Seattle Design Commission September 6, 2012

Transcript of Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation”...

Page 1: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Seattle Design Commission

September 6, 2012

Page 2: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

“Foundation” of the Waterfront Program

2

Page 3: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Seawall Project Area

Central Waterfront Team

Page 4: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Current Project Schedule

Page 5: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

2012 2013 2014 2015 2016

Project Milestones

Environmental Process

Design Development

GC/CM Procurement

Construction

Construction begins

Start final

design

60% 100%

Construction complete

Permits received DEIS Public notice

NTP

Pre-construction

Page 6: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Project Purpose and Need

Page 7: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

• Reduce the risks of coastal

storm and seismic damages

• Protect public safety, critical

infrastructure, and associated

economic activities along

Seattle’s central waterfront

• Improve the degraded

ecosystem functions and

processes of the Elliott Bay

nearshore in the vicinity of the

existing seawall

Project Purpose

Page 8: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Sample Seawall Cross-Section

Type B

Seawall

(Madison

to Union)

Page 9: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Seawall Location: Eastern Extent

Type A

Seawall

(Union to

Broad) 9

Page 10: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Structural Elements of the Wall

Relieving

Platform

Soil

Wall

Page 11: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Seawall Repairs and Vulnerability

1954 failure, Clay Street

(above/at right)

2002 relieving platform

repairs (to right)

Page 12: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Result of a Seawall Failure

Page 13: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

What’s at Risk?

• Public safety

• Transportation corridor

• Critical utilities

• Residential and commercial

structures

• Public recreation

• Tourism and local attractions

• Seattle’s front porch

Page 14: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

• Migratory corridor

– Depth

– Light

• Nearshore ecosystem productivity

– Aquatic and riparian vegetation

– Macroinvertebrates

– Substrate diversity

Degraded Nearshore Habitats

Page 15: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

• Salmon

• Trout

• Puget Sound Rockfish

Threatened and Endangered Species

Page 16: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Developing Alternatives

Page 17: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Public Engagement Themes

• For those most affected, the project is well-known and they

are ready to get construction started

• Seize the habitat opportunity by using innovative and

science-based enhancements

• Maintain a responsible project budget

• Create more physical access to water and public gathering

space

• Maintain transportation routes, including continuous non-

motorized pathways

• Consider construction impacts to businesses and tourism

• Preserve historical and cultural significance

Page 18: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Recommended Design Features

• Face of wall: 10-15 feet inland

• Soil stabilization with jet grouting

• Continuous migration corridor and nearshore restoration

• Restored Alaskan Way and pedestrian/bicycle facilities

• Early program wins

Page 19: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Soil Stabilization: Jet Grouting

• Standards – 1,000 year seismic event

– 75-year design life

• Structure – Directly addresses soil

liquefaction problem

• Time – Potentially faster

construction

• Cost – Lower than other options

Page 20: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Potential Habitat

Enhancements

• New seawall

• Intertidal corridor

• Lighting

• Riparian vegetation

• Textured wall

• Substrate

enhancement

• Cobble reefs

Potential Habitat Enhancement Measures

Page 21: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Existing – Zone 1

Page 22: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Proposed – Zone 1

Page 23: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Existing – Zone 1

Page 24: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Proposed – Zone 1

15’

Page 25: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Existing – Zone 2

Page 26: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

15’

Proposed – Zone 2

Page 27: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Existing – Zone 3

Page 28: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Proposed – Zone 3

10-15’

Page 29: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Existing – Zone 4

Page 30: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Proposed – Zone 4

10’

Page 31: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Existing – Zone 4

Page 32: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Proposed – Zone 4

10’ 10’

Page 33: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Breakdown of 35% Cost Estimate

Design and Environmental

16%

Soil Stabilization

72%

Ecosystem Restoration

4% Roadway and Access

8%

7/30/2012

Phase 1 Cost: $300M

Page 34: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Delivering Final Design

Page 35: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Key Design and Cost Questions after 35%

Structural:

Do we have the most streamlined, elegant structure, with few redundant elements?

Work sequence:

Can we maximize access and minimize impact for:

• Businesses

• Users

• Environment

• Utilities

Page 36: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Moving to Final Design

35% Design Preliminary Approach to Final Design

Page 37: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Design Team Organization

Page 38: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Systems Approach

• Waterfront vision

• Transportation

• Seawall structure

• Utilities

• Habitat

• Public realm

Page 39: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Defining the Public Realm

Page 40: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zones 1 & 2: Washington St & Colman Dock

Page 41: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zone 1 – Plan View

Page 42: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zone 1 – Cross Section

Page 43: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zone 3: Historic Piers

Page 44: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Outfalls and Habitat Benches

Page 45: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Light Penetrating Surfaces (LPS)

Glass blocks Glass plank panels

Solar tubes Grating

Page 46: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zone 4: Seattle Aquarium

Page 47: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zone 4 – Plan View

Page 48: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Zone 4 – Cross Section

Page 49: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Upcoming Fall Events and Outreach

• Light penetrating surfaces

study on Pier 62/63

• Habitat/fish migration

studies

• Habitat education

• Fairs, festivals, events

• Briefings

• Collaboration with

Waterfront Seattle activities

Page 50: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M

Contact Information