SECTION 09605 - VINYL FLOORING

38
Bicol International Airport Development Project Division 9 Finishes Section VI- Technical Specifications Vinyl Flooring 1 of 4 SECTION 09605 - VINYL FLOORING PART 1- GENERAL 1.1 SCOPE This specification covers the furnishing of materials and labor necessary to complete the installation of all vinyl flooring and base as shown in drawings and finish schedule and as specified herein. 1.2 SUBMITTALS 1.2.1 Catalog Data Complete descriptive literature for each type of the following items: a. Floor tile b. Wall base Clearly mark data to indicate which type, size, model or item will be provided. Data shall be sufficient to show conformance to specified requirements. 1.2.2 Manufacturer's Installation Procedures Submit four (4) current copies of the flooring manufacturer's recommended standard installation procedure for each type of flooring material. 1.2.3 Colors and Patterns One (1) sample of each color and pattern of each of the following items: a. Floor tile b. Wall base Where colors and patterns are not indicated, submit not less than 12 different samples of manufacturer's standard colors and patterns for selection by the Architect / Engineer and/or Owner. 1.2.4 Manufacturer's Maintenance Data and Instructions Upon completion and prior to acceptance of the work, submit current copies in triplicate of the flooring manufacturer's printed recommendations for maintenance methods and products for each type of flooring material. 1.3 DELIVERY AND STORAGE Deliver materials to the job in the manufacturer's original unopened containers with the brands, names, and production runs clearly marked thereon. Handle materials carefully and store them in their original containers at not less than 21 degrees C for at least 48 hours before work is started. Do not open containers until inspected and accepted. 1.4 ENVIRONMENTAL CONDITIONS Maintain spaces in which flooring work is to be performed at not less than 18 degrees C at the floor level for at least 48 hours prior to starting the work, during the time work is performed, and for at least 48 hours after the work is completed. Maintain a minimum temperature of 12 degrees C thereafter. Provide adequate ventilation to remove moisture and fumes from the area.

Transcript of SECTION 09605 - VINYL FLOORING

Page 1: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss VViinnyyll FFlloooorriinngg

1 of 4

SECTION 09605 - VINYL FLOORING

PART 1- GENERAL

1.1 SCOPE

This specification covers the furnishing of materials and labor necessary to complete the installation of all vinyl flooring and base as shown in drawings and finish schedule and as specified herein.

1.2 SUBMITTALS

1.2.1 Catalog Data

Complete descriptive literature for each type of the following items:

a. Floor tile b. Wall base

Clearly mark data to indicate which type, size, model or item will be provided. Data shall be sufficient to show conformance to specified requirements.

1.2.2 Manufacturer's Installation Procedures

Submit four (4) current copies of the flooring manufacturer's recommended standard installation procedure for each type of flooring material.

1.2.3 Colors and Patterns

One (1) sample of each color and pattern of each of the following items:

a. Floor tile b. Wall base

Where colors and patterns are not indicated, submit not less than 12 different samples of manufacturer's standard colors and patterns for selection by the Architect / Engineer and/or Owner.

1.2.4 Manufacturer's Maintenance Data and Instructions

Upon completion and prior to acceptance of the work, submit current copies in triplicate of the flooring manufacturer's printed recommendations for maintenance methods and products for each type of flooring material.

1.3 DELIVERY AND STORAGE

Deliver materials to the job in the manufacturer's original unopened containers with the brands, names, and production runs clearly marked thereon. Handle materials carefully and store them in their original containers at not less than 21 degrees C for at least 48 hours before work is started. Do not open containers until inspected and accepted.

1.4 ENVIRONMENTAL CONDITIONS

Maintain spaces in which flooring work is to be performed at not less than 18 degrees C at the floor level for at least 48 hours prior to starting the work, during the time work is performed, and for at least 48 hours after the work is completed. Maintain a minimum temperature of 12 degrees C thereafter. Provide adequate ventilation to remove moisture and fumes from the area.

Page 2: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss VViinnyyll FFlloooorriinngg

2 of 4

PART 2 - PRODUCTS

2.1 MATERIALS

Shall conform to the respective specifications and standards and to the requirements specified herein.

2.1.1 Color and Pattern

The color and pattern of tile shall be uniformly distributed throughout the thickness of the tile. Vinyl flooring materials of the same type, pattern, and color shall be of the same production run and shall be so marked. Variations in shades and off-pattern matches between containers will not be acceptable. Flooring in any one continuous area or that used in replacement of damaged flooring in a continuous area shall be from the same lot and have the same shade and pattern.

2.1.2 Vinyl Composition Tile:

2.1.2.1 Floor Tile

Shall be 3 mm (1/8") min. gauge, 300 mm by 300 mm (12" x 12") asbestos free vinyl composition tile. Color shall be selected by the Architect / Engineer and/or Owner.

2.1.2.2 Wall Base

Provide 3 mm (1/8") ga. Cove Vinyl wall base adjacent to resilient flooring. Base shall be 100 mm (4") high. Color shall be brown. Use flexible base to conform to irregularities in walls, partitions, and floors. Provide pre-molded corners in matching size, shape and color for all right-angle inside and outside corners with 3 mm (1/8") thick base.

2.1.2.3 Leveling compounds, underlayment, and patching compounds

As recommended or approved by flooring manufacturer.

2.1.2.4 Accessories

Shall be standard products of the flooring manufacturer.

PART 3 - EXECUTION

3.1 CONDITION OF SURFACES

The flooring shall not be installed on surfaces that are unsuitable and will prevent a proper installation. Floor surfaces that are to receive flooring shall be clean, thoroughly dry, smooth, firm and sound, and free from oil, paint, wax, dirt, and any other damaging material.

3.1.1 Preparation of Concrete Floor Surfaces

Grind all ridges and other uneven surfaces smooth. Concrete curing compounds, other than the type that does not adversely affect adhesive, shall be entirely removed from the slabs. Cut out and fill cracks with 1.5mm wide and wider with a crack filler as specified for this application. Provide latex underlayment to fill the remaining holes, cracks, and depressions, and for smoothing, leveling, and feather edging the concrete. Remove loose particles, vacuum chalky, dusty surfaces and prime the cleaned surfaces if recommended by the flooring manufacturer.

3.1.2 Moisture Test for Concrete Floors As recommended by the floor covering manufacturer.

Page 3: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss VViinnyyll FFlloooorriinngg

3 of 4

3.2 APPLICATION

Install flooring after work of other trades that might damage flooring has been completed. Apply flooring and accessories in accordance with the manufacturer’s installation procedure. Work shall be performed by workmen experienced in the application of such flooring. Detailed requirements are as follows:

3.2.1 Adhesives

Apply adhesives in accordance with the adhesive manufacture’s printed directions, unless specified or directed otherwise. Smoking, the use of open flames and other immediate sources of ignition are strictly prohibited in the area where solvent-containing adhesives are being used or spread. Post conspicuous signs reading “NO SMOKING OR OPEN FLAME” in the area of spread adhesive.

3.2.2 Flooring

Apply tile flooring in the patterns indicated. Start in the center of the room or area, and work from the center towards the edges. Keep tile line and Joint Square, symmetrical, tight, and vent; and keep each floor in a true, level plans, except where indicated as sloped. Vary edge width as necessary to maintain full-size tiles in the field but no edge tile shall be less than one-half (1/2) the field tile size, except where irregular shaped rooms make it impossible.

3.2.3 Cutting

Cut flooring to and fit around all permanent fixtures, built-in furniture and cabinets, pipes ad outlets. Cut edges, fit, and scribed to walls and partitions after field flooring has been applied.

3.2.4 Edge Strips

Provide edging strips where flooring terminates at points higher than the contiguous finished flooring, except at doorways where the thresholds are provided. Secure plastic strips with adhesives.

3.2.5 Application of Vinyl-Composition Tile

Prime concrete slabs in contact with the ground with cut-back type primer if recommended by the flooring manufacturer. Work primer with a non-absorptive base completely into the surface. Allow primer to become roughly dry before applying adhesive. Apply only cut-back adhesive to primed concrete surfaces.

3.2.6 Application of Vinyl Wall Base

Apply wall base after flooring has been completed, and the wall surface to which the base is to be applied is thoroughly dry. Form inside and outside corners with base materials as specified herein.

3.3 CLEANING AND PROTECTION

a. Remove all excessive adhesives from the surface of the flooring and the cove.

b. Perform initial maintenance on the completed installation as recommended by the

flooring manufacturer.

c. Protect the flooring as recommended by the flooring manufacturer from damage by other trades and by the placement of fixtures and furnishings.

Page 4: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss VViinnyyll FFlloooorriinngg

4 of 4

3.4 WARRANTY

Manufacturer shall warrant that its conductive vinyl tile is free from defects in materials and workmanship for a period of one year and that will meet the electrical resistance requirements of NFPA Standard 99 for a period of five (5) years.

