Section a.11 Raw Water and Circulating Water System
-
Upload
chava-teja -
Category
Documents
-
view
11 -
download
0
description
Transcript of Section a.11 Raw Water and Circulating Water System
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 1 of 26
11.0 RAW WATER SYSTEM AND CIRCULATING WATER SYSTEM
11.1 Raw Water System
11.1.1 The raw water supply to the entire power plant shall be taken from MIDC.
11.1.3 One Raw water storage reservoir of adequate capacity shall be constructed (by
Owner) in the project site.
Water supply to the proposed fire protection system shall be provided from the
Raw water reservoir. Adequate dead storage as per requirements of Tarrif
Advisory Committee shall be provided in the reservoir.
11.1.4 2 x 100 % capacity Raw water pumps shall be installed near he Raw water
reservoir to supply Raw water o the plant requirements. Provision of necessary
sleeves, valves and piping shall be one by Bidder. Provision shall be made for
isolation of individual river water pumps for maintenance. . The raw water pumps
shall be provided with discharge pipelines along with expansion joints, motorized
butterfly valves and other fittings
Raw water pumps will supply Raw water to clarifier which will be of RCC
construction.
11.1.5 Chlorination dosing equipment with associated pumps, cylinders, safety
equipment, handling and weighing facilities shall be provided as part of river
water chlorination system. The chlorine dosing rate shall be set manually at the
desired value. Cylinder storage area with adequate storage space (15 days
requirement) shall be provided under a roof covered shed with suitable handling
facilities.
11.1.6 Raw Water Clarification System
11.1.6.1 Since water required for various systems in the plant being clarified water (of
turbidity less than 20 NTU), it is proposed to include a pretreatment system to
treat the raw water.
11.1.6.2 It is proposed to install a clarifier of clariflocculator / solid contact type, The raw
water clarifier will produce raw water required for makeup to the condenser
cooling water system and DM water palnt and service water requirements (air-
conditioning & ventilation system and miscellaneous services).
Water from the clarifiers will be stored in above ground storage tanks, Clarified
water storage tank (CWST). The tank will be divided into two (2) compartments
to facilitate cleaning and maintenance and will feed to a common sump. The
capacity of the storage tanks shall be based on 8 hours requirement
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 2 of 26
The sludge from the clarifier shall be collected in a sludge pit and pumped by two
(2) nos. (one working + one standby) sludge transfer pumps to the sludge
treatment plant which shall include one (1) No. thickener and two (2) Nos. (one
working + one standby) centrifuges.
11.1.6.3 The clarified water from the clarified water storage tank shall be supplied to the
following systems:
Input to DM water plant
- for make-up to the circulating water system by gravity, - to the service water system by service water pumps Clarified water from the CWST shall be led to the the water treatment plant by
two (2) Nos. (One working + one standby) water treatment plant supply pumps.
The service water pumps, water treatment plant supply pumps shall be located
put doors. Chemical dosing equipment including tanks, pumps, Coagulant along
with poly electrolyte dosing system shall be in chemical dosing house with
monorail facility and weighing machine. Adequate chemical storage space (15
days) shall be made available in the pump house. Dosing rate of coagulant and
poly electrolyte shall be set manually at the desired value.
The clarified water storage tank shall be provided with level indicators and level switches with protection interlocks for associated pumps. All pumps drawing suction from the tanks shall be protected against operation under low suction conditions. Annunciation for abnormal conditions like levels (low and high) in the storage tanks shall be annunciated in the control panels located in the clarified water pump house. Make-up water from the circulating water system shall be supplied to the cooling tower basin in the plant through pipes. Near the basin, motor operated make-up control valves shall be provided which in-turn shall be controlled by the level controllers in the basin The MCC for providing power supply to the the pumps located in the DM water pumphouse in a separate room.
