Section 12 - Traction Power
Transcript of Section 12 - Traction Power
-
8/10/2019 Section 12 - Traction Power
1/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12 - Page 1
SECTION 12
TRACTION POWER SUBSTATION SITE WORK AND CABLE SYSTEM
12-1 General Requirements .................................................................................. 3
12-1.01
Summary of Work................................................................................ 3
12-1.02 Measurement and Payment................................................................. 5
12-1.03 Submittal Procedures ........................................................................ 12
12-1.04 Regulatory Requirements.................................................................. 16
12-1.05 References ........................................................................................ 20
12-1.06 Quality Control................................................................................... 25
12-1.07 System Assurance............................................................................. 26
12-1.08
Product Requirements.......................................................................27
12-2 Cast-in-Place Concrete ............................................................................... 28
12-2.01 Miscellaneous Cast-in-Place Concrete..............................................28
12-3 Metals.......................................................................................................... 32
12-3.01 Common Work Results for Metals ..................................................... 32
12-4 Electrical...................................................................................................... 34
12-4.01 Common Work Results for Electrical ................................................. 34
12-4.02 Common Work Results for Traction Power Conductors .................... 36
12-4.03 Low-Voltage Conductors and Cable .................................................. 42
12-4.04 Medium-Voltage Conductors and Cable............................................50
12-4.05 Grounding and Bonding..................................................................... 58
12-4.06 Hangers and Supports for Electrical Systems ................................... 64
12-4.07 Raceway and Boxes..........................................................................68
12-4.08 Underground Raceways and Vaults for Electrical Systems............... 73
12-5 Communications.......................................................................................... 80
12-5.01
Traction Power Substation SCADA ...................................................80
12-6 Earthwork .................................................................................................... 89
12-6.01 Common Work Results for Earthwork................................................ 89
12-7 Exterior Improvements ................................................................................ 90
12-7.01 Asphalt Paving...................................................................................90
-
8/10/2019 Section 12 - Traction Power
2/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12 -TOC Page 2
12-7.02 Landscaping ...................................................................................... 91
12-7.03 Fencing.............................................................................................. 92
12-8 Traction Power Distribution ......................................................................... 93
12-8.01 Common Work Results for Traction Electrification System (TES) ..... 93
12-8.02 TPSS Installation............................................................................... 97
12-8.03 Dc Disconnect Switches .................................................................. 101
12-8.04 Dc Surge Arresters.......................................................................... 105
12-8.05 TES Testing..................................................................................... 108
12-8.06 TES Spare Parts.............................................................................. 110
12-8.07 TES Record Documents.................................................................. 113
12-8.08 Modifications to Existing Traction Power System ............................ 116
-
8/10/2019 Section 12 - Traction Power
3/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.01 - Page 3
12-1 GENERAL REQUIREMENTS
12-1.01 SUMMARY OF WORK
PART 1 GENERAL
1.01 WORK INCLUDED IN SECTION 12
A. Electrical and traction power work, including but not limited to the following:
1. Coordination and scheduling to assure that revenue service operation of
RT Metro is not disrupted where the work of this Contract interfaces with
existing lines.
2. Traction power substation (TPSS) site work, including ground mat, TPSS
foundation, and setting, anchoring, and connecting four new TPSS
furnished by others.
3. Ductbanks, vaults conduits, and pull boxes.
4. Traction power feeder cables and negative returns.
5. Ground cables for aerial structure OCS poles.
6. Demolition work.
7. Dc disconnect switches and surge arresters.
8. Developing QC records during construction.
9. Developing record documents and photographs of the completed work.
10. Inspecting and testing Traction Power system during and after
completing construction, see CQCP General Requirements.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
PART 2 PRODUCTS
2.01 OWNER-FURNISHED
A. TPSS have been procured under a separate contract.
-
8/10/2019 Section 12 - Traction Power
4/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.01 - Page 4
PART 3 EXECUTION
3.01 INSTALLATION
A. Perform work as indicated on Contract Drawings and in these Technical
Specifications.
-
8/10/2019 Section 12 - Traction Power
5/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.02 - Page 5
12-1.02 MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Information for measurement and payment that applies only to this Section
12.
1.02 MEASUREMENT AND PAYMENT
A. Work in this Section 12 will be paid only as a lump sum or by unit price.
1. Lump Sum:
a. Definition: Complete payment for the work described for that item
in the Contract.
b. Break down each lump sum bid item as required by General
Provision 6.61.1, Schedule of Values.
2. Unit Price: Work indicated as unit priced will be measured by the
Engineer as described in the applicable Technical Specification sub-
section.
1.03 PAYMENT ITEMS
A. Contractor Quality Control Program (CQCP): For payment for CQCP, see
General Conditions 6.47.18, Payment for CQCP General Requirements.
B. Full compensation for performing quality control inspection and tests and
providing the test results/reports to RT is considered as included in the bid
line item for the product, material or work to be inspected/tested..Therefore,
all inspection and testing must be included in each specific bid line item.
C. TP-001, TPSS Site Work, TPSS S9:
1. Measurement for this item will be lump sum.
-
8/10/2019 Section 12 - Traction Power
6/118
-
8/10/2019 Section 12 - Traction Power
7/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.02 - Page 7
sealing between TPSS base and foundation, removing protective
covering from TPSS, and storing ancillary equipment for later use
by TPSS Contractor;
d. Providing temporary power to TPSS within 48 hours of setting it on
foundation slab and providing permanent electric utility 12 kVservice;
E. TP-003, TPSS Site Work, TPSS S11:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TPSS site work as indicated
in the Contract Documents. Work includes, but is not limited to the
following:
a. Providing a ground mat and connecting ground mat pigtails to
TPSS, signal instrument house, fencing, and other items as
indicated on the Plans;
b. Providing a concrete foundation, including earthwork, forms,
concrete, and reinforcing bar; asphalt repair, if any; and
landscaping repair, if any;
c. Removing TPSS and ancillary equipment furnished by others from
delivery trucks, setting TPSS on foundation, anchoring TPSS,sealing between TPSS base and foundation, removing protective
covering from TPSS, and storing ancillary equipment for later use
by TPSS Contractor;
d. Providing temporary power to TPSS within 48 hours of setting it on
foundation slab and providing permanent electric utility 12 kV
service;
F. TP-004, TPSS Site Work, TPSS S12:
1. Measurement for this item will be lump sum.
-
8/10/2019 Section 12 - Traction Power
8/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.02 - Page 8
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TPSS site work as indicated
in the Contract Documents. Work includes, but is not limited to the
following:
a. Providing a ground mat and connecting ground mat pigtails to
TPSS, signal instrument house, fencing, and other items as
indicated on the Plans;
b. Providing a concrete foundation, including earthwork, forms,
concrete, and reinforcing bar; asphalt repair, if any; and
landscaping repair, if any;
c. Removing TPSS and ancillary equipment furnished by others from
delivery trucks, setting TPSS on foundation, anchoring TPSS,
sealing between TPSS base and foundation, removing protectivecovering from TPSS, and storing ancillary equipment for later use
by TPSS Contractor;
d. Providing temporary power to TPSS within 48 hours of setting it on
foundation slab and providing permanent electric utility 12 kV
service;
G. TP-005, TES Cable System Work, TPSS S8:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TES cable system work as
indicated in the Contract Documents. Work includes, but is not limited to
the following:
a. Demolishing and disposing of existing ductbank;
b. Providing new underground raceways, vaults, and boxes, including
interfacing with existing vaults, OCS pole dc positive feeder conduit
risers, and other interfaces as indicated on the Plans;
c. Providing SMUD utility switchgear vault and underground raceways
from utility feeding location to switchgear vault location;
d. Providing dc positive and negative cables;
e. Testing dc positive and negative cables;
-
8/10/2019 Section 12 - Traction Power
9/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.02 - Page 9
f. Terminating dc positive and negative cables;
H. TP-006, TES Cable System Work, TPSS S9:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TES cable system work as
indicated in the Contract Documents. Work includes, but is not limited to
the following:
a. Providing new underground raceways, vaults, and boxes, including
interfacing with TPSS foundation, OCS pole conduit risers, and
other interfaces as indicated on the Plans;
b. Providing SMUD utility switchgear vault and underground raceways
from utility feeding location to switchgear vault location;
c. Providing dc positive and negative cables;
d. Testing dc positive and negative cables;
e. Terminating dc positive and negative cables;
f. Providing conductors to blue lights.