4.0 METHOD OF MEASUREMENT

Vinyl flooring shall be measured by the number of square meters laid and accepted.

5.0 BASIS OF PAYMENT

The quantity measured as provided in Method of Measurement shall be paid for at the contract unit price, respectively for each of the Pay Items listed below and shown in the Bill of Quantities, which price and payment shall constitute full compensation for furnishing and placing all materials and for all labor, equipment, tools and incidentals to complete the work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 5: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss RRuubbbbeerr SShheeeett FFlloooorriinngg aanndd SSttaaiirr TThhrreeaadd

1 of 3

SECTION 09606 - RUBBER SHEET FLOORING AND STAIR TREAD

PART 1 - GENERAL

1.1 SCOPE

This specification covers the furnishing of materials and labor necessary to complete the installation of all rubber flooring as shown in drawings and finish schedule and as specified herein.

1.2 SUBMITTALS

1.2.1 Manufacturer's Literature and Data:

a. Description of each product.

b. Stair material manufacturer's recommendations for adhesives.

c. Application and installation instructions.

1.2.2 Samples

a. Rubber Stair Treads: 150 mm (6 inches) long.

b. Rubber Sheet Flooring: 300 mm (12 inches) square.

c. Adhesive: Literature indicating each type.

1.3 DELIVERY

Deliver materials to the site in original sealed packages or containers, clearly marked with the manufacturer's name or brand, type and color, production run number and date of manufacture. Materials from containers which have been distorted, damaged or opened prior to installation will be rejected.

1.4 STORAGE

Store materials in weather tight and dry storage facility. Protect material from damage by handling and construction operations before, during, and after installation.

1.5 APPLICABLE PUBLICATIONS

The publication listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

a. American Society for Testing and Materials (ASTM):

F1344-00 Rubber Tile

F1859-00 Rubber Sheet Flooring without Backing F1860-00 Rubber Sheet Flooring with Backing

F1861-00 Resilient Wall Base

b. Federal Specifications (Fed. Spec.):

RR-T-650E Treads, Metallic and Non-Metallic, Nonskid

Page 6: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss RRuubbbbeerr SShheeeett FFlloooorriinngg aanndd SSttaaiirr TThhrreeaadd

2 of 3

PART 2 - PRODUCTS

2.1 GENERAL

Use only products by the same manufacturer and from the same production run.

2.2 RUBBER TREADS

a. Fed. Spec. RR-T-650, Composition A, Type 2, 5 mm (3/16 inch) thick on wear

surface tapering to 3 mm (1/8 inch) thick at riser end.

b. Nosing shape to conform to sub-tread nosing shape.

2.3 SHEET RUBBER FLOORING

a. ASTM F1344, F1859 or F1860, 3 mm (1/8 inch) thick, smooth face, material by the same manufacturer as the rubber treads, color and pattern to match treads.

b. Use for stair landings and passenger bridge.

2.4 PRIMER (FOR CONCRETE FLOORS)

As recommended by the adhesive and tile manufacturer.

2.5 LEVELING COMPOUND (FOR CONCRETE FLOORS)

Provide products with latex or polyvinyl acetate resins in the mix.

2.6 ADHESIVE

Use products recommended by the material manufacturer for the conditions of use.

PART 3 - EXECUTION

3.1 PROJECT CONDITIONS

a. Maintain temperature of materials above 21o C (70 F), for 48 hours before installation.

b. Maintain temperature of rooms where work occurs, between 21o C and 27o C

(70oF and 80oF) for at least 48 hours, before, during, and after installation.

c. Do not install materials until building is permanently enclosed and wet construction is complete, dry, and cured.

3.2 INSTALLATION REQUIREMENTS

The respective manufacturer's instructions for application and installation will be considered for use when approved by the Architect / Engineer. Submit proposed installation deviation from this specification to the Architect / Engineer indicating the differences in the method of installation. The Architect / Engineer reserves the right to have test portions of material installation removed to check for non-uniform adhesion and spotty adhesive coverage.

3.3 PREPARATION

Examine surfaces on which material is to be installed. Fill cracks, pits, and dents with leveling compound. Level to 3 mm (1/8 inch) maximum variations and do not use adhesive for leveling or filling. Grind, sand, or cut away protrusions; grind high spots. Clean substrate

Page 7: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss RRuubbbbeerr SShheeeett FFlloooorriinngg aanndd SSttaaiirr TThhrreeaadd

3 of 3

area of oil, grease, dust, paint, and deleterious substances. Substrate area shall be dry and cured then perform manufacturer’s recommended bond and moisture test.

3.4 STAIR TREAD INSTALLATION

a. Prepare surfaces to receive the treads in accordance with applicable portions of paragraph, Preparation.

b. Layout of Treads

No joints will be accepted in treads. Set full treads on intermediate and floor landings.

c. Application

Apply adhesive uniformly with no bare spots. Roll and pound treads to assure adhesion.

3.5 CLEANING AND PROTECTION

a. Clean all exposed surfaces of base and adjoining areas of adhesive spatter before

it sets.

b. Keep traffic off resilient material for at least 72 hours after installation.

c. Clean and polish materials in the following order:

1. After two weeks, scrub rubber tiles and tread materials with a minimum amount of water and a mild detergent. Leave surfaces clean and free of detergent residue. Polish resilient base to a gloss finish.

2. Do not polish rubber tiles and tread materials.

d. When construction traffic is anticipated, cover tread materials with reinforced Kraft

paper and plywood or hardboard properly secured and maintained until removal is directed by the Architect / Engineer.

e. Where protective materials are removed and immediately prior to acceptance,

replace damaged materials and re-clean resilient materials. Damaged materials are defined as having cuts, gouges, scrapes or tears and not fully adhered.

4.0 METHOD OF MEASUREMENT

Rubber Sheet Flooring and Rubber Treads shall be measured by the number of square meters installed and accepted.

5.0 BASIS OF PAYMENT

The quantities determined as provided in Method of Measurement shall be paid for at the contract price per unit of measurement, respectively, for each of the particular Pay Item listed below and shown on the Bill of Quantities, which price and payment shall constitute full compensation for furnishing and placing all materials, including all labor, equipment, tools and incidentals necessary to complete the work prescribed in this Item.

Payment will be made in accordance with the Bill of Quantities.

******

Page 8: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss HHoommooggeenneeoouuss TTiillee

1 of 4

SECTION 09609 - HOMOGENEOUS TILE PART 1 - GENERAL

1.1 SCOPE

The work includes the supply and furnishing of materials and performing labor necessary for the complete installation of all homogeneous tile-work as shown or indicated on drawings and as specified herein.

1.2 SUBMITTALS

1.2.1 Samples

Submit samples of each type of floor and wall tiles including all required beads, moulding, and trim units.

1.3 DELIVERY AND STORAGE

a. Deliver materials (except bulk materials) in manufacturer’s unopened containers fully

identified with manufacturer’s name, trade name, type, class, grade, size and color.

b. Store materials in unopened containers off ground and under cover, protected from damage.

1.4 EXTRA STOCK

Supply an extra two percent of each type of tile to be used in clean, marked cartons for emergency use.

PART 2 - PRODUCTS

2.1 MATERIALS

All materials shall be of the best of their respective kinds, in sizes and colors as shown on the plans, details and finish schedules or otherwise specified herein or as will be approved by the Architect / Engineer upon submission of samples. Samples of all tiles shall be submitted to the Architect / Engineer for approval before placing orders. All tiles shall be delivered to the jobsite in unopened grade-sealed containers.

2.1.1 Color and Patterns

Tile colors and patterns shall be as selected. Colors and patterns by reference to manufacturer’s name and designations are for color and pattern identification only and are not intended to limit selection of other manufacture’s products with similar color and patterns.

2.2 HYDRATED LIME ASTM C206, Type S; or ASTM C207, Type S.

2.3 SAND ASTM C144, for mortar setting beds, grouting and pointing.

2.4 WATER Clean, potable.

Page 9: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss HHoommooggeenneeoouuss TTiillee

2 of 4

2.5 PORTLAND CEMENT ASTM C1500, Type I, white for grout, gray for others uses.

PART 3 - EXECUTION

3.1 INSTALLATION

Do not start tile work until roughing in for plumbing and electrical work has been completed and tested. All surfaces to receive tile-work shall be cleaned of loose materials and given proper surface preparation prior to ceramic tile-work. Prepare and install in accordance with ANSI A108.1 and ANSI A108.5.