11.1.6.4 Clarified water drawn by the water treatment plant supply pumps for the purpose
of demineralisation shall be subjected to chlorination.The DM plant chlorination
dosing equipment with associated pumps, cylinders, safety equipment and
handling & weighing facilities shall be provided as part of clarified water
chlorination system. The chlorine dosing rate shall be set manually at the desired
value. Cylinder storage of 15 days requirement shall be provided. A separate
room within the chemical dosing pumphouse shall be provided for housing the
chlorination equipment along with suitable weighing and handling facilities
11.2 Condenser Cooling Water System 11.2.1 A recirculation type condenser cooling water system shall be provided to meet
the cooling duty necessary to cater to rated plant performance requirements. The system should be capable of ensuring supply of cooling water to the condenser at all conditions of operation.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 3 of 26
11.2.2 Circulating Water (CW) Pumps
(a) Three (3) Nos. (two operating + one standby) main circulating pumps of indoor vertical, mixed flow, wet pit type - drawing suction from the common sump beyond the CW forebay (which is connected at the other end of the cooling tower cold water outlet channel), shall be provided to cater to the condenser cooling water requirements of the power plant.
(b) The CW pumps discharge piping shall be complete with expansion joints,
motor operated butterfly valves and other fittings on individual pump discharge lines. Necessary piping, valves and fittings shall also be provided.
(c) Provision shall be made for isolation of individual pump chambers for
maintenance.
(d) The CW pumps shall be housed in the CW pumphouse with individual pump chambers. Coarse screens/ stop logs shall be located outside the pump house for each pump chamber. An ellectrically operated crane of capacity suitable for handling the CW pumps/ motors shall be provided in the CW pumphouse. Separate facilities for handling the coarse screens/ stop logs shall be provided
(e) Validation of the design of forebay/ sump / channel shall be substantiated
during post award of Contract from either identical arrangements elsewhere or by physical modeling. The forebay design shall allow operation of any permitted pump combination while ensuring reasonably uniform flow conditions to each pump.
(f) CW pump operation shall be interlocked with the basin level, CW pump
bearing lubrication water flow and the discharge valve position and operation. Pumps shall be protected against operation at low level in the CW pump chambers.
(g) Chemical dosing system for prevention of scaling in the circulating water system and biocide dosing system for control/ prevention of growth of algae/ other organisms and shall be provided (described in clause below).
11.2.3 CW Piping
The CW piping shall have motor operated butterfly valves and expansion joints at CW pumps discharge, condenser inlet/ outlet lines and cooling tower inlet line. The main discharge conduit from the CW pumps to the condenser and from the condenser to the cooling tower shall be buried.
11.3 Chemical Dosing System
11.3.1 Bidder shall design the cooling water circuit to operate at maximum cycle of concentration in order to limit water consumption and minimise blowdown. The Bidder shall substantiate the value of concentration ratio selected with calculations and from past experience. Necessary chemical dosing system to
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 4 of 26
prevent scale formation / corrosion shall also be included. All required chemical dosing equipment dosing pumps, solution tanks/ carbuoys and solution piping along with handling facilities shall be included. Adjustment of chemical dosing rate shall be manual. Adequate facilities for storage of chemicals shall also be considered (15 days storage).
11.3.2 Bidder shall provide biocide dosing as part of chemical dosing system for prevention/ control of growth of algae and other organisms. If in the opinion of the Bidder, chlorination of cooling water is required in addition to biocide treatment, he may provide a gas chlorination plant to control/ prevent fouling in the complete cooling water system. Residual Cl2 levels permitted in the cooling water shall be limited to not more than the limits permitted by the local regulatory authority. Bidder shall make provisions to ensure compliance with these limits and shall provide the necessary monitoring instrumentation. The dosage rate of chlorine shall be as specified in the data sheets. Required number of chlorine cylinders (15 days storage) with necessary handling and weighing facility and safety equipment along with leak detection and absorption system, pumps, etc. shall also be provided. The chlorination equipment shall be located adjacent to the CW pumphouse.
11.3.3 Chlorine storage / chemical storage area shall be provided under a roof covered shed along with suitable weighing and handling facilities. A separate room within the CW pump enclosure shall be provided for housing the CW chemical dosing/ chlorination equipment along with suitable weighing and handling facilities.
11.3.3 The circulating water make-up shall be ensured by gravity flow of water from the
clarified water storage tank. The quality of circulating water shall be determined by laboratory analysis of grab samples and by conductivity measurements. Accordingly, the cycle of concentration shall be maintained. Make-up to CW system shall be automatically controlled through control valves along the makeup water pipeline, which in turn shall be controlled by the level controllers in cooling tower basin.
