 4 (4.75mm)

Percent Passing Sieve: 100%

Sand Grade: No.8 (2.36mm)

Percent Passing Sieve: 95-100%

Sand Grade: No.100 (150 microns)

Percent Passing Sieve: 25% max

Sand Grade: No.200 (75 microns)

Percent Passing Sieve: 10% max

Page 88: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Ceramic Tiles Page F88

Fineness modulus 1.6 to 2.5%

Water demand, ratio by weight 0.65% maximum.

Fine Sand (for jointing): As above, except that 100% is to pass a No. 100 (150 microns) sieve.

Aggregate for Screeds graded as follows:

Passing 4.75mm sieve - 80%

Passing 6.00mm sieve - 90%

Passing 8.00mm sieve - 100%

Water: Clean drinking quality.

Mesh: Galvanised Steel welded wire fabric: minimum 2.5mm diameter wires at 100mm centres each

way.

25.203 Adhesives

Exterior/Wet Area Adhesives: Cement-based ceramic tile adhesive, complying with AS 2358.

Interior/Dry Area Adhesives: Organic based adhesive, complying with AS 2358:

25.204 Schedule of Tile Finishes

Refer to schedule.

25.205 Grout

Prepared Grout: Inorganic Portland cement integrated, ready-to-use, dry-curing grout, equal to products

manufactured by Australian Building Adhesives Pty Ltd. Colours to Schedule or to Principal’s

selection.

Supply Waterproof grout for wet area tiling.

25.206 Expansion Joints

Silicone, as recommended by manufacturer. Colour to Schedule or to Principal’s selection.

PART III EXECUTION

25.301 Examination

Visit site and inspect conditions, comparing conditions to Drawings, before delivery of materials to site.

Rectify any discrepancy or unsuitability of substrate.

Start of work means total acceptance of conditions.

25.302 Conditions of Installation

Install backing boards or panels in accordance with manufacturer's precise instructions.

Rectify substrate so that when checked with a 2m straightedge, gap under the straightedge does not

exceed 6mm.

Allow new concrete to dry out for at least 4 weeks before rendering or direct fixing of tiles.

Floor screeds: broom finished.

25.303 Setting Out

As far as possible, set out work so that no tile less than half size occurs. Align joints in floor tile at right

angles to each other and straight with walls to conform to patterns selected. Verify locations of

equipment before installing tile. Co-ordinate with plumbing and other trades. Fully tile surfaces under

surface-mounted items.

Expansion Joints

Set out panels of tiling so that tiles may expand or contract to and from corners of tiled walls and floors.

Allow for expansion in each corner of 5mm minimum. Fill expansion joints with silicone as

recommended by the manufacturer. (N.B. expansion joint filler to be sufficiently flexible)

Control Joints

Provide control joint:

At junctions of dissimilar wall construction

In walls, no more than 2.5m apart.

25.304 Bedding and Screed Mixing

Tile fixing mortar is to be adequately cohesive and water retentive but not richer than 1:3 nor leaner

than 1:4 cement/sand by volume.

Page 89: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Ceramic Tiles Page F89

Within these limits the choice of the precise proportions is governed by the need to produce a mortar of

the required properties with the minimum water content. These proportions will depend on the sand in

use and is found by practical trial before tile fixing starts.

Once the proportions are established, make every attempt to minimise random variations. Batch by

weight wherever possible. Do not batch with shovels.

The mixing of mortars by a suitable machine is to be preferred whenever it is practicable.

Volume batching: Base batching on multiples of a whole bag of cement (50kg, approximating 0.035m3

or 35 litres). In such cases measure by volume using correctly made gauge boxes or other suitable

containers of fixed, measurable volume. This method allows water addition to be checked and thus

permits approximate mix proportions to be established and maintained.

Where mixing by machine is not possible, mortars may be mixed on a clean non-absorbent surface

using clean hand tools. Whatever method of mixing is used, blend the materials thoroughly in the dry

state before water is added. Continue mixing until the batch has a uniform consistency.

No water should be added once mixing is complete. Discard mortar which is unused within 2 hours of

adding the mixing water.

25.305 Bedding Methods

Portland Cement Bedding, Semi-Dry Mix Method:

Mix: One (1) part cement to four (4) parts of sand by volume, mixed dry, with only sufficient water

added to make a crumbly consistency which retains its shape when squeezed in the hand. It is important

to ensure complete mixing of the cement and sand.

Before laying the mix, establish finished floor levels by means of dots. Spread roughly to a thickness

slightly greater than that required for the actual bed.

