SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL...

43
01 06 10 - 1 SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS PART 1 GENERAL 1.1 Introduction The requirements of this section apply to, and are a component part of, each section of the specifications. 1.2 References A. The publications listed below form a part of this contract as required by law or as referenced: B. CODE OF FEDERAL REGULATIONS (CFR) 1. 29 CFR 1910 Occupational Safety and Health Standards 2. 29 CFR 1925 Safety and Health Standards for Federal Service Contracts 3. 29 CFR 1926 Safety and Health Regulations for Construction 4. 40 CFR Parts 1 - 1068 Protection of the Environment C. NASA/MSFC PUBLICATIONS 1. NPR 8715.1 NASA Safety and Health Handbook 2. NPR 8715.3 NASA General Safety Program Requirements 3. NASA-STD-8719.11 Safety Standard for Fire Protection 4. MPR 1040.3 MSFC Emergency Plan 5. MPD 1800.1 MSFC Smoking Policy 6. MPR 1800.1 Bloodborne Pathogens 7. MPD 1840.1 MSFC Environmental Health Program 8. MPR 1840.3 MSFC Hazardous Chemicals in Laboratories Protection Program 9. MPD 1860.1 Laser Safety 10. MPD 8500.1 MSFC Environmental Management Policy 11. MPR 8500.1 MSFC Environmental Management Program 12. MPR 8500.2 MSFC Environmental Management System Manual 13. MPR 8823.2 Pressure System Safety and Certification 14. MWI 3410.1 Personnel Certification Program 15. MWI 8540.2 Affirmative Procurement Program for Environmentally Preferable Products 16. MWI 8550.2 Storm Water Management 17. MWI 8550.3 Wastewater Compliance 18. MWI 8550.4 Air Emissions Compliance 19. MWI 8550.5 Chemical Management 20. MWI 8621.1 Mishap and Close Call Reporting and Investigation 21. MPR 8715.1 Marshall Safety, Health, and Environmental(SHE) Program 22. MWI 8715.9 Occupational Safety Requirements for MSFC Contractors 23. MWI 8715.10 Explosives, Propellant, and Pyrotechnics Program 24. MWI 8715.15 Operational Safety Assessment Program

Transcript of SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL...

Page 1: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 1

SECTION 01 06 10

GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS

PART 1 GENERAL

1.1 Introduction

The requirements of this section apply to, and are a component part

of, each section of the specifications.

1.2 References

A. The publications listed below form a part of this contract as required by law or as referenced: B. CODE OF FEDERAL REGULATIONS (CFR) 1. 29 CFR 1910 Occupational Safety and Health Standards 2. 29 CFR 1925 Safety and Health Standards for Federal Service Contracts 3. 29 CFR 1926 Safety and Health Regulations for Construction 4. 40 CFR Parts 1 - 1068 Protection of the Environment C. NASA/MSFC PUBLICATIONS 1. NPR 8715.1 NASA Safety and Health Handbook 2. NPR 8715.3 NASA General Safety Program Requirements 3. NASA-STD-8719.11 Safety Standard for Fire Protection 4. MPR 1040.3 MSFC Emergency Plan 5. MPD 1800.1 MSFC Smoking Policy 6. MPR 1800.1 Bloodborne Pathogens 7. MPD 1840.1 MSFC Environmental Health Program 8. MPR 1840.3 MSFC Hazardous Chemicals in Laboratories Protection Program 9. MPD 1860.1 Laser Safety 10. MPD 8500.1 MSFC Environmental Management Policy 11. MPR 8500.1 MSFC Environmental Management Program 12. MPR 8500.2 MSFC Environmental Management System Manual 13. MPR 8823.2 Pressure System Safety and Certification 14. MWI 3410.1 Personnel Certification Program 15. MWI 8540.2 Affirmative Procurement Program for Environmentally Preferable Products 16. MWI 8550.2 Storm Water Management 17. MWI 8550.3 Wastewater Compliance 18. MWI 8550.4 Air Emissions Compliance 19. MWI 8550.5 Chemical Management 20. MWI 8621.1 Mishap and Close Call Reporting and Investigation 21. MPR 8715.1 Marshall Safety, Health, and Environmental(SHE) Program 22. MWI 8715.9 Occupational Safety Requirements for MSFC Contractors 23. MWI 8715.10 Explosives, Propellant, and Pyrotechnics Program 24. MWI 8715.15 Operational Safety Assessment Program

Page 2: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 2

25. MWI 8715.16 Supervisor Safety, Health, and Environmental (SHE) Visits 26. AS60–OI-001 Emergencies 27. AS60–OI-005 Waste Management 28. AS60-OI-022 Automatic External Defibillators 29. AS60-OI-023 Radiation Safety Program 30. AS60-OI-024 Ergonomics Program 31. AS60-OI-026 Confined Space Entries 32. AS60-OI-027 Hearing Conservation Program 33. AS60-OI-028 Hazard Communication Program 34. AS60-OI-029 Respiratory Protection Program 35. AS60-OI-030 Asbestos Program 36. AS60-OI-xxx Non Ionizing Radiation 37. AS60-OI-034 Occupational Medicine 38. QD-MAF-001 Electrical Safety Program 39. QD-MAF-002 Lockout Tagout 40. QD-MAF-003 Hazardous Identification and Warning Systems 41. QD-MAF-004 Personal Protective Equipment (PPE) and Systems 42. QD-MAF-005 Fire Safety Program

D. National Fire Protection Association 1. NFPA 241 Construction, Alteration, and Demolition

Operations

1.3 Submittals

A. The following shall be submitted in sufficient detail to show full compliance with the contract documents.

1. Safety, Health and Environmental (SHE) Plan:

Contractor shall submit a SHE Plan to the MAF MSFOC Business Office for approval prior to start of work. The SHE Plan shall describe the contractor's methods of planning, implementing, and controlling industrial safety, occupational health and environmental requirements to assure compliance with the MAF SHE program over the duration of the contract. The contractor's SHE Plan shall include, as a minimum, the following:

(Note: A contractor signed SHE Work Agreement (SEE

APPENDIX A page 31) for Construction provided by the MSFOC MAF Business Office may be used in lieu of the contractor's SHE Plan when approved by NASA MAF Safety. If the contractor performs work under multiple contracts, the MSFOC MAF Business Office and NASA MAF Safety may request the contractor to submit a SHE Plan specific to a job in addition to a signed SHE Work Agreement for Construction)

a. Health and safety program objectives and description of the methods to attain the objectives as described in Section e. b. Responsibility of key personnel for the Contractor.

Page 3: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 3

c. Lists of key personnel to be contacted in times of emergency. d. List of applicable documents. e. Describe the methods for compliance with 29 CFR 1910,"Occupational Safety and Health Standards", 29 CFR 1926, "Safety and Health Regulations for Construction" and the MAF SHE Program." f. The MAF SH&E Program has five core program requirements (CPRs), each of which shall be addressed in the contractor's safety SHE Plan. The core program components are as follows:

1. Management leadership and employee involvement:

• A description of the contractor’s policy and management's commitment to (1) provide a safe and healthful workplace for personnel(i.e., employees, customers, and public), (2) protect the property and the environment, and (3) assure compliance with EPA,OSHA, NASA, MAF SHE Plan document requirements listed in paragraph 1.2C of this section that are applicable to this contracted effort.

• A description of the techniques

implemented by the contractor to assure management and employees are (1) held accountable and fully understand their roles and responsibilities to perform their jobs/tasks in a safe and healthful manner while protecting the environment and (2) how these roles and responsibilities are flowed-down to all subcontractors, when applicable.

• A description of the actions taken

or the disciplinary program implemented by the contractor when management or employees are discovered not performing their jobs/tasks in a safe and healthful manner or protecting the environment and how these actions are flowed-down to subcontractors, when applicable.

Page 4: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 4

• A description of the contractor's safety, health, environmental awareness programs that includes documented weekly safety meetings and safety awareness training for employees.

• A description of how self

evaluations of the contractor's safety, health and environmental program are performed and documented, and includes the frequency of these self evaluations.

• Provide the identification, by title, of the individual assigned by the contractor to be responsible for implementing the contractor's SHE program elements and will serve as the day-to-day SHE Point of Contact (POC) for this contracted effort.

• A description of how the SHE plan

is maintained current with the contract, NASA and MAF requirements, and updated as necessary.

2. System and worksite analysis:

• A description of how the contractor assures potentially hazardous conditions are identified in the work area and operations (e.g., Hazardous Operations Checklist (HOC), hazard analysis, safety assessment, risk assessment and employee identified concerns).

• A description of the interrelationship between the applicable MAF documented programs listed in paragraph 1.2C of this section and the OSHA programs that require documented program applicable to this contracted effort (e.g., Respiratory Protection, Hazard Communication, Confined Space, and Lockout/Tagout).

