Scrap Convergence Plan Wuhan lens line #1 Update Feb 5 th Frédéric MORET Feb 5, 2007.
-
Upload
lewis-joseph -
Category
Documents
-
view
216 -
download
0
Transcript of Scrap Convergence Plan Wuhan lens line #1 Update Feb 5 th Frédéric MORET Feb 5, 2007.
Scrap Convergence PlanWuhan lens line #1Update Feb 5th
Frédéric MORETFrédéric MORETFeb 5, 2007
Property of Valeo – Duplication prohibitedJanuary 2005
2
Scrap Convergence Plan – Wuhan lens line #1Background
Wuhan lens line #1 results were: > 50% scrap rate
< 40% normal capacity
since it started in April 2006
Wuhan Saico Single Lens Production and Scrap Trend
0%
5%
10%
15%
20%
25%
30%
0
2000
4000
6000
8000
10000
12000
14000
16000
Pro
du
cti
on
Mold Scrap 18,7% 28,9% 11,6% 26,0% 11,7% 18,7% 12,3% 10,8% 10,3% 9,8% 11,8% 12,0% 10,8%
Coat Scrap 58,6% 33,3% 20,9% 43,4% 47,1% 41,3% 51,8% 49,6% 46,8% 42,0% 39,8% 47,0% 45,1%
Total Scrap 77,3% 62,2% 32,5% 69,4% 58,8% 60,0% 64,1% 60,4% 57,1% 51,8% 51,6% 59,0% 55,9%
Real Production 2117 1988 7669 2549 2808 2430 3509 2763 5295 5123 5407 8777 5820
Planned Production
22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec
Property of Valeo – Duplication prohibitedJanuary 2005
3
Scrap Convergence Plan – Wuhan lens line #1 Background
VLS fast recovery plan
20% scrap rate target by end of Jan 07 for Wuhan lens line #1
Branch coating specialist staying in Wuhan forcing results
No recorded scrap improvement after 2 months
Decision to launch scrap convergence plan on Jan 3 in order to achieve VLS fast recovery plan target
5. Scrap reduction J. Gregory
Conf call every 2 days with team in Wuhan to force results J. Gregory
Continue implementation and assure A. Chenet stays in Wuhan until result is achieved - Will stay until 12/20 then back after hoilidays
A. Chenet - Branch coating
specialistCheck each action and assure on track and effectively implemented - force immediate reaction if not on track - doing it but no scrap recorded improvement yet Stay on the system and force results
A. Chenet - Branch coating
specialist
Action - ObjectiveResults week -1
Wuhan Lens Scrap - fully implement STOP Scpap/IRIS to reduce average scrap rate from 50% to 20% by end of January
Cat
eg
ory
Action week +1 Responsible
Property of Valeo – Duplication prohibitedJanuary 2005
4
Scrap Convergence Plan – Wuhan lens line #1 Scope To reduce Wuhan lens line #1 average scrap rate:
From >50 to 20% from February 1st, 2007
From 20 to 10% from April 1st, 2007
Include trainings & networking to keep consistent results over time
0
10
20
30
40
50
60
Nov Dec Jan Feb Mar Apr
Before plan
Achieved
Expected
Property of Valeo – Duplication prohibitedJanuary 2005
5
WuHan SaiCo Sigle Lens Production and Scrap Trend
0,0%
10,0%
20,0%
30,0%
40,0%
50,0%
60,0%
70,0%
week
scra
p
0
2000
4000
6000
8000
10000
12000
prod
uctio
n
Mold Scrap 11,7% 18,7% 12,3% 10,8% 10,3% 9,8% 11,8% 12,0% 10,8% 11,2% 10,0% 11,8% 11,8% 13,8% 10,2% 7,4%
Coat Scrap 47,1% 41,3% 51,8% 49,6% 46,8% 42,0% 39,8% 47,0% 45,1% 43,0% 31,5% 41,7% 30,3% 28,0% 29,1% 15,9%
Total Scrap 58,8% 60,0% 64,1% 60,4% 57,1% 51,8% 51,6% 59,0% 55,9% 54,2% 41,4% 53,5% 42,0% 41,8% 39,3% 23,3%
Real Production 2808 2430 3509 2763 5295 5123 5407 4455 3820 4386 6824 3900 6621 6679 7119 9966
Real Production
W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W01 W02 W03 W04 W05
Scrap Convergence Plan – Wuhan lens line #1 Latest scrap & production weekly results
Close to target before Feb 1st
Arrival of Branch team. Reduction of cycle times
W2 & 3: Trials & tunings
resulting in scrap
Property of Valeo – Duplication prohibitedJanuary 2005
6
Scrap Convergence Plan – Wuhan lens line #1 Agenda of presentation
Step II: Achievements & status Team, organization & trainings
Capacity
Equipment
Molding
Coating
Inspection
Step III: Action plan & expected results
Property of Valeo – Duplication prohibitedJanuary 2005
7
Scrap Convergence Plan – Wuhan lens line #1 Team
Name Company Function Office Involvt January February
4/1
5/1
6/1
7/1
8/1
9/1
10/1
11/1
12/1
13/1
14/1
15/1
16/1
17/1
18/1
19/1
20/1
21/1
22/1
23/1
24/1
25/1
26/1
27/1
28/1
29/1
30/1
31/1
1/2
2/2
3/2
4/2
Team mgt F. Moret Valeo Management Bobigny 100%D. Daï Valeo Plant mgt Wuhan 30%Q. Zhou Valeo APU mgt Wuhan 50%C. Jinsong Valeo Supervisor Wuhan 100%