3.1.1 Application of Scratch Coat

a. Thoroughly dampen, but not saturate, surfaces of masonry before applying the

scratch coat. Make surface areas appear slightly damp. Allow no free water on the surface.

b. On masonry, first apply a thin coat with great pressure, then bring it out sufficiently to

compensate for the major irregularities on the masonry surfaces to a thickness of not less than 6 mm at any point.

c. Evenly rake scratch coats, but not dash coats, to provide good mechanical key for

subsequent course before the mortar has fully hardened.

d. On surfaces not sufficiently rough to provide good mechanical key, dash on the first coat with a whisk by broom or fiber brush using a strong whipping motion. Do not trowel or otherwise disturb mortar applied by dashing until it is hardened.

3.1.2 Floor Tile Installation on Mortar Bed

a. Before spreading the setting bed, establish lines of borders and center the fieldwork

in both directions to permit the pattern to be laid with a minimum of cut tiles.

b. Clean concrete sub-floor then moisture but not soak. Afterwards sprinkle dry cement over the surface and spread the mortar on the setting bed.

c. Mix mortar 1 part Portland cement to 2 parts sand. Tamp to assure good bond over

the entire area and screed to provide a smooth and level bed at proper height and slope.

d. Pitch floor to drains as required.

e. After setting bed has set sufficiently to be worked over sprinkle dry cement over

surface and lay tile.

f. Keep the joints parallel and straight over the entire area by using straight edges.

g. Tamp the tile solidly onto the bed, using wood blocks of size to ensure solid bedding free from depressions.

h. Lay tiles from center outward and make adjustments at walls.

3.1.3 Wall Tile Installation on Mortar Bed

a. Before application of mortar bed, dampen the surface of the scratch coat evenly

to obtain uniform section.

Page 10: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss HHoommooggeenneeoouuss TTiillee

3 of 4

b. Use temporary or spot grounds to control the thickness of the mortar bed. Fill out

the mortar bed even with the grounds and rod it to a true plane.

c. Apply the mortar bed over an area no greater than can be covered with tile while the coat is still plastic.

d. Allow no single applications of mortar to 19 mm thick.

e. Completely immerse wall tile in clean water and soak it at least ½ hour. After

removal, stack tile on edge long enough to drain off excess water. Re-soak and drain individual tiles then dry along edges. Allow no moisture to remain on the back of tile during setting.

f. Apply a bond coat 0.8 mm thick to the plastic setting bed or to the back of each

sheet or tile.

g. Press tile firmly into the bed and beat into place within 1 hour.

h. Lay tile field in rectangular block areas not exceeding 600 mm x 600 mm. cut the setting bed through its entire depth along the edges of each block area after placement and before subsequent blocks are installed.

i. Within 1 hour after installation of tile, remove strings from string-set tile and wet

the faces of face-mounted tile and remove the paper and glue. Avoid using excess water. Adjust any tile that is out of alignment.

3.1.4 Grouting

a. After tile has sufficiently set, force a maximum of grout into joints by trowel, brush

or finger application.

b. Before grout sets, strike or tool the joints of cushion-edge tile to the depth of the cushion.

c. Fill all joints of square-edged tile flush with the surface of the tile. Fill all gaps or

sips.

d. During grouting clean all excess grout off with clean burlap, other cloth or sponges.

3.2 CLEANING

Sponge and wash tile thoroughly with clean water after the grout has stiffened. Then clean by rubbing with damp cloth or sponges and polish clean with dry cloth.

3.3 PROTECTION

Cover finished tile floors with clean 13.6 kg. Natural Kraft paper before permitting foot traffic. Place board walkways on floors that are to be continuously used as passageways by workers. Protect tiled corners external angles, with board corner strips in areas used as passageways by workers.

Page 11: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss HHoommooggeenneeoouuss TTiillee

4 of 4

4.0 METHOD OF MEASUREMENT

Homogeneous Tile shall be measured by the actual area installed in square meters and accepted to the satisfaction of the Architect / Engineer.

5.0 BASIS OF PAYMENT

The quantity measured as provided in Method of Measurement shall be paid for at the contract unit price, respectively for each of the Pay Items listed below and shown in the Bill of Quantities, which price and payment shall constitute full compensation for furnishing and placing all materials and for all labor, equipment, tools and incidentals to complete the work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 12: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss CCaarrppeett TTiillee

1 of 5

SECTION 09611- CARPET TILE

PART 1 - GENERAL

1.1 SCOPE

This specification covers the furnishing of materials and labor including equipment necessary to complete the installation of carpet tile as shown on the drawings and as specified herein.

1.2 SUBMITTALS

1.2.1 Product Data

Submit manufacturer’s product literature and installation instructions for each type of carpet tile material and installation accessory required. Include methods of installation for each type of substrate.

1.2.2 Shop Drawings

Submit shop drawings showing carpet tile layout, clearly indicating carpet tile direction, pattern direction (if applicable), placement of cut tiles, and locations and types of edge strips. Indicate columns, doorways, enclosing walls/partitions, built-in cabinets, and locations where cut-outs are required in carpet tile. Show installation details at any special conditions.

1.2.3 Samples for Initial Selection Purposes

Submit manufacturer’s standard size samples and color yarns showing full range of colors, textures and patterns available for each type of carpet tile required.

1.2.4 Samples for Verification Purposes

Submit the following:

a. Actual samples of each type of carpet tile pattern module required.

b. 6” long samples of each type of exposed edge stripping and accessory item.

1.2.5 Prepare samples from same material to be used for the work.

1.3 QUALITY ASSURANCE

1.3.1 Manufacturer’s Qualifications

Firm (material producer) with not less than 3 years of production experience, who’s published literature clearly indicates general compliance of products with requirements of this section.

1.3.2 Installer Qualifications

Firm specializing in carpet tile installation with not less than 2 years of experience in installation of carpet tile similar to that required for this project.

1.3.3 Single Source Responsibility

Provide material produced by a single manufacturer for each carpet tile type.

1.4 DELIVERY, STORAGE AND HANDLING 1.4.1 Deliver materials to project site in original factory wrappings and containers, clearly labeled

with identification of manufacturer, brand name, quality or grade, fire hazard classification,

Page 13: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss CCaarrppeett TTiillee

2 of 5

and lot number. Store materials in original undamaged packages and containers, inside well-ventilated area protected from weather, moisture, soiling, extreme temperatures, humidity, laid flat, blocked-off ground to prevent sagging and warping.

1.4.2 Comply with instructions and recommendations of manufacturer for special delivery, storage,

and handling requirements.

1.5 SEQUENCING & SCHEDULING

1.5.1 Sequence carpet tile with other work to minimize possibility of damage and soiling during remainder of construction period.

1.6 WARRANTY

1.6.1 Special Project Warranty

Submit a written Warranty executed by the Contractor, Installer, and the Manufacturer, agreeing to repair or replace carpet tiling which fails in materials or workmanship within the specified warranty period. This warranty shall be in addition to and not a limitation of other rights the Owner may have against the Contractor under the Contract Documents.

a. Warranty period is 2 years after the date of substantial completion.

1.7 MAINTENANCE

1.7.1 Maintenance Instructions

Submit manufacturer’s printed instructions for maintenance of installed work, including methods and frequency recommended for maintaining optimum condition under anticipated traffic and use conditions. Include precautions against materials and methods which may be detrimental to finishes and performance.

1.7.2 Replacement Materials

After completion of work, deliver not less than 5% of each type, color, and pattern of carpet tiling, exclusive of material required to properly complete installation. Furnish accessory components as required. Furnish replacement materials with protective covering, identified with appropriate labels.

PART 2 - PRODUCTS

2.1 MATERIALS

2.1.1 General

The following carpet tile data shall be as selected by the Architect / Engineer from the manufacturer’s standard range. a. Pile Material: 100% nylon 6.6

b. Carpet Tile Construction File: Flocked textile floor covering

c. File Density: 80 million / m2

d. Total Thickness: 5.3 mm

e. Pile Face Weight: Approx. 4.5 kg/m2

f. Tile Size: 500 mm x 500 mm

Page 14: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss CCaarrppeett TTiillee

3 of 5

g. Backing material

Backing material shall be resilient waterproof backing carpet.

2.2 CARPET TILE ACCESSORIES 2.2.1 Installation Adhesive

Releasable type adhesive as recommended by carpet tile manufacturer and which complies with flammability requirements for installed carpet tile.

2.2.2 Carpet Edge Guard, Metallic

Extruded aluminum bend-down type edge guard with concealed gripper teeth and minimum 38 mm (1-½”) wide anchorage flange and minimum 16 mm (5/8”) wide face flange. Provide with anodized aluminum finish of colors as selected by the Architect / Engineer, from standard colors available with the manufacturer.

2.2.3 Miscellaneous Materials

As recommended by the manufacturer of carpet tile and selected by Installer to meet project circumstances and requirements.