Thoroughly compact and draw-off to the required level. Lay only sufficient bedding mix for one man to

deal with satisfactorily in one operation.

Pour a slurry consisting of one (1) part cement to one (1) part sand by volume with sufficient water to

make it slightly fluid, over the bedding and spread with a trowel until it is about 3mm thick.

Place tiles, which preferably are dry, in position and firmly beaten into the bedding. Form joints of at

least 2mm and regulating should be done at this time.

Wash off if necessary after the joints have set thoroughly.

Minimum bedding thickness 25mm.

Bedding with Adhesives (Walls Only):

Apply adhesive to a thin bed or thick bed according to site conditions:

Apply thin bed adhesives when the background is true to within 3mm when tested with a 2 metre

straightedge, at thickness not less than 1.5mm and not more than 3mm. Apply with a notched trowel.

Apply thick bed adhesives when deviations up to 6mm, over a 2 metre length, are present in the

background, or when applying tiles having deep keys or ribs on their backs. Thick bed adhesives should

be used at thicknesses not less than 3mm and not exceeding 12mm. Apply with either 10 x 10 x 10mm

notched trowel, solid bed or buttering method.

Application Methods:

Notched Trowel Method: Apply the adhesive to the background as a screed, then form ribs by combing

it with a notched trowel of the type recommended for the particular application. Do not apply adhesive

in areas larger than one square metre at a time.

Solid Bed Method: Apply the adhesive to the background as a screed and bring it to a true surface,

working in one square metre area at a time.

Buttering Method: Spread the adhesive evenly over the back of the tile to a thickness slightly greater

than the final bed thickness required, so that when the tile is pressed or tapped firmly into position, the

correct thickness is achieved and the tile is solidly bedded over its entire surface.

Apply dry tiles immediately into the adhesive, before it skins.

Press the first tile firmly into position and then remove it to check that complete contact is being made

with the adhesive. Make occasional similar checks throughout the tiling work. The whole of the back of

the tile is to be in good contact with the adhesive. Do not allow voids to occur beneath tiles.

Remove surplus adhesive remaining on the face of the tile or in the tile joints, after fixing, before it

skins.

Form joints straight and constant in width. Under no circumstances fix tiles with tight joints.

Allow tiles to set for a minimum 24 hours before grouting and protect from weather, water penetration,

etc. during this period.

Page 90: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Ceramic Tiles Page F90

Expansion Joints: Refer Clause 303 B, complying with AS 3958.1. See Clause below.

Cement based Adhesive method for extruded, quarry or terracotta floor tiles:

Secure to a prepared concrete surface with cement based adhesive 10mm thick with a 10mm notched

trowel. Comply with manufacturer’s current instructions

25.306 Installation - General

Wall tiling: Comply with the recommendations of AS 3958.1 and AS 3740.

Floor tiling: Comply with the recommendations of AS 3958.1 and AS/NZS 3661.

Adhesives: Comply with AS 2358 and recommendations of adhesive manufacturer.

25.307 Tolerances and Cleaning

General: Install tiles in true planes so that when checked with a 2m straightedge, gap under the

straightedge does not exceed 3mm. In sloped floor tiling this tolerance does not apply across

intersections of fall planes. Adjust tiles within 10 minutes of fixing.

Cleaning: Clean down using a damp cloth before cement smears and surplus mortar begin to harden on

the surface or in the joint spaces, care being taken to avoid disturbance of the tiles during the setting of

the bedding.

Lighting: Whenever possible the lighting at the time of applying the bedded finish is not to be

appreciably different from the ultimate permanent lighting.

25.308 Grouting

Except as otherwise required, do not commence grouting for at least 24 hours after placing of tiles.

Follow specific instructions of materials manufacturer.

Grout Mix:

General use, except as noted below: Apply an approved pigmented prepared grout mix, one (1) part

Portland cement to one (1) part fine dry sand by volume mixed to a paste consistency with the

minimum of water; too wet a mix may result in the joint filling cracking or drying out.

Floors: Prepared grout, acid resistive.

Walls: Epoxy-based mortar grout, mildew resistant.

Colours: as per Schedule or as selected by the Principal.

Grouting and Curing:

Apply the grouting mix to as large an area as can be worked before hardening commences. Apply with

a squeegee working back and forth over the area until the joints are completely filled. Remove surplus

grout from the tiles with the aid of a damp, not wet, cloth and the joints then tooled. After the grouting

has dried, final polish using a clean, dry cloth.