I. TP-007, TES Cable System Work, TPSS S10:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TES cable system work as
indicated in the Contract Documents. Work includes, but is not limited to
the following:
a. Providing new underground raceways, vaults, and boxes, including
interfacing with TPSS foundation, OCS pole conduit risers, and
other interfaces as indicated on the Plans;
b. Providing SMUD utility switchgear vault and underground raceways
from utility feeding location to switchgear vault location;
c. Providing dc positive and negative cables;
d. Testing dc positive and negative cables;
-
8/10/2019 Section 12 - Traction Power
10/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.02 - Page 10
e. Terminating dc positive and negative cables;
f. Providing conductors to blue lights.
J. TP-008, TES Cable System Work, TPSS S11:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TES cable system work as
indicated in the Contract Documents. Work includes, but is not limited to
the following:
a. Providing new underground raceways, vaults, and boxes, including
interfacing with TPSS foundation, OCS pole conduit risers, and
other interfaces as indicated on the Plans;
b. Providing SMUD utility switchgear vault and underground raceways
from utility feeding location to switchgear vault location;
c. Providing dc positive and negative cables;
d. Testing dc positive and negative cables;
e. Terminating dc positive and negative cables;
f. Providing conductors to blue lights.
K. TP-009, TES Cable System Work, TPSS S12:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, inspection and
testing and incidentals required to perform TES cable system work as
indicated in the Contract Documents. Work includes, but is not limited to
the following:
a. Providing new underground raceways, vaults, and boxes, includinginterfacing with TPSS foundation, OCS pole conduit risers, and
other interfaces as indicated on the Plans;
b. Providing SMUD utility switchgear vault and underground raceways
from utility feeding location to switchgear vault location;
c. Providing dc positive and negative cables;
-
8/10/2019 Section 12 - Traction Power
11/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.02 - Page 11
d. Testing dc positive and negative cables;
e. Terminating dc positive and negative cables;
f. Providing conductors to blue lights.
L. TP-010, TPSS SCADA
1. Providing TPSS SCADA as specified and indicated on the Plans.
M. TP-011, TES Testing:
1. Testing TPSS SCADA in cooperation with Powell Industries (Powell),
the TPSS supplier.
2. Participating in short circuit testing conducted by Powell.
N. TP-012, TES Spare Parts:
1. Measurement for this item will be lump sum.
2. Payment for this item will be for all direct and indirect costs associated
with furnishing all submittals, labor, materials, equipment, and
incidentals required to furnish and deliver specified spare parts.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-
8/10/2019 Section 12 - Traction Power
12/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.03 - Page 12
12-1.03 SUBMITTAL PROCEDURES
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. Requirements for submittals that modify or exceed the requirements of
General Conditions (GC) Section 6.45, Project Submittals and Deliverables.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 DEFINITIONS
A. Product Data: As defined in GC Section 6.45.9, Product Data.
B. Shop Drawings: Drawings, diagrams, schedules and other data specially
prepared for the Work by Contractor or a subcontractor, sub-subcontractor,
manufacturer, supplier, or distributor to illustrate some portion of the Work.
C. Samples: Physical examples of materials, equipment, or workmanship that
illustrate functional and aesthetic characteristics of a material or product and
establish standard by which the work will be judged.
1.04 SUBMITTALS
A. Schedule of Submittals: Within the time required in General Conditions
6.45.1, Contract Submittal and Deliverable Requirements Lists (CSDRL),
submit a complete Technical Submittal List (TSL) for this Technical
Specification Section 12 as part of the required CSDRL:
1. Include each submittal listed in the Submittals Article of each sub-section
of this Section 12, whether or not a submittal date or time from NTP is
given.
2. Include for each planned submittal:
a. Submittal title.
b. Contract Technical Specifications reference, by sub-section and
Article.
c. Drawing or document numbers.
-
8/10/2019 Section 12 - Traction Power
13/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.03 - Page 13
d. Date on which each submittal will be submitted.
e. Submittal description identifying the product by description, model
number, style number, serial number, or lot number.
f. Intended resubmission date(s).
g. Lead time to delivery/anticipated delivery date(s).
h. Submittal status.
3. Highlight submittals that are on the critical path.
4. Add submittals as requested by the Engineer.
5. After acceptance, add to progress schedule described in GC SECTION
6.29, Progress Schedule.
6. Update and resubmit on a monthly basis as part of the Monthly CPM
Schedule Update, as described in GC Section 6.29.6, Monthly CPM
Schedule Update Submittals.
B. Submittals in CPM Schedule: Within the time required in General Conditions
6.29.4,3.b Detailed Requirements for Schedule Deliverables- Submittals,
include submittals as part of the CPM Schedule.
1.05 CONTRACTORS RESPONSIBILITIES
A. General:
1. Furnish each submittal listed in the Submittal Article of each Sub-Section
of this Section 12.
2. Submittals must be in Imperial (or British) units and in the English
language.
3. Identification:
a. Submittal Number: For each submittal, the submittal number is the
corresponding number of the section, sub-section, article,paragraph, and subparagraph of the Contract Technical
Specifications under which each is required.
b. Tracking Number: In addition to submittal number, furnish a
sequential tracking number as required by GC Section 6.45.2,
General Requirements for Submittals.
-
8/10/2019 Section 12 - Traction Power
14/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.03 - Page 14
c. Revision Number: Furnish as part of the tracking number, as
required by GC Section 6.45.2.
4. Attach the Submittal Cover Page, as described in GC Section 6.45.2,
to each submittal. In addition to the requested information on this form,
furnish the following information:
a. Submittal number.
b. Applicable standards, such as ASTM or IEEE.
5. Submittal Medium:
a. Furnish hard copies as required in GC Section 6.45.2.
b. Furnish electronic copy in pdf format with bookmarks to separate
sections.
c. Drawings: In addition to hard copies and pdf format requirements
above, furnish drawings in AutoCAD format and version required by
GC Section 6.55, As-Built Plans.
B. Product Data:
1. Clearly indicate on product selection tables which product and which
options are being provided.
2. Line through or delete information that is not applicable to the Contract.
3. For submittals with more than four items, include a table of contents,
with tabs or other means of locating items in table of contents.
C. Shop Drawings:
1. Show dimensions, connections, and other details necessary to assure
that the Plans are accurately interpreted.
2. Use standard IEEE/ANSI device symbols and nomenclature on
drawings.
3. Drawings must be fully legible. Text on 22 by 34 drawings must not be
smaller than 1/8 inch and on 11 by 17 drawings must not be smaller
than 1/16 inch.
4. On each drawing, furnish title block, and blank space for acceptance-
stamp, per GC Section 6.45.10, Submission of Working and Shop
Drawings.
-
8/10/2019 Section 12 - Traction Power
15/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.03 - Page 15
D. Samples:
1. Procedures: GC Section 6.45.12, Samples.
2. Furnish samples indicated in Contract Documents per GC Section
6.45.12, Samples.
E. Submit in a timely manner:
1. Submit Product Data, Shop Drawings, and Samples and obtain
acceptance before ordering material, products, or equipment.
F. Contractor's Review:
1. Procedures: GC Section 6.45, Project Submittals and Deliverables.
2. Verify that submittal is in the English language.
G. Submittal Meetings: Attend meetings as requested by the Engineer to
address issues related to the review of submittals.
1.06 ENGINEERS REVIEW
A. Engineer will indicate the submittal disposition as described in GC Section
6.45.6, Corrections.
B. Engineer will transmit the disposition of the Contractors submittal within 30
days after submittals have been received.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-
8/10/2019 Section 12 - Traction Power
16/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.04 - Page 16
12-1.04 REGULATORY REQUIREMENTS
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. Compliance with local, state, and federal statutes, regulations, and other
mandatory requirements.
C. Compliance with local utilities.
D. Permit requirements.
1.02 REFERENCE STANDARDS
A. Sub-section incorporates by reference the latest revisions of the followingdocuments:
1. California Code of Regulations (CCR):
a. CCR Title 8, Industrial Relations (OSHA)
1) Construction Safety Orders, Division 1, Chapter 4, Subchapter
4.