PART3 - EXECUTION

3.1 PRE-INSTALLATION REQUIREMENTS

3.1.1 Installation Adhesive

Releasable type adhesive as recommended by carpet tile manufacturer and which complies with flammability requirements for installed carpet tile.

3.1.2 Carpet Edge Guard, Metallic

Extruded aluminum bend-down type edge guard with concealed gripper teeth and minimum 38 mm (1-½”) wide anchorage flange and minimum 15 mm (5/8”) wide face flange. Provide with anodized aluminum finish of colors as selected by the Engineer, from standard colors available with the manufacturer.

3.1.3 Miscellaneous Materials

As recommended by the manufacturer of carpet tile and selected by Installer to meet project circumstances and requirements.

3.2 PRE-INSTALLATION REQUIREMENTS

a. Examine substrates for moisture content to verify a maximum allowable 65%

corrective measures as required if moisture content exceeds 65%.

b. Examine substrates for alkalinity. Corrective measures are required if pH reading is greater than 10.

c. Do not proceed until unsatisfactory conditions have been corrected.

d. Clear away debris and scrape up cementitious deposits from concrete surfaces to

receive carpet tile; apply sealer to prevent dusting.

Page 15: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss CCaarrppeett TTiillee

4 of 5

e. Patch all holes and level to a smooth surface. If previous finish was chemically stripped, re-seal concrete. Seal all powdery or porous surfaces with sealer recommended by carpet tile manufacturer.

3.3 INSTALLATION

3.3.1 General

Comply with manufacturer’s instructions and recommendations for direction of carpet tile; maintain uniformity of carpet tile direction and lay of pile.

a. Extend carpet tile under open-bottomed obstructions and under removable flanges

and furnishings, and into alcoves of each space, or as otherwise indicated.

b. Install carpet edge guard where edge of carpet is exposed; anchor guards to substrate.

c. Determine the center of the room using standard tile laying methods. The center

chalk lines, dividing the room into quadrants, should be off-center, if necessary, to ensure that perimeter modules will be half-size or larger.

d. On both sides of chalk-line, apply a strip of adhesive at least 228 mm (9”) in width,

using a twist-textured paint roller. When adhesive is ready, lay modules firmly along these anchor lines. Fill in each quadrant section laying using the “stair step” technique, completing the installation from center to corner of room in each quadrant, then moving to the next quadrant.

e. In large areas, a control grid of adhesive should be laid every 3050 mm (10 feet) as

control of the uniformity of the installation.

f. As each module is installed, ensure that the installation remains square and conforms to chalk lines.

g. Adhere perimeter tiles and cut tiles with a full spread of adhesive. Dry fit all cut tiles and apply adhesive to tile back after tile has been cut.

3.4 CLEANING

a. Remove and dispose of debris, cartons and unusable tile scraps.

b. Remove spots and smears of adhesive from carpet surface with approved cleaning agent. Replace any tile which cannot be cleaned.

c. Vacuum carpet using commercial machine. Remove any protruding face yarns with

sharp scissors.

3.5 PROTECTION

a. Advice the Contractor of protection methods and materials needed to ensure that

carpet tiles will be without deterioration or damage at time of substantial completion.

3.6 INSPECTION

a. Upon completion of the installation verify that work is complete, properly installed and acceptable. Remove and replace all work not found acceptable at the Installer’s expense and to the satisfaction and acceptance of the Engineer.

Page 16: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss CCaarrppeett TTiillee

5 of 5

4.0 METHOD OF MEASUREMENT

Carpet tiles of the size specified and inclusive of backing shall be measured by the number of square meters installed and accepted.

5.0 BASIS OF PAYMENT

The quantity measured as provided in Method of Measurement shall be paid for at the contract unit price per square meter of Carpet Tiles which price and payment shall constitute full compensation for furnishing and placing all materials and for all labor, equipment, tools and incidentals to complete the work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 17: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss GGrraavveell WWaasshhoouutt FFiinniisshh

1 of 3

SECTION 09613 - GRAVEL WASHOUT FINISH PART 1 - GENERAL

1.1 SCOPE This specification covers the furnishing of materials including equipment and performing labor

necessary to complete the installation of gravel washout finish as shown on drawings and as specified herein.

1.2 SUBMITTALS a. Samples: Prior to delivery of materials to the site, submit and receive approval of

the following samples:

1. Gravel washout finish. Two 300 mm by 300 mm sample panels of each type finish or color combination.

2. Divider Strip. Two 150 mm lengths. 1.3 DELIVERY, HANDLING AND STORAGE Deliver materials in the manufacturer’s original unopened containers marked with the

manufacturer’s name and brand. Deliver, handle and store materials in a manner that will prevent contamination or deterioration.

1.4 ENVIRONMENTAL CONDITIONS Ambient temperature and temperature of cementitious mixtures shall be not less than 50

degrees F from the item mixture are placed until completely cured. PART 2 - PRODUCTS 2.1 MATERIALS a. Cement: ASTM C150, type 1 gray or white to match the pebbles indicated or

specified. b. Gravel: Gravel shall be Selected No. 10 for floors. Color shall be as indicated.

Gravel shall have abrasive hardness not less than 8% when tested in accordance with ASTM C241.

c. Curing Materials: 1. Curing Materials shall be liquid – forming compound. 2. Water: Water shall be clean, clear, and potable. d. Sealer: Sealer shall be penetrating type, free from harmful alkali or content. The

sealer shall not discolor the pebbles nor leave a tacky or sticky finish on the surface after buffing.

e. Sand ASTM C33 for line aggregate:

f. Transparent Waterproofing: Vinyl acrylic emulsion paint. Supralux LX-33 is an emulsified paint that produces a durable weather resistant decorative paint with good exterior and interior color retention. Meet or exceed Federal Specs TTP-295 & TT-P-19D.

Page 18: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss GGrraavveell WWaasshhoouutt FFiinniisshh

2 of 3

2.2 GRAVEL WASHOUT MIXES

Gravel topping shall be composed of 90.7 kilos of gravel per 44.6 kilos bag of Portland cement. Thoroughly mix dry ingredients before adding water in the amount of 18.925 liters per bag of cement.

PART 3 - EXECUTION 3.1 PREPARATION a. Concrete Surfaces: Clean concrete surfaces of all foreign matter. Saturate

cleaned surfaces with water and after removing excess water, slush with a coating of neat cement immediately ahead of placing under-head.

b. Under-head: One part Portland cement, and 4 – ½ parts sand by volume with

sufficient water to produce workability, spread to a level of 12 mm approximately 30 mm. Vertical surfaces shall have 30 mm under-head.

3.2 INSTALLATION OF GRAVEL WASHOUT Apply washout pebbles with the colors indicated on the drawings. a. Placing: Thoroughly moisten, but do not saturate the under-head and slush with

neat cement of the same type as that used for topping. Apply washout pebble uniformity over the surface. The quantity used shall be not less than one quarter per square foot area. Pebbles shall be thoroughly dampened before spreading and shall be tamped flush with the surfaces using a steel trowel, care shall be taken not to completely bury the particles; pebbles shall be worked into a level and uniform surfaces. The compacted topping shall be not less than 16 mm thick.

b. Curing: Keep the completed washout pebble moist and free of traffic during a 6-

day period. Cure by covering with liquid membrane –forming compound, covering with sheet materials, or sprinkling with water.

c. Brushing: Following the curing period wire brush or rubbed with an abrasive

brick and water sufficiently to bare slightly the washout pebbles. 3.3 CLEANING AND SEALING Wash gravel finish surfaces with water to remove stains or cement smears. Rinsed the

cleaned surfaces when thoroughly dry, apply a sealer as buff, in accordance with the manufacturer’s direction.

3.4 FINISHING Finish wall surfaces with two coats of natural color, elastomeric type waterproofing

compound. Waterproofing compound shall be as specified under section entitled “Membrane Waterproofing”.

3.5 PROTECTION

Cover and protect washout pebble finish work from damage until completion of the work of all other trades.

Page 19: SECTION 09605 - VINYL FLOORING

BBiiccooll IInntteerrnnaattiioonnaall AAiirrppoorrtt DDeevveellooppmmeenntt PPrroojjeecctt DDiivviissiioonn 99 –– FFiinniisshheess

SSeeccttiioonn VVII-- TTeecchhnniiccaall SSppeecciiffiiccaattiioonnss GGrraavveell WWaasshhoouutt FFiinniisshh

3 of 3

4.0 METHOD OF MEASUREMENT

Gravel Washout Finish shall be measured by the number of square meter laid and accepted.

5.0 BASIS OF PAYMENT

The accepted quantity measured as prescribed in Method of Measurement shall be paid for at the contract unit price for Gravel Washout Finish which price and payment shall be full compensation for furnishing and placing all materials, including labor, equipment, tools and incidentals necessary to complete the work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 20: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes Section VI- Technical Specifications Floor Hardener

1 of 2

SECTION 09614 - FLOOR HARDENER PART 1 - GENERAL 1.1 SCOPE

Furnish all labor and materials to complete finish work indicated, as specified herein.