Remove surplus grout from the floor surface; on no account use sawdust for this purpose, as there is a

danger that sawdust entering moist joint surfaces may break down their strength, and cause them to

become porous.

In dry weather, grout joints after maintaining damp condition for three days by sponging down, fog-

spraying or other methods. Allow floors to set 48 hours before permitting ordinary foot traffic.

25.309 Protection

Prevent walking on or contact with floor or wall tiles for a minimum of seven days. During that period,

cover floor tiles

25.310 Completion

Complete contracted work in accordance with contract documents.

Page 91: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Tanking Page F91

26 Tanking to Wet Areas

PART I GENERAL

26. 101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Supply and install tanking membrane to areas shown on Drawings plus preparatory and protective work

and associated materials including but not limited to the following:

Concrete and masonry patching and filling.

Tanking membrane fixing.

Surface protection and finishing.

26.102 Related Work

Co-ordinate and co-operate with the following trades:

Concrete

Masonry

Tiling

Plumbing

26.103 Quality Assurance

Use experienced Sub-Contractors licensed by the material supplier. Provide evidence of the licence to

the Principal if requested.

26.104 References

Ensure that sheet membrane materials and their associated primers and adhesives are of the type and in

the condition approved by the material supplier.

Installation to be in accordance with Australian Standards AS3740-2004.

26.105 Submissions

Prior to ordering materials submit samples and product data of specified products.

26.106 Delivery, Handling and Storage

Keep on-site storage of materials to a minimum, delivering them as required for direct installation. Be

responsible for loss and damage to delivered materials, both stockpiled and in place.

26.107 Warranty

Provide to the Proprietor a warranty, for a period of fifteen years from the date of Practical Completion,

covering the whole of the tanking including penetrations for equipment supports, pipes, flues, upstands,

flashings and the like.

For the period of the warranty and without cost to the Proprietor, provide an undertaking to make good,

including finish or thing disturbed during the making good, any defect resulting from inadequate

materials or workmanship.

PART II MATERIALS

26.201 Acceptable Manufacturers

Ardex or equal as approved by the Principal

26.202 Materials

Ardex WPM265 Primer.

Ardex Superflex WPM 001, 002 or 155 or equal as approved by the Principal

PART III EXECUTION

26.301 Examination

Inspect conditions before start of work on site to ensure that everything is satisfactory. Undertake any

needed rectification.

Page 92: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Tanking Page F92

Start of work means total acceptance of conditions.

26.302 Preparation

Prepare surfaces affected by the installation in accordance with the material manufacturer's

instructions.Ensure floor and walls are clean and dry, free of dirt and oil and all forms of

contaminations. Cut or grind back any protrusions. Fill any gaps, cracks or hollows.

Apply primer with paint roller or brush to cracks, wall and floor corners and leave to dry. Install bond

breakers as required and in accordance with manufacturer’s instructions. Install reinforcing mat at

junctions if required and in accordance with manufacturer’s instructions. Apply additional coats as per

manufacturer’s instructions.

Apply a 10mm bead of silicone to internal corners where sheet linings exist and to pipework

penetrations and allow to cure.

26.303 Installation

Install in accordance with manufacturer’s instructions. Execute seals around penetrations, upstands, etc.

as instructed by the manufacturer.

Allow full drying time in accordance with existent environmental conditions prior to tiling.

26.304 Quality Control

Arrange for inspection by the Principal on completion.

26.305 Extent of Work

Provide tanking membrane to:

Room Location Size (length x width x height)mm

Bathroom Floor-wall junction full x 200 x 200

Bathroom Wall-wall junction other than shower 200 x 200 x 1350

Bathroom Wall-wall junction, shower 200 x 200 x 1800 (min)

Shower alcove Floor Length + 200 x width + 200

Laundry Floor-wall junction, adjacent trough Full x 150 x 150

Laundry Wall-wall junction, adjacent trough 200 x 200 x 1350 (min)

Laundry Skirting tile Full x 150 x 150

WC Floor-wall junction Full x 150 x 150

26.306 Cleaning

Thoroughly clean work on completion, including affected adjacent surfaces.

26.307 Completion

Complete contracted work in accordance with contract documents and written variation orders issued

by the Principal.

Page 93: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Resilient Flooring Page F93

27 Resilient Flooring

PART I GENERAL

27.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Provide vinyl surfacing material with necessary accessories and related equipment required for the

work.

27.102 Related Work

Co-ordinate and co-operate with the following trades:

Concrete

Carpenter

27.103 Quality

Suppliers and installers need to be widely experienced in the class of work required for the work of this

Section.