11.4 Cooling Tower
11.4.1 One (1) No. induced draught cooling tower shall be provided to cool the hot water from the condenser. The cooling tower shall be complete with basin, associated supporting structures, foundations, casing with internals such as fills, drift eliminators and hot water distribution system including hot water temperature indicator, isolating valves, etc. The basin shall be partitioned into two compartments complete with draining facilities, cold water outlet channel with screens and stoplogs.
11.4.2 Suitable handling facilities to handle fans, associated motors, and screens /
stoplog shall be provided.
11.4.3 Vibration limit switches for cooling tower fans shall be provided..Bidder shall
ensure lightning protection of the cooling tower.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 5 of 26
11.4.4 The heat load on the cooling tower shall be based on the condenser parameters.
11.5 CW Blow down
11.5.1 CW system blowdown shall be drawn from the hot water conduits and shall flow by gravity to the the guard pond.
11.6 Auxiliary Cooling Water System
11.6.1 The principal criteria for the design of the system shall be to ensure a continuous and reliable supply of adequate auxiliary cooling water to the GTG coolers and STG coolers at all conditions and at all times.
11.6.2 The auxiliary cooling water system shall be a closed loop system comprising of two (2) nos. (both working) plate type heat exchangers and three (3) nos. (2 operating + 1 standby) auxiliary cooling water pumps. The auxiliary cooling water shall be passivated DM water.
11.6.3 Three (3) nos. (2 working + 1 standby) ACW booster pumps shall be provided to circulate cooling water on the secondary side of the plate type heat exchangers. The booster pumps shall draw suction from tap-off from main condenser cooling water pump discharge header and shall circulate the cooling water through the plate type heat exchangers back into the condenser cooling water line downstream of the condenser.
11.6.4 The ACW pumps and the ACW booster pumps shall be of horizontal centrifugal type along with necessary discharge isolation valve at the outlet of each pump.
11.6.5 The ACW pumps, the ACW booster pumps and the plate type heat exchangers shall be located in the STG building. Make-up to the closed loop ACW system shall be through the ACW expansion tank located on the roof of the STG building.
11.6.6 The technical particulars related to circulating water system have been covered
under the data sheets.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 6 of 26
CIRCULATING WATER PUMPS
1.0 Total number of pumps Three (3)
2.0 No. of pumps operating continuously Two (2)
3.0 Design capacity See Note - 4
5.0 Total head ( Excluding losses in the pump) By Bidder
6.0 Location Indoor
7.0 Maximum rated speed rpm By Bidder
8.0 Type of pump Vertical, mixed flow, wet-pit, non-pullout
type.
9.0 Type of line bearing lubrication Self
10.0 Liquid for lubrication Pumped liquid
10.0 Coupling Flexible
12.0 Prime mover Direct with AC Electric motor
13.0 Material of Construction
13.1 Pump column pipe Fab steel to IS 2062 with epoxy painting
13.2 Pump bowel and discharge elbow CI to IS 210 FG 260
13.3 (a) Impeller SS304
13.4 (b) Shaft SS 410
13.5 (c) Line shaft coupling SS 410
13.6 (d) Line shaft bearing Cutlas rubber in SS shell
13.7 (e) All hardware under water SS 304
13.8 (f) Base plate MS IS2062
13.9 (g) Shaft sleeve SS
13.10 (h) Thrust bearing cooling system
pipes and valves
SS
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 7 of 26
14.0 Shop performance test
To be conducted on all pumps
15.0 Inspection requirements
As per relevant section
NOTE:
1.0 The pump set shall be capable of reverse rotation due to back flow of water from the other
running pump in the event of tripping of the pump for a short duration of time (about 5
minutes)
2.0 Following instruments / monitoring devices shall be provided for each pump: Motor winding temperature detectors and dial type bearing temperature indicators with
alarm contacts.
3.0 The pump shall be capable of operation under shut-off conditions for a duration of 5 minutes
4.0 CW Pumps Total capacity of two pumps shall be equal to 105 % of condenser cooling
water and auxiliary cooling water requirements.