1.2 GENERAL REQUIREMENTS

Deliver hardener in bags or bulks for the building site with the label intact and seals unbroken, subject to inspection by the Owner’s Representative before being opened.

1.3 SUBMITTALS

1.3.1 Catalog cuts 1.3.2 Samples: 300 mm square panel of each type of finish

PART 2 - PRODUCTS

2.1 MATERIALS

Provide materials conforming to specifications and the requirement specified.

2.1.1 Portland Cement

Available brand in the local market in conformity with ASTM requirements.

2.1.2 Heavy Traffic Floor Hardener

Powder composed of Non-Metallic aggregate, permanent coloring media, dispersing agents, and binding elements.

2.1.3 Hardener finish color shall be ‘Natural Gray’, or as selected by the Owner or Architect /

Engineer. PART 3 - EXECUTION 3.1 APPLICATION

Monolithic Method: The hardener shall be applied into the fresh concrete hardener substrate. The surface is finished the same day slab is poured in place.

3.2 Basis of Payment

The quantity measured as prescribed in Method of Measurement shall be paid for at the contract unit price per square meter of Floor Hardener which price and payment shall constitute full compensation for furnishing and placing all materials and for all labor, equipment, tools and incidentals to complete work prescribed in this Section.

Page 21: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes Section VI- Technical Specifications Floor Hardener

2 of 2

4.0 METHOD OF MEASUREMENT Floor hardener shall be measured by actual area installed in square meters and accepted to the satisfaction of the Architect / Engineer.

5.0 BASIS OF PAYMENT

The quantity measured as prescribed in Method of Measurement shall be paid for at the contract unit price per square meter of Floor Hardener which price and payment shall constitute full compensation for furnishing and placing all materials and for all labor, equipment, tools and incidentals to complete work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 22: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

1 of 7

SECTION 09615 - ACCESS FLOORING (RAISED FLOOR)

PART 1 - GENERAL

1.1 SCOPE

This specification covers the furnishing of materials and labor necessary to complete the

installation of raised access flooring as shown in drawings and as specified herein.

1.2 SPECIAL REQUIREMENTS

1.2.1 Pre-Construction Conference:

Before beginning access flooring installation, conduct a conference at the project site with

access flooring manufacturer, installer, and other parties as designated by the Contractor or

review procedures, schedules and coordination of the access flooring installation with other

elements of the work.

1.2.2 Regulatory Requirements:

Comply with the applicable requirements of the laws, codes, ordinances, and regulations with

the Municipal Authorities having jurisdiction. Obtain necessary approvals from such

authorities.

1.3 SYSTEM DESCRIPTION

1.3.1 Performance Description:

Provide access flooring to comply with performance requirements as specified.

1.3.2 The access flooring shall meet the following requirements:

a. The access floor system shall be stringerless and shall incorporate fastened floor

panels and/or enlarged floor pedestals to increase lateral resistance.

b. Perforations within the floor shall have eased or radiused leading edges to prevent

bootie shredding.

c. Flow resistance shall be 0.4 inch wg at an entrance velocity of 100 fpm or 400 cfm

per 24 inch x 24 inch panel.

d. Design load shall be 250 lbs per square foot minimum.

e. Floor modules to fall inside of wall finished face to allow removal of panels. Walls not

allowed to be mounted on access floors.

f. Floor shall be isolated from the adjacent perimeter walls.

1.3.3 Design Criteria:

a. Floor Panels to conform to the following:

1. Size: 24 inch x 24 inch

2. Concentrated Load: 1000lbs on 1 square inch at any location on the panel

with a maximum top surface deflection of 0.080 inches.

Page 23: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

2 of 7

3. Permanent Deformation: Not to exceed 0.010 inches

4. Uniform Load: 250 lbs per square foot with a maximum deflection of 0.40

inches.

5. Rolling Load: 1000 lbs. (CISCA test procedure) with a permanent set of less

than 0.020 inches after 10,000 passes of load on a 6 inch diameter x 1.50

inch wide wheel.

6. Impact Load: To withstand an impact load of 80 lbs., when dropped from 12

inches onto a 1 square inch area located anywhere on the panel.

7. Ultimate Strength: Not less than 2.0 times design load.

b. Pedestals

1. Minimum axial load of 5,000 lbs without permanent deformation.

2. Pedestal base shall withstand minimum overturning moment of 1,000 inch-

pounds. Indicate with bid if mechanical fastening of pedestals will be

required. Coordinate with manufacturer.

3. Length: as shown on drawings.

c. Lateral Stability of Understructure

Design system to meet Seismic Zone 3 conditions as defined by the applicable

building code.

1.4 QUALITY ASSURANCE

1.4.1 Contractor’s Quality Assurance Responsibilities

The Contractor is solely responsible for quality control of the work.

1.4.2 Manufacturer’s Qualification:

Manufacturer shall have been engaged in the fabrication of access flooring of types and sizes

required and whose products have been in satisfactory use in similar service for not less than

10 years. Like items of material provided herein, shall be the products of one manufacturer in

order to achieve standardization for appearance, maintenance and replacement.

1.4.3 Installer

Access flooring installer shall be trained, approved by the floor system manufacturer and shall

have successfully completed within the last three years, at least three installations similar in

type and size to that of this project.

1.4.4 Field Samples

Provide a simple sample of access flooring, not less than 10 sq. feet in an area designated by

the Contractor. Utilize the same materials and installation methods in the sample as required

for the final work. Schedule the installation so that the sample may be examined and any

necessary adjustments made, at least 1 week prior to date scheduled for commencing

installation of the work. When accepted, sample areas shall serve as the standard for

materials, workmanship and appearance for such work throughout the project and shall

remain a part of the final work.

Page 24: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

3 of 7

1.4.5 Pre-installation Meeting

Prior to installation of the access flooring system, and at Project Manager’s direction, a

meeting shall be held to discuss alternates, project procedures, installation and

coordination of the work with outer trades. Meeting shall include Owner, Engineer, Project

Manager, Contractor, access flooring system Contractor, and component manufacturer’s

representative, and other subcontractors whose work requires coordination with the

access flooring system.

1.5 DELIVERY, STORAGE AND HANDLING

a. Materials shall be protected from weather, soil, and damage during delivery,

storage, and construction. Do not open packaging nor remove labels until time

for installation.

b. Materials shall be delivered in the original unopened packages, containers or

bundles bearing the brand name and the name of the material.

1.6 SUBMITTALS

1.6.1 Samples

Furnish two sets of samples for each type of access floor panel and pedestal. Label

samples to indicate product characteristics and locations in the work. Samples shall be

reviewed for color, range and appearance.

1.6.2 Shop Drawings

Drawings shall show layout of work, sections and details of access floor adjacent to

vertical surfaces, sizes and details of all components, location of grounding conductors

and grounding points, location of different type of panels, horizontal and diagonal

bracing, cut-out details and locations, panel surfacing material and method of installation.

1.6.3 Test Reports

Provide test reports from a qualified independent testing laboratory that show compliance

of the access flooring with performance requirements indicated based on comprehensive

testing of the system by the laboratory within the last three years.

1.6.4 Statement of Manufacturer’s Review

Furnish statement signed by the Installer and Manufacturer, stating that the Contract

Documents have been reviewed with qualified representatives of the materials

manufacturers, and that they are in agreement that the selected materials and systems

are proper and adequate for the application shown including compatibility with adjacent

systems and materials.

PART 2 - PRODUCTS

2.1 MATERIALS

2.1.1 Floor System:

a. Fabrication Drawings shall be submitted for elevated floor systems consisting of

fabrication and assembly details to be performed in the factory.

Page 25: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

4 of 7

b. Location Drawings shall show location of pedestals, ventilation openings, cable

cutouts, and the panel installation pattern.

c. Detail Drawings shall show details of the pedestals, pedestal-floor interlocks,

floor panels, panel edging, floor openings, floor opening edging, floor registers,

floor grilles, cable cutout treatment, perimeter base, expansion joints, and

peripheral support facilities.

d. Design and workmanship shall be such that the floor, as installed, shall be

completely planar within plus or minus 0.060 inch in 10 feet, 0.100 inch 1.5

millimeter in 3050 millimeter, 2.5 millimeter for the entire floor, and 0.030 inch

0.7 millimeter across panel joints.

e. Floor-panel joint-width tolerances shall be 0.008 inch 0.20 millimeter as

measured with a feeler gage at any point in any joint when the panels are in the

pressure contact required in final installation. System assembly shall be based

upon an interference fit of connections.