27.104 References

Comply with applicable portions of the following Australian Standards:

AS 1884 1985 Floor coverings - Resilient sheet and tiles - Laying and maintenance practices

AS 3553 1988 Adhesives for floor and wall applications - Resilient vinyl, linoleum and rubber

sheet and tiles - Interior and exterior use.

AS/NZS 3661 Slip resistance of pedestrian surfaces

3661.1 1993 Requirements

3661.2 1994 Guide to the reduction of slip hazards

Comply also with instructions of manufacturers of materials to be installed.

27.105 Delivery, Handling and Storage

Deliver materials in the packaging of the supplier, bearing the brand name, colour, thickness and other

relevant data.

Store materials in a secure dry area away from other materials which may cause deterioration.

On completion store 1m2 of surplus vinyl tiles in roof space for future supply for repairs.

PART II MATERIALS

27.201 Materials

Refer to Schedule for material selection. Where no selection identified sheet vinyl Armstrong ‘Bravo’

2.0mm.

Adhesive: As per manufacturer’s specification Refer AS 1884, Clause 1.4.2

Installation: Full stick with heat welded seams, colour matched.

27.202 Equipment

Supply equipment required for the preparation of floor, and installation of vinyl materials as

recommended by the material manufacturer.

PART III EXECUTION

27.301 Examination

Examine the site conditions applicable to each installation and comply with AS 1884, Clause 1.5.

Start of work means total acceptance of conditions.

27.302 Preparation

Prepare each area to be surfaced in accordance with AS 1884, Clause 1.4.3, Section 2 and Section 3.

Test the dryness of concrete sub-floor in accordance with AS 1884, Appendix A.

Page 94: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Resilient Flooring Page F94

27.303 Installation

Delay installation of resilient flooring until concrete has dried to the percentage established in Appendix

A of AS 1884.

Adhesives: Comply with AS 1884, Clause 3.2 and manufacturer's instructions.

Install material in accordance with AS 1884, Section 3, including conditioning of both the materials and

the sub-floor. Refer Clause 3.1.

Weld joints of vinyl sheet.

Sheet flooring is to be continuous under raised joinery (RHS framed cupboards without plinths) and

removable fixtures (eg. stove) and furniture (eg. bedroom shelving units).

Fix all edges to prevent lifting by either: installing skirtings or trims over edges or applying flexible

colour matched caulk to perimeter. Where caulking is applied allow 3 – 4mm gap.

27.304 Cleaning

Remove excess adhesive and blemishes from the completed surfaces of flooring and skirtings.

27.305 Protection

Apply suitable hardboard or plywood to completed floors and maintain in position until final cleaning

prior to Practical Completion.

Remove and replace work which cannot be successfully repaired or cleaned.

27.306 Completion

Complete contracted work in accordance with contract documents.

Page 95: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Painting Page F95

28 Painting

PART I GENERAL

28.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section including Clause 204.

Supply labour and materials, services and equipment necessary for the preparation, application and

finishing of painting and staining as indicated on Drawings, Schedules and as specified herein, to

internal and external surfaces of buildings.

Consult with the Principal with regard to requirements of other Sections of the Specification which

require painting, and include as part of the work of this Section the appropriate preparation, painting,

and finish required to complete the installation.

28.102 Related Work

Co-ordinate and co-operate with the following trades:

Substrates to receive paint finish.

Cleaning and finishing.

Scaffolding.

28.103 Quality

General: To standard AS 2311 Sections 3, 6 and 7.

Protection of steelwork: To AS/NZS 2312 Sections 5, 8 and 10.

Compatibility of Shop and Field Paints:

Determine that the materials specified in the Schedule of Finishes are compatible with shop coats.

Failure to do so will be construed as accepting the paints specified. Contractor is to correct, at his own

expense, defects in his work resulting from the use of such materials.

Test Samples:

Prepare test samples for painting types and typical locations, where determined by the Principal. Do not

commence painting of the substrate type until the sample is approved by the Principal. Apply samples

in conditions approximating as closely as possible the lighting conditions of the finished work.

Test Samples include the suitable preparation of substrates.

After approval, Test Samples are to be the standard for quality control of the completion of work of

same type.

28.104 References

Comply with applicable portions of the following Australian Standards:

AS 2311 1992 The painting of buildings (NB: Maintain this document at the project site as a

Controlling General Reference) This Standard is incorporated by reference as

part of this Specification and applies to the work below to the same extent as if

written herein. In the event of conflict between manufacturer's

recommendations and the provisions of AS 2311, manufacturer's

recommendations govern.