5.0 Motor rating shall be min 116% of duty point requirement at 50 Hz frequency
6.0 The pumps shall be capable of operating from shut-off point to a maximum flow of 10% over
the point of intersection between system resistance curve and pump H-Q curve for single
pump operation.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 8 of 26
1.0 Service CW Pumps Discharge / Condenser
Inlet / Outlet - electrically operated
ACW pump discharge / ACW booster
pump discharge - electrically operated
ACW pump suction / ACW booster
pump suction / Plate type heat
exchanger inlet & outlet lines -
manually operated
electrically operated
Raw water pumps discharge
electrically operated
2.0 Valve size mm By Bidder
3.0 Number of valves Nos. By Bidder
4.0 Hand wheel required Yes
5.0 Valve opening / closing time Sec. By Bidder
6.0 Flow - Maximum / Normal m3/hr By Bidder
7.0 Maximum / normal operating pressure kg/cm2 By Bidder
8.0 Design pressure kg/cm2 By Bidder
9.0 Location Indoor
10.0 Face to face dimension mm As per AWWA C504 / BS 5155
11.0 Material Of Construction
11.1 Body CI IS 210 FG 260
11.2 Disc CI IS 210 FG 260
11.3 Shaft SS AISI 410
11.4 Body seat rings SS AISI 410
11.5 Disc seal rings Natural Rubber
11.6 Seal retaining rings SS AISI 410
11.7 Companion Flange Carbon Steel to IS 2062 Gr. B
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 9 of 26
11.8 Internal hardware SS 304
11.9 External hardware IS 1367, Gr. 4.6
12.0 Bidder shall include end limit switches, torque limits and adjustable limit switches suitably as per
the logics and interlock controls for motorised valves.
13.0
NOTES :
Fabricated valve is acceptable only for sizes 1000 mm and above provided, butt welded joints are
of fill penetration welds, welded ends are subjected to 100% radiography and disc & internal
surfaces of valves are provided with 3 coats of epoxy paint.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 10 of 26
COOLING TOWER
1.0 Designation Induced Draught Cooling Tower
2.0 Number of towers One (1)
3.0 Tower Capacity m3/hr Bidder to indicate based on total
cooling water flow and sahll be equal
to the flow of two nos. CW pumps.
4.0 No. of cells Multi cell, Refer Note 1
5.0 Cells operating All, Refer Note - 1
6.0 Type of tower Cross flow / Counter flow
7.0 Design atmospheric wet bulb temperature 0C As per Project Information given
8.0 Cold Water Outlet temperature 0C These shall be equal to the CW inlet
and outlet temperature of the condenser, corresponding to design heat load of condenser.
9.0 Hot Water Inlet Temperature 0C
During 100% HP-IP-LP bypass operation, the CW inlet and outlet temperature would be higher. This would occur for short durations. Refer also Note 2.
10.0 Wind Velocity :
(a) For performance
(b) For design of structures
kmph
m/sec.
10.0
50
11.0 Tower operation Continuous
12.0 Safe bearing capacity of soil Tonne/
Sq.m
By Bidder
13.0 Seismic zone As per Project Information,
14.0 Pumping head at hot water inlet w.r.t.
normal water level in the basin including
static head and friction losses
mWC By Bidder
15.0 Liquid handled Clarified water
16.0 Drift eliminators Yes
Drift not to exceed 0.02% of
circulating water flow
17.0 Screens / stoplogs at CW outlet channel Required
18.0 Monorail with hoist for handling screens,
Required
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 11 of 26
fans, motors, stoplogs
19.0 Construction
19.1 Type of fill Film
19.2 Tower Arrangement By Bidder
20.0 Elevations
20.1 Grade Level m By Bidder
20.2 Sill Level m 300 mm above ground level
20.3 Normal Water level m By Bidder
21.0 Material of Construction
21.1 Fill PVC
21.2 Fill Support RCC / Stainless steel
21.3 Drift Eliminator PVC
21.4 Water distribution nozzles Polypropylene
21.5 Water distribution system Carbon steel / PVC
21.6 Tower casing / Tower basin RCC
21.7 Fan deck RCC
21.8 Fan blades FRP / GRP
21.9 Fan cylinders / Recovery stack RCC
21.10 Hardware Hot dipped galvanised (HDG) above
fan deck and stainless steel /
phosphor bronze below fan deck
21.11 Screen
a) Frame Mild steel, epoxy coated
b) Mesh Stainless steel, 10 mm sq. mesh
22. Performance Tests Method As per BS 4485 / CTI Code, USA
CTI Code
23. Codes and Standards
23.1 CI Code Standard III
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11
RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 12 of 26
23.2 AGMA
23.3 BS
Note :
1.0 While deciding the number of cells, Bidder shall note that in the event of one cell not being in operation due to maintenance, the remaining cells shall be capable of taking up the entire cooling load and provide cooling water temperature which should permit generation of guaranteed net output of the unit.