2) Low-Voltage Electrical Safety Orders, Division 1, Chapter 4,
Subchapter 5, Group 1, (Sections 2299-2599)
3) High-Voltage Electrical Safety Orders, Division 1, Chapter 4,
Subchapter 5, Group 2, (Sections 2700-2989)
2. California Public Utilities Commission (CPUC):
a. General Order (G.O.) 95, Overhead Electric Line Construction.
b. General Order (G.O.) 128, Construction of Underground Electric
Supply and Communication Systems.
c. General Order (G.O.)143-A, Rules for the Design, Construction and
Operation of Light Rail Transit Systems.
3. Institute of Electrical and Electronics Engineers (IEEE)
a. IEEE C2, National Electrical Safety Code
-
8/10/2019 Section 12 - Traction Power
17/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.04 - Page 17
4. National Fire Protection Association (NFPA)
a. NFPA 70, National Electrical Code (NEC)
1.03 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.04 APPLICABLE STATUTES, CODES, RULES, REGULATIONS, AND STANDARDS
A. Work is governed by all applicable statutes, codes, rules, regulations, and
standards of Federal, State, and local governmental agencies and
jurisdictions having authority over the Work.
B. Perform Work in conformance with all rules and regulations of public utilities,
utility districts, and other Authorities Having Jurisdiction.
C. Authority: Applicable statutes, codes, rules, regulations, and standards,
whether referenced in the Contract Documents or not, have the full force and
effect as though printed in their entirety in the Contract Technical
Specifications.
1.05 PRECEDENCE OF STATUTES, CODES, RULES, REGULATIONS, AND
STANDARDS
A. Where specified requirements differ from the requirements of applicable
codes and ordinances, the more stringent requirements take precedence.
B. Where the Contract Documents require or describe products or execution of
better quality, higher standard, or greater size or rating than required by
applicable codes and ordinances, the Contract Documents take precedence
so long as such increase is legal.
C. Where applicable statutes, codes, rules, regulations, and standards require
more care or greater time to accomplish Work, or require better quality, higher
standards, greater size, or higher ratings, perform Work in conformance to
such requirements with no change to the Time for Completion and Total
Consideration, except where changes in the statutes, codes, rules,
regulations, and standards occur subsequent to the execution date of the
Contract.
D. When no requirements are identified in the Contract Documents, comply with
all requirements of applicable statutes, codes, rules, regulations, and
standards of the Authorities Having Jurisdiction.
-
8/10/2019 Section 12 - Traction Power
18/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.04 - Page 18
1.06 DATES OF STATUTES, CODES, RULES, REGULATIONS, AND STANDARDS
A. The applicable edition of all codes is that adopted by an Authority Having
Jurisdiction and includes all modifications and additions adopted by that
jurisdiction.
B. The applicable date of statutes, rules, regulations, and standards is the date
of execution of the Contract to perform the Work.
1.07 FEDERAL REGULATIONS
A. At a minimum, comply with regulations of the Occupational Safety & Health
Administration (OSHA).
1.08 STATE REGULATIONS
A. At a minimum, comply with regulations of the following state agencies,
including but not limited to those regulations listed below each agency:
1. California Public Utilities Commission (CPUC):
a. G.O. 95, Overhead Electric Line Construction.
1) Where applicable, all work must comply with G.O. 95, which
takes precedence over these Section 12 Technical
Specifications.
2) Representatives from the CPUC will randomly inspect the
work for compliance with G.O. 95.
b. G.O. 128, Construction of Underground Electric Supply and
Communication Systems.
c. G.O. 143-A, Rules for the Design, Construction and Operation of
Light Rail Transit Systems.
2. California Code of Regulations (CCR):
a. Title 8, Industrial Relations (OSHA)
1) Construction Safety Orders, Division 1, Chapter 4, Subchapter
4.
2) Low-Voltage Electrical Safety Orders, Division 1, Chapter 4,
Subchapter 5, Group 1, (Sections 2299-2599).
-
8/10/2019 Section 12 - Traction Power
19/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.04 - Page 19
3) High-Voltage Electrical Safety Orders, Division 1, Chapter 4,
Subchapter 5, Group 2, (Sections 2700-2989).
1.09 MINIMUM STANDARDS
A. At a minimum, comply with the following standards:
1. NFPA 70, National Electrical Code (NEC): Performance of the Work
must meet or exceed the minimum requirements of NFPA 70 as adopted
and modified by the Authority Having Jurisdiction.
2. IEEE C2, National Electrical Safety Code.
1.10 UTILITIES
A. Electric Utility:
1. Conform to requirements of Sacramento Municipal Utility District(SMUD) for ac electrical service installations.
2. Coordinate with SMUD to confirm primary utility feed pole and switch
gear vault locations.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.01 POSTING PERMITS
A. Post permits at the site of Work.
B. Post permits required by law only.
-
8/10/2019 Section 12 - Traction Power
20/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.05 - Page 20
12-1.05 REFERENCES
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. Definitions of terms used in this Section 12.
C. Explanation of Technical Specifications style for this Section 12.
D. Referenced Standard Specifications.
E. Reference Standards.
F. Abbreviations.
G. Definitions.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 DEFINITION OF TECHNICAL SPECIFICATIONS TERMS
A. Furnish, Install, and Provide:
1. Furnish means to supply and deliver to Project site, ready for installation.
2. Install means to place in position for service or use.
3. Provide means to furnish and install, complete and ready for intended
use.
B. Engineer:
1. The Contract representative for Sacramento Regional Transit District
(RT) for this Contract.
2. The term Engineer may also be used for representatives of the
Engineer.
-
8/10/2019 Section 12 - Traction Power
21/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.05 - Page 21
C. Authority Having Jurisdiction (AHJ):
1. An organization, office, or individual responsible for enforcing the
requirements of a code or standard, or for approving equipment,
materials, an installation, or a procedure.
2. Where public safety is primary, the AHJ may be a federal, state, local, or
other regional department or individual such as a fire chief; fire marshal;
chief of a fire prevention bureau; labor department; building official;
electrical inspector; or others having statutory authority.
1.04 SPECIFICATION STYLE
A. These Section 12 Technical Specifications are written in imperative mood and
streamlined form. This imperative language is directed to the Contractor,
unless specifically noted otherwise. The words must be or must comply
with, as appropriate, are included by inference where a colon (:) is usedwithin sentences or phrases.
B. Examples:
1. Prepare meeting minutes within 3 days following the meeting, means
that the Contractor must prepare the meeting minutes.
2. Adhesive: Spread with a notched trowel means adhesive must be
spread with a notched trowel and Contractor is responsible for this
work.
1.05 REFERENCED STANDARD SPECIFICATIONS
A. State of California, Department of Transportation (Caltrans)
1. Caltrans Standard Specifications are referenced in this Specification
Section 12 as State Standard Specifications.
2. State Stanndard Specifications are available from the California
Department of Transportation.
1.06 REFERENCE STANDARDS
A. Reference standards are referenced in Section 12 of these Technical
Specifications to establish requirements for the Work. These references are
identified in each sub-section by document number and title.
B. Applicability of Standards: Unless the Contract Documents include more
stringent requirements, applicable industry standards have the same force
and effect as if bound or copied directly into the Contract Documents to the
-
8/10/2019 Section 12 - Traction Power
22/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.05 - Page 22
extent referenced. Such standards are made a part of the Contract
Documents by reference.
C. Conflicting Requirements: Where compliance with two or more standards is
specified and the standards establish different or conflicting requirements for
minimum quantities or quality levels, comply with the most stringentrequirement. Refer uncertainties and requirements that are different, but
apparently equal, to the Engineer for a decision before proceeding.
D. Publication Dates: Comply with standards in effect as of date of the Contract
Documents, unless otherwise indicated.
E. Copies of Standards: Each entity engaged in Work on this Contract should
be familiar with industry standards applicable to its construction activity.
1. Copies of applicable standards are not bound with the Contract
Documents.
2. Where copies of standards are needed to perform a required
construction activity, obtain copies directly from publication source.