AS/NZS 2312 1994 Guide to the protection of iron and steel against exterior atmospheric corrosion.

28.105 Submissions

Submit the following materials for the Principal’s approval prior to commencement of painting:

A. List of proprietary lines to be used in the Contract and corresponding to the Schedule.

B. Product literature on proposed painting systems.

Submit evidence that paints used in the Contract comply with the approved list of proprietary lines prior

to Practical Completion.

28.106 Delivery, Handling and Storage

Store materials in designated spaces in a manner which meets the requirements of applicable codes and

fire regulations. When not in use, keep such spaces locked and inaccessible to those not employed

under this Section. Provide each space with a fire extinguisher of carbon dioxide or dry chemical type

bearing a tag of recent inspection.

Page 96: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Painting Page F96

Bring materials to the building and store in manufacturer's original sealed containers, bearing the

manufacturer's standard label, indicating type and colour. Deliver materials in sufficient quantities in

advance of the time needed in order that work will not be delayed in any way.

28.107 Project Conditions

Temperature: Comply with the requirements of Clause 6.3 of ‘S 2311 The painting of buildings’ and of

paint manufacturers with regard to both ambient temperature and relative humidity.

PART II MATERIALS

28.201 Materials

Provide paints and other materials which are scheduled in the Australian Paint Approvals Scheme ‘List

of Approved Products’.

All lines shall be premium quality.

28.202 Paint Systems

Final coat: If a paint or clear finish system is referred to only by its final coat (for example by the

manufacturer's brand name, or the generic name) provide in addition to the final coat, the appropriate

stains, primers, sealers and undercoats, suitable for the substrate and compatible with the finish coat and

each other.

No system description given: If a surface is to be painted but no system is nominated select the system

from AS 2311 Section 5, using System 1 where a choice is offered.

Number of coats: Unless specified as one coat or two coat systems, each paint system consists of at

least 3 coats. Provide additional coats if necessary.

Prepare porous or reactive substrates with prime or seal coats consistent with the manufacturer's

recommendations.

Achieve the total film thickness or texture; or

Achieve a satisfactory opacity.

28.203 Schedules

Refer to Schedule included in Section F.

28.204 Paint Schedule

Paint all items as scheduled and including:

all exposed internal surfaces such as walling, ceilings, cornices and mouldings excluding Colorbond

pre-finished steel;

all exposed internal timber surfaces such as doors, skirtings, architraves, mouldings, and to prime

coated baseboards;

all exposed internal metalwork including door frames and bare, primed or pre-finished steel framing;

exposed external metalwork, service pipes (including PVC), brackets, cleats to match their backgrounds

or as scheduled excluding colorbond steel and structural members such as rafters and battens that are

pre-finished with an anti-corrosion treatment (eg DuraGal, zincalume, galvanised etc.);

shop primed structural steel, metal boxes etc, and zincanneal, galvanised, zincalume and zinc silicate

treated surfaces;

Paint the following items only when scheduled including:

verandah posts, fascias and colorbond steel.

Page 97: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Painting Page F97

28.205 Australian Paint Approval Scheme Products

External Timber – Painted

Tempered Hardboard

Black Steel

Primed Steel

Zinc Coated Steel

APAS 0015/1 Full gloss alkyd enamel

External Timber – Painted

Black Steel

Primed Steel

Zinc Coated Steel

PVC

APAS 0280/1 Full gloss exterior acrylic

Internal Steel – Painted

Door frames

APAS 0015/1

APAS 0015/2

Full gloss ext/int alkyd enamel

Full gloss interior alkyd enamel

Internal Timber – Painted

Medium density fibreboard

Tempered Hardboard

Skirtings, architraves, reveals

APAS 0015/1

APAS 0015/2

APAS 0015/3

Full gloss ext/int alkyd enamel

Full gloss interior alkyd enamel

Semi-gloss interior alkyd enamel

Internal Timber – Varnished

Medium density fibreboard

APAS 0114 Satin or full gloss one pack clear

polyurethane

Villaboard walls and ceilings APAS 0260/2 Semi gloss acrylic

Plywood walls and ceilings -

Varnished

APAS 0114 Satin or full gloss one pack clear

polyurethane

Plywood walls and ceilings -

Painted

APAS 0260/2 Semi gloss acrylic

Steel & aluminium - Powdercoated APAS 0155/2 Thermosetting powdercoating

exterior grade

Cut, ground or welded surfaces to

pre-finished steel with anti-

corrosion treatment - Primer

APAS 0014 Zinc rich primer

Primer for alkyd enamel APAS 0016 Solvent borne undercoat

Primer for acrylic painting APAS 0183 Latex wood primer

Villaboard and other compressed

fibrous cement sheeting – Primer

for painting

APAS 0172 Latex sealer

28.205 Priming Materials

Colours of priming coats and undercoats are to be lighter than subsequent coats.