2.1.2 Floor Panels:

a. Floor panels shall be modular and completely interchangeable with other standard

floor panels. Panels shall be easily placed and removed without disturbing

adjacent panels or understructure by one person using a portable lifting device.

b. Nominal Panel size: 600 mm x 600 mm (24” x 24”)

c. Fabrication Tolerances:

Panels shall be edged-machine after casting to a tolerance of plus minus 0.005

inches and square to a tolerance of plus or minus 0.015 inches measured on the

diagonal.

d. Material

Shall consist of 24” x 24” steel top sheet welded to a formed steel bottom pan and

a painted finish.

2.1.3 Floor Panel Finish

a. Finish shall be high-pressure laminate vinyl tile.

b. Colors and Pattern: Submit available color pattern for Architect’s approval.

2.1.4 Perimeter Steel Angle

a. Manufacturer shall field install a continuous electroless nickel-plated steel angle at

perimeter of the recessed concrete slab opening where indicated on the drawings.

The angle shall be installed level above the existing concrete subfloor to align with

top access floor panels, floor tile and chemical resistant coating surfaces.

b. Existing or new concrete subfloor surfaces shall be prepared by leveling

irregularities in the surface to maximum flatness tolerance requested by

manufacturer.

Page 26: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

5 of 7

2.1.5 Accessories

2.2.1 Cutouts

Fabricate manufacturer’s standard cutout assemblies in floor panels as required or as

indicated on the drawings. Comply with requirements indicated for size, shape, number,

and location. Provide reinforcement or additional support if needed, to make panels with

cutouts comply with standard performance requirements. Fabricate cutouts in floor panels

to accommodate cable, pipe and/or duct penetrations, if any. Use manufacturer’s standard

grommet where applicable.

PART 3 - EXECUTION

3.1 EXAMINATION

a. Examine subfloor and report all defects, which would prevent proper installation of

access flooring. Do not proceed with work until all defects have been corrected.

b. Prior to installation take field measurements to ensure proper fitting of work. If there

are discrepancies with previously submitted shop drawings, revise to indicate final

measurement and resubmit drawings for final approval.

3.2 PREPARATION

a. Locate each pedestal and complete any necessary subfloor preparation. Vacuum

clean the subfloor of all dust, dirt and construction debris before stating installation.

b. Perform pre-installation pedestal adhesive field test. See Section 3.4 for test

procedure.

3.3 INSTALLATION

a. Install access floor system and accessories under supervision of the access flooring

manufacturer’s authorized representatives to ensure rigid, firm installation free of

rocking, rattles, squeaks, and other unacceptable performance.

b. Secure pedestal bases with adhesive as recommended by the access flooring

manufacturer to provide full bearing of the pedestal base on the subfloor.

c. Floor panels shall be installed according to the layout indicated on the drawings to

keep the number of cut panels at the floor perimeter to a minimum.

d. Thoroughly clean up dust, dirt and construction debris caused by floor installation,

including vacuuming the subfloor area, as installation of floor panels proceeds.

Extend cleaning under installed panels.

e. Cutting and Trimming of Parts: Cutting and trimming or other dirt-or-debris-producing

operations will not be permitted in the areas where the floor is being installed.

Perform cutting and trimming or other dirt-or-debris-producing operations as remotely

as possible from installation area and in manner to prevent contamination of subfloor

surfaces, which already have been installed.

3.2 FIELD QUALITY CONTROL

a. Pre-installation Adhesive Subfloor Field Test: Prior to proceeding with installation of

pedestals, field test their adhesion to subfloor surfaces as follows:

1. In areas representative of each subfloor surface condition, set typical

Page 27: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

6 of 7

pedestal assemblies in same adhesive and methods required for completed

work.

2. Allow test installation to cure for 14 days, with a pressure of 25 lbs. applied

vertically to pedestals during this period.

3. After curing, apply lateral loads against a straight steel extension bar

inserted 2 inches into pedestal stems. Measure with spring scale the force

needed to cause adhesive failure between pedestal base and subfloor.

4. Do not proceed with installation until tests evidence complied with the

indicated requirements for pedestal’s capability to resist overturning bending

movement.

b. Provide an overall floor which is level (within 1/16 of an inch in 10 feet).

c. Install floor system and accessories under supervision of the manufacturer’s

authorized representatives to ensure rigid, firm installation free rocking, rattles,

squeaks and other unacceptable performance.

d. Only new access floor system components shall be installed on this project.

e. Contractor’s Quality Assurance Responsibilities: The Contractor is solely responsible

for quality control of work.

3.2.1 Fabricator’s Qualifications

Firms shall be engaged in the fabrication of access flooring of types and sizes required, and

whose product have been in satisfactory use in similar service for not less than 10 years.

3.2.2 Erector’s Qualifications

Firms shall have at least 5 years of successful; installation/erection experience with projects

utilizing access flooring similar to that required for this project.

3.3 Project Conditions

3.3.1 Field Measurements

Take measurements before fabrication; show recorded measurements on final shop

drawings. Notify Project Manager in writing of dimensions found to be different than shown,

including specified tolerances. Use established benchmarks as basis of measurements.

3.4 Maintenance

3.4.1 Maintenance Manuals

Furnish complete manuals describing the materials, devices, and procedures to be followed

in cleaning and maintaining the work. Include manufacturer’s brochures and parts lists

describing the actual materials used in the work, including metal alloys, finishes, glass,

sealants, gaskets, and other major components. Assemble manuals for component parts into

single binders identified for each system.

3.5 Cleaning And Protection

3.5.1 Upon completion of the work, repair surfaces that have been permanently stained, marred, or

otherwise damaged. Replace work, which is damaged or cannot be adequately cleaned as

directed. Remove unused materials, debris, containers, and equipment from the project site.

Page 28: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Access Flooring (Raised Floor)

7 of 7

In addition to the initial cleaning procedure required, and before acceptance by the Owner,

clean the work as recommended by the manufacturer. After completion of installation,

vacuum cleans the entire floor.

3.5.2 Protect the work during the construction period so that it will be without any indication of use

or damage at the time of acceptance.

4.0 METHOD OF MEASUREMENT

Access flooring shall be measured by the number of square meter installed and accepted.

5.0 BASIS OF PAYMENT

The quantity measured as prescribed in Method of Measurement shall be paid for at the

contract unit price per square meter of Access Flooring which price and payment shall

constitute full compensation for furnishing and placing all materials and for all labor,

equipment, tools and incidentals to complete work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 29: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes Section VI- Technical Specifications Vinyl Coated Wall Covering

1 of 4

SECTION 09702 - VINYL COATED WALL COVERING

PART 1 - GENERAL

1.1 SCOPE

Furnish all labor, materials, equipment and other facilities to complete the installation of vinyl fabric wall covering as shown on drawings and herein after specified.

1.2 APPLICABLE PUBLICATIONS

a. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.

b. Chemical Fabrics and Film Association, Inc., (CFFA)

Document #6 Vinyl Coated Fabric Wall covering

c. American Society for Testing and Materials (ASTM)

G21-96 Determining Resistance of Synthetic Polymeric Materials to Fungi

1.3 SUBMITTALS 1.3.1 Samples

a. One sample of each type, pattern, and color required. Samples shall be of

sufficient to show complete pattern.

b. Cap molding: One 305 mm long piece of each type used.

c. Corner guard: One 305 mm long piece.

1.3.2 Manufacturer's Certificates

Wall covering manufacturer's approval of adhesive. 1.3.3 Manufacturer's Literature and Data

a. Primer and adhesive. b. Installation instructions. c. Maintenance instructions, including recommended materials and methods for

maintaining wall covering with precautions in use of cleaning material.

1.4 DELIVERY AND STORAGE

Deliver the material to the site in manufacturer’s original wrappings and packages and clearly labeled information. Store in a safe, dry, clean, and well-ventilated area at temperatures not less than 50 degrees F and within a relative humidity range of 30 to 60 percent. Store all covering material in a flat position and protect from damage, soiling, and moisture. Do not open containers until needed for installation, unless verification inspection is required.

PART 2 - PRODUCTS

2.1 VINYL COATED FABRIC WALL COVERING

2.1.1 Wall covering Medium Duty

Page 30: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes Section VI- Technical Specifications Vinyl Coated Wall Covering

2 of 4

2.1.2 Fungi Resistance

ASTM G21, rating of 0.

2.1.3 Factory-applied clear delustered polyvinyl-fluoride (PVF) coating:

1. Minimum 0.0125 mm (1/2 mil) thickness. 2. Do not include PVF coating weight in minimum total coating weight.

3. Fire hazard classification with PVF coating: Class A unless specified otherwise.

2.1.4 Primer, Sealer and Adhesive Shall be mildew resistant, non-staining to the wearing surface, and of the type supplied or

recommended by the wall covering manufacturer.