F. All work in this Section 12 of these Technical Specifications must conform to
or exceed the latest edition of the standards listed below:
1. NFPA 70, National Electrical Code (NEC)
2. IEEE C2, National Electrical Safety Code (NESC)
-
8/10/2019 Section 12 - Traction Power
23/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.05 - Page 23
1.07 ABBREVIATIONS
A. The following abbreviations are in addition to those indicated in the State
Standard Specifications:
AHJ Authority Having JurisdictionCALTRANS State of California, Department of Transportation
CPUC California Public Utilities Commission
CQC Contractor Quality Control
LRT Light Rail Transit
LRV Light Rail Vehicle
OCS Overhead Contact System
PG&E Pacific Gas and Electric
QC Quality Control
RT Sacramento Regional Transit District
SMUD Sacramento Municipal Utility District
TES Traction Electrification System
TPSS Traction Power Substation
UPRR Union Pacific Railroad
1.08 DEFINITIONS
A. The following definitions are in addition to those indicated in the State
Standard Specifications:
1. Overhead Contact System (OCS): A complete overhead system for
supporting a wire by catenary suspension, including but not limited to
poles, support assemblies, OCS conductors and cables, and tensioning
devices.
2. Manhole, Vault, or Handhole: An enclosure, typically made of pre-cast
concrete and covered with a single or split-type lid, used to facilitate
cable pulling through conduit or duct systems. The term pull box may
also be used for this type of enclosure, or may refer to a metal
enclosure.
3. Salvage: Work required to disassemble and load removed equipment,
transport to the RT storage facility, offload and make ready for inventory.
4. Traction Power System: All equipment and materials from points of
receiving power from the utility to points of use of that power by light rail
vehicles. The equipment includes TPSS, overhead contact system,
positive and negative cabling, and related accessories.
-
8/10/2019 Section 12 - Traction Power
24/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.05 - Page 24
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-
8/10/2019 Section 12 - Traction Power
25/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.06 - Page 25
12-1.06 QUALITY CONTROL
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. General quality control requirements for this Section 12.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 QUALITY REQUIREMENTS
A. Quality control must be in accordance with General Conditions Section 6.47,
Contractor Quality Control Program (CQCP) and this Section 12 of the
Contract Technical Specifications.
B. As required by the CQCP, maintain as quality records the documentation for
inspections and tests submitted to Engineer for acceptance as required by
sub-section 12-1.03, Submittal Procedures, and various sub-sections of this
Section 12.
C. Impose upon suppliers and subcontractors the same QC requirements,
including inspection and test procedures, as imposed upon Contractor by
these Technical Specifications, Plans, and referenced standards.
D. Apply appropriate controls designed to ensure that materials supplied comply
with requirements of these Technical Specifications.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-
8/10/2019 Section 12 - Traction Power
26/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.07 - Page 26
12-1.07 SYSTEM ASSURANCE
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. Traction electrification elements to include in Section 11, Overhead Contact
System (OCS), System Assurance submittals.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 SUBMITTALS
A. Procedures: Sub-section 12-1.03, Submittal Procedures.
B. Include Section 12 traction electrification elements as part of Section 11-1.08,
OCS System Assurance. Include the following elements in each required
submittal:
1. Traction power feeder and negative return circuits.
2. Dc disconnect switches.
3. Surge arresters.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-
8/10/2019 Section 12 - Traction Power
27/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-1.08 - Page 27
12-1.08 PRODUCT REQUIREMENTS
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. General Section 12 product requirements.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
PART 2 PRODUCTS
2.01 GENERAL REQUIREMENTS
A. Provide products that comply with these Technical Specifications.
B. Products must be new unless specified otherwise.
C. Contractor may not use products that have been discontinued by the
manufacturer, even if new.
D. Products of the same generic type must be by the same manufacturer.
PART 3 EXECUTION
Not Used.
-
8/10/2019 Section 12 - Traction Power
28/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-2.01 - Page 28
12-2 CAST-IN-PLACE CONCRETE
12-2.01 MISCELLANEOUS CAST-IN-PLACE CONCRETE
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. TPSS foundations.
1.02 MEASUREMENT AND PAYMENT
A. TPSS foundations are included in TPSS Site Work pay items. See TPSS Site
Work pay items in Sub-Section 12-1.02, Measurement and Payment.
1.03 REFERENCE STANDARDS
A. State of California, Department of Transportation (Caltrans)
1. Caltrans Standard Specifications (State Standard Specifications)
1.04 SUBMITTALS
A. Procedures: Sub-Section 12-1.03, Submittal Procedures.
B. Submit concrete mix design.
C. Shop Drawings:
1. Before constructing foundations, submit foundation Shop Drawings
showing coordination between TPSS foundation and conduit stub-up
locations, including dimensions.
1.05 QUALITY CONTROL
A. General Requirements: Sub-Section 12-1.06, Quality Control.
B. Source Quality Control. Contractor must:
1. Perform work, including all sampling and testing, in accordance with
American Concrete Institute Publication No. 301 (ACI 301).
2. Perform slump and compression tests in accordance with ASTM C94.
3. Cylinders for compression tests must be 6 diameter x 12 depth.
-
8/10/2019 Section 12 - Traction Power
29/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-2.01 - Page 29
PART 2 PRODUCTS
2.01 CONCRETE
A. Concrete: Ready-mixed class A concrete, minimum 564 pounds of Portland
cement per cubic yard, with 28-day compressive strength of 3,500 psi.
1. Cement: Standard brand of Portland cement in accordance with ASTM
C150/C150M.
2. Admixtures: Water reducing, retarding, accelerating, workability agents
and other types of admixtures may be used after Engineers written
acceptance.
a. Conform to ASTM C494/C494M.
b. Under no circumstances may calcium chloride be used in concrete
as an admixture.
3. Aggregates: Well graded, composed of sand, and clean, uncoated
round or angular particles of gravel.
a. Conform to ASTM C33/C33M.
b. Maximum nominal size: 1-1/2 inches.
4. Water:
a. Potable with no impurities, algae or dissolved natural salts inamounts that will cause corrosion of reinforcing steel, volume
change that will increase shrinkage cracking, and efflorescence.
b. Minimum pH level: 5.
5. Slump:
a. Maximum: 3 inches.
b. Minimum: 1 inch.
B. Reinforcing Steel:
1. Conform to State Standard Specifications, Section 52, Reinforcement.
2. Reinforcing bars: Comply with ASTM A706/A706M, Grade 60.
-
8/10/2019 Section 12 - Traction Power
30/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-2.01 - Page 30
PART 3 EXECUTION
3.01 GENERAL REQUIREMENTS
A. Provide TPSS foundations as indicated on the Plans.
B. Protect drainage pipes and ditches during construction of TPSS foundation
slab.
C. See Section 10, Civil and Track Construction for additional installation
requirements.
D. Contractor must place concrete in accordance with ACI 301.
3.02 TPSS FOUNDATIONS
A. Coordination:
1. Coordinate exact location of concrete foundation with Engineer.
a. TPSS doors must have the following clearances from LRT track
when fully opened, including LRT tracks designated as future.
1) Personnel Doors: Minimum 6-1/2 feet.
2) Equipment Access Doors: Minimum 15 feet.
2. Before constructing foundation, coordinate dimensions and conduit stub-
up locations with TPSS Shop Drawings, which will be furnished by theEngineer.
3. Indicate coordinated dimensions and stub-up locations on foundation
Working Drawing and submit for acceptance before construction.
B. Provide compacted aggregate base to bottom of TPSS foundation as
indicated on Contract Drawings.
C. Slab:
1. Top of slab elevation must be as indicated on Contract Drawings.
2. Slab must be flat and level and must not allow standing water.
3. Surface finish: Comply with State Standard Specifications 51-1.03F(2),
Ordinary Surface Finish.
4. Immediately after placement, protect concrete from premature drying,
excessively hot or cold temperatures, and mechanical injury.
-
8/10/2019 Section 12 - Traction Power
31/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-2.01 - Page 31
5. Maintain concrete with minimal moisture loss at relatively constant
temperature for period necessary for hydration of cement and hardening
of concrete.
-
8/10/2019 Section 12 - Traction Power
32/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-3.01 - Page 32
12-3 METALS
12-3.01 COMMON WORK RESULTS FOR METALS
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. Requirements only for work in this Section 12.
B. Requirements for miscellaneous steel items.
C. Requirements for galvanizing.
D. Requirements for welding.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 REFERENCE STANDARDS
A. Sub-section incorporates by reference the latest revisions of the following
documents:
B. American Welding Society (AWS)
1. AWS D1.1/D1.1M, Structural Welding Code - Steel
C. State of California, Department of Transportation (Caltrans)
1. Caltrans Standard Specifications (State Standard Specifications)
1.04 SUBMITTALS
A. Procedures: Sub-section 12-1.03, Submittal Procedures.
B. Submit the following for welding:
1. Welding Procedure Specifications (WPS), Procedure Qualification
Records (PQR) and manufacturers data sheet for each filler metal to be
used.
