Section 6 B2H SOP

download Section 6 B2H SOP

of 91

Transcript of Section 6 B2H SOP

  • 5/26/2018 Section 6 B2H SOP

    1/91

    Ooredoo FTTx NationalBroadbandProject

    FiberforBusiness

    StandardOperationProcedure B2HConnectionsGuideBook

    1

  • 5/26/2018 Section 6 B2H SOP

    2/91

    Standard Operation Procedure B2H Connections Guide Book

    FiberForBusiness

    Chapter1:B2HScenariosOverview 7.5:Stripping,leadingin,SplicingandFixingof

    ap er : roce ure or ns a a on

    Chapter3:CommunicationandSurvey

    Chapter4:PreparationforB2H

    Chapter5:StandardLayingofOutdoorOFC

    5.1: SafetyEnvironmentDeployment

    7.6:PreparingofVerticalRisercable

    7.7:PreparingofRisercable

    7.8:Leadingin,splicing andFixingoffibers.

    7.9:Exampleinstallations

    . : tan ar raw ngs

    5.3: ImplementationPreparation

    5.4: TransportingofCable

    5.5:

    FixingCable

    Drum5.6: ManholeOpening

    .

    Chapter8:Standard Installation of Sub FAT3101

    8.1: Plantheinstallationspace

    8.2: Fixingonthewall

    8.3: PreparingofVerticalRisercable

    5.7: DuctRo ng5.8: Makingtractionend

    5.9: Laying thecable

    Chapter6: StandardLayingofRiserandDropCable

    6.1: TransportingandFixingofCableinside

    .

    8.5: Leadingin,Fixingandsplicing ofDropfibers.

    8.6: Splicingrequirementpercustomer

    8.7: Additionalrecommendations

    Chapter9:StandardLabeling

    6.2: Layingof VerticalCable6.3: Layingof DropCable

    Chapter7: Standard Installation of FAT3201-24and FAT3201-48 (direct drop fibers)

    7.1:Procedureof FATInstallation

    . :

    Chapter10:StandardISPinstallation

    10.1:InstallationprocedureforSCS

    10.2:StandardInstallationofATBandONT

    Chapter11:StandardSplicing

    7.2:InstallationofFATinthewall

    7.3:Preparationof FeederCable

    7.4:LeadinginandFixingofDropCables

    . : p c ng roce ure

    11.2: JointSplicingintheManhole

    2

  • 5/26/2018 Section 6 B2H SOP

    3/91

    Chapter OneBusiness Lines B2H ScenariosOverview

    3

  • 5/26/2018 Section 6 B2H SOP

    4/91

    Feasibilit Surve

    Beforestartinganyactivitywithimplementationinthebuilding,ensurethatthe

    buildingwiringandinfrastructurecorrespondstooneofthefollowingscenarios.

    Incaseofanydeviations refertoHuaweiSiteEngineer/AreaManagerforguidance.

    4

  • 5/26/2018 Section 6 B2H SOP

    5/91

    DropcablesaredistributeddirectfromtheFAT3201 24(2nd Splitterwith16

    1.B2HScenarios

    st , .Expansion).

    X*Delnumber/CustomerReferenceNumber/ElectricityNumber

    of DELs 1,2,3,4 5,6,7,8 948 >48

    2nd Floor

    DirectDrop

    Cables

    Equipment 1ONTSupports 4Ports

    (ONT8447)

    2ONTSupports 4PortsEach

    2*(ONT8447)

    MA5612 nxMA5612

    1stFloor

    GroundFloor

    Basement

    FAT320124(16)

    (1Splitter)Feeder

    Cable

    5

  • 5/26/2018 Section 6 B2H SOP

    6/91

    Ifabuildinghas47floorsandeachfloorhas2connections,itispossible

    nd

    1.B2HScenarios

    conduithasenoughspacetoaccommodate814dropcables.

    6thFloor

    DirectDropCables

    oor

    4thFloor

    2ndFloor

    1stFloor

    Basement

    GroundFloor

    (1splitters)

    Feeder

    cable

    6

  • 5/26/2018 Section 6 B2H SOP

    7/91

    DropcablesaredistributeddirectfromtheFAT3201 48(32)(2splitters,

    rd

    1.B2HScenarios

    X*Delnumber/CustomerReferenceNumber/ElectricityNumber

    of DELs 1,2,3,4 5,6,7,8 948 >48

    Equipment 1ONTSupports 4Ports 2ONTSupports 4PortsEach M5612 nxMA5612

    2ndFloor

    DirectDrop

    Cables

    (ONT8447) 2*(ONT8447)

    1stFloor

    GroundFloor

    Basement

    FAT320148(32)(2splitters)

    Feeder

    cable

    7

  • 5/26/2018 Section 6 B2H SOP

    8/91

    IfDistancefromFATtothenecessaryflooristoolong,orriseris

    th

    1.B2HScenarios

    congeste ,poss etouse u ,connecte tot e a n v a ser

    Cable.

    of DELs 1,2,3,4 5,6,7,8 948 >48

    2ndFloor

    Dro Cables

    SubFAT3101

    (ONT8447)

    2*(ONT8447)

    1stFloorVertical

    RiserCables DropCables

    SubFAT3101

    GroundFloor

    BasementFeeder

    Cable

    FAT320148

    (2Splitters)

    8

  • 5/26/2018 Section 6 B2H SOP

    9/91

    InthiscaseDropCablesaredistributedbySubFAT3101,eachSubFATis

    5

    th

    Case

    1.B2HScenarios

    servicing2floors(upto6Onts perfloor).

    2ndFloor

    DropCables

    1stFloor

    DropCables

    SubFAT3101

    GroundFloor

    VerticalRiser

    Cables

    SubFAT3101

    Basement

    Feeder

    Cable

    FAT320148

    (2Splitters)

    9

  • 5/26/2018 Section 6 B2H SOP

    10/91

    IncaseifoneSubFATisservicingmorethanonefloor:6th Case1.B2HScenarios

    3rdFloor

    AllflatsfromthesamefloorshouldbeconnectedtothesameSubFATonly.

    2ndFloor

    SubFAT3101

    1stFloor

    GroundFloor

    SubFAT3101

    Basement

    Feeder

    Cable

    10

  • 5/26/2018 Section 6 B2H SOP

    11/91

    TwoFAT

    3201

    48

    is

    combined,

    Drop

    cables

    are

    distributed

    by

    Sub

    FAT3101,

    each

    7th Case1.B2HScenario's

    3rdFloor

    FATisservicing2floors(7to12ONTsperfloor).

    DropCables

    2ndFloorVerticalRiserCables

    u

    1stFloor

    Sub FAT3101

    GroundFloor

    SubFAT3101

    BasementFeeder

    FAT320148

    (2Splitters)

    Cable FAT320148

    (2Splitters)

    11

  • 5/26/2018 Section 6 B2H SOP

    12/91

    IncaseifnumberofSubFATisequaltothenumberofsplittersandfreesplitterports8th Case1.B2HScenario's

    arestillavailable,itispossibletousedirectdropsfromFATtotheSAMEfloor.

    3rdFloor

    2ndFloor

    u

    1stFloorVertical

    RiserCables

    SubFAT3101

    DirectDrop

    Cables

    GroundFloor

    Feeder

    FAT320148(2Splitters)

    Cable

    (1Splitters)

    12

  • 5/26/2018 Section 6 B2H SOP

    13/91

    SimilarscenarioforsingleFAT320148.Wehave2splittersand2ofSub9th Case1.B2HScenario's

    . x u cancon a n rop ersmax mum. ccor ng o

    Ooredoo businessrules,wecanconnect28Onts to2splitters.So,4

    splitterportsstillfreeandcanbedistributedbydirectdrops(onlytothe

    nearestfloor).

