SCT Service Installation

18
27 September 2005 A.Ciocio - ID Week 1 SCT Service Installation • Overview • Status of Type IV Cable Installation • Type II/III Cable Installation • Plan for the next six months Safety course today @ 12:45

description

SCT Service Installation. Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the next six months Safety course today @ 12:45. Overview. 2044 (+spares) double length Type IV cables (Power & Control) from PP3 racks through holes to US(A)15 racks - PowerPoint PPT Presentation

Transcript of SCT Service Installation

Page 1: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 1

SCT Service Installation

• Overview

• Status of Type IV Cable Installation

• Type II/III Cable Installation

• Plan for the next six months

Safety course today @ 12:45

Page 2: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 2

Overview • 2044 (+spares) double length Type IV cables (Power & Control) from PP3

racks through holes to US(A)15 racks• 4088 (+100 spares) Type II/III (spliced on the outside of the calorimeter and

up at z=0) from PPB(F)1 to PP3 racks• DCS, Heater Cables, and PP3 (will be discussed in the ID installation)• 8 PP3 racks in each side of the cavern (US&USA sides)

– Up to 10 crates of 30 PP3 units

• 11 power racks in US15 and 11 in USA15– Up to 4 crates of 48 channels

• TC installation team: – S.Malyukov, E.Kudinov, L.Reed, N.Massol – 27 people from IHEP Protvino– Several teams are working in parallel (~9 people per team)

Page 3: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 3

PP3 Racks in UX15 (US15 side)

Y.52-4.X7, Y.53-4.X7Y.52-1.X6, Y.46-1.X6Y.43-1.X6, Y.34-1.X6Y.51-2.X2, Y.52-2.X2

Page 4: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 4

PP3 Racks in UX15 (USA15 side)

Y.51-23.X8 Y.52-23.X8 Y.53-23.X8Y.51-26.X5, Y.53-26.X5Y.52-25.X2, Y.53-25.X2Y.51-25.X1

Page 5: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 5

Layout of PP3 rack in UX cavern

Page 6: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 6

PP3 to USPP3 rack US rack hole

UX/US

Y.37-1.X6 Y.05-14.S2 12

Y.43-1.X6 Y.10-15.S2 11

Y.43-1.X6 Y.11-15.S2 10

Y.47-1.X6 Y.11-15.S2 10

Y.43-1.X6 Y.12-15.S2 9

Y.47-1.X6 Y.12-15.S2 9

Y.52-1.X6 Y.23-15.S2 7

Y.52-4.X7 Y.23-15.S2 7

Y.52-4.X7 Y.24-15.S2 21

Y.53-4.X7 Y.25-15.S2 20

Y.53-2.X2 Y.26-15.S2 6

Y.51-2.X2 Y.27-15.S2 19

Y.53-4.X7 Y.27-15.S2 19

Y.51-2.X2 Y.28-15.S2 5

Y.52-1.X6 Y.28-15.S2 5

Y.52-2.X2 Y.29-15.S2 4

Page 7: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 7

Installation of Type IV Cables• Type IV cables are delivered in double lengths and pulled between the UX15 and the

US(A) caverns

• ~800 pieces (double length cables) installed on US side (almost completed)– Up to 40 cables per day pulled from UX to US(A)

UX side US(A) sidePP3 Power Supply

Dummy PP3Racks on Level 6US side

Hole

Page 8: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 8

In US15• Cut cables and connectors on the power supply side

installed in situ• First rack (200 cables/connectors) completed early in July

– Work performed by SEDELEC (subcontract of KontaktSysteme that provides the double length cables

– Many mistakes (~20 connectors have just been repaired) several label mismatch still to be fixed

– They raised the cost significantly for future connector work

• New Plan– TC will help with connector attachment– Nicolas Massol joined TC in September. One of his tasks is to

organize connector activity – Work with Petr Kubik (Prague) to discuss technical aspects and

qualify samples made by other companies being contacted– Meanwhile cables are being cut to some extra length and ~ all

tooling has been purchased to make prototypes

Page 9: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 9

Delivery Issues

• Installation rate driven by delivery schedule– Delivery in July/August was very slow