Coating F. Kanazawa Valeo Process Bobigny 100%process & A. Chenet Valeo Process Bobigny 100%equipment J.P. Dubois Valeo Process Bobigny 100%
G. Vottero Valeo Equipment Pianezza 80%M. Bourgeois Valeo Equipment Wuhan 25%M. Delorme Valeo Purchasing Wuhan 10%E. Dai Valeo Purchasing Wuhan 10%W. Wang Valeo Process Wuhan 50%W. Yang Valeo Maintenance Wuhan 30%
Jig toolmaker Equipment Wuhan 100%Jig toolmaker Equipment Wuhan 100%
Molding M. Hugol Valeo Process Bobigny 100%process & A.A. Racaud Valeo Process Bobigny 100%equipment J. Ortiz Valeo Process Wuhan 50%
J. Truong Valeo Process Wuhan (VIE) 100%N. Castellino Valeo Process Wuhan (VIE) 100%M. Bourgeois Valeo Equipment Wuhan 25%R. Pehl Valeo Purchasing Bobigny 5%M. Delorme Valeo Purchasing Wuhan 5%
MEP Process China 100%FKK Equipment China 100%Toolmaker Equipment China 100%
Quality C. De Poncins Valeo Industrial Bobigny 100%inspection M. Li Valeo VPS Wuhan 100%
Z. Luo Valeo Quality Wuhan 100%
Arrival of Branch team
in Wuhan
Decision for new
organization
Integration of 2 jig makers
2 people in charge of
new T21 jigs
Production of W5 totally managed by Wuhan
team without any support of Branch team
Property of Valeo – Duplication prohibitedJanuary 2005
8
Scrap Convergence Plan – Wuhan lens line #1 Organization
« Product » APU organizationsince Sept 1, 2006
People having backgroundto manage lens line
Change in organization since Jan 26, 2007 to restore « process » APU structure
Champion for lens line
scrap reduction
Champion for HL
assembly
Future Champion for
lens scrap reduction to be
coached by present one
Property of Valeo – Duplication prohibitedJanuary 2005
9
Scrap Convergence Plan – Wuhan lens line #1 Trainings Trainings done
In meeting room– 5 courses
Reaction modes for:– Molding defects– Grain defect (varnishing)– Fallen lens & varnish dot defects (varnishing)
Inspection– IRIS– Lens inspection
– 30-35 people attending each time
OJT– 5 trainings
Supplier for jig manufacturing Production team for jig tuning Production team for molding Maintenance team Quality inspection
Property of Valeo – Duplication prohibitedJanuary 2005
10
Scrap Convergence Plan – Wuhan lens line #1 Documentation
Database All results &
documents related to this plan, including updated action plans
All data related to lens line & its maintenance
Booklet Reaction modes Working instructions Main messages of
trainings
Property of Valeo – Duplication prohibitedJanuary 2005
11
Scrap Convergence Plan – Wuhan lens line #1 Organization
Further improvements of the team Coaching of line supervisor by APU manager
Varnishing method engineer position to fill
Property of Valeo – Duplication prohibitedJanuary 2005
12
Scrap Convergence Plan – Wuhan lens line #1 Capacity
Capacity issue because of low « real » TRS
Snowball effect Not enough capacity No time to improve More inefficiency
1st priority has been to recover capacity and to use it for improving: Reduce injection cycle time (-24%) Reduce changeover time by
installing a fork on press platen (-30%)
Learn team how to avoid stoppages Do not accept new product trials
which are not mandatory
Maintenance overtime
3%Changeover
overtime17%
Stoppages13%
Over cycle time18%
Scrap27%
TRS22%
Maintenance overtime
3%Changeover
overtime17%
Stoppages6%
Over cycle time0%
Scrap30%
TRS44%
Maintenance overtime
1%
Changeover overtime
10%Stoppages1%
Over cycle time0%
Scrap18%
TRS70%
Property of Valeo – Duplication prohibitedJanuary 2005
13
Scrap Convergence Plan – Wuhan lens line #1 Equipment
No major issue on equipment & maintenance Haitian press & Wittmann robot
– No major issue
– Maintenance action plan done: Hot runner heater changed, robot gear changed
Saico line– No major issue
– Maintenance globally well done
– Maintenance action plan done: 13 improvements, detailed maintenance documents
Property of Valeo – Duplication prohibitedJanuary 2005
14
Scrap Convergence Plan – Wuhan lens line #1 Achievements & Status
Molding Molds
– X11J: No major issue
– R23: Small crack issue, solved by team (change in tool)
– T21: Silver streak (5%) because of poor design & making of tool, cannot be solved by process, needs a tool improvement (on-going action plan). Design of new tool (expected by end of March) checked.