    2ndFloorSubFAT3101

    1stFloorVertical

    RiserCables

    SubFAT3101

    FAT 320148

    DirectDrop

    Cables

    GroundFloorFeeder

    Cable

    (2splitters)

    13

  • 5/26/2018 Section 6 B2H SOP

    14/91

    10th Case1.B2HScenario's

    SubFAT3101

    SubFAT3101 5thFloor

    6thFloorIdealscenario ifwehaveupto7ofSubFAT.In

    thiscaseispossibletoterminateeachof24F

    SubFAT3101 4thFloor

    .

    Otherwiseweneedtosplitthecablesto

    differenttrays.

    2ndFloor

    3rdFloor

    22UCabinet,5Splitters,72ONTsMaximum.

    SubFAT3101

    SubFAT3101

    GroundFloor

    1stFloor

    Vertical

    RiserCables

    SubFAT3101

    SubFAT3101

    BasementFeeder

    22UCabinet

    Cable

    14

  • 5/26/2018 Section 6 B2H SOP

    15/91

    22Ucabinet 6s litters 84connectionsmaximum.

    11th Case1.B2HScenario's

    SubFAT3101

    SubFAT3101 5thFloor

    6thFloorForabuildingwhichhas7184connections,

    Install1x22Ucabinetwith6splitters.Use

    SubFAT3101 4thFloor

    .

    alsopossibletoterminateeachof24Fcableto

    dedicatedsplicing/terminationtray.Otherwise

    weneedtosplitthecablestodifferenttrays.

    2ndFloor

    3rdFloorSubFAT3101

    SubFAT3101

    GroundFloor

    1stFloor

    Vertical

    RiserCables

    SubFAT3101

    SubFAT3101

    Basement

    Feeder

    22UCabinet

    cable

    15

  • 5/26/2018 Section 6 B2H SOP

    16/91

    IncaseifnumberofONTsperfloorismorethan12 twoSubFATstobe12th Case1.B2HScenario's

    .

    3rdFloor

    Dro Cables

    EachcasetobedealtwithonacasebycasebasisinagreementwithOoredooDesignApproval

    2ndFloor

    SubFAT3101

    SubFAT3101

    SubFAT3101

    SubFAT3101

    1stFloor

    SubFAT3101SubFAT3101

    GroundFloor

    SubFAT3101SubFAT3101

    Basement

    Vertical

    RiserCables

    Feeder

    Cable

    22UCabinet

    (WallMounted)

    16

  • 5/26/2018 Section 6 B2H SOP

    17/91

    Scenariowithtworisers,1324ONTsperfloor.

    13th Case1.B2HScenario's

    3rdFloor

    SubFAT3101SubFAT3101

    SubFAT3101SubFAT3101

    2ndFloor

    1stFloor

    SubFAT3101SubFAT3101

    roun oor

    SubFAT3101SubFAT3101

    Riser2

    Feeder

    Riser1

    22UCabinet

    (WallMounted)

    Basement

    17

  • 5/26/2018 Section 6 B2H SOP

    18/91

    Scenariowithtworisers,712ONTsperfloor.

    `

    14th Case1.B2HScenario's

    ac case o e ea w onacase ycase as s nagreemen w ore oo es gn pprova

    SubFAT3101SubFAT3101

    2ndFloor

    1stFloor

    GroundFloorSubFAT3101SubFAT3101

    Riser2

    Feeder

    Cable

    Riser1

    22UCabinet

    (WallMounted)

    18

  • 5/26/2018 Section 6 B2H SOP

    19/91

    B2HRestrictions

    3rdFloor

    SubFAT3101

    2ndFloor

    1stFloor

    SubFAT3101

    GroundFloor

    BasementFeeder

    cable22UCabinet

    (WallMounted)

    19

  • 5/26/2018 Section 6 B2H SOP

    20/91

    Chapter TwoProcedureforBusinessLinesB2Hinstallation

    20

  • 5/26/2018 Section 6 B2H SOP

    21/91

    2.1B2HBusinessLinesProcess

    21

  • 5/26/2018 Section 6 B2H SOP

    22/91

  • 5/26/2018 Section 6 B2H SOP

    23/91

    2.3NamingConvention

    SE+ISPInstallationTeam:A

    1. InstallationofATB&ONT

    cabinet/casing

    2. Knowrouteofbuilding

    B2HInstallationTeam:B

    1. Installationofrisercable,

    FATandsubFAT

    2. Installationof2Fdrop

    .

    communicationskills

    .

    3. Knowrouteofbuilding

    4. SimpleEnglish

    communicationskills

    SplicingTeam:D

    1. HaveexpertFusionsplicing

    OSPInstallationTeam+OSP

    SplicingTeam:C

    capability.

    2. SimpleEnglish

    communicationskills.

    3. Havegoodknowledgeof

    healthandsafety.

    1. Haveagood

    understandingofOSPwork

    2. HaveexpertFusionsplicing

    capability.

    3. Havegoodknowledgeof

    healthandsafety

    MigrationTeam:E

    1. Provisioning&testingofall

    services.

    2. Troubleshootingcapability

    3. HaveknowledgeofISP

    MigrationTeam:F

    1. Haveprofessional

    electricalcertification

    2. Troubleshootingcapability

    3. GoodEnglish

    .

    4. GoodEnglishcommunicationskills.

    .

    Huawei/OoredooisnotresponsibleforanyThirdParty

    23

    internalcabling.PleaserefertolocalITdepartment

    relatingtoanyissue.

  • 5/26/2018 Section 6 B2H SOP

    24/91

    Chapter ThreeCommunication and Survey

    24

  • 5/26/2018 Section 6 B2H SOP

    25/91

    3.1CommunicationandSurveySN Task Description Operator Duration

    Communication and Surve1

    . Procedure

    1 Introduce oneself at the office reception. As shown in Picture 1

    2 Show the ID card to the Customer;

    3Get the access signature from customer on new Ooredoo Authorisation forms.

    .

    4 Converse with the customer according to the script (Ask for IT person if available)

    5Agree the location of ONT/ATB with the Customer and confirm the installation

    scenario based on xxxxxx (power socket location).

    6 Survey the ODP location (drop cable route) as Image 4 shown.

    7 Validate the customer's data information with customer;

    Note

    1If it is inconvenient for the Customer to give access there and then, ISP

    coordinator will make an appointment with customer and record the appointment

    time via Ooredoo Call Center.

    2

    2

    work.

    3If customer does not allow ISP team to carry out installation then ISP coordinator

    will note this into his report and quality sign off sheet, will request the customer to

    sign the sheet for not allowing the installation and report back.

    4 The workers should be in neat and clean Ooredoo uniform at all times.

    5e wor ers mus e a equa e y ra ne e ore ey v s cus omer; uawe w

    provide the technical training & Ooredoo will provide the communication training)6 The workers should take off shoes if needed;

    7 Ooredoo will provide the Authority letter;

    Tools

    ODP

    25

    1 Iron wire push rod 2

    screwdriver3 Straight Screwdriver

    Materials

    1 Introduction letter 2 Work order 3 Authority letter

  • 5/26/2018 Section 6 B2H SOP

    26/91

    Chapter FourPreparationforB2H

    26

  • 5/26/2018 Section 6 B2H SOP

    27/91

    Preparation for B2H SN Task Description Co-ordination Duration

    4.1 Preparation for B2H A & B

    1 Refer to door knocking procedure for the building access

    2Refer to building survey report, familiarize yourself for all the works needed to

    be done

    Before start an activit ive a brief safet instruction for the workin force.

    3 Check the uniform and their appearance and ensure cleanliness and

    professionalism to upheld at all times

    4Politely speak to the building property manager, building owner or the security

    guard regarding the installation

    5 Inspect the building scenario and compare it with the building survey report.

    6If any mismatches found (different quantity of floors, cable routes, FAT

    capacity and etc.) immediately report to Huawei site engineer.