PART III EXECUTION

28.301 Examination

Inspect surfaces and determine that they are in proper condition to receive the work to be performed

under this Section.

The starting of work under this Section will be taken to mean acceptance of such surfaces as being

satisfactory and defects in work resulting from accepting poor surfaces are to be corrected at no cost to

the Principal.

28.302 Preparation

General: Prepared to a standard not less than that described under AS 2311, Section 3: Preparation of

Un-Painted Surfaces, pages 17 - 22 inclusive, and other Clauses of Australian Standards referenced

therein.

This Standard is incorporated by reference as part of this Specification and applies to the work below to

the same extent as if written herein.

Broom clean floor surfaces before painting. Remove dust, dirt, plaster, grease and other extraneous

matter affecting the finish work.

Page 98: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Painting Page F98

Putty-stop or plug nail holes and cracks on both exterior and interior work, as required. Natural or

stained wood finishes are to have putty coloured to match. Putty wood after prime coat or sealer coat

has been applied.

Clean bare metal surfaces of mill scale, rust, grease, oil, dirt, or other foreign matter, then properly

washed with spirit or other approved cleaning agents. After cleaning, etch, pickle, prime, or otherwise

prepare, as recommended by the paint manufacturer.

Remove blisters or other imperfections in previous coats caused by foreign substances or paint skins

from painted surfaces before the subsequent coat is applied.

Rub down wood and metal surfaces before finishing and between coats with 180 grit and finer

sandpaper or steel wool, leaving a perfectly clean surface. Sand smooth-finished surfaces before

finishing and between coats as required to smooth out rough areas and to assure a smooth, even finish.

Surfaces to receive paint are to be smooth and free of sandpaper scratches, mill-marks, and other

imperfections.

Remove hardware, accessories, plates, lighting fixtures and similar items in place prior to painting and

re-position upon completion of each space, or protect as otherwise directed by the Principal.

Thoroughly stir materials in containers before application, unless otherwise directed by the

manufacturer of the paint used, to ensure uniformity of colour and mass. Strain out paint skins or other

materials which would cause lumps or roughness. Thin only as recommended by the manufacturer.

28.303 Protection

Furnish and lay suitable drop cloths in areas where painting is being done to protect floors and other

surfaces from damage during the work.

28.304 Application

General: Execute work of this Section in strict compliance with paint manufacturer's recommendations,

and with the provisions of AS 2311, Section 6: Paint Application, pages 36 - 40 inclusive.

Maintenance or Repainting: Execute work of this Section in strict compliance with paint manufacturer's

recommendations, and with the provisions of AS 2311, Section 7: Maintenance of Painted Surfaces on

pages 41 - 45 inclusive and Section 8: Maintenance Painting Systems, pages 47 - 49.

28.305 Cleaning

At completion of work in each area, remove paint spots, oil and stain from adjacent surfaces, including

finish hardware.

Replace hardware previously removed.

28.306 Completion

Complete contracted work in accordance with contract documents.

Page 99: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Mirrors Page F99

29 Mirrors

PART I GENERAL

29.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Install mirrors as scheduled in Section F

29.102 Related Work

Co-ordinate and co-operate with the following trades:

Fibre Cement

Ceramic Tiling

Painting

29.103 Quality

All work shall be of the highest standard and carried out by specialists experienced in the particular type

of work.

29.104 References

Comply with applicable portions of the following Australian Standards:

AS/ NZS 2208 1996 Safety glazing materials for buildings

29.105 Delivery, Handling and Storage

Handle materials with care. Do not store on site. Install directly in place.

PART II MATERIALS

29.201 Selection of Mirror Types

Refer to Schedule for material selection and size.

Where no material identified polycarbonate shall apply.

Where no size identified: 400mm x 600mm shall apply.

29.202 Accessory Materials

Stainless steel: 4 x 10-12 x 25 Wafer head Buildex 6-031-0068-3.

Polycarbonate: 8 x pan head CP brass screw with cup washer.