Page 5: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 5

• A description of how the contractor performs and documents weekly worksite safety inspections.

3. Hazard prevention and control:

• A description of how the contractor assures potentially hazardous conditions are controlled in the work area or in an operation. This can include the generation of plans, procedures, and other working documents that clearly identify the hazardous conditions and the necessary cautions taken to mitigate the hazards. (NOTE: NASA-MAF Safety concurrence is required for all onsite hazardous procedures and MAF requires these procedures and plans to be reviewed annually.)

• A description of how the contractor assures (1) the procurement, storage, issuance, and use of hazardous chemical and materials is in accordance with MPR 8500.1 and (2) the recycling and disposal of any hazardous waste generated under this contracted effort is in accordance with MWI 8550.1 (NOTE: This can be described in paragraph 5. environmental compliance if CPR 5. is applicable.)

• A description of the contractor's emergency management program and provide a list of contractor emergency points of contact located onsite.

• A description of how the contractor assures all mishaps and close calls are reported and investigated to the extent necessary to determine the root cause.

Page 6: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 6

• A description of how the contractor provides safety, health, and environmental services applicable to this contracted effort (e.g., hazardous waste disposal industrial hygiene monitoring, emergency medical support, hearing conservation program, respiratory protection, and hazard communication). (NOTE: Provide a list of all services that are to be provided by MAF for onsite work.)

• A description of how contractor employees are trained to and given the authority to suspend work where safety, health or environmental conditions warrant such action.

4. Safety, health and environmental training:

• A description of how each contractor employee is (1) trained to recognize hazards, (2) avoid accidents, (3) know the hazards specific to their job, and (4) fully understands the contractor's disciplinary program in accordance with 29 CFR 1926.1.

• A description of how contractor

employee training needs are determined that are specific to the job the employee is expected to perform in accordance with applicable parts of 29 CFR 1910 and 29 CFR 1926.

• A description of how the contractor

provides and documents training for employees that are designated as (1) competent, or (2) qualified, or (3) authorized, or (4) certified to perform operations and/or inspections that require job specific training and/or knowledge and experience in accordance with applicable parts of 29 CFR 1910 and 29 CFR 1926.

Page 7: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 7

[NOTE: This applies to job categories being performed onsite that do not require a MAF Safety Certification.]

• Provide a list of operations or job categories performed by the contractor that require a MAF Safety Certification under this contracted effort (NOTE: This is only applicable if the contractor will operate MAF owned equipment or perform processes that require MAF Safety Certification. If a MAF Safety Certification is required, it shall be tracked in the Certification Database (CERTRAK).

• A description of how the contractor will provide evidence of any required employee training (i.e. PPE, personal fall arrest systems, confined space entries, operate cranes/material handling equipment, welding and cutting) in accordance with the applicable parts of 29 CFR 1910 and 29 CFR 1926.

5. Environmental compliance - A description of how the contractor assures compliance with environmental laws and regulations CFR Title 40 Parts 1 - 1068,Louisiana Department of Environmental Quality (LADEQ)under this contracted effort by:

• Reporting hazardous and toxic

substance use in accordance with MWI 8550.5 Implementing and reporting green procurements in accordance with MWI 8540.2

• Reducing, reusing, and recycling of hazardous and toxic substances prior to disposal in accordance with MWI 8550.1

• Minimizing storm-water pollution in accordance with MWI 8550.2

Page 8: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 8

• Ensuring equipment and processes permitted by applicable laws in accordance with MWI 8550.4 Disposing of solid and liquid materials as permitted by applicable laws in accordance with MWI 8550.1

g. Describe the procedures for securing the accident site so that the area remains secure until arrival of security officer and/or a safety investigator. The accident site shall remain secured until released by NASA-MAF Safety or his designee.

h. Describe the process to ensure structures,

utilities,pavements, and other facilities immediately adjacent to excavations are protected against damage.

i. Control of Hazardous Energy, Lockout/Tagout System (29 CFR 1910.147, 29 CFR 1926.417, and QD - MAF – 002 Lockout Tagout). Only locks with a red case and tags with red diagonal strips containing the word "lockout" are to be used for lockout/tagout during construction, maintenance and servicing activities. All construction employees authorized to perform Lockout/Tagout activities at MAF are required to attend and complete the MAF Lockout/Tagout Awareness Training. Contact FMO or NASA-MAF Safety for more information. NOTE: Work on energized equipment shall only be allowed under special situations and shall be reviewed by NASA MAF Safety prior to any work.

j. Hazard Communication (29 CFR 1910.1200 and AS60

- OI- 028 Hazard Communication Program). During the Pre-Construction Conference, to be arranged by the MAF MSFOC Business Office, NASA-MAF Safety Office may discuss common safety and health requirements at MAF and distribute handouts addressing these requirements.

k. Fall Protection. If under this contracted

effort the work will be performed on elevated surfaces, the contractor shall describe in detail the methods to ensure a proper fall protection system (guard rails, personal fall arrest system, or safety net) is provided in accordance with 29 CFR 1926.501 and 29 CFR 1926.502. If a conventional fall protection system cannot be provided, a Site Specific Fall Protection Plan shall be provided in accordance with 29 CFR 1926.502(k) and QD MAF 004 Personal Protective Equipment (PPE) and Systems.

Page 9: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 9

B. Reports

In addition to documentation and reports required elsewhere in this section, the following reports shall also be submitted:

1. Monthly Report: The Contractor shall complete each month MSFC Form 4371, MSFC Contractor Accident and Safety Statistics, and submit to the responsible Construction Engineer by the 15th day of the month following the report month. The form shall be complete and accurate in every detail.

2. General: a) Safety meetings and training shall be documented and retained at the construction site. Safety meeting sign-in sheets and a general description of the items covered shall be submitted to the responsible Construction Engineer. b) All job hazard analyses (JHA's) and Hazardous Operations Checklists (HOC's) shall be in writing and communicated to all affected workers. c) All safety, health, and environmental related documents (plans, forms, reports, supervisor safety visits, inspections, correspondence, JHA's MSDS, logs, certifications, etc.) shall be retained in an orderly fashion at the construction site and readily available for review. 3. MSFOC MAF SHE 101 Construction Awareness training will be conducted for the contractor supervisors prior to initiation of work. The contractor shall then provide this training to all contractor employees that will be working onsite prior to any work performed by the employees. It is recommended that this training be provided during a weekly safety meeting. A signed attendance sheet of employees attending this training shall be provided to MSFOC MAF Safety as a record of this training being completed.

1.4

General Safety Provisions

A. Contractor is subject to applicable federal, state, and local laws, regulations, ordinances, codes, and orders relating to safety and health in effect on the date of this Contract.

B. During the performance of work under this Contract, the

Contractor is responsible for control and safety of persons working on and visiting the project site. Contractor is responsible for ensuring his and his subcontractors' compliance with the safety requirements. Contractor shall advise the responsible Jacobs Construction Engineer of any special safety restriction he has established so that Government personnel can be notified of these restrictions.

C. For any operation or task identified in 29 CFR 1910 or 29 CFR

1926 that references a "competent" person, the contractor shall identify that person(s) by name and he/she shall be on the project site during such operation.

Page 10: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 10

1.5

LOCKOUT/TAGOUT FOR HAZARDOUS ENERGY

A. Contractor shall comply with the MSFOC MAF lockout/tagout program (QD-MAF–002 Lockout Tagout), when working at MAF, to control hazardous energy. Only employees that have been trained in the proper use of Lockout/tagout devices shall be authorized to place lockout/tagout devices. The employees shall attend the MAF Lockout/Tagout Awareness Training. B. Working on energized equipment at MAF is prohibited and allowed only in special situations when reviewed by NASA MAF Safety. The work shall be performed by employee trained in accordance with the requirements in 29 CFR 1910.331 - 335 (Subpart S). In these special situations the contractor shall provide documentation of this training when requested by NASA- MAF Safety.

1.6 ACCIDENT TREATMENT AND RECORDS

A. Contractor shall post emergency first aid and ambulance information at project site. B. Contractor employees may utilize government dispensary facilities located in Building 320 only for injury and emergency medical treatment. Contact Medical (telephone 504-257-2701). C. Contractor shall report all mishaps in accordance with the procedures described in MWI 8621.1, "Mishap and Close call Reporting and Investigation Program."

1.7

FIRE PREVENTION AND PROTECTION

A. Open-flame heating devices will not be permitted except by approval in writing from NASA-MAF Safety or designee. Approval for the use of open fires and open-flame heating devices will not relieve the Contractor from the responsibility for any damage incurred because of fires. B. Burn Permits are issued by the CIS Fire Department. Details for requesting burn permits will be provided during the Pre- Construction Conference. C. Burning trash, brush, or wood on the project site shall not be permitted.