• Vacation and QA problems• Connectors quality• Bobbins damage

– Bobbins already at CERN are going to be sent back to the fabrication company (Novacavi) to get cleaned up

• Delay of components delivery from CERN to company• Need to keep contact with CERN purchasing and Vendor

• Ramp up – 200 pieces/week expected soon after bobbins damage crisis is

solved but so far the max number of pieces we have seen is 120– Hopefully all type-IV delivered by mid-November

Page 10: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 10

Delivery (QA - Connectors)

• Connector’s signal wires too long• Some cables couldn’t be used• One week halt of production

Page 11: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 11

Delivery (QA - Packaging)

• Packaging: palette were sent with only plastic wrap around bundles

• Cables were getting wet during transportation and delivery at CERN

• About 40 cables lost (~30 in one delivery)

Page 12: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 12

Delivery (QA - Bobbins)• Cable bobbins dirty and damaged

• Bobbins are kept outside (at CERN) for long time

• Other (than water) damage under investigation

• Company claims delay in fabrication to deal with these problems

• Don’t know yet delay due to shipping bobbins back to Italy

Page 13: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 13

Type II/III Cables

• Double harness ordered from Ineo• Work on splicing started in August• Installation of connectors on the PP3 end at the factory

– Need to provide exact length for both types– Use dummy PP1 with some load to test that the splice didn’t get damaged after installation– JST and FCI connectors very delicate – better to test at the PP3 end

• Two Contracts first to produce all the harnesses and then to install the connectors• Splice is verified at the company• Need QA going on during production• Last visit by Pepe B. Maarit W. and Laurent Gillain(CERN purchasing) quite

satisfactory• By November all harness will be made• Cables with PP3 connectors between November and March

Connector type II:JST SHDR-20V-S-B and FCI65239-002

Connector type III:CONEC 3017W5PBK99A1OX, 131C11019X, and 132J14019

MPP2(Type III)

Splicing connection

Strip-Back Length

B

MPPBF1(Type II)

Strip-Back Length

A

Foil Shield

Page 14: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 14

Current Installation Activities (Type IV)• Overall coordination (Sandra)

– Work closely with Sergei Malyukov and the TC team – Provide complete layout/mapping for racks in both sides

– Bjarne is still helping from Bergen

– Regular presence to check mapping/labels and prepare racks – Discussion on installation priority and occasional revise original layout– update DB table and EDMS documents*– Organize cable testing shifts

• Connector at the power supply end (Petr Kubik/Prague)• Cable testing (Sandra, Petr and SCT Collaboration)• Follow up cable procurement and delivery (Pippa, Sandra, Maarit/TC)• PP3 installation soon (Ashley French/Melbourne with Petr)

*SCT Cables EDMS ID: 624679, Cable Procurement Follow up table ID:508310,

Overall Safety and Health Procedure ID: 593278

Page 15: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 15

Type IV Testing• Tester designed and provided by Ljubljana (Gregor, Erik)

– 2 Test box + 2 Laptops + test cables– Gregor and Erik upgraded features of tester in July– Web based DB

• Test steps:– Cables are tested at reception (acceptance test)– After being pulled from UX15 to US(A)15 (uncut-double length)– After they are cut in the US side at connectors are installed

• Shift planner (developed by D. Robinson) works very well for planning the activities and have people to sign up

• http://www.hep.phy.cam.ac.uk/si-bin/sctworkplanner.cgi– (register and contact me)

• What is needed to be able to take a shift:1) take the 3-levels safety training course (at the pompiers station)2) make the access request on EDH (ATLAS-U, LHC Tunnel)3) get your safety boots & helmet at the CERN store (or borrow them)

Page 16: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 16

Procurement Schedule

• Type IV delivered and installed December

• Connector work of Type IV (power supply end) could start in 3 weeks and it will take ~4 months January

• Type II/III double harness with splicing Januarysingle cable with PP3 connector Nov-March

• PP3 delivery and installation Oct/Nov

Page 17: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 17

Work Plan

Page 18: SCT Service Installation

27 September 2005 A.Ciocio - ID Week 18

Safety Training Course