    Note

    1 Ensure all PPE is in place

    2 Ensure all the accreditation cards are available

    3

    4

    Tools

    See separate tool list

    Requirements

    1Installation

    2Building Survey

    3 Way leaves form

    Remember -Think Safety - Work Safely

    4 5 6

    27

  • 5/26/2018 Section 6 B2H SOP

    28/91

    Chapter FiveStandard Laying of Outdoor OFC

    28

  • 5/26/2018 Section 6 B2H SOP

    29/91

    Safety Environment

    De lo ment

    SN Task Description Operator Duration

    5.1 a e y env ronmendeployment

    A & C 10 Min

    Procedure

    1 Ensure All PPE is worn

    2

    3

    Note

    1Always wear safety glasses, high visibility jerkins, suitable safety

    Helmet and protective gloves.

    2 Keep all food and beverages out of the work area.

    3Don't touch your eyes while working with fiber optic systems until

    they have been washed thoroughly.

    4

    Tools

    Safety glasses Hi-Vis Vest

    oa a e y

    Signs

    Safety Helmets Safety foot wear Gloves

    MaterialsRemember -

    1 2 3Think Safety, Work Safely

    29

  • 5/26/2018 Section 6 B2H SOP

    30/91

    Safety Environment Deployment SN Task Description Operator Duration5.1.1 Safety environment

    deployment

    A & C 10 Min

    Procedure1 Deploy road safety precaution:"Keep left-Right" (see pic 1)(Observance of

    the sign is mandatory and drivers must pass on the side indicted). Care must

    therefore be taken to ensure that drivers are not directed onto the footway by

    unintentionally placing the sign the wrong way round. The sign is always

    placed at the start of a temporary kerbed line taper and at other locations.)

    1

    2 Cones, Reflecting (see pic 2)(cones are used to delineate a temporary

    kerbed line). For day and night work, they should be used in conjunction withlamps. Road caution, a cone and a lamp being placed alternately around the

    obstructions that will be removed before darkness. Only cones should be

    used to guard the area. Where cones are placed at between 45 and 90to2approaching traffic, they must be spaced 1.2m apart. Where cones are

    placed in line of traffic ,they must be spaced 9m apart.

    3 Lamps, Road caution (see pic 3)(lamps, road caution are used with

    cones),reflecting to delineate a working area for night work, lamps being.

    during the day. Lamps are used on footways at night to warn pedestrians of

    obstruction.

    Note

    1 Deploy all required SLG(Signing ,Lighting and Guarding ) as per traffic

    requirements

    3

    2 You are responsible for your own safety, the safety of your workmates and

    that of public.

    3

    4

    Tools

    1 Cones 2 Lamps 3 Sign for Keep left-

    Right

    30

  • 5/26/2018 Section 6 B2H SOP

    31/91

    Implementation Preparation SN Task Description Operator Duration

    .

    Procedure

    1 Legend details (see pic 1)

    2 Layers by colour (see pic 2)

    1

    3 Duct details (see pic 4)

    4 Update the duct details used in FAT section of design

    5

    Note

    1 Always Used the Approved OSP As-built Drawing

    2

    3

    Tools

    1 2 3

    4 5Materials

    1 Drawing 2 3

    4 5 6

    31

  • 5/26/2018 Section 6 B2H SOP

    32/91

    Implementation Preparation SN Task Description Operator Duration

    5.3Implementation

    A & C 5mins

    Procedure

    1 Refer to the cable route design to start installation

    2Cross Check the Actual Route on cable route design and ODF

    design.

    3

    4

    5

    6

    Note

    1 Always Used the Approved OSP As-built Drawing

    2

    4

    Tools

    4 5

    Materials

    1Cable route

    design2 3

    4 5 6

    32

  • 5/26/2018 Section 6 B2H SOP

    33/91

    Standard laying of Distribution O.F. cable SN Task Description Operator Duration

    5.4 Transporting of Cable A & C 5mins

    Procedure

    1 Unload the O.F.cable drum from the truck (see pic 1)

    2 Roll the cable tray to the place near the manhole.1

    3 Secure the working area and set up the materials and tools properly

    4Observe the safety standard precaution measurement when carrying

    out the work

    5

    Note

    1 Ensure proper PPE is used

    2 Ensure stopping block is in place when off loading cable drum2

    4

    5

    6

    Tools

    1 2 34 5

    Materials

    1 Cable 2 3

    4 5 6

    33

  • 5/26/2018 Section 6 B2H SOP

    34/91

    Standard Laying of Distribution O.F. Cable

    SN Task Description Operator Duration

    5.5 Fixing Cable Drum A & C 15mins

    1 Fix the cable drum on drum hydraulic as pic 1.

    2 Adjust the height of holder as the pic 2 shown.

    3Put a ground sheet underneath the cable drum to prevent any

    1

    4

    5

    6

    Note

    1 Make sure the cable rolling direction is correct.

    2The drum hydraulic should be set up at safe distance from the open

    manhole

    2

    3 Do not block door entry or customer access

    Tools

    1Cable

    hydraulics2 PPE 3 Ground Sheet

    Materials

    1 Cable Drum 2 Cable 3

    4 5 6

    34

  • 5/26/2018 Section 6 B2H SOP

    35/91

    Standard Laying of Distribution O.F. Cable

    SN Task Description Operator Duration

    5.6 Manhole Opening A & C 5mins

    Procedure

    1Deploy cones and warning tape around manhole(see pic 1), clean

    manhole cover (see pic 2)

    2

    Open manhole with proper Ooredoo manhole key as the pic 3,4 and

    5 shown. Always ensure gas detector is used when opening

    21

    .

    3 Check the detail design and choose the right duct as pic 6 shown.

    4 If there is water, sundries or sand in manhole which will affectimplementation, need to clean out with bailer, shovel or other tools.

    5

    Note

    1 Always bring detail design and diagram drawing with the team.

    2 Use proper key for different manholes.

    3 Not allowed to change the design on site.

    43

    4 When opening the cover of manhole, there should be two people.

    5 Must use gas detector for all manholes.

    Tools

    1 Manhole keys 2 Bailer 3 Shovel5 6

    4 Gas Detector 5 Gloves 6 Brush

    7 SLG 8 Cones

    Materials

    1 2 3

    4 5 6

    35

  • 5/26/2018 Section 6 B2H SOP

    36/91

    Standard Laying of Distribution O.F.

    Cable

    SN Task Description Operator Duration

    5.7

    Duct Roding

    (No Rope or Rope

    can not be used)

    ABCDE 30mins

    Procedure

    1

    Pay attention to the connector of PVC duct rod,one side is the

    female,the other is the male.And then start duct rodding,as pic

    1,2,3,4,5,6 and 7 shown.

    Take the push rod from truck, and disjoin them as the pic 1,2

    . , .

    the tools near both of the manhole A and B at the same time,

    3

    Install the female connector on one side of the duct rod at manhole

    A, and the male connector at manhole B. Use the tape to fix the

    two connectors firmly(pic 4,5,6).

    4Lead the duct rod to the underground duct both of manhole A and

    . , ,

    5Tie up the draw rope on the push rod, turn back the push rod to the

    manhole until the rope is in the duct from manhole A to manhole B.