2. Welders qualification records: Submit certified copies of qualification
test records for each welder in accordance with requirements of AWS
D1.1/D1.1M, and AWS QC1.
-
8/10/2019 Section 12 - Traction Power
33/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-3.01 - Page 33
3. Welding Inspector: Certified Welding Inspector (CWI) Certification.
4. Coating Inspector: NACE Level 3 Coating Inspector
5. Welding Procedures: WPS, PQR and manufacturers data sheet for
each filler metal to be used.
6. Test reports conforming to the requirements of AWS D1.1/D1.1M.
1.05 QUALITY CONTROL
A. General Requirements: Sub-section 12-1.06, Quality Control.
B. Qualifications:
1. Welding Inspector: Contractor must provide a 3rdparty currently-certified
AWS CWI.
2. Coating Inspector: Contractor must provide a 3rdparty NACE Level 3
Coating Inspector for all coating work.
PART 2 PRODUCTS
2.01 MATERIALS
A. Minor steel material must conform to Section 75, Miscellaneous Metal, of the
State Standard Specifications.
2.02 GALVANIZING
A. Steel and malleable iron hardware: Hot-dip galvanized, complying with
requirements of Section 75-1.05, Galvanizing, of the State Standard
Specifications unless otherwise indicated in the Contract Documents.
2.03 WELDING
A. Welding: Conform to AWS D1.1/D1.1M.
B. Welding electrodes and fluxes: Conform to AWS D1.1/D1.1M.
C. Welding filler metal: Meet Charpy V-notch (CVN) impact tests per AWS
D1.1/D1.1M.
PART 3 EXECUTION
3.01 WELDING
A. Welding: As indicated on Contractors Shop Drawings.
-
8/10/2019 Section 12 - Traction Power
34/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.01 - Page 34
12-4 ELECTRICAL
12-4.01 COMMON WORK RESULTS FOR ELECTRICAL
PART 1 GENERAL
1.01 SUB-SECTION INCLUDES
A. General requirements that apply to all 12-4 sub-sections.
B. Electrical demolition work.
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 REFERENCE STANDARDS
A. Sub-section incorporates by reference the latest revisions of the following
documents, or if standard is adopted by the Authority Having Jurisdiction
(AHJ), the latest revision adopted, with modifications by the AHJ.
B. Institute of Electrical and Electronics Engineers (IEEE)
1. IEEE C2, National Electrical Safety Code
C. National Fire Protection Agency (NFPA)
1. NFPA 70, National Electrical Code (NEC)
1.04 QUALITY CONTROL
A. General Requirements: Sub-section 12-1.06, Quality Control.
B. Minimum standard of quality and safety: NFPA 70 and IEEE C2.
C. Listing Requirement: Unless otherwise specified, electrical equipment and
material must be listed and labeled for the purpose for which it is used by the
Underwriters Laboratories, Inc. (UL).
PART 2 PRODUCTS
Not Used.
-
8/10/2019 Section 12 - Traction Power
35/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.01 - Page 35
PART 3 EXECUTION
3.01 INSPECTIONS BY AUTHORITY HAVING JURISDICTION
A. Electrical inspections, if required by the Authority Having Jurisdiction, may be
observed by the Engineer.
B. Schedule electrical inspections 7 days in advance with the Engineer and as
required by the appropriate jurisdiction.
C. Perform corrections required by inspector at no additional cost to RT.
3.02 ELECTRICAL DEMOLITION
A. Remove existing ductbanks and vaults where indicated on the Plans.
B. Where ductbanks contain dc feeders or negative returns, remove cables and
scrap.
C. Coordinate with RT for power outage to remove cables.
3.03 INSTALLATION
A. Torque bolted connections with a calibrated torque wrench in accordance with
manufacturers recommendations and apply torque marks.
B. Dissimilar material connections:
1. Not permitted at electrical connections or connections requiringdisassembly for maintenance or for removal and replacement of
equipment.
2. Not permitted except at permanent connections.
3. Where permitted, provide suitable electrochemical isolation.
4. Isolation treatments must be permanent and not require maintenance or
replacement for the life of the equipment or installation.
-
8/10/2019 Section 12 - Traction Power
36/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.02 - Page 36
12-4.02 COMMON WORK RESULTS FOR TRACTION POWER
CONDUCTORS
PART 1 GENERAL
1.01 SUMMARY
A. Sub-section Includes:
1. Cable pulling.
B. Related Sub-sections:
1. Sub-section 12-4.04 Medium-Voltage Conductors and Cable
2. Sub-section 12-4.08 Underground Raceways and Vaults for Electrical
Systems
3. Sub-section 12-8.01 Common Work Results for Traction Electrification
System
1.02 MEASUREMENT AND PAYMENT
A. Traction power conductors are included in TES Cable System Work pay item.
See TES Cable System Work pay item in sub-section 12-1.02, Measurement
and Payment.
1.03 REFERENCE STANDARDS
A. Sub-section incorporates by reference the latest revisions of the following
documents, or if standard is adopted by the Authority Having Jurisdiction
(AHJ), the latest revision adopted, with modifications by the AHJ:
B. Institute of Electrical and Electronics Engineers (IEEE)
1. IEEE 1210, Standard Tests for Determining Compatibility of Cable-
Pulling Lubricants With Wire and Cable
C. National Fire Protection Agency (NFPA)
1. NFPA 70, National Electrical Code (NEC)
1.04 SUBMITTALS
A. Procedures: Sub-section 12-1.03, Submittal Procedures.
-
8/10/2019 Section 12 - Traction Power
37/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.02 - Page 37
B. Product Data:
1. Cable pulling lubricant.
C. Cable Pulling Plan:
1. Include description of pulling method, pulling equipment, and personnel
to be used in each cable pull.
D. Cable Pulling Calculations:
1. Submit minimum of 30 days before cable installation.
2. Furnish with maximum tensions for each cable run.
1.05 QUALITY CONTROL
A. General Requirements: Sub-section 12-1.06, Quality Control.
1.06 NOTIFICATION
A. Notify Engineer at least 48 hours in advance of each scheduled pull.
B. Adjust schedule as necessary to permit observation.
PART 2 PRODUCTS
2.01 CABLE RACKS
A. UL listed, heavy duty, non-metallic, glass-reinforced polymer, suitable for the
support of dc feeder cables without additional insulators, with sufficient load
capacity to support the installed and future cables.
B. Size: Racks must be of adequate length to support the number of cables
indicated without stacking, with space for 25 percent more cables.
C. Acceptable Manufacturer/Product:
1. Underground Devices, Inc., Heavy Duty Nonmetallic Cable Rack, or
approved equal.
2.02 CABLE PULLING LUBRICANT:
A. Commercially-available non-petroleum-based product that will not damage
cable, cable sheathing, or insulation or cause corrosion to metal boxes or
fittings of the raceway system.
1. Product must be approved by the cable manufacturer.
-
8/10/2019 Section 12 - Traction Power
38/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.02 - Page 38
2. Product must meet the requirements of IEEE 1210.
3. Product must not be harmful to the environment.
B. Provide special-formulation pulling lubricant where required due to low
ambient temperature or where a lower coefficient of friction is required to
meet pulling tension and sidewall pressure limits.
C. Acceptable Manufacturer/Product:
1. Polywater J, or Polywater WJ for low ambient temperature, or approved
equal.
2.03 TOOLS AND EQUIPMENT
A. Pulling winches and associated equipment must be of adequate capacity to
assure a steady continuous pull on the cables.
2.04 CABLE TIES (TIE WRAPS)
A. See Sub-section 12-8.01, Common Work Results for Traction Electrification
System.
2.05 FIREPROOFING TAPE
A. Fireproofing Tape: Fire and Electric Arc Proofing Tape.
1. Tape must be self extinguishing and must be compatible with conductor
insulation and jacket.
2. Tape must not deteriorate when subjected to water, salt water, gases
and/or sewage.