1.8

USE OF EXPLOSIVES

A. Explosives shall not be permitted on Government Property unless authorized by NASA-MAF Safety.

1.9

ELECTRICAL

A. Contractor shall appoint a competent employee familiar with the safety requirements in 29 CFR 1926. 400 - 449 (Subpart K) to be responsible for the electrical safety of the contracted effort and to restrict entry to dangerous locations to only those authorized by NASA-MAF Safety.

Page 11: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 11

1.10

CONFINED SPACE ENTRY

A. Safety clearance from NASA-MAF Safety is required before personnel are allowed to enter a confined space at MAF. Confined Space Entry shall be performed in accordance with AS60-OI-026 Confined Space Entries and 29 CFR 1910.146. Contractor shall contact NASA-MAF Safety for support services at least 24 hours in advance. B. Contractor shall be responsible for removing water and debris before commencement and during execution of work in manholes. C. Contractor shall have one or more employees properly trained in operation of gas testing equipment and formally qualified as gas inspectors who shall be on duty during times contractors are in confined spaces in accordance with 29 CFR 1910.146(g)&(i). Their primary functions shall be to test for gas and operate testing equipment. Unless equipment of constant supervisory type with automatic alarm is employed, gas tests shall be made at least every 2 hours or more often when character of ground or experience indicates gas may be encountered. A gas test shall be made before contractors are permitted to enter the excavation after an idle period exceeding one-half hour.

D. Special requirements, coordination, and precautions will apply to areas that contain a hazardous atmosphere or, by virtue of their use or physical character may be oxygen deficient. A check by NASA-MAF Safety is required prior to entering confined space. Surveillance and monitoring shall be required in these types of work spaces by both Contractor and NASA-MAF Safety personnel.

1.11

RADIATION SAFETY REQUIREMENTS

A. The Contractor shall comply with 29 CFR1926.53 and AS60 OI-023 Radiation Safety Program for use of all radioactive material. The Contractor shall notify the NASA-MAF Safety Radiation Safety Officer (RSO) at least 48 hours in advance of any planned radiography. However, if planned during a weekend, notice shall be provided by Thursday. The Contractor shall report to the RSO once on-site and prior to starting work. B. Loss of radioactive material shall be reported immediately to the NASA MAF RSO. C. Actual exposure of the radiographic film or unshielding the source shall not be initiated until after 5 p.m. on weekdays, unless prior approval is obtained from NASA-MAF Safety and RSO to accomplish such activities prior to 5:00 p.m.

Page 12: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 12

D. In instances where radiography is scheduled near or adjacent to buildings or areas having limited access or one-way doors, no assumptions shall be made as to building occupancy. Where necessary the NASA-MAF Safety RSO will direct the Contractor to conduct an actual building entry, search, and alert. Where removal of personnel from such a building cannot be accomplished and it is otherwise safe to proceed with the radiography, a fully instructed employee shall be positioned inside such building or area to prevent exiting while external radiographic operations are in process. E. Contractor shall perform a hazard analysis (HA) when lasers are used or are in the work area. The HA shall be approved by the NASA-MAF Safety and communicated to all personnel and all necessary protective measures taken.

1.12

FACILITY OCCUPANCY CLOSURE

A. Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from NASA-MAF Safety.

1.13

PROTECTION OF UNDERGROUND UTILITIES

A. Prior to performing any excavation work or any surface penetrations, the Contractor shall obtain from the responsible Construction Engineer a dig permit to include the current subsurface utility drawing of the particular area to be worked on. Requests for dig permits shall be made a minimum of two working weeks prior to conducting any planned digging or excavation activities. Contractor shall stake out subsurface high voltage cables, communication cables, and pipe lines indicated within the scope of the work contemplated. After exposure, the Contractor shall obtain agreement from NASA-MAF Safety on how much closer to cable or pipe the excavations can be permitted.

B. Contractor shall notify the responsible Construction Engineer, two working days prior to the start of excavation work or surface penetration, to enable NASA-MAF Safety to review measures being taken to prevent hazard to employees and possible damage to subsurface utilities. Where emergency conditions preclude the 48 hours advance notification, the Contractor shall immediately inform NASA-MAF Safety of his intention to initiate work prior to actual start of activity.

C. After obtaining clearance from NASA-MAF Safety, the Contractor shall proceed with excavating work, or other surface penetration work. Contractor, however, shall temporarily halt any machine excavation work or other surface penetration when approaching within 10 feet (3 meters) of the staked-out cable or pipe line until the Contractor has exposed the cable or pipe by hand excavation to fix its location.

Page 13: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 13

1.14

ROOFING AND COATING

A. At the beginning of each work day the Contractor shall check with the responsible JACOBS Construction Engineer before proceeding to work on the roof to ensure safe work conditions. Roofing and coating work shall adhere to NFPA-241.

1.15

FALL PROTECTION

A. Use of the monitoring system as the sole fall protection method shall not be allowed at MAF. All roof related work activities shall be specifically addressed by a written fall protection plan and approved by the responsible JACOBS Construction Engineer and NASA- MAF Safety. When an employee is engaged in leading edge work during construction conventional fall protection devices shall be used unless the contractor can demonstrate that it is infeasible or it creates a greater hazard to use conventional fall protection equipment in accordance with 29 CFR 1926.502(k). NOTE: The Fall Protection Plan shall be site specific. At MAF, fall protection is required for heights over four feet. B. The Contractor shall ensure employees requiring fall protection are trained in accordance with 29 CFR 1926.503 and provide documentation of this training when requested by the responsible JACOBS Construction Engineer and NASA-MAF Safety. C. The Contractor shall ensure compliance with the MSFOC MAF Fall Protection Plan defined in QD-MAF-004 Personal Protective Equipment (PPE) and Systems and MAF fall protection requirements.

1.16

TEMPORARY HANDRAILS

A. Temporary hand rails shall be provided on all stairwells until permanent hand rails are installed. All floor and wall openings from which there is a drop of more than 4'shall be guarded by rail. Where there is exposure below of falling materials, a removable toe board or equivalent shall also be provided. In places where people are required to access an area close to or underneath walkways, handrails, and toe boards; approved netting shall be used.

1.17

PORTABLE TOOLS

A. All portable electrically-powered tools used on this work shall be grounded via ground fault interrupter. Operators of power- operated tools shall be familiar with their safe operation in accordance with 29 CFR 1910.241-244 (Subpart P) and 29 CFR 1926.300 - 307 (Subpart I). B. The use of explosive activated tools shall require approval from NASA-MAF Safety. Operators shall be trained in accordance with 29 CFR 1926.302(e) and provide documentation of this training when requested by NASA-MAF Safety.

Page 14: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 14

1.18

REVERSE SIGNAL ALARM

A. Self-propelled construction equipment (except light service vehicles), crawler-type equipment, such as cranes, power shovels and draglines, whether moving alone or in combination shall be equipped with a reverse signal alarm in accordance with 29 CFR 1926.601. The alarm shall be mounted on the rear of the equipment and shall withstand severe wear and tear, adverse weather, and unfavorable environmental working conditions and shall be certified by the manufacturer as fully meeting the following performance standards. B. The alarm shall produce a relatively pure tone which shall peak within the United Standard Association standard octave pass band of 600 to 2,400 cycles per second and shall produce a 0.2 to 0.5 second audible warning within the initial 3 feet of backward movement of the vehicle on which it is mounted and at regular intervals, not to exceed 3 seconds, throughout the backward movement. The alarm shall automatically cut out when the backward movement ceases. The sound intensity of the alarm shall range from and not exceed 100 dB at a horizontal distance of 5 feet from the alarm. C. Actuation of the alarm shall be automatic by direct connection to any part of the equipment that moves or acts in a manner distinctive only to the rearward movement of the vehicle with no manual controls of any kind between the source of actuation and the alarm. Where application of this requirement to specific types of equipment has impractical application, other means of actuation may be used upon written approval of NASA-MAF Safety.

1.19

RADIOS

A. To insure safety to personnel on nearby test stands and to prevent dangerous radio interference from damaging space vehicle test programs underway near the site, the Contractor shall not use any radio communication on or near the site without coordinating with NASA-MAF Safety and the responsible JACOBS Construction Engineer. All radio frequencies used shall be approved by the responsible JACOBS Construction Engineer prior to use.

1.20

WELDING, FLAME CUTTING, AND MELTING

A. Contractor shall clear welding and cutting operations with the responsible JACOBS Construction Engineer and the CIS Fire Department before operations begin. B. Contractor shall ensure welding and cutting operators are familiar with the safe operation of welding and cutting equipment requirements in 29 CFR 1926.350-354 (Subpart J).

