SDO Status

1
SDO Status HMI & AIA & EVE all integrated onto SDO Doing “CPT” now. PER 15 March Deliver to KSC August Ready for launch 1 Dec THIS YEAR Likely launch still Jan ’09 JSOC development continuing Hardware ordered, some arrived, rest in March New hardware operating by April DRMS/SUMS nearing completion Export tools lagging Level-0 done soon (c. 2 weeks) Level-1 getting started Level-2 (pipeline modules) ready to get moving ASAP Teams Meeting in March – register by 7 Feb. Hope for “SDO Science Center” AO before March – NOT FINAL YET !!!

description

SDO Status. HMI & AIA & EVE all integrated onto SDO Doing “CPT” now. PER 15 March Deliver to KSC August Ready for launch 1 Dec THIS YEAR Likely launch still Jan ’09 JSOC development continuing Hardware ordered, some arrived, rest in March New hardware operating by April - PowerPoint PPT Presentation

Transcript of SDO Status

Page 1: SDO Status

SDO Status• HMI & AIA & EVE all integrated onto SDO• Doing “CPT” now.• PER 15 March• Deliver to KSC August• Ready for launch 1 Dec THIS YEAR• Likely launch still Jan ’09• JSOC development continuing

– Hardware ordered, some arrived, rest in March– New hardware operating by April– DRMS/SUMS nearing completion– Export tools lagging– Level-0 done soon (c. 2 weeks)– Level-1 getting started– Level-2 (pipeline modules) ready to get moving ASAP

• Teams Meeting in March – register by 7 Feb.• Hope for “SDO Science Center” AO before March – NOT FINAL YET !!!