3. Acceptable Manufacturer/Product: 3M, Type 77, or approved equal.
2.06 IDENTIFICATION
A. Cable tags: See Sub-section 12-8.01, Common Work Results for Traction
Electrification System.
PART 3 EXECUTION
3.01 CABLE INSTALLATION
A. General:
1. Pull cables in strict accordance with manufacturer's recommendations.
-
8/10/2019 Section 12 - Traction Power
39/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.02 - Page 39
2. Pull cables in presence of Engineer.
3. Do not install cable with visible manufacturing defects or physical
damage.
4. Cable Bends: Minimum cable bending radii must comply with minimum
requirements of NFPA 70.
5. Do not pull cables by conductors unless authorized by Engineer.
B. Separation of Cables:
1. Install positive and negative cables in separate ductbanks, and vaults.
C. Preparation:
1. Where water has accumulated in ductbanks and vaults, pump water out;
comply with environmental rules and regulations for disposal of water.
2. Provide ventilation to disperse collections of noxious gases.
3. Mandrel and Brush:
a. Before installation of cable in conduit, repeat mandrel, brush, and
swab as required for First Article Inspection in Sub-section 12-4.08,
Underground Raceways and Vaults for Electrical Systems.
D. Cable Pulling:
1. Accessories:
a. Use cable feeder tubes and nozzles to protect cable and reduce
pulling tensions.
b. Attach a roller-bearing swivel between the pulling rope and pulling
basket or eye to reduce twist to cable.
2. Cable reels:
a. Set up in tandem so that cables may be fed into conduits without
changing direction of bend.
b. Turn supply reels while pulling cable to reduce tension.
3. Record pulling tension during each dc feeder cable pull using a
calibrated dynamometer.
-
8/10/2019 Section 12 - Traction Power
40/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.02 - Page 40
4. Pulling tension: Keep below maximum tension recommended by
manufacturer for both longitudinal tension and side pressure.
5. Use sufficient lubricant to meet tension requirements.
6. Communications: Use cell phones to maintain contact between teams
unless ends of pull are within voice or visual range.
E. After Cable Pulling:
1. Immediately after cable pulling, cut off damaged ends of cable and seal
cable at each end of cut cable and cable end on reel with approved
cable end seal to prevent entrance of dirt and moisture.
2. See Sub-section 12-4.04, Medium-Voltage Conductors and Cable, for
cable end seals.
3. Attach temporary cable tags to the cable as soon as it is pulled.
4. Leave sufficient slack cable lengths of half perimeter of vault, or as
directed by Engineer to allow for proper racking and future splicing
during the life of the cable.
5. Temporarily support cables until they are permanently racked.
6. Remove lubricants from cable in vaults after pulling cable.
7. Cable Racking:
a. Install cable racks specified under this sub-section in accordance
with manufacturers recommendations.
b. Rack cables on cable racks.
c. Provide cleats and supports if needed.
d. Form cable around wall of vault as soon as cable pull is completed,
leaving 6 inches of cable straight where it emerges from conduit.
8. Cable Supports in Vertical Runs:
a. Support and spacing must conform to NFPA 70, cable
manufacturers recommendation, or as indicated.
b. Basket grips may be used.
-
8/10/2019 Section 12 - Traction Power
41/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.02 - Page 41
c. Cable must not be supported by the terminals to which it is
connected.
9. Fireproofing Cables:
a. Fire tape each dc positive feeder and negative-return cable in each
vault from cable entrance to cable exit using specified tape.
3.02 CABLE SPLICING
A. Splices must not be made unless specifically authorized by the Engineer.
3.03 CABLE TERMINATION
A. Terminate positive dc feeder cables in each TPSS and at OCS disconnect
switches.
B. Terminate negative return cables in each TPSS and at rail or impedancebond, as indicated on the Plans.
3.04 IDENTIFICATION
A. Identify each cable at both ends with permanent cable tags imprinted with
indelible and legible characters.
B. Main Feeders 240 V or higher: Identify phase.
-
8/10/2019 Section 12 - Traction Power
42/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 42
12-4.03 LOW-VOLTAGE CONDUCTORS AND CABLE
PART 1 GENERAL
1.01 SUMMARY
A. Sub-section Includes:
1. Insulated wire and cable, 600 V and 2kV.
2. Wire and cable terminations and splices.
B. Related sub-sections:
1. Sub-section 12-4.02 Common Work Results for Traction Power
Conductors
1.02 MEASUREMENT AND PAYMENT
A. Work specified in this sub-section is incidental to Work described in other sub-
sections.
1.03 REFERENCES
A. Definitions:
1. Low-voltage cable: A single or multiconductor insulated cable rated
2000 V or less.
B. Reference Standards:
1. Sub-section incorporates by reference the latest revisions of the
following documents:
2. ASTM International (ASTM)
a. ASTM B3, Specification for Soft or Annealed Copper Wire
b. ASTM B8, Standard Specification for Concentric-Lay-Stranded
Copper Conductors, Hard, Medium-Hard, or Soft
c. ASTM B33, Standard Specification for Tin-Coated Soft or Annealed
Copper Wire for Electrical Purposes
d. ASTM B172, Standard Specification for Rope-Lay-Stranded Copper
Conductors Having Bunch-Stranded Members, for Electrical
Conductors
-
8/10/2019 Section 12 - Traction Power
43/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 43
3. Insulated Cable Engineers Association (ICEA)
a. ICEA S-95-658/NEMA WC 70, Power Cables Rated 2000 Volts or
Less for the Distribution of Electrical Energy
4. International Organization of Standards (ISO)
a. ISO 9001, Quality Management Systems Requirements
5. National Electrical Manufacturers Association (NEMA)
a. NEMA WC 26, Binational Wire and Cable Packaging Standard
6. Underwriters Laboratories (UL)
a. UL 44, Standard for Thermoset-Insulated Wires and Cables
1.04 SUBMITTALS
A. Procedures: Sub-section 12-1.03, Submittal Procedures.
B. Product Data:
1. Each type of proposed wire and cable.
2. Cable terminals.
3. Compression tool product line.
C. Samples: Two foot samples for each type of proposed wire and cable after
factory testing and before delivery.
D. Certification substantiating that cables have been designed, manufactured,
inspected, and tested in accordance with applicable portions of the referenced
standards, and these Technical Specifications.
Substantiation must be in the form of certified test reports or certifications.
E. Test Procedures:
1. Dc feeder cables: Submit minimum of 30 days before planned start of
field testing.
F. Test Reports:
1. Design test reports.
2. Production test reports.
-
8/10/2019 Section 12 - Traction Power
44/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 44
3. Field test reports: Submit before final termination of cables.
1.05 QUALITY CONTROL
A. General Requirements: Sub-section 12-1.06, Quality Control.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Labeling:
1. Label each reel with an appropriate, weatherproof label, securely
fastened, indicating the following:
a. Physical, mechanical, and electrical properties.
b. UL type designation.
c. ASTM designation.
d. Name and mark of the manufacturer.
e. Purchase order number.
f. Date of manufacture.
B. Packaging:
1. Package cables on standard domestic non-returnable wood reels that
meet requirements of NEMA WC 26 and are suitable for the weightinvolved.
2. Reels must be constructed and cables packed to protect the cable from
damage:
a. During transport by the shipping method to be used.
b. During field handling using type of equipment normally available
and used for handling of such material.
c. In storage.
C. Handling:
1. Handle cables according to cable manufacturers guidelines to preserve
cable and reel integrity.
-
8/10/2019 Section 12 - Traction Power
45/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 45
2. Crane-type loading and unloading: Use a shaft and spreader bar to
prevent lifting devices from pressing against cable or cable reel flanges.
Position lifting devices equally on the shaft.
3. Forklift-type loading and unloading:
a. Forks must be at a 90 degree angle to the flanges, long enough to
contact both flanges.
b. Under no circumstances may the cable or protective coating be
forced against lifting or stopping devices.
4. See also CQC Handling, Storage, Packaging, Preservation and
Delivery section of the General Conditions.
PART 2 PRODUCTS
2.01 600 V SINGLE CONDUCTOR WIRE AND CABLE
A. Conductor Material: ICEA stranded or solid copper meeting requirements of
ASTM B3, soft drawn.