Page 15: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 15

C. Contractor shall discontinue burning, welding, or cutting operations 1 hour prior to the end of the normal work day. Contractor employee shall remain at the site for 1 hour, or as required by the Hot Work Permit, after discontinuing these operations to make a thorough inspection of the area for possible sources of latent combustion. He shall be equipped with two full 15-pound (6.8 kilogram) carbon dioxide fire extinguishers. Details for reporting fires will be provided by NASA-MAF Safety during the Pre-Construction Conference. D. During operations involving possible fire hazard, the Contractor shall notify the responsible JACOBS Construction Engineer and the CIS Fire Department and not proceed until clearance is obtained in writing. The responsible Construction Engineer and/or NASA-MAF Safety may request a standby from the CIS Fire Department. This requirement does not relieve the Contractor of his responsibility for welding and cutting safety. E. Roofing/Tar Melting/Handling Devices shall comply with the requirements of NFPA 241. Tar melting kettles and handling devices shall be used in a safe manner to eliminate any chance of an employee being burned or starting a fire. Melting kettles shall be placed on a level, firm foundation and protected against traffic, accidental tipping or similar hazard. An approved type of fire extinguishers shall be available at all locations where melting kettles or heating devices are in use. Melting kettles or heating devices, when in use, shall be provided with a lid and thermometer.

1.21

HIGH NOISE LEVEL PROTECTION

A. Contractor shall ensure employees required to wear Personal Protective Equipment (PPE) been trained in PPE usage in accordance with 29 CFR 1910.132(f) and QD-MAF-004 Personal Protective Equipment (PPE) and Systems. B. Operations performed by the Contractor that involve the use of equipment with output of high noise levels (jackhammers, air compressors, and explosive device activated tools)shall be scheduled for weekends or after duty working hours as directed at the pre-construction conference. Use of any such equipment shall be approved in writing by the responsible Construction Engineer prior to commencement of work. C. When the sound pressure level in any working area exceeds 82 dBA, personnel shall be required to wear hearing protective devices in accordance with 29 CFR 1926.101. D. When the sound pressure level in any work area exceeds 120 dBA, hearing protection equivalent to the combination of ear plugs and ear muffs shall be required.

Page 16: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 16

1.22

SEVERE STORM PLAN

A. In the event of a severe storm warning, the Contractor shall:

1. Secure outside equipment and materials and place materials possible to damage in protected locations.

2. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.

3. Ensure that temporary erosion controls are adequate. 4. Vacate temporary construction trailers. 5. Comply with instructions of NASA-MAF Safety concerning

weather emergencies.

1.23

SCAFFOLDS

A. Scaffolds. The Contractor shall comply with the requirements of 29 CF 1926 Subpart L and 29 CFR 1910.66 for use of scaffolds. The Contractor shall ensure employees erecting and working on scaffolds are trained in accordance with 29 CFR 1926.454 and provide documentation of this training when requested by NASA-MAF Safety. The following shall apply to use of swinging scaffolds.

1. Scaffold machines used for hoisting personnel shall be approved by the Underwriters' Laboratories. Scaffolds shall not be loaded beyond manufacturer's rated capacity.

2. Scaffold machines with cast-iron parts or components shall not be used. 3. A positive action pawl or brake shall be provided to prevent free fall of scaffold. 4. Scaffold machines with latching arrangements for locking out pawls or brakes shall not be used. Operation of the scaffold machine shall be performed only from the working level of the scaffold.

B. All scaffolds, platforms, and runways shall be constructed in accordance with OSHA requirements and be inspected by qualified personnel. All scaffold boards shall be 2"x10". Barricades or covers shall be provided for all roof or openings which present a hazard. An adequate number of ladders will be furnished at all times. Job constructed ladders shall be of select material. All fixed ladders above 20 feet in height will be staggered or caged. All ladders placed on concrete floors or slippery surfaces shall be equipped with an approved type no-skid shoe or adequately made to prevent slipping. Hand rails with intermediate rails and toe boards shall be provided on all scaffolds 4' or greater in height.

C. All personnel working from swing scaffolds shall wear a full body harness attached to an independently suspended safety line. Independent line shall not be attached to any scaffold component or supporting beam. D. Mobile scaffolding shall not be moved while personnel are on the scaffolding.

Page 17: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 17

1.24

TRENCHING/EXCAVATIONS

A. Prior to beginning any excavations, a dig permit shall be coordinated through the responsible JACOBS Construction Engineer. Trenching machines and augers shall not be used unless approved in advance by NASA-MAF Safety and it shall be so annotated on the issued dig permit. Before starting any earth work, the location of underground utilities shall be carefully verified. Utilities to be left in place shall be protected from damage. Trench excavations over 4' in depth shall be shored braced or sloped to the angle of repose of the material. Excavated or other materials shall be shored and retained at least 2' from the edge of the excavation to prevent it from falling or sliding back into the excavated area and to prevent excessive pressure upon the side of the excavation.

B. Excavations, trenching and shoring requirements for the protection of employees in OSHA Regulation, CFR 29 part 1926.650 shall be employed and enforced. Side and slopes of excavations shall be maintained in a safe condition by scaling, benching or barricading. Where employees are required to be in trenches, a ladder extending from the floor of trench/excavation to at least 3' above top of excavation, located as to provide means of exit without more than 25' of lateral travel. Excavations will be barricaded and posted with warning signs for the safety of personnel. Flashing lights will be provided during hours of darkness.

C. The Contractor shall ensure employees working in or around excavation projects are trained and familiar with the safety requirements in 29 CFR 1926. 650 - 652 (Subpart P).

D. Excavations within 10' of the edge of any roadway must be approved by NASA-MAF Safety prior to excavation.

1.25

ROPES/SLINGS/CHAINS

A. No loads shall pass over workmen and other personnel at any time. Slings, their fittings and fastenings, when in use, shall be inspected daily by a qualified craft person for evidence of overloading, excessive wear or damage. Defective slings shall be removed from service. Proper storage shall be provided for qualified slings when not in use. Wire rope shall be inspected by a competent person at the time of installation and at scheduled intervals thereafter. Drums, sheaves, or pulleys having eccentric bores or cracked hubs, spokes, or flanges shall be removed from service. To eliminate rope damage: drums, sheaves, and pulleys shall be smooth and free of surface defects.

Page 18: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 18

B. Connections, fittings, fasteners, parts, etc., used in connection with ropes shall be of good quality and of proper size and strength, and shall be installed in accordance with recommendations of the manufacturer. Chains used for lifting loads shall be inspected before each use. After the initial inspection, the chains shall be inspected each week. Chains shall be removed from service when showing evidence of cracks, nicks, or other damage. All hooks, used to support human loads (on approved lifting devices) or any loads, shall be closed or equipped with a safety latch.

C. Hooks, shackles, rings, pad eyes, and other fittings that show excessive wear or that have been bent, twisted or otherwise damaged shall be removed from service. Frozen fiber rope shall not be used. Fiber rope that has been subjected to acids or excessive heat shall not be used. Fiber rope shall be protected from abrasion by padding where it is fastened. The same protection applies for fiber rope drawn over square corners, sharp or rough surfaces.

D. The Contractor shall ensure employees performing rigging and hoisting operations are trained and familiar with the safety requirements in 1926.753 and 761.

1.26

OPERATIONS ADJACENT TO POWER LINES

Equipment or any part thereof shall not have the capability of coming within the following minimum clearances from energized power lines. Positioning and blocking of equipment to assure that no part thereof, including cables, can come within 10' of any high voltage lines (greater than 500VAC).

A. The Contractor shall ensure employees performing operations

adjacent to power lines are trained and familiar with the safety requirements in 29 CFR 1926. 950 - 960 (Subpart V).

1.27

CONSTRUCTION EQUIPMENT

A. All construction equipment and machinery, including required guards, brakes, cable, etc., shall be inspected by qualified personnel before use for safe and serviceable mechanical condition. All inspections shall be done daily before each shift and will be properly maintained by qualified personnel. A warning device or service of a signal-man shall be provided where there is danger to personnel from moving equipment, swinging loads, buckets, booms, etc. All equipment capable of hauling 5 tons of material is considered to be heavy duty and shall be equipped with an emergency brake system. The State Commercial Drivers License, (CDL) requirement and regulation applies on MAF.

Page 19: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 19

B. Before any machinery or mechanized equipment is placed in use, it shall be inspected and tested by a competent mechanic and certified to be in safe operating condition. Records of tests and inspections will be maintained at the site and will be available upon request. All machinery or equipment found to be unsafe shall be tagged out and its use prohibited until unsafe conditions have been corrected. Machinery or equipment requiring an operator shall not be permitted to run unattended. Equipment shall be locked or secured to prevent operation by unauthorized personnel. All guards and devices shall be replaced immediately after completion of repairs and adjustments.