2.0 The tower should be capable of cooling the circulating water to the conditions as required as per condenser design, during all conditions, particularly during that of summer months.
3.0 The civil structural requirements as shall be as per Civil section of specification.
4.0 The cooling tower basin shall have a storage capacity of about six (6) hours of make-up water
flow.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 13 of 26
1.0 Designation CW System
2.0 Numbers required Nos. CW pumps discharge
Condenser Inlet / Outlet
3.0 Fluid handled *Clarified water ,.
4.0 Flow Normal / Maximum m3/hr By Bidder (Refer Note 2).
6.0 Pressure operating / design / test mwc By Bidder
7.0 Pressure drop across the expansion joint mwc By Bidder
9.0 Vacuum (test) in mm of Hg 700
10.0 Operating temperature 0C By Bidder
11.0 Movements (min)
Axial compression
Axial elongation
Lateral movement
mm
mm
mm
mm
12
12 (Refer Note 1)
12
12
12.0 No of arches By Bidder
13.0 Control unit to be provided Yes
14.0 Companion flanges Can be made in one piece or in
segments. If segmentally welded 100%
radiography shall be carried out
15.0 Material of construction
15.1 Main body High grade abrasion resistant natural or
synthetic rubber compound
15.2 Reinforcement Steel rings
15.3 Retaining ring Galvanised steel retaining rings
15.4 Outer cover Exposed surface shall be given 3 mm
thick coating of neoprene
15.5 Bolts and nuts IS 1367 Gr. 4.6
15.6 Stretcher bolt plates IS 2062
NOTE :-
1. Bidder to check the value with the movement of condenser and design the expansion joint.
2. Flow values to be based on single pump operation.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 14 of 26
CHLORINATION EQUIPMENT (for CW system, only if chlorination is required)
1.0 Evaporator
a) Type Electrically heated
b) Control Automatic with thermostat
c) No. of Evaporators 2 x 50% for CW system only
d) Capacity / Evaporator kg/h By Bidder
2.0 Chlorinator
2.1 Quantity 2 x 50% for CW chlorination system
2 x 50 % for DM plant chlorination
system
2.2 Type Free standing floor (or) wall mounted
for CW system and DM plant
chlorination systems.
2.3 Cooling water flow quantity m3/h By Bidder
2.4 Design capacity of each chlorinator kg/h By Bidder
2.5 Booster pumps
2.5.1 No. 2 x 100% (Ref. Note - 1)
2.5.2 Material of Construction Impeller : SS 304 / Bronze ASTM B 584, alloy no. 905
Casing : CI, IS 210, Gr.FG 260
Shaft : Steel 080 M 36, BS 970, Part 1
Impeller ring & casing ring : SS / Leaded Bronze
Stuffing box packing : Asbestos
Base plate : MS IS:2062, epoxy painted
2.5.3 Speed ppm 1500
2.5.4 Capacity / head By Bidder
2.6 Motive pressure available at tap off point kg/sq.cm By Contractor
2.7 Back pressure at dosing point kg/sq.cm 1
2.8 Control Manual regulation and timer operated
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 15 of 26
3.0 Material of Construction
3.1 Chlorine gas vacuum line UPVC/Fibre glass reinforced polyester
3.2 Chlorine liquid gas pressure line Seamless steel to IS 1239 (Heavy) /
ASTM-A-106-Gr-B
3.3 Motive water lines Carbon steel to IS 1239/ HDPE (up to
NB 150)