29.203 Fixing Holes

Drill stainless steel mirrors 8mm diameter at each corner to receive face fixing screws. Locate holes for

polycarbonate mirrors 50mm minimum from corner of mirrors and 10mm from edges.

29.204 Polycarbonate Edge Finishes

Finish edges of polycarbonate mirrors arrised and polished smooth.

PART III EXECUTION

29.301 Examination

Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are

satisfactory for installation. Perform rectification required before delivery of materials.

Start of work means total acceptance of conditions.

29.302 Preparation

Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.

Clean mirror surfaces immediately before applying silicone sealants to the edges of mirrors. Remove

dirt, insecure coatings, moisture and other substances that could interfere with the bond of the sealant.

Thoroughly clean down the backings to remove dust, dirt and other substances.

Page 100: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Mirrors Page F100

29.303 Edge Sealing to Mirrors

Arris the outer corner of backings and seal around edges of the mirrors with clear neutral cure (non-

acetic) silicone sealant gunned into place between the backings and the edges of the mirror and finished

off to smooth even fillet, lapping slightly over the back edges of the mirror.

29.303 Face Fixing of Mirrors

Fasten mirrors to the backings using proprietary brand brass screws through holes drilled through the

mirror.

Provide domed caps screwed onto the threaded outer ends of the screws - refer to Clause 29.203 of this

Section.

29.304 Protection

Protect mirrors from damage immediately upon installation and until Practical Completion.

Remove and replace mirrors and metal parts that are broken, cracked, abraded or damaged in other

ways before, after or during installation up to the date of Practical Completion.

29.305 Cleaning

Remove labels, excess silicone, stains, spots and other foreign matter from mirrors, frames, hardware

and other finished surfaces immediately upon completion of the installation of each mirror. Use

cleaning systems recommended by the manufacturer of the mirror type.

Debris: Remove rubbish and debris resulting from glazing operations each day.

29.306 Completion

Complete contracted work in accordance with contract documents.

Page 101: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Metal Finishes Page F101

30 Metal Finishes

PART I GENERAL

30.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

Supply all labour and material, services and equipment necessary for the preparation, application and

finishing of metal surfaces as indicated on drawings, schedules and as specified herein, to internal and

external metal surfaces.

30.102 Related Work

Co-ordinate and co-operate with the following trades:

Metalwork

Structural Steel

Metal Door Frames and Fire Doors

Metal Windows

30.103 Quality

The work of this section shall be performed by tradespersons well experienced in the type of work.

30.104 References

Comply with applicable portions of the following Australian Standards:

AS 1231 1985 Aluminium and aluminium alloys - Anodised coatings for architectural

applications

AS 1627 Metal Finishing: Method selection guide

AS 1956 1976 Anodic oxidation coatings on aluminium for decorative and automotive

applications

AS 2832 Guide to the cathodic protection of metals (2 amendments 1993). There are 3

parts to this standard.

AS 3715 1989 Metal finishing - Thermoset powder coatings for architectural applications

30.105 Delivery, Handling and Storage

Handle all materials with care.

Do not store on site.

Install directly in place.

PART II MATERIALS

30.201 Materials - General

Where manufacturer makes more than one grade of any material specified, use the highest grade of each

type, whether or not the material is mentioned by trade name in these specifications.

30.202 Metal Finishes

Anodising

Anodise to colour selected and approved by the Principal. Pre-treat and apply anodising by applicators

approved by the Principal.

Minimum coating thickness of 25 microns subjected to random testing after installation. Remove and

replace non-conforming material.

Polyester Powdercoat

Apply polyester powdercoat, to colour approved by the Principal to metal surfaces specified.

Perform pre-treatment and application of powder coating by applicators approved by the Principal and

by the manufacturer of the powder material.

Minimum coating thickness of 50 microns subjected to random testing after installation. Remove and

replace non-conforming material.

30.203 Finishes Schedule

Refer to Schedule of Finishes.

Page 102: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Metal Finishes Page F102

PART III EXECUTION

30.301 Examination

Inspect all surfaces and determine that they are in proper condition to receive the work to be performed

under this section.

The starting of work under this section means acceptance that surfaces are satisfactory to receive finish.

30.302 Preparation

General: Prepared to a standard not less than that described in the Australian Standards.

Clean base metal surfaces of all mill scale, rust, grease, oil, dirt or other foreign matter then properly

wash with spirit or other approved cleaning agents.

After cleaning, etch, pickle or prepare as recommended by manufacturer of the finish applied.