C. The Contractor shall ensure employees working with construction

equipment are trained in its safe operation and are familiar with the safety requirements in 29 CFR 1926.600 - 606 (Subpart O).

D. Contractor shall operate only propane (LP) or electric powered

mechanized equipment inside MAF buildings. If gasoline or diesel powered equipment is required to be used inside MAF buildings to support a construction project, the Contractor must develop a mitigation plan (exhaust removal) and submit it to the responsible JACOBS Construction Engineer for review and approval by NASA MAF Safety.

1.28

ELECTRICITY AND LIGHTING

A. All temporary wiring (in use for less than 90 days) shall be in accordance with the National Electric Codes, OSHA standards, and installed by competent personnel. Adequate, safe lighting shall be provided in advance for any work requiring artificial light. Grounding of all electrical portable equipment and hand tools shall be accomplished by installing three-wire plug systems. All 120 volt, single-phase, 15 and 20 ampere receptacle outlets on construction sites which are not part of the permanent wiring of the building or structure and which are in use by employees shall have approved ground fault circuit interrupters (GFCI) for personnel protection.

1.29

STOCK PILING IN A CONSTRUCTION AREA

A. GENERAL SAFETY RULES

1. The contractor's superintendent shall inspect to see that there are no ragged ends of stockpiles and that spread or collapse is prevented. The following rules shall be observed:

a. Stockpiles must have firm level foundations.

b. Materials shall not be stored under or piled against buildings, doors, exits or under stair- ways.

c. Ample room for passageways shall be maintained.

d. Depending on the shape of the material, cross tier each layer when possible.

Page 20: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 20

e. When the shape of the material does not permit cross-tiering, skids or pallets shall be employed. f. Stockpiling in the vicinity of a fire hydrant must leave the hydrant readily visible and accessible. g. Areas shall be kept clear around sprinkler control valves, fuse boxes, electrical switch panels, fire extinguishers, fire alarm boxes and first aid equipment.

2. PIPE STOCK PILING a. All pipe and round stock require special racks or blocks when stock piled.

b. For short periods of time, it is permissible to stack pipe to a maximum of three high with every precaution taken to prevent spreading. c. The longer pipe lengths shall always be on the bottom and he shorter on the top.

3. LUMBER STOCK PILING

a. Lumber shall be stored on level ground in solid, even piles. b. If piled more than two feet high, cross piling must be used unless otherwise approved by NASA- MAF Safety. c. When lumber is removed from the stockpile, it shall be removed from the top and the remaining top layer maintained as near level as possible. d. When there is manual handling of lumber, leather palm-type gloves shall be worn. All nails shall be removed from used lumber before stockpiling.

1.30

HOUSEKEEPING

A. Stairs, steps and scaffolds shall be kept clean and free of debris.

B. Floors shall be kept clean, dry, and in good condition at all times.

C. Work areas shall be kept clean and free of debris and tripping/slipping hazards.

Page 21: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 21

1.31

LADDERS

A. There are two general classifications: manufactured ladders and job-made ladders. The following rules apply for the construction, maintenance and use of both.

B. MANUFACTURED LADDERS shall meet these requirements:

1. OSHA 29 CFR 1910.25/26 and 1926.450

C. JOB-MADE LADDERS shall meet these requirements:

1. Ladders built on the job should be carefully inspected by the foreman before putting them to use and should meet the following requirements: 2. All material should be free from defects. Lumber shall meet OSHA requirements. 3. Rungs shall be evenly spaced and not over 12 inches apart, straight grained and well secured to the side rails with nails driven flush. 4. Strips must be placed between cleats and shall be fastened to the uprights with two 10d nails. 5. Cleats may be recessed into rails a depth of one-half inch. 6. Cleats shall be nailed to each upright with three 10d nails.

1.32

TRAFFIC

A. MAF traffic regulations shall be in accordance with MPR 1600.1, "MSFC Security Procedural Requirements".

1.33

SPRAY PAINTING

A. Spray painting using flammable materials shall not be permitted in any part of the plant unless applied in NASA-MAF Safety approved paint spray booths. Spray painting shall conform to the requirements of NFPA Number 33. Any exception to this rule shall require written permission from NASA-MAF Safety.

1.34

SOLVENT CLEANING OPERATIONS

A. Adequate ventilation shall be provided for all solvent cleaning operations. If the quantity of solvent is small, general plant ventilation should be sufficient to reduce concentration of vapors to acceptable levels. Solvent cleaning must never be done in a small enclosed area without proper mechanical ventilation. Solvent cleaning shall never be done close to any open flame which includes welding torches and welding ventilation intakes that could transmit vapors into other areas. Potentially explosive atmospheres must be considered when generating flammable vapors.

Page 22: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 22

B. Notify the responsible JACOBS Construction Engineer and MSFOC MAF Environmental who will notify the Industrial Waste Water Treatment Facility at (504)257-4709 at least 24 hours in advance of dump time, when chemical storage tanks are being pickled, flushed, cleaned, or rinsed and large quantities of chemicals and/or water contaminated with chemicals will be dumped into the facility chemical drain system.

1.35

STEEL ERECTION

A. All personnel in construction area must wear a hard hat.

B. Care should be used in carrying, hanging and working from floating scaffolds. Scaffold platforms must be kept clear of bolts, nuts and debris.

C. Scaffolds must be thoroughly inspected before they are used.

D. Personnel working aloft on open steel shall wear a full body safety harness tied off to permanent structures, except where safety nets are hung directly below.

E. Work shall not be performed on open steel framework during high winds or inclement weather.

F. In setting the steel, each piece should be secured in place before the line is taken off.

G. When setting steel trusses secure side or cross brace until permanent braces are in place.

H. Material should not be hoisted to a structure until it is ready to be put into position and fastened.

I. Cranes or other equipment shall not be operated within a minimum of 10 feet of electric power lines except where electrical distribution and transmission lines have been de-energized and visibly grounded.

J. Loads shall not pass over personnel.

K. Hoisting bundles of steel shapes should be avoided except when

each piece is secured to prevent slipping from the bundle.

L. Tag lines shall be used to control the loads when hoisting materials.

M. Sheets or small bundles of material must be loaded so they cannot slip out. Baskets or boxes may be used to hoist small pieces.

N. All bolts, nuts, wrenches or other loose articles should be kept in boxes or baskets so that they will not fall through or over the edge of planking.

Page 23: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 23

O. Welding leads, air lines and oxygen/acetylene hoses shall be laid out to avoid tripping hazards. They should be protected from damage and out of the way of walkways and roadways. Cylinders used for welding/cutting shall be secured in an upright position. Empty cylinders will be removed from the job as soon as possible.

P. In buildings or other structures of skeleton construction, the

entire tier of beams on which the structural iron or steel work is being erected, generally called the working floor, must be thoroughly covered (planked) except for the openings required for erection work.

Q. Where there are more than two stories of the open steel frame

erected and where bolting, riveting, welding or other work is being done, the lower two stories below the working floor should be planked.

R. Planks used for temporary flooring in skeleton construction shall not be less than two inches thick. They shall be placed so that they cannot tip over under the weight of the worker at any point and secured so they cannot slip out of place. They should be laid close together to form a solid floor and should overlap at least 12 inches at the ends. Splices shall have a minimum overlap of six inches.

S. Workers shall be prohibited from working under areas where riveting, bolting or welding is being done unless they are protected by a planked floor between them and the overhead work. Workers shall be prohibited from working where loads are passed overhead unless protection is provided.

T. Safety and/or debris "nets" shall be used in areas where temporary floors cannot be readily installed.

U. Workers shall not be hoisted or lowered in tackle and runner lines or on the load.

1.36

ABRASIVE BLASTING

A. Abrasive blasting shall conform to the following requirements:

1. Only aluminum oxide blasting material or equivalent may be used. 2. Silica (sand) or glass blasting material is prohibited. 3. All blasting shall comply with OSHA Standard 1910.94. 4. Any exception to the above rules shall require written permission from NASA-MAF Safety.

1.37

PRESSURE PIPING, COUPLINGS AND FITTINGS

A. A pressure system is defined as any combination of equipment, pipe and associated fittings operating under pressure.

Page 24: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 24

1. GENERAL. The following safe practice rules will be followed when installing, maintaining or repairing pressure piping systems. The safe practice rules are the minimum requirements for a safe working condition.

a. SAFE PRACTICE RULES FOR COUPLINGS 1) CLAMP-ON TYPE COUPLINGS:

a) A foreman or supervisor familiar with the type of coupling being used will instruct installation, maintenance or service personnel in features of the coupling. b) Installation, maintenance or service personnel will verify that there is zero pressure on the pipe system prior to working on the couplings. c) Visually inspect all couplings to see that they are seated and tight prior to re- pressurization of the system.