Carbon steel to IS 3589 (above NB
150) with rubber lining
3.4 Chlorine solution line UPVC/FRP/steel with 3 mm Rubber
lining
3.5 Injector CIRL/PTFE throat
3.6 Cabinet FRP
3.7 Vaporising Chamber Boiler quality steel
3.8 Water Chamber Galvanised steel
4. Chlorine Cylinders
4.1 No. of Cylinders 15 days storage requirement.
4.2 Gas capacity/cylinder Ton 0.9
4.3 Design code BS 1500 Part-1 Class-I vessels
4.4 Design temperature and pressure 650C / 21kg/sq.cm
4.5 Material of construction IS 2002 Grade 2A/ASTM-A515 Gr 60
4.6 Platform scale of range 0 2 tonne Nos. 1
5.0 Dosage Rate
5.1 Continuous Dosing ppm 2
5.2 Shock Dosing ppm 5
6.0 Safety Equipment (Only For CW System
Chlorination)
6.1 Chlorine gas leak detectors Nos. 2
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 16 of 26
6.2 FRP hood Nos. 1
6.3
6.4
6.5
6.6
6.7
6.8
7.0
8.0
9.0
10.0
10.1
10.2
10.3
10.4
11.0
Blower
Caustic storage tank
Absorbent tower
Recirculation pump
Flexible hose
Chlorine gas masks
Diffuser Assemblies
Chlorine residual kit of range 0-0.5 ppm in
step of 0.05 pp and 0.5 to 6 ppm in step of
0.5pp
Lifting beam with chain pulley block
List of Instruments
Pressure indicators and pressure switches
on the discharge and suction side of
Booster pump and blowers with alarm and
interlocks.
Differential pressure switch with alarm for strainers, level gauges for absorption tank
Pressure indicators and pressure switches
on chlorine gas lines and solution lines.
All other instruments associated with
chlorinators and evaporators.
Annunciations :
Annunciations for abnormal conditions
such as low chlorine header pressure, low
m
No.
m
Nos.
Nos.
Nos.
Nos.
No.
1 x 100% capacity
10
1
1 x 100% capacity
30
3
As per system requirement with a
minimum of two diffuser sets per pump
chamber.
2
1
Required
Required
Required
Required
Required
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 17 of 26
vacuum, temperature abnormalities, low
suction pressure in booster pumps, low
ejector vacuum, high pressure in chlorine
gas tanks and other alarms required for
leak detection system shall be annunciated
in the control panel.
NOTE
1) 1.Should biocide treatment be considered
adequate by the Bidder for control/
prevention of growth of algae/ organisms
in the CW system, CW chlorination
described in this section shall be ignored.
2) 2.Bidder to decide the necessity of
chlorination booster pumps for river water
and DM plant chlorination systems. Bidder
to provide booster pumps for CW system
chlorination.
3)
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 18 of 26
CLARIFIER SYSTEM
1.0 Stilling Chamber and Parshall Flume
1.1 Number One (1)
1.2 Material RCC
2.0 Coagulant Solution Tank
2.1 Number Two (2) nos preparation tanks-cum-
measuring tanks
2.2 Material RCC
2.3 Agitator of SS 316 One(1) for each tank of SS 316 material
3.0 Coagulant Dosing Pumps
3.1 Number 2 x 100 %
3.2 Capacity and Head By Bidder
3.3 Material SS 316
4.0 Flash Mixer
4.1 Quantity One (1)
4.2 Material RCC
4.3 Agitator of SS 316 One (1)
4.4 Accessories
4.4.1 Approach ladder platform, isolating gates,
handrail and SS 316 agitator
Required
5.0 Poly Electrolyte Solution Tanks
5.1 Number One (1)
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 19 of 26
5.2 Tank material IS 2062 with 4.5 mm thick rubber lining
5.3 Agitator of SS 316 Yes
5.4 Dissolving basket Yes
6.0 Poly Electrolyte Dosing Pumps
6.1 Number Two ( 1 working + 1 stand by)
6.2 Capacity and Head By Bidder
6.3 Material of wetted parts SS 316
7.0 Clarifiers
7.1 Quantity One (1) No.
7.2 Type clariflocculator /solid contact type
7.3 Rise rate By Bidder
7.4 Detention time (minimum) By Bidder
7.5 Accessories
7.5.1 Drive assembly for rack, gear box for rack,
drive assembly for turbine, gear box for
turbine, bridge, platform with chequered
plate, hand-railing, staircase sampling
lines for clarifiers telescopic pipe (one for
each clarifier).