B. Conductor Type:
1. Size No. 12 AWG and Smaller: Solid conductor.
2. Size No. 10 AWG and Larger: Class B stranded per ASTM B8.
3. Size No. 14 to 1/0 AWG: Type XHHW-2, cross-linked polyethyleneinsulated in accordance with ICEA S-95-658/NEMA WC 70.
4. Size No. 2/0 AWG and Larger: Type XHHW-2, cross-linked
polyethylene insulated in accordance with ICEA S-95-658/NEMA WC 70
or type RHH/RHW, ethylene-propylene-rubber-insulated in accordance
with ICEA S-95-658/NEMA WC 70.
C. Insulation Rating: 600 V.
D. Temperature Rating: Insulation temperature rating not less than 90 degrees
C in wet or dry locations.
2.02 2 KV DLO/DEL CABLE
A. Cable Type: Diesel locomotive, type DLO, or diesel-electric locomotive, type
DEL, 2 kV, UL listed RHH/RHW-2 per UL 44.
B. Size: As indicated on Plans.
-
8/10/2019 Section 12 - Traction Power
46/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 46
C. Conductor: Extra flexible, coated copper, stranded per AAR MSRP, Section
M, RP-588, as applicable, and ICEA S-95-658/NEMA WC70.
D. Insulation: Heat-resistant, mechanically-rugged, ethylene-propylene based.
E. Jacket: Thermoset chlorinated polyethylene (TS-CPE), resistant to
mechanical abuse, flame, weathering, most oils, acids, and alkalies.
F. Flame resistance: Must meet UL vertical and horizontal flame test
requirements.
G. Temperature Rating:
1. Continuous: 90 degrees C.
2. Emergency overload: 130 degrees C.
3. Short circuit: 300 degrees C.
H. Acceptable Manufacturers:
1. Okonite, or approved equal.
2.03 2 KV SPLICES AND TAPS
A. Provide a system of components rated 2 kV, 2000 A.
B. Type: High Strength, high-conductivity cable-receptacles and tapered
compression sleeves.
C. Acceptable Manufacturer/Product:
1. Dossert MICON Type MC network connector range with Type MS
insulating sleeve, or approved equal.
D. Alternate Type (may be used only with Engineer authorization):
1. Wraparound, completely waterproof splice comprised of the following:
a. Heavy duty heat shrink sleeves,
b. 5 kV insulating tubing
c. Strip environmental sealant.
-
8/10/2019 Section 12 - Traction Power
47/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 47
2. Acceptable Manufacturer/Product:
a. Raychem, CRSM wraparound heat shrink sleeves, type BPTM 5 kV
insulating tubing, with red insulating mastic environmental sealant
type S-1254-25-300-4.
b. Submit to Engineer documentation demonstrating that alternate-
type splice is required.
2.04 TERMINATIONS
A. Fittings must be tool-applied, compression, compatible with conductors on
which they are used, and listed for use with provided cable.
B. No. 10 AWG and smaller conductors:
1. Wire terminations: Heavy duty, ring type, nylon insulated.
2. Splices: Self-insulating or provided with an insulating cap or heat-shrink
insulating sleeve.
C. No. 8 AWG to No. 4 AWG: Provide double-bolted NEMA two-hole terminals
where rotation of a single-bolted terminal would result in contact or
unacceptable clearance with other conductors or the enclosure.
D. No. 2 AWG to No. 3/0 AWG: Provide terminals with two NEMA-standard bolt
holes in tongue unless otherwise indicated.
E. No. 4/0 AWG and larger conductors: Provide long-barrel, double-compression type, with two NEMA-standard bolt holes in tongue unless
otherwise indicated.
F. Fine-stranded cable: For stranding finer than Class C, terminations must be
listed for use with fine stranded cables.
G. Compression Tools:
1. Must apply a hexagonal compression using mechanical, electrical, or
hydraulic power mechanism that ensures a complete compression cycle.
2. Must permanently imprint die information on the completed connection.
3. Must be the tool and die recommended by the manufacturer for the
particular termination used.
-
8/10/2019 Section 12 - Traction Power
48/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 48
H. Acceptable Manufacturers:
1. AMP;
2. Thomas & Betts;
3. Burndy, or approved equal.
2.05 SOURCE QUALITY CONTROL
A. Production Tests: Perform in accordance with applicable engineering
standards or manufacturer's standards, whichever are more stringent.
PART 3 EXECUTION
3.01 WIRE AND CABLE TYPE REQUIREMENTS
A. Blue lights fed from new TPSS: 600 V single conductor cable, No. 6 AWG.
B. Surge arrester grounding cables: 2 kV insulated cable, type DLO or DEL.
3.02 WIRE AND CABLE INSTALLATION
A. Wire and Cable: Comply with the requirements of Sub-section 12-4.02,
Common Work Results for Systems Conductors.
3.03 SPLICE AND TERMINATION INSTALLATION
A. Use continuous lengths of wire and cable between power source andequipment. Splices are subject to acceptance by Engineer.
B. Where splices are required and authorized by Engineer, make them only in
approved outlet, junction or pull boxes, in vaults, or in equipment cabinets, in
accordance with cable and terminator manufacturers instructions.
C. Connect conductors No. 8 AWG or larger to apparatus, bus work, switch or
fuse blocks, by means of compression type lugs, unless otherwise indicated.
Permanently bolt lugs to give maximum contact surface.
D. 2 kV splice assemblies:
1. Preferred type assemblies must be neatly taped after assembly.
2. Alternate type assemblies must be installed per the manufacturers
instructions.
3. Where splices are detailed on the Plans, install as shown and as
directed in writing by the Engineer.
-
8/10/2019 Section 12 - Traction Power
49/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.03 - Page 49
E. Tools:
1. Use tool as recommended by the terminal manufacturer.
2. Smaller than No. 2 AWG: Apply with mechanical ratcheting type or
electric/hydraulic type compression tool.
3. No. 2 AWG and larger: Apply with electric/hydraulic type compression
tool.
-
8/10/2019 Section 12 - Traction Power
50/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 50
12-4.04 MEDIUM-VOLTAGE CONDUCTORS AND CABLE
PART 1 GENERAL
1.01 SUMMARY
A. Sub-section Includes:
1. Traction power positive conductors, 2.4 kV.
2. Wire and cable terminations and splices.
B. Related Sub-sections:
1. Sub-section 12-4.02 Common Work Results for Traction Power
Conductors
1.02 MEASUREMENT AND PAYMENT
A. Traction power conductors are included in TES Cable System Work pay item.
See TES Cable System Work pay item in Sub-section 12-1.02, Measurement
and Payment.
1.03 REFERENCES
A. Definitions:
1. Medium-voltage cable: A single or multi-conductor insulated cable rated
more than 2000 V.
2. Dc feeder cables: Includes both positive cables from TPSS to OCS and
negative return cables from TPSS to rail.
B. Reference Standards:
1. Sub-section incorporates by reference the latest revisions of the
following documents:
2. ASTM International (ASTM)
a. ASTM B3, Specification for Soft or Annealed Copper Wire
b. ASTM B8, Standard Specification for Concentric-Lay-Stranded
Copper Conductors, Hard, Medium-Hard, or Soft
c. ASTM B496, Standard Specification for Compact Round
Concentric-Lay-Stranded Copper Conductors
-
8/10/2019 Section 12 - Traction Power
51/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 51
3. Institute of Electrical and Electronics Engineers (IEEE)
a. IEEE 383, Standard for Qualifying Class 1E Electric Cables and
Field Splices for Nuclear Power Generating Stations
b. IEEE 1202, Standard for Flame Propagation Testing of Wire &
Cable
4. Insulated Cable Engineers Association (ICEA)
a. ICEA S-96-659/NEMA WC 71 - Standard for Nonshielded Cables
Rated 2001-5000 Volts for Use in the Distribution of Electric Energy
5. International Organization of Standards (ISO)
a. ISO 9001, Quality Management Systems Requirements
6. National Electrical Manufacturers Association (NEMA)
a. NEMA WC 26, Binational Wire and Cable Packaging Standard
7. Underwriters Laboratories (UL)
a. UL 1072, Medium-Voltage Power Cables
1.04 SUBMITTALS
A. Procedures: Sub-section 12-1.03, Submittal Procedures.
B. Product Data for:
1. Each type of proposed wire and cable.
2. Cable terminals.
3. Compression tool product line.
4. Cable end seals.
C. Samples: One for each type of proposed wire and cable.
-
8/10/2019 Section 12 - Traction Power
52/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 52
D. Certification that substantiates that cables have been designed,
manufactured, inspected, and tested in accordance with applicable portions of
the referenced standards, and these Technical Specifications. Substantiation
must be in the form of certified test reports or certifications.