2) MECHANICAL OR FLANGED COUPLINGS:

a) A foreman or supervisor familiar with the type of coupling being used will instruct installation, maintenance or service personnel in the features of the coupling being used. b) Installation, maintenance or service personnel will verify that there is zero pressure on the pipe system prior to working on the couplings. c) When using mechanical joint couplings, the installation, maintenance or service personnel will insure adequate pipe is in the coupling to ensure a good joint. When using flange connections, a visual inspection of the flange and flange weld will be made for cracks. If cracks are found, the flange is unsafe and must be changed.

Page 25: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 25

d) Bolts in the joint being worked on and the adjacent joints will be manually and visually checked before re-pressurization.

3) PIPING

a) A foreman or supervisor familiar with the type of coupling being used will instruct installation, maintenance or service personnel in the features of the coupling being used. b) A foreman or supervisor familiar with the type of pipe and the system being worked will instruct installation, maintenance or service personnel in the features of the pipe and the system. c) Installation, maintenance or service personnel will verify that there is zero pressure on the pipe system prior to working on the pipe. d) Pipe repairs will be inspected before re-pressurization of the system.

B. PRESSURE TESTING 1. SAFE PRACTICES FOR PRESSURE SYSTEMS

a) Study the schematic diagram of any pressure system prior to pressurization.

b) Use only equipment which is designed, constructed and maintained for the pressure and fluid service of the pressurized system.

c) The burst pressure rating of all components of a pressure system shall meet ASME standard maximum operating pressures. d) Gages shall be equipped with blow- out plugs or safety cases. e) Never disable gage blow-out protection.

Page 26: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 26

f) Gage scale shall be 1-1/2 to 2 times working pressure to be measured.

g) A certified safety relief valve shall be installed on all pressure vessels or in the piping system between the pressure source and the vessel.

h) Safety relief valves shall have

a discharge capacity greater than the maximum flow rate to which the protected item may be pressurized.

i) Relief valves shall be tested once

per year. j) All flexible hoses shall be

pressure proof tested prior to installation or as integrated into the system.

k) No repairs shall be performed on

pressurized systems. l) All accumulators in systems using

flammable fluids shall be charged with nitrogen or any inert gas that does not support combustion.

m) After using regulators, pressure

shall be bled off. Do not store dome regulators while pressurized.

n) When testing large volume

containers in order to reduce the effective volume, fill the container with relatively incompressible materials.

o) It is advisable to use liquids in

place of gasses for pressure testing whenever possible. Pneumatic tests shall be approved by NASA-MAF Safety before such testing begins.

p) All high pressure lines shall be

secured against whipping in case of failure.

q) High pressure hoses shall be

secured at both ends and every 6' throughout the length.

Page 27: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 27

r) Employees engaged in pressure

testing shall be qualified and certified.

s) Test areas shall be controlled and

maintained. Access shall be limited to test personnel.

t) All vessels to be pressure

tested that do not meet ASME boiler and pressure vessel code must have the following information attached:

1) Material of construction 2) Design ultimate pressure 3) Maximum working pressure 4) Proof pressure 5) Date of last proof pressure test 6) Any special limitations or precautions

2. SAFE PRACTICES FOR PRESSURE SYSTEMS

a) The strength of many materials is degraded by significant temperature exposure. Before activation of any system that is to be pressurized, exposure to unusual heat or cold conditions must be evaluated. Exposure of flexible, metal or reinforced hydraulic lines to unusual heat such as welding, cutting or adjacent heating equipment, including sun-gun lamps used for illumination, has resulted in line ruptures, serious fires and/or explosion.

Page 28: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 28

b) Vessels which do not meet ASME boiler and pressure vessel code shall be pressurized for the first time without personnel exposure. Adequate protection such as protective walls, block houses and natural terrain features must be provided. Not until a vessel is proof tested and its integrity verified, will personnel be exposed and then only those absolutely necessary for the efficient conduct of a test will be present. A test conductor shall require all unnecessary personnel to leave the test area. Subsequent pressurization must be considered hazardous and no personnel shall be exposed until desired pressure has stabilized, unless the reliability of the pressurization system and appropriate relief mechanisms are assured through redundancy and positive limiting devices. Unrestricted personnel exposure is permitted only around those vessels with a safe factor of at least 4 to 1 (maximum designed ultimate burst: maximum design working). The safety of personnel may be further assured around pressurized vessels by first exceeding the working or test pressure without exposing personnel, then reducing the pressure to the desired level.

c) The test supervisor shall

coordinate with NASA-MAF ll pressure testing. Written SOPs will be prepared for approval by NASA-MAF Safety.

Page 29: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 29

3. SPECIAL REQUIREMENTS

a) The strength of many materials is degraded by significant temperature exposure. Before activation of any system that is to be pressurized, exposure to unusual heat or cold conditions must be evaluated. Exposure of flexible, metal or reinforced hydraulic lines to unusual heat such as welding, cutting or adjacent heating equipment, including sun-gun lamps used for illumination, has resulted in line ruptures, serious fires and/or explosion.

1) Pneumatic (requires prior written approval from

NASA-MAF Safety)

2) Hydrostatic a) Protect personnel against fluid jets or squirts when they are hydraulic pressure testing. This may be accomplished by remote testing, personal protective equipment, etc. b) When hydrostatic pressures are used, all air must be bled from the vessel being tested. c) Hydrostatic leak tests exceeding the operations pressure shall be considered hazardous. d) Hydrostatic proof test areas shall be considered as hazardous test areas. Controlled access shall be maintained. e) Control consoles and other equipment shall be located so that a failure of the test vessel would not deluge them with large volumes of liquid. f) Hydrostatic testing shall be performed with non-flammable liquids.

Page 30: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 30

1.38 BREATHING AIR

A. Plant air shall never be used for breathing purposes

1.39 TETHERING OF TOOLS, EQUIPMENT AND LOOSE ITEMS

A. Contractors required to work inside, above or in proximity to flight hardware, or above personnel will coordinate requirements through responsible Construction Engineer and NASA-MAF Safety prior to commencing the work.

Page 31: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 31

EXHIBIT A

August 13, 2008 Safety, Health and Environmental (SHE) Work Agreement for Construciton Contracts Company Name: Contract Number: Date: MAF Organization Supported: MAF Contracting Officer: MAF Contracting Officer Technical Representative: Contract Begin Date: Contract End Date:

Page 32: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 32

MSFOC MAF is committed to providing a safe and healthful work place to all employees and visitors, and to protecting the MSFOC MAF environment and property. During the construction, alteration, demolition and/or repair under this contracted effort (company name)

1. Ensure a safe and healthful workplace is provided for company employees and customers and the MAF environment and property are protected during the performance of work under this contracted effort.

______________________ shall:

2. Ensure compliance with all regulations and requirements applicable to this contracted effort (i.e., Environmental Protection Agency (EPA),Occupational Safety and Health Administration (OSHA), National Aeronautics Space Administration (NASA), Marshall Space Flight Center (MSFC), MSFOC MAF), etc.

3. Ensure management and employees are held accountable for implementing their work tasks in a safe and healthful manner while also protecting property and the environment.

4. Ensure a method of motivational or innovative techniques are used to make employees aware to implement their tasks in a safe and healthful manner.

NOTE: When requested by the responsible Construction Engineer and/or NASA MAF Safety the contractor will implement the company's disciplinary program if an employee is identified to regularly or intentionally fail to perform their tasks in a safe and healthful manner while working at MAF.

5. Ensure a safety (toolbox) meeting and/or safety awareness training is conducted at least weekly for employees.

[NOTE: Meeting topic and sign-in sheets of these meetings shall be documented and made available to NASA-MAF Safety upon request.]

6. Ensure that this signed SHE Work Agreement is reviewed at least annually and updated as necessary.

[NOTE: This review shall be documented and made available to NASA-MAF Safety upon request.]

7. Ensure all SHE Program requirements applicable to this contracted effort are flowed down through all company levels located onsite and when applicable to any subcontractors supporting this contracted effort.

8. Ensure contractor employees are assigned to serve as the company

SHE Point of Contact (POC) and an alternate SHE POC. They will serve as the POC of any SHE related issue and ensure all SHE Program requirements are implemented by the contractor while working on MAF. [NOTE: The names of these employees shall be posted on the attached Emergency Phone listing.]

Page 33: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 33

9. Ensure each company employee is made aware of their role and responsibility in performing their work in accordance with the SHE Program requirements and this SHE Agreement for Constructio Construction. This also includes subcontractor employees working onsite supporting this contracted effort.