2.1.5 Cap Molding: As indicated.

2.1.6 Corner Guard

Shall be clear acrylic plastic angle with 29 mm legs, 1.2 m long surface mounted.

PART 3 - EXECUTION

3.1 JOB CONDITIONS

3.1.1 Temperatures

Do not perform work until surfaces and materials have been maintained at minimum of 60

F for three days before work begins. Maintain minimum temperatures of 60 F until adhesives are dried or cured.

3.1.2 Lighting

Do not proceed unless a minimum lighting level of 15 candlepower per square foot occurs. Measure light level at mid-height of wall.

3.1.3 Ventilation

Provide uniform continuous ventilation in space. Ventilate for a time for not less than complete drying or curing of adhesive.

a. Protect other surfaces from damage which may be caused by this work.

b. Remove waste from building daily.

3.2 SURFACE CONDITION / PREPARATION

Inspect surfaces to receive wall coverings to assure that; patches and repairs are completed, surfaces are clean, smooth and prime painted. Do not proceed until discovered defects have been corrected by other trades and surfaces are ready to receive wall covering. Carefully remove electrical outlet and switch plates, mechanical diffusers, escutcheons, registers, surface hardware, fittings and fastenings, prior to starting work. Carefully store items for reinstallation. Fill cracks, crevices and holes with compound recommended by the wall covering manufacturers. Sand rough spots smooth and remove residual powder using a damp cloth. Surfaces to be covered shall be thoroughly dry. Prime

Page 31: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes Section VI- Technical Specifications Vinyl Coated Wall Covering

3 of 4

and seal surfaces to be covered, in accordance with wall covering manufacturer’s printed instructions.

3.3 APPLICATION OF ADHESIVE

Mix and apply adhesives in accordance with manufacturer's directions. Prevent adhesive from getting on face of wall covering. Apply adhesive to wall covering back.

3.4 WALL COVERING INSTALLATION

a. The substrate and conditions: Use wall covering of same batch or run in an area.

Use fabric rolls in consecutive numerical sequence of manufacture. b. Install material completely adhered, smooth, and clean, without wrinkles, air

pockets, gaps or overlaps. c. Extend wall covering continuous behind non-built-in casework and other items

which are close to but not bolted to or touching the walls. d. Install wall covering before installation of resilient base. Extend wall covering not

more than 6 mm (1/4 inch) below top of resilient base. e. Install panels consecutively in order in which they are cut from the roll including

filling spaces above or below windows, doors, or similar penetrations. f. Do not install horizontal seams. g. Except on match patterns, hang fabric by reversing alternate strips, except as

recommended by the manufacturer.

h. Cutting:

(1) Cut on a work table with a straight edge. (2) Joints or seams that are not cut clean are unacceptable. (3) Trim additional selvage to achieve a color and pattern match at seams. (4) Do not double cut seams on wall unless specified. (5) If double cutting on the wall is necessary, place a three inch strip of Type I

wall covering under pasted edge. (i) Do not cut into wall surface. (ii) After cutting, remove strip and excess adhesive from seam before

proceeding to next seam. (iii) Smooth down seam in adhesive for tight bond and joint.

i. Trim strip-matched patterns, which are not factory pre-trimmed.

j. Inside Corners

(1) Wrap wall covering around corner. (2) Do not seam within 50 mm (2 inches) of inside corners. (3) Double cut seam.

Page 32: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes Section VI- Technical Specifications Vinyl Coated Wall Covering

4 of 4

k. Outside Corners

(1) Wrap wall covering around corner. (2) Do not seam within 150 mm (6 inches) of outside corners. (3) Double cut seam.

3.5 PATCHING

a. Replace surface damaged wall covering in a space as specified for new work.

(1) Replace full height of surface. (2) Replace from break in plane to break in plane when same batch or run is

not used. Double cut seams. (3) Adjoining differential colors from separate batches or runs are not

acceptable.

b. Correct loose or raised seams with adhesives to lay flat with tight bonded joint as specified for new work.

3.6 CLEANING AND INSTALLING TEMPORARY REMOVED ITEMS

a. Remove adhesive from wall covering as work proceeds.

b. Remove adhesives where spilled, splashed or splattered on wall coverings or adjacent surfaces in a manner not to damage surface from which it is removed.

c. Reinstall previously removed electrical outlet and switch plates, mechanical

diffusers, escutcheons, registers, surface hardware, fittings and fastenings.

4.0 METHOD OF MEASUREMENT

Vinyl wall covering shall be measured by the number of square meters installed and accepted.

5.0 BASIS OF PAYMENT

The quantity measured as provided in Method of Measurement shall be paid for at the contract unit price per square meter of Vinyl Wall Covering which price and payment shall constitute full compensation for furnishing and placing all materials and for all labor, equipment, tools and incidentals to complete the work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 33: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Plastering

1 of 5

SECTION 09703 - PLASTERING

PART 1 - GENERAL

1.1 SCOPE

The work under this section of the specification covers the furnishing of materials including

equipment and performing labor necessary for the complete installation of plastering work as

shown on drawings and as specified herein.

1.2 GENERAL REQUIREMENTS

Portland-cement plaster as included herein shall be applied as specified hereinafter to those

areas indicated in the finish schedule. Plaster may be applied directly to interior masonry walls.

1.3 DELIVERY AND STORAGE

Deliver manufactured materials in the manufacturer’s original unbroken packages or containers

that are labeled plainly with the manufacturer’s names and brands. Keep cementitious materials

dry and stored off the ground, under cover, and away from sweating walls and other damp

surfaces until ready to be used.

1.4 ENVIRONMENTAL CONDITIONS

1.4.1 Portland Cement Plaster

Maintain an ambient temperature of not less than 27 degrees C continuously where plastering

work will be done. Maintain this temperature for not less than 48 hours prior to the application of

plaster while the plastering is being done and during the curing operation.

1.4.2 Protection from Sun and Dry Winds

During the application of the finish coat, and for a period of 48 hours following the completion of

finish coat application for any given area, the surface of the plaster shall be protected from direct

sunlight and direct winds. Use of tarpaulins or other temporary means may be acceptable.

Moist curing shall be provided in accordance with paragraph 3.3, Portland Cement-Lime Plaster.

PART 2 - PRODUCTS

2.1 MATERIALS

Provide materials conforming to specifications and the requirements specified.

2.1.1 Portland Cement

ASTM C 150, gray Portland cement Type I.

2.1.2 Hydrated Lime

ASTM C206, Type S

2.1.3 Aggregates

Sand for Portland Cement Lime Plaster shall be ASTM C 144, except gradation of sand shall

conform to the following requirements.

Page 34: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Plastering

2 of 5

2.1.3.1 Sand Gradation for Basecoats:

Percentage Retained by weight (plus or minus 2 percent) on each sieve

Sieve Min Max

No. 4 0

No. 8 0 10

No. 16 10 40

No. 30 30 65

No. 50 70 90

No. 100 95 100

2.1.3.2 Sand for Finish Coats

Sand for finish coat shall be near white and shall be graded within the limits shown above for

basecoats, except that the sand shall pass the No. 8 sieve, and for smooth finish the sand shall

pass the No. 30 sieve.

2.1.3.3 Water

Clean, fresh, suitable for domestic consumption, and free of mineral and organic substances that

affect the hardening or durability of the plaster.

2.2 PROPORTIONING AND MIXING

Except where specified otherwise, materials are specified on a volume basis and shall be

measured in approved containers, which will ensure that the specified proportions will be

controlled and accurately maintained during the progress of the work. Measuring materials with

shovels "shovel count" will not be permitted. Ready-mix plasters shall be prepared for use by the

addition of water only.

2.2.1 Basecoat Proportions

2.2.1.1 Portland Cement-Lime Plaster Basecoats

Mix scratch coat in the proportion of one part by volume of Portland cement to not more than 3/4

part by volume of hydrated lime and not less than 2-1/2 nor more than 4 parts by volume of

damp loose sand. Mix brown coat in the proportion of one part by volume of Portland cement to

not more than 1/2 part by volume hydrated lime and not less than 3 nor more than 5 parts by

volume of damp loose sand. Workability shall govern the actual amount of lime and sand used

in the scratch and brown coats.

2.2.2 Finish Coat Proportions

2.2.2.1 Portland Cement-Lime Plaster Finish Coat

Mix finish in the proportion of one part by volume of Portland cement to not more than one part

by volume of hydrated lime, and not more than 4 parts by volume of damp loose sand.

Workability shall govern the actual amount of lime and sand used in the finish coat, within the

limits specified herein. Where smooth toweled finish is indicated, allow plaster to set up to the

extent that it does not flow ahead or under the trowel, yet has not solidified, then trowel the face

lightly to embed the granules. Do not over-trowel or burnish the surface.