E. Test Procedures:
1. Dc Feeder Positive Cables: Submit test plan and procedure minimum
30 calendar days before planned start of field tests.
F. Test Reports:
1. Design test reports.
2. Production test reports.
3. Field test reports:
a. Dc feeder cable: Submit before final termination of cables.
1.05 QUALITY CONTROL
A. General Requirements: Sub-section 11-1.06, Quality Control.
B. Manufacturers Qualifications:
1. Cable must be manufactured and factory tested under the control of a
Quality Assurance program that meets the requirements of ISO 9001.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Cable Ends:
1. Seal both ends of cable with approved cable end seal before winding on
the reel.
2. Keep cable ends sealed at all times during delivery and storage.
B. Labeling:
1. Label each reel with an appropriate, weatherproof label, securely
fastened, indicating the following:
a. Manufacturer
b. Consignee
c. Customer PO number
-
8/10/2019 Section 12 - Traction Power
53/118
-
8/10/2019 Section 12 - Traction Power
54/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 54
4. See also Section 6.47.11 Handling, Storage, Packaging, Preservation
and Delivery section of the General Conditions.
PART 2 PRODUCTS
2.01 TRACTION POWER FEEDER CABLE
A. General:
1. Cable: UL Type MV-90, 90 degrees C, 2.4 kV, unshielded, size as
indicated on Contract Drawings.
2. Application: Cable must be suitable for use on service and feeders,
indoors or outdoors, in wet or dry locations, in conduit, and in cable tray.
B. Conductors:
1. Stranded, annealed copper conforming to or exceeding the requirementsof ASTM B3.
2. Stranding: Per ASTM B8 or ASTM B496, Class B or C, unless otherwise
indicated.
C. Insulation:
1. Ethylene propylene rubber (EPR) meeting or exceeding the
requirements of ICEA S-96-659/NEMA WC 71 and UL 1072.
2. No polyethylene is allowed as a component of the insulation.
3. EPR insulation must be compounded by the cable manufacturer.
D. Overall Sheath Jacket: Sunlight resistant, heavy-duty thermosetting
chlorinated polyethylene (TS-CPE), meeting or exceeding the requirements of
UL 1072.
E. Temperature Rating:
1. Suitable for installation at 0 degrees C.
2. Continuous operating rating: 90 degrees C.
3. Emergency rating: 130 degrees C.
4. Short circuit rating: 250 degrees C.
-
8/10/2019 Section 12 - Traction Power
55/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 55
F. Acceptable Manufacturer/Product:
1. The Okonite Company, Okoguard-Okolon TS-CPE, or approved equal.
2.02 2.4 KV SPLICES AND TAPS
A. Provide a system of components rated 2.4 kV, 2000 A.
B. Type: High Strength, high-conductivity cable-receptacles and tapered
compression sleeves.
C. Acceptable Manufacturer/Product:
1. Dossert MICON Type MC network connector range with Type MS
insulating sleeve, or approved equal.
D. Alternate Type (may be used only with Engineer authorization):
1. Wraparound, completely waterproof splice comprised of the following:
a. Heavy duty heat shrink sleeves,
b. 5 kV insulating tubing
c. Strip environmental sealant.
2. Acceptable Manufacturer/Product:
a. Raychem, CRSM wraparound heat shrink sleeves, type BPTM 5 kVinsulating tubing, with red insulating mastic environmental sealant
type S-1254-25-300-4, or approved equal.
b. Submit to Engineer documentation demonstrating that alternate
type splice is required.
2.03 TERMINATIONS
A. Fittings must be tool-applied, compression, compatible with conductors on
which they are used, and listed for use with provided cable.
B. No. 4/0 AWG and larger conductors: Provide long-barrel, double-
compression type, with two NEMA-standard bolt holes in tongue unless
otherwise indicated.
C. Compression Tools:
1. Must apply a hexagonal compression using mechanical, electrical, or
hydraulic power mechanism that ensures a complete compression cycle.
-
8/10/2019 Section 12 - Traction Power
56/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 56
2. Must permanently imprint die information on the completed connection.
D. Acceptable Manufacturers:
1. AMP;
2. Thomas & Betts;
3. Burndy, or approved equal.
2.04 CABLE END SEALS
A. Heat shrinkable cap, polyolefin, providing a watertight after shrinking.
B. Cap must seal to the cable and not require tape to hold it in place.
2.05 SOURCE QUALITY CONTROL
A. Dc Feeder Cables:
1. Design Tests: Perform design tests in accordance with ICEA S-96-
659/NEMA WC 71 and UL 1072.
2. Qualification Flame Tests:
a. Cable must pass the UL 1072 vertical tray flame test.
b. Cable must meet the vertical tray flame test requirements of IEEE
383 and IEEE 1202.
3. Production Tests: Perform in accordance with applicable engineering
standards or manufacturer's standards, whichever are more stringent.
PART 3 EXECUTION
3.01 WIRE AND CABLE INSTALLATION
A. Wire and Cable: Must comply with the requirements of Sub-section 12-4.02,
Common Work Results for Systems Conductors.
3.02 SPLICE AND TERMINATION INSTALLATION
A. Use continuous lengths of wire and cable between power source and
equipment. Splices may not be used without written authorization of the
Engineer.
-
8/10/2019 Section 12 - Traction Power
57/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.04 - Page 57
B. Where splices are required by conditions and authorized by Engineer, make
them only in approved outlet, junction or pull boxes, in vaults, or in equipment
cabinets, in accordance with cable and terminator manufacturers instructions.
C. Connect conductors No. 8 AWG or larger to apparatus, bus work, switch or
fuse blocks by means of compression type lugs, unless otherwise indicated.Permanently bolt lugs to give maximum contact surface.
D. 2.4 kV splice assemblies:
1. Preferred type assemblies must be neatly taped after assembly.
2. Alternate type assemblies must be installed per the manufacturers
instructions.
3. Where splices are detailed on Contract Drawings, install as shown and
as directed by Engineer.
E. Tools:
1. Use tool as recommended by the terminal manufacturer.
2. Smaller than No. 2 AWG: Apply with mechanical ratcheting type or
electric/hydraulic type compression tool.
3. No. 2 AWG and larger: Apply with electric/hydraulic type compression
tool.
3.03 FIELD QUALITY CONTROL
A. Dc Feeder Cables:
1. High Potential Test: Perform test at voltages and for time durations in
accordance with ICEA and NETA recommendations.
2. Test positive feeder and negative return cables separately.
3. Test is passed if there is no insulation breakdown or excessive leakage
current.
4. If a failure is detected, locate and determine the trouble, replace the
defective cables, make necessary corrections, and retest the cables at
no additional cost RT.
-
8/10/2019 Section 12 - Traction Power
58/118
Construction of South Sacramento Corridor Phase 2, Civil, Track, Structures, Stations & Systems
410.08.02/01.22.13 TECHNICAL SPECIFICATIONS Section 12-4.05 - Page 58
12-4.05 GROUNDING AND BONDING
PART 1 GENERAL
1.01 SUMMARY
A. Sub-section Includes:
1. TPSS ground mats.
2. OCS pole grounds.
3. Aerial structure OCS pole grounds.
4. Surge arrester grounds.
B. Related Sub-sections:
1. Sub-section 12-6.01 Common Work Results for Earthwork
1.02 MEASUREMENT AND PAYMENT
A. Ground mat and related work is included in TPSS Site Work pay item. See
TPSS Site Work pay item in Sub-Section 12-1.02, Measurement and
Payment.
B. Grounding for OCS poles and OCS surge arresters is included in Overhead
Contact System (OCS) pay items. See OCS pay items in Sub-section 11-
1.02, Measurement and Payment.
1.03 REFERENCE STANDARDS
A. Sub-section incorporates by reference the latest revisions of the following
documents or, if standard is adopted by the Authority Having Jurisdiction
(AHJ), the latest revision adopted, with modifications by the AHJ:
B. Institute of Electrical and Electronics Engineers (IEEE)
1. IEEE 81, Guide for Measuring Earth Resistivity, Ground Impedance, and
Earth Surface Potentials of a Gro