    Note

    1 Ensure proper PPE is used

    3

    4

    5

    Tools

    1Distance

    measurer2

    Tools for

    dredging3 PVC Duct Rods

    4 Gloves 5 PVC tape 6 Rope

    Distancemeasurer

    1 Draw Rope 2Ground

    Sheet3

    4 5 6

    Duct X

    Female ConnetorMale Connetor

    36

  • 5/26/2018 Section 6 B2H SOP

    37/91

    Standard Laying of Distribution O.F. CableSN Task Description Operator Duration

    5.8 Making traction end A & C 5mins

    Procedure

    1 Connect the Cable Grips and Cable Swivel as pic 1 shown.

    2 Insert cable end into cable grips as pic 2 shown.

    3 Wrap the cable and cable grips with tape (see pic 3).

    1 2

    4Connect the cable Swivel and the pulling rope. splice the pulling

    rope and wrap the splice rope with a PVC tape as pic 4,5

    5

    6

    3

    1

    2

    3

    4

    4

    5

    6

    Tools5

    4 5

    Materials

    1 Tape 2 3

    Connectto

    O.F.cable

    viaswivel

    37

  • 5/26/2018 Section 6 B2H SOP

    38/91

    Standard Laying of Distribution O.F. CableSN Task Description Operator Duration

    5.9 Laying the cable A & C 20mins

    Procedure

    1Put the ground sheet on the ground between the cable drum

    and the manhole (see pic 1).

    2 Deploy the bellmouths at both sides of duct (see pic 2)

    12

    x u w .

    4

    In order to feed the cable into the duct in preparation for pulling

    E.G. person at manhole A pulls the pulling rope slowly whileperson at cable drum E.G. person at pic 4 feeds the cable into

    the duct . Pull the cable accordingly.

    After the cable is installed Leave maintenance loop of 8 meters

    43 Manhole A

    inside the splitter/joint manhole

    6Coil a loop of cable atleast 5 meters inside telecom room for

    arranging and splicing purposes

    7Seal the duct entry point from the manhole and inside telecoms

    room by using compound 16.

    Note

    RopeGuiding

    Roller

    Always adhere for the safety standard precaution measurement

    Cable labeling should be in this format Approved format by

    Ooredoo

    to be confirmedManhole B

    6

    Tools

    1Split Bell

    mouths2

    Rope Guiding

    Roller3

    Road safety

    precaution

    4 Ladder 5 ground sheet 6 Screw drivers

    Materials

    1 Cable 2 PVC tape 3

    4 5 638

  • 5/26/2018 Section 6 B2H SOP

    39/91

    Chapter SixStandardLayingofRiserandDropCable

    39

  • 5/26/2018 Section 6 B2H SOP

    40/91

    SN Task Description Operator Duration

    Transporting and

    fixing of cable

    . drum insidetelecom room

    Procedure

    1

    Make sure that the cable drum is correctly positioned. See pic 1

    as shown1

    2

    3

    Note

    1 Ensure proper PPE

    2

    cable drum, If not take the cable drum outside telecom room

    and proceed for the standard laying of the cable and ensure all

    the safety precautions are taken

    3

    Tools

    1 Cable Cutter 2Ground

    Sheets3 Cable Jacks

    Materials

    1 Cable Drum 2 Drop cable

    40

  • 5/26/2018 Section 6 B2H SOP

    41/91

    Standard Laying of Vertical Cable

    SN Task Description Operator Duration

    6.2 Laying of Vertical Cable B

    1Open the tray works safely and Identify the route of the riser

    cable.(see pic 1)

    2Rod and Pull the vertical cable from the telecom room to the

    next floor where the sub FAT is located. (see pic 2)

    Keep a loop of cable for splicing inside the telecom room

    1

    3(approximately 3 meters for main FAT) and to the designated

    floor where the sub FAT is required (approximately 2 meters for

    the sub FATs) (see pic 3)4

    Mark the vertical cable with a temporary label according to the

    floor number where the sub FAT will be installed.

    Tie up the vertical cable neatly in the existing tray works in the

    2 3

    dry riser by using cable ties. (see pic 4)

    6Seal the duct entry point by using fire stopping compounds from

    telecom and riser room. (see pic 5)

    6 close the tray works safely. (see pic 6)

    Note4

    1 The minimum bending radius of the fibre is 8 cm.

    2The cables should be routed neatly and together. Do NOT mix or twist

    the cables up with the existing copper cables in the dry riser.

    3 Label the cables as per Labeling SOP

    Tools

    1 Screw drivers 24 mm

    cobra rod3 Cutter

    4 Ladder 5 6

    Materials

    65

    1 12/24F cable 2 Cable ties 3 Insulation tape

    4Fire stopping

    compound

    5Ground

    Sheets

    6

    41

  • 5/26/2018 Section 6 B2H SOP

    42/91

    Standard Laying of Vertical Cable

    SN Task Description Operator Duration

    6.3Laying of Drop

    CableA

    Procedure

    1Identify the primary telephone socket outlet in the customer

    premises. (see pic 1)

    2Identify the route of the drop cable from installed FAT or sub-

    1 2

    3Open the telephone socket and search if there is a pulling rope.

    Push rod should be used if there is no pulling rope. (see pic 2)

    4Tie up the pulling rope and drop cable with PVC tape. (see pic

    3)

    Lay the drop cable from the installed FAT or Sub FAT to inside

    customer premises

    6

    Keep a loop of cable inside the ONT cabinet (approximately 2

    meters) and inside FAT or Sub FAT(approximately 2 meters)

    for splicing

    7 Mark each drop cable with a temporary cable and ensure its

    Note

    1Keep the maintenance loop safe and avoid unnecessary

    bends.

    2Minimum bending radius of the drop cable shall be maintained

    according to the cable specification.

    Dropcable

    3 4

    3

    Tools

    1 Screw Drivers 2 Cutter 3 4mm rod

    Materials

    1 pulling rope 2 PVC Tape 3 Drop cable

    4Cable

    Lubricant5

    Ground

    Sheets6

    42

  • 5/26/2018 Section 6 B2H SOP

    43/91

    Chapter SevenStandard Installation of FAT3201-24 and FAT3201-48 (direct drop fibers)

    43

  • 5/26/2018 Section 6 B2H SOP

    44/91

    SurveyInformation

    BeforestartinganyB2HinstallationitisMANDATORYthatthepresitesurvey

    informationformisrequested,studiedandapreimplementationsurveyis

    .

    yourintendedinstallationdate.

    Thisformwillprovidecontactdetailsforaccessintothebuilding.

    WillprovideasuggestedsolutionforB2Hinstallation.

    Willprovideaguidetothematerialrequirementsforinstallinginthebuilding.

    Willgiveyouanopportunitytocompleteyourownpresitesurveytoconfirm

    .

    Willgiveyouanopportunitytoarrangeforanyamendmentsandchangesto

    material andimplementationrequirements.

    Willsupportyourplanandmakeyourteamsmoreefficient.

    44

    SN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    45/91

    Standard Installation of FAT3201-24 and

    FAT3201-48 7.1Procedure for FAT

    installationB

    Feedercable

    FAT320124

    Dropcableinlet

    The personnel in charge of installation and maintenance must betrained and master the correct operating methods and safety

    precautions before beginning of work. Ensure permission to work on premiseshas been granted

    Procedure

    1 Check FAT and the accessories are fit for purposes

    2 Check the space where the FATs will be installed.

    The preferred installation location of FATs is nearby of Cable Trays , as close as

    Riser/Drop

    cableinlet

    Feeder

    cableinlet

    poss e to t e ex st ng copper

    4

    5

    If FAT is installed in Telecom room, the new cable tray is required, to link the FAT

    with existing cable trays. In other cases 60 x 40 or 100 x 50 cable trunk, to provide

    smooth banding radius, (not less than 80 mm)

    FAT320148

    FeedercableoutletDropcableinletIn case of combination of 2 FATs, vertical cascading

    is preferable, to reduce the length and routes of

    cable trays or cable trunks .5

    Note

    1 Please make sure that the FATs are leveled properly by using spirit level

    Riser/Drop

    cableinlet

    Feeder

    cableinlet

    2Please make sure to keep clear the area of work from obstacles like :

    decoration or any material that can be damaged due to work.