Required
7.6 Painting All steel surfaces shall be coated with
epoxy
8.0 Sludge Pit (Common to both raw water clarifier and DM plant clarifier)
8.1 Quantity One (1)
8.2 Material RCC
8.3 Capacity By Bidder
9.0 Sludge Transfer Pumps (Common to both raw water clarifier and DM water clarifier)
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 20 of 26
9.1 Number of Pumps Two (2) ( 1 working + 1 standby)
9.2 Capacity / Head By Bidder
9.3 Material
9.3.1 Impeller SS 316
9.3.2 Casing CI 210 Gr FG 260
9.3.4 Shaft and Sleeves SS 316
9.3.5 Impeller ring and casing ring SS 316
9.3.6 Base plate MS or CI with epoxy paint
10.0 Thickener and centrifuge (Common to
both raw water clarifier and DM plant
clarifier)
10.1 Quantity Thickener - One (1) No.
Centrifuge - One
10.2 Material RCC
10.3 Capacity By Bidder
11.0 Inlet control valves to the clarifiers Butterfly valves
12.0 Instrumentation Control
12.1 List of Instruments
12.1.1 One(1) floor mounted control panel to
house the following:
Required
(a) Instruments: Flow indicator,
integrator and recorder for parallel
flume, level indicators for tanks.
Required
(b) Annunciation Window
(i) Clarified water storage tank
common sump level low, DM
plant clarified water storage
tank, sump level low sludge
pit level high, chemical tank
level low
Required
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 21 of 26
(ii) Control supply failure Required
(iii) Clarified water storage tank
common sump level high, DM
plant clarified water storage
tank high and other
annunciations to make the
system complete
Required
(c) Illuminated push buttons set with
indicating lamps for all the drive
motors
Required
(d) Illuminated push buttons (open /
close) with indicating lamps (green /
red) for the clarifier inlet valves
Required
(e) Selector switch for all motor driven
equipment for selecting the standby
equipment into service
Required
(f) Mimic diagram of plant shall be
displayed on the control panel of
plant
Required
13.0 Minimum clarifier effluent quality to be
guaranteed
Turbidity = 20 NTU
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 22 of 26
CW-CHEMICAL DOSING SYSTEM
1.0 Type of chemical Dispersant / anti- scalant for prevention
of scaling and maintaining the cycles of
concentration;
Biocide treatment for prevention of
growth of algae and other organisms
2.0 Chemical Dosing Tank
2.1 Numbers 2 Nos. tanks/ carbuoys for storing each
chemical
2.2 Capacity Each tank to store 12 hours requirement
2.3 Material of construction FRP
3.0 Chemical Dosing Pumps
3.1 Number 2 x 100% for each chemical tank
3.2 Capacity and Head By Bidder
3.3 Material of construction (all wetted parts) SS 316
3.4 Stroke length adjustment 0-100%
4.0 Accessories to be provided Suction strainer of SS 316, Ball check
valve, Built in type common base plate
5.0 Type of control Relay based control for chemical dosing
system
6.0 Instrumentation
6.1 Pressure indicators and pressure switches
on discharge and suction line of the
dosing pumps with alarm and interlock with
pumps
Required
6.2 Differential pressure switches across the
suction strainers with alarms.
Required
6.3 Level switches (low levels) and level
gauges for each of the dosing tanks with
alarm and interlocks with pump.
Required
7.0 Safety shower end Eye Wash fountain One (1) No.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 23 of 26
Note : 1 For any other chemical required for maintaining the concentration ratio in the CW
circuit/ prevention of scaling/ growth of algae, Bidder shall include 1 No. day tank and
2 x 100% dosing pumps.