Page 35: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Plastering

3 of 5

2.3 MIXING

Mix materials in approved mechanical mixers of the type in which the quantity of water can be

controlled accurately and uniformly, except that finish coats containing lime may be hand mixed.

While the mixer is in continuous operation, add approximately 90 percent of the estimated

quantity of water, half of the sand, all of the cementitious materials, and introduce the other

one-half of the sand into the mixer in that sequence and mix thoroughly with the remainder of the

water until the mixture is uniform in color and consistency. Avoid excessive mixing or agitation.

Discard plaster which has begun to set before it is used; re-tempering will not be permitted. Do

not use caked, or lumped materials. Empty mixers and mixing boxes after each batch is mixed,

and keep free of old plaster.

PART 3 - EXECUTION

3.1 PREPARATION OF SURFACES

Clean surfaces to which plaster is to be applied of all projections, dust, loose particles, grease,

bond breakers, and foreign matter. Do not apply plaster directly to (1) surfaces of masonry or

concrete that has been coated with bituminous compound or other waterproofing agents, or (2)

to surfaces that have been painted. Before plaster work is started, wet masonry and concrete

surfaces thoroughly with a fine fog spray of clean water to produce a uniformly moist condition.

Check metal grounds, corner beads, screeds, and other accessories carefully for alignment

before the work is started. Check expansion and control joints and supporting metal structures

to ensure that expansion and control joints can move unrestrained.

3.2 APPLICATION OF PLASTER

3.2.1 General

Plaster may be applied by hand or by machine. When a plastering machine is used the fluidity of

Portland cement-lime plaster shall be controlled to have a slump of not more than 63 mm when

tested using a 50 by 100 by 150 mm high slump cone. Subsequent to determining water content

to meet this slump, do not add additional water to the mix. Conduct the slump test according to

the following procedure:

a. Place cone on level, dry, non-absorptive base plate.

b. While holding cone firmly against base plate, fill cone with plaster taken directly from the

hose or nozzle of the plastering machine, tamping with metal rod during filling to release

air bubbles.

c. Screed off plaster level with top of cone. Remove cone by lifting it straight up with a slow

and smooth motion.

d. Place cone in a vertical position adjacent to freed plaster sample, using care not to jiggle

base plate.

e. Lay a straight edge across top of cone, again being careful not to vibrate cone. Measure

slump in inches from the bottom edge of the straightedge to the top of the slumped

plaster sample.

3.2.2 Workmanship

Apply plaster in three coats, except as follows:

a. Provide scratch coat. Apply base coats with sufficient pressure and plaster shall be

sufficiently plastic to provide a good bond to bases. Work base coats into screed at

Page 36: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Plastering

4 of 5

intervals of from 1.50 to 2.40 meters. Plaster shall not be continuous across expansion

and control joints occurring in walls, and partitions. Finish plasterwork level, plumb,

square, and true, within a tolerance of 3 mm in 2.40 meters, without waves, cracks,

blisters, pits, crazing, discoloration, projections, or other imperfections. Form plasterwork

carefully around angles and contours, and well up to screeds. Special care shall be

taken to prevent sagging and consequent dropping of applications. There shall be no

visible junction marks in finish coat where one day’s work adjoins another.

3.3 PORTLAND CEMENT – LIME PLASTER

Apply base coats with sufficient pressure to curl the keys around the back of metal lath or wire

fabric and to provide good bond on masonry or concrete bases.

3.3.1 Plaster except Scratch Coat for Ceramic Tile Backing

Apply in three coats to a thickness of not less than 16 mm. Apply the scratch coat not less than

6 mm thick, lightly score horizontally, and moist cure for not less than 24 hours. Apply the brown

coat after the scratch coat has been aged at least 24 hours in addition to the moist curing period.

Apply the brown coat to bring the base coat out to the screeds, compact and straighten to a true

surface with rod and Darby, and float to receive the finish coat. After the brown coat has been

moist cured for not less than 24 hours and aged at least than additional 5 days, apply the finish

coat to a thickness of not less than 3 mm. Where any previous coat has become dry, dampen

the surface evenly with water, prior to the application of the next coat. The finish coat for plaster

shall have a troweled finish. Moist cure plaster for 24 hours using a fine fog spray of water and

apply to the finish coat as frequently as required to prevent dry-out of the plaster. Do not

saturate the plaster to the point where free water stands on the surface. Prevent staining of the

finish coat. Provide moist curing.

3.3.2 Scratch Coat for Ceramic Tile and Marble Backing

Apply scratch coat and keep continuously damp for not less than 24 hours before tile is to be set.

Apply scratch coat in thickness indicated or as necessary to bring the face of the tile and marble

to the required plane, but not les than 6 mm from the face of the material it is being applied to

and with a level surface within a tolerance of 6 mm in 2.40 meters. Apply scratch coat after

substantial grounds, plugs, hangers and other electrical outlets, and other fixtures and fittings

have been installed that are to be secured to tiled and marbled surfaces. Apply scratch coat with

sufficient pressure to ensure a proper bond and key with the base and a proper base for the

setting bed. While the mortar is still plastic, cut the scratch coat with a trowel at internal vertical

angles to the depth of the coat and for the full height of the tile bed, score horizontally or cross-

scratch coats within one hour after mixing, and at no time shall the mortar be re-tempered.

Protect scratch coat and keep moist during curing period. A leveling coat of the same mix

specified for the scratch coat shall be applied over the scratch coat when the surface of the

scratch coat is not level within the specified tolerance or when a base coat thickness of more

than 19 mm is required. Scratch leveling coat and cure for not less than 24 hours.

3.4 PATCHING AND POINTING

Upon completion of the building, cut out and patch loose, cracked, damaged, or defective

plaster. Patching shall match existing work in texture, color and shall be finished flush with

plaster previously applied. Do pointing and patching of plaster work abutting or adjoining any

other finish work in a neat and workmanlike manner. Remove plaster droppings or spattering

from surfaces, in condition ready to receive paint or other finish. Remove protective covering

from floors and other surfaces, and rubbish and debris from the building.

Page 37: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Plastering

5 of 5

4.0 METHOD OF MEASUREMENT

All cement plaster finish shall be measured in square meters or part thereof for work actually

completed and accepted.

5.0 BASIS OF PAYMENT

The quantity measured as provided in Method of Measurement shall be paid for at the contract

unit price per square meter of Cement Plaster Finish which price and payment shall constitute

full compensation for furnishing and placing all materials and for all labor, equipment, tools and

incidentals to complete the work prescribed in this Section.

Payment will be made in accordance with the Bill of Quantities.

******

Page 38: SECTION 09605 - VINYL FLOORING

Bicol International Airport Development Project Division 9 – Finishes

Section VI- Technical Specifications Abuse Resistant Interior Veneer Plastering

1 of 2

SECTION 09704 - ABUSE RESISTANT INTERIOR VENEER PLASTERING

PART 1 GENERAL

1.1 SCOPE

The work under this section of the specification covers the furnishing of materials including

equipment and performing labor necessary for the complete installation of plastering work as

shown on drawings and as specified herein.

1.2 DELIVERY AND STORAGE

Deliver manufactured materials in the manufacturers' original unbroken packages or containers

that are labeled plainly with the manufacturers' names and brands. Bags should be stored in a

secure, indoor, dry space. It is important that bags maintain their seal and are free of puncture or

tear.

PART 2 PRODUCTS

2.1 PRODUCT DESCRIPTION

The interior veneer plaster is formulated for industrial strength and high abuse protection. The

product can be painted or stained and finished in a wide range of textures.

2.2 PERFORMANCE

a. Superior abrasion resistance compared to gypsum board products and conventional

gypsum plasters.

b. Class A fire rated noncombustible building material (ASTM E136)

c. Zero flame spread and smoke developed indexes (ASTM E84)

d. Exceeds USEPA, State of California and CHPS (Collaborative for High Performance

Schools) VOC emission and indoor air quality standards

e. Mold and mildew resistant

f. Complies with ASTM C587

2.3 COVERAGE

Each 50lb. bag covers approximately 1.2sq.m. To 3.7sq.m. At thickness ranging between 3/8”

and 1/8”. Product yields may vary due to water content and substrate conditions.

PART 3 - EXECUTION

3.1 PREPARATION OF SURFACES

Clean surfaces to which plaster is to be applied of all projections, dust, loose particles, grease,

bond breakers, and foreign matter. Do not apply plaster directly to (1) surfaces of masonry or

concrete that has been coated with bituminous compound or other waterproofing agents, or (2)

to surfaces that have been painted. Before plaster work is started, wet masonry and concrete

surfaces thoroughly with a fine fog spray of clean water to produce a uniformly moist condition.

Check metal grounds, corner beads, screeds, and other accessories carefully for alignment

before the work is started. Check expansion and control joints and supporting metal structures

to ensure that expansion and control joints can move unrestrained.