    3 ALWAYS install the FAT-48 above the FAT-24 whenever 3 splitters are requiredas Pic545

    SN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    46/91

    Standard Installation of FAT3201-24 and

    FAT3201-48 (direct drop fibers) 7.2Installing of FAT in

    the wallB

    1

    Marker

    Procedure1

    Determine the installation position. Use Cable avoidance tool to identify

    Level

    Installation

    location

    e ex s ng serv ces e ore r ng e wa ensure no serv ces n e wa

    2Put a piece of ground sheet on the ground just under the

    installation space to cover the floor/carpet from waste

    material, dirt etc. as picture 2 shown;

    3 Drill holes using a percussion drill as picture 3 shown;

    2 3

    8drillbit

    Install the anchor bolts and remove the nut with washer.44 5O en the lower la er of FAT, then han the case to the ex ansion bolts on

    Note

    42mm45mm

    the wall, fasten the nuts.

    For safety concern, at least two persons are required to install the case. One

    person is to hold the case and the other person to fasten the nuts

    b

    ALWAYS check for other services BEFORE drilling any holes using a metal

    detector and by using information from the Building in - charge.

    46

    St d d I t ll ti f FAT3201 24 dSN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    47/91

    Standard Installation of FAT3201-24 and

    FAT3201-48 7.3Preparing o f

    Feeding cableCD

    Striptheoutdooropticalcableaccordingtotheactualscenario.MakesurethatcablewillfitinsideofFATwithfollowingrouting.

    Procedure

    1

    FAT 3201-24Fiber Tubes Route

    Feeder

    Pig Tails

    FAT 3201-48 Fiber Tubes Route

    Pig Tails

    b

    Feeder

    47

    Standard Installation of FAT3201 24 andSN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    48/91

    Standard Installation of FAT3201-24 and

    FAT3201-48 7.3Preparing o f

    Feeding cableCD

    Cascading of FAT 3201-48 and FAT 3201-24

    Tube 1 Route

    Pig Tails

    Bridge between splitter

    modules

    Tube 2 Route

    Pig Tails

    b

    Feeder

    48

    Standard Installation of FAT3201 24 andSN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    49/91

    Standard Installation of FAT3201-24 and

    FAT3201-48 7.3Preparing o f

    Feeding cableCD

    Cascading two of FAT 3201-48

    Tube 1 Route

    Bridge between splitter

    modules

    Note: In this situation a maximum of four Fibres will

    be used One for each s litter.

    Two from the Red Tube and Two from the green

    Tube

    Pig Tails

    Bridge between splittermodules

    b

    Feeder

    49

    Standard Installation of FAT3201-24 andSN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    50/91

    Standard Installation of FAT3201-24 and

    FAT3201-48 7.3Preparing o f

    Feeding cableCD

    1 2

    Dressthefiberloosetubesinto protectivetube1Polishthesheathwhichisnearthestrippedpointusingthesand

    paper2

    Procedure

    wrapitwith insulatingtape.3

    4Remove the tower plug on the case. Cut a cable hole on the

    tower plug based on the diameter of the optical cable.

    5 Insert and fix the Feeding optical cable.

    6 Seal the cable inlet/outlet using insulating tape

    6

    Thediameteroftheopticalcablemustbelessthan 20mm.1

    2 Thestrippedlengthoftheopticalcabledependsonthecable

    route.

    When cutting the cable hole, please pay attention to the

    different diameters mark on the tower plug .3

    50

    Standard Installation of FAT3201-24 andSN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    51/91

    Standard Installation of FAT3201 24 and

    FAT3201-48 7.4 LeadinginandFixing

    ofDropCablesCD

    Procedure

    Lead in and fix the drop cable.

    For FAT3201-24, the drop cable inside the FAT should

    be 1600 mm in len th.

    1a 1b

    Drop

    Cable

    For FAT3201-48, when the drop cable and distribution

    optical cable are led into the bottom section, the drop

    cable inside the FAT should be 2500 mm in length.

    Arrangement of Drop Fibers must be done according to

    figures 1-3, dependant of the Drop Fibers Entry point

    location.

    2 Drop Cable

    Copex

    Tube

    1-a

    Note: Labeling of Drop Fibers shou ld be done

    according to the Chapter of SOP B2H Labeling

    Entry point is on top of FAT

    1-bEntry point is on the bottom of FAT. In this case

    drop fibers MUST BE PROTECTED with Copex

    tube or Cable Trunk.

    2 Routes of drop fibers for FAT 3201-243

    3 Routes of drop fibers for FAT 3201-48

    b 51

    Standard Installation of FAT3201-24 andSN Task Description Operator Duration

    Stripping Leading in

  • 5/26/2018 Section 6 B2H SOP

    52/91

    Standard Installation of FAT3201 24 and

    FAT3201-48 7.5Stripping,Leadingin,

    splicing andFixingof

    fibers.

    CD

    1 Arrange the loose tube and drop cables according to table

    Procedure

    Splicing Tray NO

    Tray 1 (Bottom tray)

    Side A

    Feeder INPUT

    Splitter input

    Feeder output (if

    Side B

    1 Specification of splicing tray module

    1

    Note:Dropfibers/loosetubesmustbewrappedwiththe

    Tray 2Splitter outputs 0-3

    Pigtails 1-4

    casca ng o

    Drop Fibers 1-4

    Tray 3Splitter outputs 4-7

    Pigtails 5-8Drop Fibers 5-8

    2 Strip the Drop Cables with the length of 950 mm

    insulationtapeandbefixedattheportsofthesplicingtray

    withstraps.

    3

    the optical fiber.Tray 4

    Splitter outputs 8-11

    Pigtails 9-12Drop Fibers 9-12

    Tray 5Splitter outputs 12-15

    Pigtails 13-16

    Drop Fibers 13-16

    Tray 2- Tray 5Side A Side B

    Splicing

    Bottom tray

    Splicing

    Side A Side B

    Drop Fibers

    Splitter

    Pig Tails

    Splitter outputsInsulation Tape

    Insulationtape

    b

    p ce e ers accor ng o ap er o .Feeding input

    Arrange fibers and protective heat shrinks inside of splicing tray.5

    52

    Standard Installation of FAT3201-24 andSN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    53/91

    FAT3201-48 7.6Preparing o f

    Vertical Riser cableCD

    1

    Before start any operation with Vertical

    Riser cable, you should pay attention to

    the Color Code Table fi ure 1 .

    2

    Cores 1-12 have pure colors, cores 13-24 have the same color coding as 1-12,

    but w ith b lack marks, every 5 cm. (figure

    2)

    b

    53

    Standard Installation of FAT3201-24 and

    SN Task Description Operator Duration

    7 7Preparing of Riser

    CD

  • 5/26/2018 Section 6 B2H SOP

    54/91

    FAT3201-487.7

    cableCD

    Procedure

    Route 2 - 1900 mm

    (950 mm of spiral tube)

    Route 3 - 2200 mm

    StriptheRiserCablesto2.2moflengthfromtheEntryPoint.1

    IdentifyfiberroutestoallocatedsplittermodulesaccordinglytotheRoutingTable.Dividefiberstodifferentbundles(8fiber

    perbundle) Dressthebundles intospiral protectivetube.2

    Route 1 - 1550 mm

    3 WrapthejointingplaceofCablesheathandspiraltubes with

    insulatingtape.

    4 LeadallcablesintotheFATandfixattheentrypointwith

    CableStraps.