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 24 of 26
1.0 GENERAL
1.1 Service of heat exchanger
Auxiliary Cooling Water/ Condenser
cooling water
1.2 Quantity required 2 Working + 1 Standby
1.3 Location
Indoor
1.4 Operation
Continuous
1.5 Design code ASME VII/ASME.III (ND)
2.0 DESIGN DATA AND CONSTRUC- TION REQUIREMENT FOR ONE HEAT
EXCHANGER
HOT FLUID COLD FLUID
2.1 Fluid circulated Passivated Condenser
DM water cooling
water
2.2 Fluid characteristics
(a) Viscosity kg/m.sec. By Bidder
(b) Specific gravity
(c) Specific heat at mean temp.
kcal/kg. By Bidder
C
(d) Thermal conductivity at mean temp.
kcal/ By Bidder
hr.m
C
(e) pH value By Bidder
(f) Turbidity ppm By Bidder
(G) Chlorides ppm By Bidder
2.3 Flow rate kg/hr. By Bidder
2.4 Heat exchanged kcal/hr. By Bidder
2.5 Operating temperature
(a) Inlet
C By Bidder
(b) Outlet C By Bidder
2.6
Normal operating pressure
kg/cm
(g) By Bidder
2.7 Design pressure kg/cm By Bidder
(g)
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 25 of 26
HOT FLUID COLD FLUID
2.8 Maximum allowable pressure
drop including in nozzle
kg/cm 0.5 0.7
(g)
2.9 Minimum hydrostatic test
Pressure
kg/cm This shall be 1.5 times the operating
(g) pressure
2.10 Maximum differential pressure
between hot fluid & cold fluid sides
kg/cm Equal to design pressure
(g)
2.11 Design temperature C By Bidder
2.12 Overall fouling resistance
(minimum) to be considered
hr.m 0.4 x 10-4
C/kcal
2.13 Design margin on frame to
accommodate additional plates
15%
2.14 Seismic design criteria, if any
Refer Project information
2.15 Flange drilling standard ANSI B 16.5 #
3.0 MATERIAL OF CONSTRUCTION
3.1 Heat transfer plates SS AISI 316
3.2 Compression/fixed plates IS 2062
3.3 Guide rail SS CLAD IS 2062
3.4 Support beam/column IS 2062
3.5 Tie bolts and nuts
SA 193 GR.B7/ SA 194 GR 2H or 7
3.6 Plate gaskets Nitrile rubber
3.7 Nozzles:
(a) Hot fluid side
(b) Cold fluid side
SA 106 GR.B
SA 106 GR.B
3.8 Nozzle gaskets GRAFOIL
3.9 Nozzle flanges/counter flanges
(a) Hot fluid side
SA 105
-
PIONEER GAS POWER LIMITED
380-425 MW COMBINED CYCLE POWER PLANT APSIPL-05-EPC- 3-A11 RAW WATER SYSTEM AND CIRCULATING WATER
SYSTEM
Page 26 of 26
(b) Cold fluid side SA 105
3.10 Nozzle flange bolts/nuts SA 193 GR. B7/ SA 194 GR. 2H or 7
3.11 Name plate 18-8 SS (3 mm thick)
4.0 ACCESSORIES & SERVICES
4.1 Companion flanges with bolts,
Nuts and gaskets
Yes
4.2 Lifting lugs Yes
4.3 Earthing cleats Yes
4.4 Foundation bolts and nuts Yes
4.5 Name plate with design data Yes
4.6 Erection Yes
5.0 MAINTENANCE TOOLS
5.1 Wrenches for every kind of nuts used Yes
5.2 Pneumatic/Hydraulicoperated Wrench
Yes
6.0 NOTES
6.1 Double gasket system with vents moulded into the gasket shall be provided to avoid mixing and easy detection of leakage.
6.2 All pipes for nozzle shall be seamless
6.3 Holding down bolts shall be provided
6.4 One coat of Zinc Chromate primer followed
by final shop coat of paint, type of which
will be advised later by the
owner/consultant
6.5 All nozzle flanges shall have a raised face
6.6 All testing is to be done using calibrated instruments traceable to national standard.