10. Ensure a safety assessment is conducted for each operation to be performed under this contracted effort identified as potentially hazardous. The safety assessment can be conducted by performing a Job Hazard Analysis (JHA) or an equivalent method, or completing a Hazard Identification Checklist (HIC) specific to the worksite and operations.

[NOTE: The assessments or checklists shall be documented and made available to NASA-MAF Safety upon request. NASA-MAF Safety can assist in obtaining the HIC.]

11. Ensure all work is performed in compliance with the SHE programs applicable to the contracted effort (Respiratory Protection, Hazard Communication, Confined Space, Lockout/Tagout, etc.).

12. Ensure an inspection is conducted at least weekly of the worksite, materials, and equipment by a competent employee in accordance with 29 CFR 1926.20 (a)(2) & 25.

[NOTE: The inspection shall be documented and made available to NASA-MAF Safety upon request.]

13. Ensure plans or procedures are generated when determined necessary to control potentially hazardous conditions.

[NOTE: The plans or procedures shall clearly identify the potentially hazardous situations, the mitigation techniques necessary to control the hazard, be documented, and made available to NASA-MAF Safety upon request.]

14. Ensure the procurement, storage, use of hazardous chemicals and materials brought on MAF are coordinated through NASA-MAF Safety.

15. Ensure the recycling and disposal of any hazardous waste generated at MAF is coordinated through MSFOC MAF Environmental Services.

16. Ensure all work performed on MAF is in compliance with environmental laws and regulation of 40 CFR, Louisiana Dept. of Environmental Quality (LDEQ)by:

a. Reporting hazardous and toxic substance use. b. Implementing and reporting green procurements. c. Reducing, reusing, and recycling of hazardous and

toxic substances prior to disposal. d. Minimizing storm water pollution.

Page 34: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 34

e. Ensuring equipment and processes permitted by applicable laws.

f. Disposing of solid and liquid materials as permitted by laws. [NOTE: Coordination with MAF Environmental Services.]

17. Ensure all employees working on MAF are made aware of the MAF Emergency Management Plan in accordance with 29 CFR 1926.35.

[NOTE: Each employee shall be made aware of the location of the nearest protective areas within MAF buildings adjacent to the worksite. The responsible Construction Engineer and NASA- MAF Safety can assist in identifying these protective areas adjacent to the work site.]

18. Ensure all mishaps and close calls are reported in accordance with MWI 8621.1. Investigations can be required by the NASA-MAF Safety to determine the root cause.

[NOTE: If the mishap or close call involves personnel injury or property damage site shall be secured until the arrival of a Security Officer and/or NASA-MAF Safety Investigator and remain secured until released by NASA-MAF Safety. This includes mishaps resulting in minor first aid. [NASA-MAF Safety shall be contacted for all mishaps.]

19. Ensure all employees are made aware of how to receive emergency medical attention at MAF in accordance with 29 CFR 1926.23 & 50.

20. Ensure all employees are made aware of their authority to "halt or suspend work" at MAF when a safety, health or environmental condition warrants such action.

[NOTE: Work cannot resume until the condition has been corrected.]

21. Ensure all employees receive training in how to recognize hazards, avoid accidents, know the hazards specific to their job in accordance with 29 CFR 1926.21(b)(2).

[NOTE: This training can be accomplished during a safety (toolbox) meeting.]

22. Ensure all employees are aware of the company's disciplinary program if they regularly or intentionally fail to perform their tasks in a safe and healthful manner while working at MAF.

23. Ensure all employees are trained and made aware of how to report an emergency or accident while working at MAF.

Page 35: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 35

24. Ensure all employees are assessed to ensure they are adequately trained to perform their job. [NOTE: Evidence of this training shall be documented and made available to NASA-MAF Safety upon request for any tasks/activities that requires documented training in accordance with 29 CFR 1910 and 29 CFR 1926.]

25. Ensure employees that are required to operate any MAF equipment (forklift, crane, etc.) have received training and have a MAF certification in accordance with MWI 3410.1.

26. Ensure employees that are required to operate Contractor equipment and machinery are qualified by training or experience in accordance with 29 CFR 1926.20(a)(4).

27. Ensure any Contractor owned or rented motorized vehicles and lifting equipment brought on MAF in support of this contracted effort comply with the applicable requirements in 29 CFR 1910.178 - 184, 29 CFR 1926.550-606 and 29 CFR 1926.1000-1003.

28. Ensure employees that are required to handle or use poisons, caustics, and other harmful substances have received training in the safe handling and use, and are made aware of the potential hazards, personal hygiene, and personal protective measures required in accordance with 29 CFR 1926.21(b)(3).

29. Ensure employees that are required to handle or use flammable liquids, gases, or toxic materials have received training in the safe handling and use of these materials and made aware of the specific requirements for the liquid, gas or material contained in 29 CFR 1926 Subparts D, F, and other applicable subpart of 29 CFR 1926 in accordance with 29 CFR 1926.21(b)(5).

30. Ensure employees that are required to enter into confined or

enclosed spaces have received training as to the nature of the hazard involved, the necessary precautions to be taken, and in the use of protective and emergency equipment in accordance with 29 CFR 1926.21(b)(6).

NOTE: Employees entering confined spaces at MAF shall be trained and certified in accordance AS60 - OI - 026 Confined Space Entries.

31. Ensure employee(s) are identified to serve in the role of a "Competent person" for pre-job inspections/verifications/activities (scaffolding, trenches, etc.) as required by the applicable subparts of 29 CFR 1910 and 29 CFR 1926 for this contracted effort.

Page 36: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 36

[NOTE 1: A "competent person" is identified in 29 CFR 1926.32 and 29 CFR 1910 as "capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who have authorization to take prompt corrective measures to eliminate them."] [NOTE 2: Justification/rational of selecting these employees shall be documented (employee's training or knowledge of the task and work experience) and made available to NASA-MAF Safety upon request. The name(s) and the corresponding job/task that they are designated to serve as the "Competent person" shall be listed on the attached Emergency Phone listing, Appendix B.]

32. Ensure an employee is appointed to be "in charge and responsible" and is physically located onsite while work is being performed.

[NOTE: This is normally a job superintendent or foreman.]

33. Ensure the use of any equipment, machinery or tools discovered to be in an unsafe operating condition is prohibited in accordance with 29 CFR 1926.20 (a)(3).

[NOTE: Equipment, machinery or tools discovered in an unsafe operating condition shall be removed from the worksite or identified (tagged) as unsafe, or rendered inoperable by the use of a lock.]

34. Ensure fire protection equipment appropriate for the work being performed is available at the worksite in accordance with 29 CFR 1926.24.

[NOTE: Portable fire extinguishers are to be located at the worksite]

35. Ensure all scrap lumber and debris is kept cleared from work areas, passageways and stairs in accordance with 29 CFR 1926.25(a).

36. Ensure combustible scrap and debris is removed from the worksite at regular intervals in accordance with 29 CFR 1926.25(b).

37. Ensure containers are provided to collect waste/trash and they are emptied at regular intervals in accordance with 29 CFR 1926.25(c).

[NOTE: Containers for garbage and other oily, flammable, or hazardous wastes, such as caustics, acids, harmful dusts, etc. shall be equipped with covers and the covers kept closed.]

Page 37: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 37

38. Ensure adequate lighting (permanent or temporary) is provided in the work area to enable the employees to safely perform their tasks in accordance with 29 CFR 1926.26.

39. Ensure all equipment and systems are de-energized, placed in a safe work condition and lock out devices applied in accordance with 29 CFR 1910.147, 29 CFR 1926.417 and QD - MAF - 002 Lockout Tagout.

[NOTE 2: Work on energized equipment is strictly prohibited at MAF, but occasionally a situation will arise where this is not possible. In these situations an Energized Electrical Work Permit shall be required. Contact NASA-MAF Safety for more information.]

40. Ensure barricade fencing is erected around hazardous conditions such as excavations, trenches, etc. in accordance with 29 CFR 1926.200 -203, Subpart G.

[NOTE: Orange mesh barricade fencing is the preferred method for construction at MAF, but other means (signs, signals, tags) of warning employees are also acceptable. NASA-MAF Safety can provide more information.]

41. Ensure appropriate signage is posted at the worksite or for operations that require the use of PPE.

42. Ensure temporary guardrails are provided where there are open sides or openings where the walking/working surface is 4 foot or more above the next lower level in accordance with 29 CFR 1910.23(c)(1).

43. Ensure a fall protection system (guardrails, personnel fall arrest system, etc) is provided for any activity performed on a walking/working surface that is 4 foot or more above the next lower level. [NOTE: If a conventional fall protection system cannot be provided a site specific (building) fall protection plan shall be required in accordance with 29 CFR 1926.501(k). The fall protection plan shall be approved by NASA-MAF Safety.]