    Entry Point

    2

    3

    4

    b 54

  • 5/26/2018 Section 6 B2H SOP

    55/91

    Standard Installation of FAT3201-24 and

    FAT3201 48

    SN Task Description Operator Duration

  • 5/26/2018 Section 6 B2H SOP

    56/91

    FAT3201-48 7.9 Exampleinstallations CD

    56

    Standard Installation of FAT3201-24 and

    FAT3201 48

    SN Task Description Operator Duration

    7.10 Finishing CD

  • 5/26/2018 Section 6 B2H SOP

    57/91

    FAT3201-48

    No Check list

    1 Splitters are installed incorrect inside FATs and MUST be removed , rotated 180 degrees and re-installed

    BEFORE any dressing in of Fibres takes place. If not , the dressing in is not to SOP and will have to be re-done

    2 Is the optical cable properly fixed?

    3 Is the optical fiber neatly routed and fixed (with optical fiber fastener)?

    4 Is the optical fiber routing correct?

    5 Fibre A, Fibre 1 or the blue core will ALWAYS be spliced to the Ooredoo network.nd , .

    6 Splicers MUST follow the colour code for the riser cable.

    Example:

    Customer for port 00 will have the Blue and Orange cores Blue is Ooredoo, Orange is 2nd service provider.

    Customer for port 06 will have the Blue and Orange cores with black dashes Blue/black is Ooredoo and

    Orange/black is 2nd service provider.

    Blue & Blue/black, Orange & Orange/black etc IS NOT the colour code and MUST NOT be followed.

    7 Maximum number of ports allocated per splitter is 14. (00-13) If ports 14/15 are required to be used permission

    MUST be requested from Ooredoo BEFORE using these ports.

    8 If an additional splitter is required due to more customers identified than on the survey, a DCR MUST be

    submitted through normal procedures.

    9 Has the Labeling SOP been followed 100% - This is a MUST DO task and is critical.

    10 Does the pigtail storage meet the requirement for the bending radius and is fixed (with roll protection tube)?

    11 Does the door open and close with ease?

    12 Is the earthing good (if OF cables have a metal element)?

    14 All keys for FAT-24 & FAT-48 are universal One fits all.

    15 FAT patch panel door access keys must be handed to Ooredoo

    16 Implementation details for each building installation must be recorded for future maintenance purposes. 57

  • 5/26/2018 Section 6 B2H SOP

    58/91

    Chapter EightStandard Installation of Sub FAT3101

    58

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8 1Plan the

    CD

  • 5/26/2018 Section 6 B2H SOP

    59/91

    8.1installation space

    CD

    The personnel in charge of installation and maintenance must be trained and master the correct operating

    methods and safety precautions before beginning of work. Ensure permission to work at premises has been granted

    ExteriorandStructureoftheCase

    Procedure

    1Check the quality of FATs and the

    accessories

    2Check the space where the FATs will be

    installed.

    3The preferred installation location of FATs is

    on top of existing copper IDP

    Opticalcablestrippingandfixingarea

    Note

    1 Please make sure that the FATs are leveled properly by using spirit level

    2Please make sure to keep clear the area of work from obstacles like :

    decoration or an material that can be dama ed due to work.

    SubFAT has 2 kinds: 12F and 18F. 12F subFAT can accommodate a maximum of 9

    customers 3 trays 3 customers per tray 6 splices per tray 2 splices per

    customer. 18F subFAT can accommodate a maximum of 12 customers 4 trays 3

    customers per tray 6 splices per tray 2 splices per customer

    3

    59

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8 2 Fixing on the wall CD

  • 5/26/2018 Section 6 B2H SOP

    60/91

    8.2 Fixing on the wall CD

    Marker

    Wall

    Level

    1Determine the installation position. Use Cable avoidance tool to identify

    Procedure1

    Mountinghole

    Template

    e ex s ng serv ces e ore r ng e wa nsure no serv ces n e wa

    2Put a piece of plastic sheet on the ground just under

    the installation space to cover the floor/carpet from

    waste material, dirt etc. as picture 2 shown;

    2 3

    8drillbit

    Flatwasher

    Drill holes using a percussion drill as picture 3 shown;

    4 5

    Nut

    Coneheadbolt

    42mm45mm

    Install the anchor bolts.4

    Open the lower layer of FAT, then hang the

    case to the expansion bolts on the wall,

    fasten the nuts.5

    b 60

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8 3Preparing o f

    CD

  • 5/26/2018 Section 6 B2H SOP

    61/91

    8.3Vertical Riser cable

    CD

    1

    Before the start any operation withVertical Riser cable, you should pay

    attention to the Color Code Table (figure

    .

    2

    Cores 1-12 have pure colors, cores 13-

    24 have the same color coding as 1-12,

    but w ith b lack marks, every 5 cm. (figure

    2)

    b

    61

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8.3Preparing of Riser

    blCD

  • 5/26/2018 Section 6 B2H SOP

    62/91

    cable

    Procedure

    1

    Striptheopticalcable.UsingIndustrystandardstrippers&

    cleansingwipes1

    Dressthefibersintospiral protectiontube,6fiberspertube.32Prepare4piecesofspiralprotectiontube,55cmlength2

    4 WrapthejointingplaceofCablesheathandspiraltubes with

    insulatingtape.

    5 CablenowreadyforthefixinginsideofSubFAT

    3

    4

    b

    5

    62

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8.4 LeadinginandFixing

    of Riser CableCD

  • 5/26/2018 Section 6 B2H SOP

    63/91

    ofRiser Cable

    1 Lead in and fix the Vertical Riser optical cable.

    -

    Procedure

    , .

    3Insert the spiral tube with fibers 1-6 into the splicing tray 1 and fix

    with cable ties.

    1 24

    Coil the fibers inside of the splicing tray and fix end of the bundle

    with iece of insulatin ta e

    3

    5 Repeat item 3 and 4 for the rest of splicing trays.

    o e

    Arrangement of fibers inside of splicing

    trays must be done in order to the

    following table

    Tray 1 Fiber 1 to 6

    Tray 2 Fiber 7 to 12

    Tra 3 Fiber 13 to 18

    b 5

    Tray 4 Fiber 19 to 24

    63

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8.5

    Leadingin,Fixingand

    splicing ofDrop CD

  • 5/26/2018 Section 6 B2H SOP

    64/91

    fibers.

    1 2 3Labels Labels

    Procedure4 Specification of splicing tray module

    M3flatheadscrewdriver

    1 Confirmthenumberoftheleadinginflatdropcables,andpiercethecable

    leadinginholesofthesamenumber.

    2Leadintheflatdropcable fromthecableleadinginholeatthebottomofthe

    fiberaccessterminal.

    RunDropFibersthrough thelabelingrings,accordingtothelabelingrules.

    Splicing Tray NOSide A (Riser

    Cable)

    Tray 1 Fiber 1-6

    Side B (Drop

    Cables)

    Drop Fibers 1-3

    Tray 2 Fiber 7-12 Drop Fibers 4-6

    ,

    theentrypoint.

    Splicethe fibersaccordingtothetable,arrangefibersandprotectiveheat

    shrinksinsideofsplicingtray4

    Repeattheitem2,3and4fortherestofsplicingtrays.Fixdropfiberswiththe

    strapsatFAT d/fiberentry point.5

    Side A Side B

    - -

    Tray 4 Fiber 19-24 Drop Fibers 10-12

    Splicing

    5 Straps

    bFeeding input Drop Fibers

    64

    Standard Installation of subFAT 3101SN Task Description Operator Duration

    8.6 Splicingrequirement

    per customerCD

  • 5/26/2018 Section 6 B2H SOP

    65/91

    percustomer

    65

    Standard Installation of Sub FAT3101SN Task Description Operator Duration

    8.7 Additional

    recommendationsCD

  • 5/26/2018 Section 6 B2H SOP

    66/91

    1Position of FAT must be as close as possible to the existing

    copper IDP or to existing cable tray/cable trunk.1

    2All visible vertical riser cable and drop fibers must be

    protected with cable trunk or Copex tube

    No Item

    1 Are all the bolts tightened?

    2 Is the optical cable properly fixed?

    3 Is the optical fiber neatly routed and fixed (with optical fiber

    fastener)?