30.303 Protection

Protect finished metal surfaces as necessary during handling, transport and erection to prevent

mechanical imperfections such as scratches, scrapes, dents, spots, stains and streaks.

Do not use adhesive protective coating. Protect by other means with the approval of the Principal.

30.304 Application

Execute all work in this section in strict compliance with the manufacturer's recommendations and with

the provisions of the Australian Standards which are incorporated by reference as part of this

specification and apply to the work in this section to same extent as if written herein. In the event of

conflict between manufacturer's recommendations and the provisions of the Australian Standards,

manufacturer's recommendations govern.

30.305 Cleaning

At completion of work, keep and maintain finished surfaces clean and free from dust, dirt and other

foreign matter.

30.306 Completion

Complete all contracted work in accordance with contract documents.

Page 103: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Fences & Gates Page F103

31 Fences and Gates

PART I GENERAL

31.101 Scope

Refer to Drawings & Schedules for the extent of work related to this section.

The scope of this work includes the supply, delivery and erection of welded mesh fencing and gates.

31.102 Related Work

Co-ordinate and co-operate with the following trades:

Concrete

Site Excavation trades

31.103 Quality

Where requested submit evidence of experience appropriate to the class of work required. Install under

the direct supervision of a capable foreman with a proven background in the trade.

31.104 References

Comply with the applicable portions of the following Australian Standards:

AS 1379 1997 The specification and supply of concrete.

AS 1650 1989 Hot-dipped galvanised coatings on ferrous articles

AS 2423 1991 Galvanised wire fencing products

31.105 Delivery, Handling and Storage

Deliver, handle and store products so that damage, deterioration and loss will be prevented. Control

delivery schedules to minimise long-term storage at site.

PART II MATERIALS

31.201 Fencing

Refer to Schedule for material selection. Where no selection provided materials as below shall apply.

A. Posts

’DuraGal’ or ‘Galtube Plus’ manufactured by Tubemakers Australia.

Line posts 50mm CHS wall thickness 2mm, Gate posts 75mm CHS wall thickness 2.5mm.

Provide galvanised caps at top of posts where top rail is not continuous.

Bracing or diagonal stays where required 40 mm CHS

B. Rails

‘Galtube Plus’ manufactured by Tubemakers Australia.

50mm x 2.0 SHS wall thickness.

C. Mesh Panels

2100mm x 50mm x 2.5mm heavy galvanised chainwire knuckle

D. Gates

Double gates 4200mm wide. Single gates 900mm wide.

31.202 Post Bases

Concrete strength for post footings 20MPa.

31.203 Gates

Construct gates with welded joints adequately braced and stayed to prevent sway and distortion.

31.204 Dropbolts

Equip gates with heavy galvanised hinges, 16mm dia dropbolt to galv pipe retainers cast in concrete and

heavy duty latches.

PART III EXECUTION

31.301 Examination

Refer drawings and visit the site and verify the existing conditions.

Page 104: SECTION F TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION

SECTION F - TECHNICAL SPECIFICATION – Fences & Gates Page F104

Resolve differences prior to delivery and erection of materials.

Report damage to adjoining properties and paving caused by the work.

Make good to the approval of the Principal.

Start of work means total acceptance of conditions.

31.302 Preparation

Consult with Principal before clearing site of the work.

Obtain instructions regarding removing or retaining plants or trees existing near the new work.

Construct adequate protection for plants to be retained and prevent damage to plants.

Consult with neighbours and reach agreement on methods of construction and access to work areas.

Remove from the site material that is not required and as directed by the Principal dispose of it, or store

it appropriately

31.303 Footings

Gate posts and corner or terminal post footings shall be 900mm deep x 300mm diameter and 600mm

deep x 250mm min diameter appropriately.

Footings for bracing shall be 500mm min depth and length and 250mm diameter.

Pour concrete around all posts below ground level to sizes and depths shown on drawings.

31.304 Fence Erection

Unless otherwise specified the following will apply:

Fencing to be 2100mm high with line posts at 3000mm nominal centres.

Bury bottom of fabric 100mm into ground.

31.305 Gates

Provide hand gates and pair of double gates as per drawings. Provide additional gates as indicated on

site plans.

All gates are to be DN35 (min) galvanised steel tube with smooth rolled corners to top with welded

cross rails and bracing (where gate width is equal to or greater than 2100mm). Welded galvanised mesh

infill. Entrapped pipe adjustable upper hinge with lower pin pivot.

Provide galvanised pipe NB20 gate stops set flush in concrete pad.

31.306 Completion

Paint all welds