Operation– Black dot scrap reduced by avoiding stoppages and respect of re-
start instruction
Property of Valeo – Duplication prohibitedJanuary 2005
15
Scrap Convergence Plan – Wuhan lens line #1 Achievements & Status
Coating Jigs
– For all: poor making and bad tuning In-feed conveyor: All jigs tuned as well as possible, new jig
design tested on Feb 1st
Varnishing conveyor: – X11J & R23: Tuning of jig improved– T21: New design of jig tested, complete new set done,
installed on Feb 1st
Process– No major issue, some flow-coater tunings have been improved
Operation– Bad jig design and tuning results in many door opening (to set
lens on jig) and so many grain and varnish dot defects. Improved by team, still possible to improve.
Property of Valeo – Duplication prohibitedJanuary 2005
16
Scrap Convergence Plan – Wuhan lens line #1 Jig sub-project Design & manufacturing of new
T21 jigs as a project
Selection of supplier (8 visited), 1 selected
– Good design & manufacturing means, but no autonomy in design & manufacturing
Training of supplier for design, prototyping & manufacturing
Making & test of prototype 1: OK
Making & test of prototype 2 (simplified design): OK
Making of complete set
Installation & tuning of complete set on Feb 1
Detailed manufacturing instruction provided
Property of Valeo – Duplication prohibitedJanuary 2005
17
Scrap Convergence Plan – Wuhan lens line #1 Achievements & Status
Quality inspection & logistics
IRIS– Badly known and implemented resulting in overquality. Training provided, tools updated.
Production quality– Defects badly known by operators. No inspection standard per product. Setting of operator training
by quality each 2 weeks. Update of all inspection standards.– Re-organization of line quality, in order upstream quality engineer is now in charge of auditing
quality of all actions on the line.– QRAP restarted. – Rules for standard reaction defined (line QRQC). Action plan defined with quality, time schedule to
be defined with APU manager and supervisor.– Line management: Display boards re-organized to provide just necessary up-to-date information
Logistics– Use of cardboxes, plastic bags and foam sheets for packaging WIP lenses resulting in many wastes
(operator time, footprint, scrap, packaging materials). Was limitating cycle time reduction. Replaced by standard lens plastic totes.
Scrap follow-up sheet (Kosu sheet)– Sheet updated for defect definition (more precise), removal of injection trial shots. Change to be
made to remove a mistake in fallen part calculation.
STOP Scrap– Standard display of trend charts and action plans for X11J and T21. Definition of scrap
convergence plan actions according to STOP Scrap system.
Property of Valeo – Duplication prohibitedJanuary 2005
18
Scrap Convergence Plan – Wuhan lens line #1 Step II
Main issues remaining on Jan 22 Varnish dot defect on T21 (18% of total scrap)
– Only solution is new jig (tested, production of complete set followed-up by Marc Bourgeois)
Grain defect on X11J (16% of total scrap)– Closed door operation (to be followed-up by supervisor)
Silver streaks on T21 (9% of total scrap)– Injection process parameters to be developed by Maxime Hugol
Fallen parts on all products (7% of total scrap)– Robot & jig tuning (to be followed-up by supervisor)
Stoppages, maintenance & changeover delays (5% of total scraps, 40% of productive time)
– Short mold changeover device to be used, maintenance & operation management (to be followed-up more closely by maintenance manager & supervisor)
Property of Valeo – Duplication prohibitedJanuary 2005
19
Scrap Convergence Plan – Wuhan lens line #1 Step II Roadmap defined on Jan 22
W4: Closed door operation for X11J, jig tuning for fallen parts, closer management to reduce stoppage & changeover times
W5: New jig for T21, new injection process parameters for T21, jig tuning for fallen parts, closer management to reduce stoppage & changeover times
W6 & W7: Tunings to decrease rate of other scraps
0
20
40
60
80
Scrap (%)
Stop (%)
TRS (%)
Scrap (%) 40 32 22 20 18
Stop (%) 40 30 13 13 13
TRS (%) 36 47 68 70 72
W3 W4 W5 W6 W7
Property of Valeo – Duplication prohibitedJanuary 2005
20
Scrap Convergence Plan – Wuhan lens line #1 Step III To reduce Wuhan lens line #1 average scrap rate:
From 20 to 10% from April 1st, 2007
Definition of action plans in progress
2nd period of Branch team defined (3 weeks in March)
0
10
20
30
40
50
60
Nov Dec Jan Feb Mar Apr
Before plan
Achieved
Expected