    4 Is the optical fiber routing correct?

    2

    5 Does the door open and close with ease?

    6

    7

    8

    b 66

  • 5/26/2018 Section 6 B2H SOP

    67/91

    Chapter NineStandardLabeling

    67

    B2HLabeling

  • 5/26/2018 Section 6 B2H SOP

    68/91

    Inordertorepresentthebestinquality,serviceandperformance,

    , ,

    understandprofessionallabelingsystemthatshouldnotbeabletobe

    removed,abradeorfadeinashortperiodoftimebyusingthecorrect

    toolsand materialsasstatedintheLabelingSOP.

    AccordinglylabelingMUSTbedoneaspertheagreedsolutionwith

    Ooredoo

    68

    B2HLabeling

    FAT with S litter s & Feeder Cable

  • 5/26/2018 Section 6 B2H SOP

    69/91

    FATwithS litter s &FeederCable

    FAT320148

    (2splitters)

    FAT320124

    (1splitter)

    FAT320124and320148 aretobelabeled

    ontheoutsidewithfeedercableand

    splitterinformation

    FAT320124Example:KRG/1/F1

    Explanation: Area/Cable/buildingsplitter

    FAT320148Example:KRC/1/F1F2

    Explanation:Area/Cable/buildingsplittersKRC/1/J17F1/12F(1)

    FeedercablesaretobelabeledasOSPandnumberinbracketsdenotes

    howmanysplittersinthebuilding

    Example:KRC/1/J17F1/12F(3) Explanation:Area/cable/jointBuildingsplitter/cablesize/Totalsplitters

    KRC/1/J17F1/12F(2)

    69

    FAT&subFATLabeling

  • 5/26/2018 Section 6 B2H SOP

    70/91

    70

    B2HLabelingOverview

    labelin in FAT and sub FAT

  • 5/26/2018 Section 6 B2H SOP

    71/91

    labelin inFATandsubFAT

    Labeltherisercablewithdetailsasshown

    inPic1.

    1

    2Fibredropcabletobelabeledwith

    splitterandportdetailsinsideeachFATas

    showninPic1.

    Note:IncaseofSubFAT,onlySplitterport

    Noisrequired

    00,01,02etc istherecommendedmethod.

    2

    A/PP2/00

    /121A

    71

    B2HLabelingOverview

    Sub FAT Customer Routin Information for ODF & 22U Scenario

  • 5/26/2018 Section 6 B2H SOP

    72/91

    SubFATCustomerRoutin InformationforODF&22UScenario

    FAT310112/18

    (12F/24Fsplices)

    1 2 A/PP2/2

    1 3 4

    ODF:A/PP2/1(24)

    F1/00/SED

    5 6

    7 8

    2 9 10

    11 12

    13 14

    3 15 16

    17 18

    19 20

    4 21 22

    23 24

    Customerinformationlabelinside

    subFATtobeshownHorizontally. SubFATODFtermination Address Spare coreODFAddress

    Example:F1/00/E4532889

    Explanation:buildingsplitter/port

    number/Electricitynumber

    Example:A PP2 1(24)

    Explanation:TerminationBlock/Patch

    Panel/FirstPatchPanelPort(numberof

    terminatedfibers)

    Example:A/PP2/2

    Explanation:TerminationBlock/Patch

    Panel/FirstPatchPanelPort

    72

    B2HLabelingOverview

    Sub FAT Customer Routin Information for FAT Scenario & Riser Cable

  • 5/26/2018 Section 6 B2H SOP

    73/91

    Sub Custo e out o at o o Sce a o& se Cab e

    FAT310112/18

    (12F/24Fsplices)

    1 2 B/1

    1 3 4

    FAT:B/F3/0011(24)

    F3/00/SED

    5 6

    7 8

    2 9 10

    11 12

    13 14

    3 15 16

    17 18

    19 20

    4 21 22

    23 24

    ProvidelabeltagonrisercabletoeachsubFAT

    SubFAT FATtermination Address

    Example:B/F3/00 11(24)

    Explanation: TerminationBlock/

    Splitteroutputport .used/ of

    Example:B/1

    Explanation:Termination

    Block/FATPigtail

    SpareCoreAddress

    ExampleFAT320124/48scenario:A/F3/00/121/AExplanation: TerminationBlock /Buildingsplitter /firstsplitterport used/totalnumberofsplitter

    portsused Floor /subFATcode

    ExampleODFCabinetScenario:A/PP2/1/121/AExplanation: TerminationBlock /PP/firstPPport//totalnumberofPPportsFloor /subFATcode

    73

    B2HLabelingOverview

    SubFAT&RiserCable

  • 5/26/2018 Section 6 B2H SOP

    74/91

    Splicinginformationlabelinside

    subFATtobeshownHorizontally

    FAT310112/18(12F/24Fsplices)

    FAT310112/18(12F/24Fsplices)

    Providelabelsonrisercable

    from1st subFATto2nd subFAT.3

    xamp e or

    cabinetscenario:

    xamp e or

    24/48scenario:

    SubFATtobelabeledonthe outsideofthe

    subFATasshowndisplayingfloornumber2/A 2/B

    SubFATtobenumberedperfloorfroma

    clockwisedirectionaseachfloorisentered

    fromeithertheliftorthestairs

    an su FAT es gnat onco e

    74

    IdentifyingandlabelingsubFATsandsubFATportallocation

    subFAT labeling 03 04

  • 5/26/2018 Section 6 B2H SOP

    75/91

    First Floor Note: No matter which location you enter the

    floor the first subFAT will be the first one on

    your left from where you enter the floor.

    1 is floor # A is subFAT A etc

    If you have more than one entry onto a floor,subFAT subFAT

    02

    choose the left side of the building from the

    ground floor entrance as your starting point.1/A 1/BClockwise Direction

    01

    Lift or Stairs

    First Floor

    Port allocation

    00

    2/01 1/00 3/02

    Clockwise Direction

    Note: If there are no numbers on the doors of

    each apartment then follow the same

    instruction as for subFAT labeling and allocate

    accordingly.

    If the apartments have numbers then follow the

    numbers regardless of sequence.

    subFAT

    1/A

    subFAT

    1/B

    Lift or Stairs

    xamp e: par men s oppos e or

    stair entrance and apartments 2 & 3 are either

    side (as shown) then you will still allocate portsto the apartment number and not in a

    clockwise direction from Apartment 1.

    6/057/06

    Existing

    Ooredoo

    access panel

    SubFAT Clockwise Direction

    75

    B2HLabelingOverview

    labelin inATB&ONTCabinet

  • 5/26/2018 Section 6 B2H SOP

    76/91

    PlaceroutinginformationoninsideofinspectioncoverofONTCabinet

    Placeroutinginformationon

    insideofinspectioncoverofATB

    ForODFCabinetScenario

    KRC/1/F1/00 COName/Cable

    /Splitter

    /Splitterport

    v ONTcabinet cover

    KRC/1/F1/00

    A/PP2/2

    SpareFiberODFterminationAddress

    (TerminationBlock /PP /PPport )

    ForFAT320124/48Scenario

    ATBcoverONTCabinetcover

    KRC/1/F1/00A/1 COName/Cable /Splitter

    /Splitterport KRC/1/F1/00

    A/1SpareFiberFATterminationAddress

    (TerminationBlock /PPPort )

    76

  • 5/26/2018 Section 6 B2H SOP

    77/91

    A

    77

  • 5/26/2018 Section 6 B2H SOP

    78/91

    78

  • 5/26/2018 Section 6 B2H SOP

    79/91

    79

  • 5/26/2018 Section 6 B2H SOP

    80/91

    80

    Standard Labeling of FAT, sub FAT, 22U and

    42U cabinet

    SN Task Description Operator Duration

    9.9 Labeling D

  • 5/26/2018 Section 6 B2H SOP

    81/91

    No Check list

    Additional Information and check list1

    1 Labeling SOP MUST be followed 100% - This is critical

    2 Labeling is required to be 100% accurate for providing information for 2nd service

    provider by Ooredoo

    3 Existin labelin inside the subFAT is wron Vertical and must be chan ed.

    4 ALL routing information is to be entered horizontally inside the subFAT. (See slide

    68)

    5 Alternative labeling template is available from the Processes, procedures and

    SOPs team. (See Slide 68)

    6 SubFAT labeling follows the floor level and locations in a clockwise direction

    from the left as you enter each floor. From the lift or stairs.