44. Ensure employees required to wear a personal fall arrest system have received training and are familiar with the correct use of these systems in accordance with 29 CFR 1926.503.

45. Ensure tasks that require Personal Protective Equipment (PPE) to be worn to reduce employee exposure to hazardous conditions are communicated to all employees performing these tasks in accordance with 29 CFR 1926.28 and QD - MAF - 004 Personal Protective Equipment (PPE) and Systems.

Page 38: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 38

46. Ensure the following abatements/impairment plans are obtained when needed for:

• Lead removal-29 CFR 1926.62 • Asbestos removal - 29 CFR 1926.1101 • Fire Protection system outages - 29 CFR 1926.150 and

QD - MAF - 005 Fire Safety Program.

47. Ensure the following permits are obtained when needed: Hot Work Permits shall be required for activities that are not performed in a Designated Hot Work Area and use an "open flame", welding, cutting, grinding, Tar Kettles. etc. [NOTE: All hot work shall end 1 hour prior to the end of the normal work day.]

• Digging Permits shall be required for all excavations and trenching

• Confined Space Entry Permits shall be required for all entries in MAF spaces identified as a confined space in accordance with As60 - OI - Confined Space Entries.

• Energized Electrical Work Permit shall be required if the equipment or system cannot be de- energized to perform work.

[NOTE: No work shall be performed on energized equipment without concurrence from the responsible Construction Engineer and approval from NASA-MAF Safety.]

48. Ensure all power portable tools are double-insulated or grounded by means of a 3-wire polarity type grounding system via a ground fault interrupter in accordance with 29 CR 1926.302.

49. Ensure all single-phase 15 and 20 ampere receptacle outlets on

construction sites are equipped with ground-fault circuit interrupters (GFCI) for employee protection in accordance with 29 CFR 1926.404(b)(1).

50. Ensure all cord sets and receptacles the construction site where an employee can connect equipment by means of a flexible cord and plug are grounded in accordance with 29 CFR 1926.404(b)(1). NOTE: This applies to cord sets and receptacles that are not part of the permanent building structure.

Page 39: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 39

51. Ensure all self-propelled construction equipment is equipped with a reverse signal alarm in accordance with 29 CFR 1926.601.

NOTE: This is not required for light service vehicles.

52. Ensure equipment and materials located outdoors are placed and stored so to not cause possible damage to other buildings or structures during severe weather.

53. Ensure scaffolds are erected and used in accordance with 29 CFR 1926 Subpart L and 29 CFR 1910.66.

54. Ensure scaffolds and scaffold components are inspected prior to use each day by a "competent employee" in accordance with 29 CFR 1926.451(f)(3).

55. Ensure excavations/trenches are dug, formed and inspected prior to entry and as needed throughout the day by a "competent person" in accordance with 29 CFR 1926.651, 29 CFR 1926.652 and 29 CFR 1926.651(k).

56. Ensure Contractor owned or rented hoisting equipment (cranes and forklifts) brought on MAF have their rated load capacities conspicuously posted on the equipment in accordance with 29 CFR 1926.550(a)(2).

57. Ensure Contractor owned or rented hoisting equipment (cranes and forklifts) brought on MAF have a documented annual inspection in accordance with 29 CFR 1926.550(a)(6).

[NOTE: The annual inspection documentation shall be made available to MSFC upon request.]

58. Ensure a visual inspection is performed of each hoisting equipment (cranes or forklifts) prior to use in accordance with 29 CFR 1926.753(c )(1).

59. Ensure rigging and hoisting operations are performed by employees that have received training in these operations and are familiar with rigging and hoisting safety requirements in accordance with 29 CFR 1926.753-761 and 29 CFR 1910.178(l)6).

60. Ensure operations performed adjacent to power lines are performed by employees that have received training in this type operation and are familiar with the safety requirements for these type operations in accordance with 29 CFR 1926.950-960.

Page 40: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 40

61. Ensure operations that require the use of construction equipment considered as heavy equipment or machinery are performed by employees that have received training in the safe operation of this type equipment or machinery and are familiar with the safety requirements in accordance with 29 CFR 1926.600-606.

Provide a list of company employee(s) to be contacted in the event of an emergency while work is performed onsite under this contracted effort.

62. Post the "Emergency Phone List" Appendix B at the worksite, or a designated meeting area where workers gather prior to commencing work, or for other activities. The "Emergency Phone List" can also be located in company vehicles if the Contractor does not have a designated meeting area.

63. Provide additional requirements not previously listed, if required, specific to the work performed under this contracted effort.

64. Ensure that evidence of any required training (certificate or letter from company providing rational why employee is considered competent or trained) can be provided when requested by NASA-MAF Safety.

REPORTS/DOCUMENTATION SUBMITTAL Reports/documentation listed below shall be made available to NASA MAF Safety upon request.

1. Safety (toolbox) meeting and/or safety awareness training documentation

2. Safety Assessments: Job Hazard Analysis (JHA), Hazardous Inventory Checklists (HIC)

3. Worksite inspection documentation 4. Employee training/qualification/certification records 5. Equipment inspection documentation 6. Material Safety Data Sheets (MSDS) for chemical and hazardous MATERIALS SUBMISSIONS FREQUENCY

1. Contractor Accident and Safety Statistics or an equivalent method to the responsible Construction Engineer and NASA-MAF Safety. This information shall be provided in accordance to the reporting requirements determined by the MSFOC MAF Business Office. At a minimum the following information shall be provided:

• Contract number • National American Standard Industry Code (NASIC) • Number of employees and supervisors • Number of hours worked during the month • Lost work day cases, days away from work, and

restricted work days

Page 41: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 41

• Number of safety meetings and worksite inspections

2. Initial notification for Type A, Type B, Type C, Type D mishaps and close calls - shall be reported to NASA-MAF Safety as soon as possible, but no later than one hour of awareness of the occurrence. 1) Call the responsible Construction Engineer and NASA-MAF.

3. The initial notification for all mishaps/close calls shall include 1) location and time of incident, 2) number of fatalities and/or hospitalized employees (if known), 3) Company and organization contact person and phone number, 4) a brief description of the mishap/close call including damage to equipment and/or facilities.

4. Follow-up reporting and documentation of a mishap/close call shall be within 24 hours of initial notification.

5. The extent of investigation to determine the root cause of

the mishap or close call shall be conducted in accordance MWI 8621.1.

By signing this SHE Work Agreement, contact agrees to comply with all the MAF SHE Program rules and regulations. Name(s) of company person(s) responsible for ensuring compliance with all the requirements listed above while working on MAF.

Company Name:

Company owner/representative (Print): (Signature): Title: Date:

Company onsite superintendent/foreman (Print): (Signature): Date:

(Signature): Company onsite SHE representative (Print):

Date:

Page 42: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 42

APPENDIX B EMERGENCY TELEPHONE LIST

[Post at worksite or a designated meeting area where workers gather prior to commencing work or for other activities. The "Emergency Phone List" can

also be located in company vehicles if the Contractor does not have a designated meeting area]

MAF NETWORK TELEPHONE OTHER TELEPHONE

MAF AMBULANCE 911 504-257-2333 CHEMICAL SPILLS 911 504-257-LEAK or 504-257-2333 FIRE 911 504-257-2333 SECURITY 911 504-257-2333 MEDICAL CENTER (Bldg. 320) 7-2701 504-257-2701 [Identify that you are on MAF property if using a cell phone and give location, building number, road, intersection, etc. if known.]

CONTACTS: 1. TO REPORT AN UNSAFE, UNHEALTHFUL OR ENVIRONMENTAL

CONCERNS CONTACT MSFOC MAF SAFETY OR ENVIRONMENTAL SERVICES.

2. TO REQUEST A WELDING/BURNING/CUTTING PERMITCONTACT THE CIS FIRE DEPARTMENT.

3. TO REQUEST A CONFINED SPACE PERMIT CONTACT MSFOC MAF SAFETY.

Company Name: Company Emergency Contact: Phone: Company Emergency Contact: Phone: Company Emergency Contact: Phone: Company SHE POC: Phone: Competent SHE POC (Alt) Phone: Competent Person: Examples -Rigging Competent Person: Excavation/Trench Competent Person: Lifting Equipment Competent Person: Competent Person: Competent Person:

Page 43: SECTION 01 06 10 GENERAL SAFETY AND INDUSTRIAL HYGIENE ...€¦ · GENERAL SAFETY AND INDUSTRIAL HYGIENE REQUIREMENTS . PART 1 GENERAL . 1.1 Introduction . ... AS60-OI-024 Ergonomics

01 06 10 - 43