    Example: G/A Ground floor subFAT A. 2/B 2nd Floor subFAT B

    81

  • 5/26/2018 Section 6 B2H SOP

    82/91

    Chapter TenStandardISPinstallation

    82

    Installation of Structured

    Cabling System

    SN Task Description Operator Duration

    10.1-aInstallation procedure for

    SCSAB

  • 5/26/2018 Section 6 B2H SOP

    83/91

    Procedure

    1 Rod the section from location a to b

    2 Prepare CAT6 (see pic 1)

    1

    3 Tie up the push rod and CAT6 with tape(see pic 2)

    4 One worker pulls the push rod from location B (see pic 3)

    5 One worker should feed in the cat6 from location A(see pic 3 and 4)

    2

    NOTE

    1Pulling of cat 6 must be in one direction

    3

    4

    Tools

    LocationB3

    1 4mm rod 2Cross

    screwdriver3 Gloves

    4 5 6

    Materials

    LocationA

    4

    1 CAT6 2 ground sheet 3 Tape

    4 5 6

    83

    Installation of Structured

    Cabling System

    SN Task Description Operator Duration

    10.1-bInstallation procedure for

    SCSAB

    Procedure

  • 5/26/2018 Section 6 B2H SOP

    84/91

    1If the location A doesn't connect to B directly, we should open the intermediate

    box between location A and B as pic 1 shown.

    2 Lay the push rod from location B to intermediate ,and then to location A;

    1

    location

    Intermediate

    3 Lay the CAT6 from location A to intermediate ,and then to location B;

    4

    Note

    A oca on

    2If there is no existing internal conduit, trunking should be installed with the

    permission of the customer.

    3

    4

    Tools

    1 4mm rod 2 Gloves 3 Cross screwdrivers

    4 5 6

    Interme ate

    Materials

    1 CAT6 2 Ground sheet 3Insulating Tape

    4 5 6

    84

    StandardInstallationofATBandONT

  • 5/26/2018 Section 6 B2H SOP

    85/91

    Refer to Section 5 Chapter 8

    85

  • 5/26/2018 Section 6 B2H SOP

    86/91

    Chapter ElevenStandardSplicing

    86

    Standard Splicing ProcessSN Task Description Operator Duration

    11.1 Splicing procedureSplicing

    technician15 Minutes

    Procedure

    1 Arrange the drop cable inside ONT cabinet and splicing traySpliceprotection0.25Optical

    fib

  • 5/26/2018 Section 6 B2H SOP

    87/91

    2Strip the optical fiber cable sheathing, expose the bare fibres and then

    install the splice protection sleeve. See Pic 1.

    3 Strip, cleave, clean and splice both optical fibres. See Pic's 2 - 5

    4

    After the splicing is complete and passes the check, heat shrink the

    protection tube. Insert the splice protection sleeve into the fixing base of

    sleevefiber0.25

    Opticalfiber

    1

    the splicing tray to protect the splicing point. See Pic 6.

    5Put the splicing information according to the coding standard approved by

    Ooredoo

    6 Arrange the spliced fibres in the fibre management tray7

    Note

    2 3

    1All route cables from the same splitters to be labeled firmly as per the

    labeling standard approved by Ooredoo

    2Labeling inside ATB to be confirmed

    Isopropyl alcohol and lint free cloth MUST be used for all splicing

    4 5

    operat ons.4

    Tools

    1Cable Sheath

    Cutter2

    Cable(Tube)

    Cutter3

    Isopropyl alchohol and lint free

    cloth

    4 Fusion splicer 5 Fibre Cleaver 6 Sharps box6 7

    p c ng oo s c ssors u er s r pper

    10 11 12

    13 14 15Materials

    1Splice protection

    sleeve2

    soft ground

    tube3 Cable tie

    4 Ground sheet 5 6

    87

    Splicing from the Splitter or joint

    SNTask Description Operator Duration

    11.2Joint Splicing in the

    Manhole

    Splicing

    technician30 minutes

    Procedure

  • 5/26/2018 Section 6 B2H SOP

    88/91

    1 Open the closure inside an air conditioned splicing vehicle or splicing tent

    2 Label th drop cable outside the closure with the port number allocated.

    3 Prepare, lead-in and fix the drop cable into the closure.

    1

    r p, c eave, c ean an sp ce e op ca ers.

    5 Arrange the spliced fibres in the splicing tray or cassette.

    6Update the fiber label according the coding standard for the drop cable.

    See Pic 2.

    7close and replace the closure fixing it to the wall of the manhole using the

    bracket rovided and arran in the cables neatl to OSP s ecifications.

    8 Clean the site

    Note

    1 A vehicle or tent must be used when opening closures.

    2 The detailed splicing procedure is the same with OSP splicing;2

    3Fibre shards after cleaving are dangerous and must be disposed of

    properly.

    Tools

    crew r ver agona p ers re s r pper

    4Adjustable

    wrench5

    Black sealing

    tape6 Cable (Tube) Cutter

    7Cable Sheath

    Cutter8 Fusion splicer 9

    Isopropyl alchohol and lint free

    cloth

    10 Fibre Cleaver 11 Sharps Box 12 Splicing tools

    88

  • 5/26/2018 Section 6 B2H SOP

    89/91

    Cha ter 12BusinessLines Migration

    89

    MigrationSN Task Description Operator Duration

    12 1

    Preparation for

    migration Co ordinator 1 hour

  • 5/26/2018 Section 6 B2H SOP

    90/91

    12.1 migration Co-ordinator 1 hour

    Procedure

    1 Run off the work orders from CRM

    2 Confirm appointments with the customers

    3Confirm number and types of existing services

    n e wor or er y a a ase

    4Confirm existing services are working in the

    premises,

    5 Issue work orders to Supervisor.

    6 Plan the work in advance.

    Note

    Exchange D-Side DP-Pairs DP No CAB No. Telephone Customer Name Status Electricity Equipment

    Installatio

    n

    KTR 256 2 3267 69 44878308

    CONSULTANT

    LEGAL

    CONSULTATI

    ON &

    ARBITRATION O SU B 1 41 658

    E3_008-

    12 7

    1 ONT ,

    1Drop

    Cable 4

    ports

    (8447) ,

    CONSULTANT

    KTR 287 5 3267 69 44873938

    LEGAL

    CONSULTATI

    ON &

    ARBITRATION O SU B 1 41 658

    E3_008-

    1328

    overthesplitter

    KTR 294 9 3267 69 44873877

    CONSULTANTLEGAL

    CONSULTATI

    ON &

    ARBITRATION O SU B 1 41 658

    E3_008-

    1672

    EASTERN

    GALAXY

    TRADING & SX 10.10.

    1 ONT ,

    1Drop

    Cable 4

    No Shahry

    Subscriptio

    n

    KTR 224 21 3267 69 44869159

    CONT . CO.

    W.L.L. O SU B 1 41 657

    _

    19.148:29

    44-0-29-1

    l

    ports

    (8447) ,

    KTR 295 10 3267 69 44869154

    EASTERN

    GALAXY

    TRADING &

    CONT . CO.

    W.L.L. O SU B 1 41 657

    SX_10.10.

    19.148:29

    44-1-7-29

    1portoverthesplitter

    Shahry

    Subscriptio

    n

    90

  • 5/26/2018 Section 6 B2H SOP

    91/91

    From this point onwards, you should follow:Migration SOP guidebook (Section 9) to continue with

    Migration

    91