SCOPE OF WORK AND TECHNICAL SPECIFICATIONS, TECHNICAL … · Dehydration Package). However general...

33
PEPL/CBM/INTR/LC/GCDGU/06-R/2019 1 SCOPE OF WORK AND TECHNICAL SPECIFICATIONS, TECHNICAL PART OF SPECIAL CONDITIONS OF CONTRACT & SPECIAL TERMS AND CONDITIONS FOR HIRING GAS COMPRESSION AND DEHYDRATION SERVICES FOR THE NORTH KARANPURA CBM BLOCK .

Transcript of SCOPE OF WORK AND TECHNICAL SPECIFICATIONS, TECHNICAL … · Dehydration Package). However general...

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

1

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS,

TECHNICAL PART OF SPECIAL CONDITIONS OF CONTRACT & SPECIAL TERMS AND CONDITIONS

FOR HIRING GAS COMPRESSION AND DEHYDRATION SERVICES FOR THE NORTH KARANPURA CBM

BLOCK.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

2

1 INTRODUCTION OF PROJECT

2 ABOUT TENDER

3 Tender Description

4 TECHNICAL PART OF SPECIAL CONDITIONS OF CONTRACT

5 Other Conditions of the Contract

6 The Contractor will be required to demonstrate that:

7 Facilities to be provided at site by PEPL

8 Other responsibility of contactor

9 Safety aspects & Shut-down requirements

10 Excess gas compression

11 De-commissioning, Demobilization & Transport-out

12 Time Schedule

13 APPENDIX A - DATA SHEET

14 Appendix B (LOG RECORD FOR GAS COMPRESSOR & DEHYDRATION PACKAGE(S)

15 Appendix C – NOT IN USE

16 Appendix D

17 Appendix E

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

3

1. INTRODUCTION OF PROJECT

The North Karanpura Coalfield is the western most and second largest (1230 km2) coal basin of the Hazaribagh, Palamu and Chatra districts of Jharkhand, India. It is situated about 60 km northwest of Ranchi and 20km SW of Hazaribagh. North Karanpura CBM Block (NK-CBM-2001/1) is a part of the North Karanpura Coal field covering an area of 340 sq. Kms. Subsequent to relinquishment of 68.5 sq.km area after initial assessment, 271.5 sq.km are left for CBM exploration and development. Presently, approx. 49 sq. kms area has been carved out for initial development with a provision for further development in future. The North Karanpura block area is sparsely populated with a forest cover of over 20% of the area. Active coal mines are few in this coalfield and all are located outside the block area. The block area is approachable from Ranchi on the southern side and Hazaribagh on the northern side by all-weather metaled road, which in turn connects to nearby towns by fair-weathered metaled roads. The nearest domestic airport is located at Ranchi. Ramgarh is the nearest town with railway station.

The location map of North Karanpura CBM block

Map of North Karanpura CBM Block Showing Block Boundaries

Map of North Karanpura CBM Block Showing Sectors, Relinquished Area, FDP and NTPC Coal Block

North Karanpura

Block

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

4

PEPL, referred to as Company, on behalf of consortium partner comprises of PEPL, ONGC & IOCL have started CBM development operations by drilling 68 vertical wells in North Karanpura CBM Block NK-CBM-2001/1, Jharkhand starting in the year of 2017-18.

2. ABOUT TENDER Company proposes to award a Contract for providing the services of Gas Compressors (compression upto 255 brag) and Dehydration units at well No. NK#6 or PEPL designated site within the block area referred to as “Installation” on hire basis. Contactor has to provide these units as per detail given in the tender on the rental basis inclusive of supplying, commissioning, operation and maintenance and providing substitute units to meet the operational requirement without any interruption in the operations. Gas will be collected from 4 to 5 wells connected to Installation at inlet manifold. Gas produced from the wells will be coming to Installation after initial separation of any water, at well site, produced along with gas, through a vertical separator. The battery limit for Contractor’s scope in this tender will be after the outlet flange of Knock out drum (Low pressure Separator) at Installation till inlet manifold of CNG dispensing system. All system requirements in between outlet of KOD and inlet of manifold of CNG dispensing system for compressing and dehydrating the gas upto 255 barg will be the responsibility of Contactor. 2.1. Hiring Of Gas Compression and Dehydration Services: Compression service will be required as per details given in table.

Sr. No

Installation Quantity of gas

Remark

1. NK#6 well or PEPL designated Site

20,000 SCMD (May go upto 30,000 SCMD)

10000 SCMD Gas at Installation will be available at a pressure of 0.75-1 kg/cm2 (g) to start with. Gas availability may be ramped up to 20,000 SCMD within a span of 2-3 months from the start.

3. Tender Description:

This tender is divided in two parts for ease to understand about the requirement, specification of Compressors Package (Part A: Gas Compressors Package) and Dehydration units (Part B: Gas Dehydration Package). However general and special conditions are given at common place. 3.1. A. Gas Compressors Package:

3.1.1. Broad guidelines: The scope of work shall broadly cover the following but, not be limited to:

i. Suitable compressor shed with proper illumination inside.

ii. Shed / room / protective covers for all equipment, electrical / instrumentation items as deemed necessary.

iii. Supply / transportation / installation of skid mounted compressor packages complete as per data sheet including gas engine, motors, auxiliaries, inter-coolers, after-coolers, separators,

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

5

scrubbers, skid piping, pressure vessels, Gas gensets, instruments and control systems, electrical items etc. However, during the subsequent mobilization of Compressor, data sheet shall be provided by the Contractor for the compressors, which is intended to be mobilize, for approval of PEPL.

iv. Gas detection system (two nos. of sensors) should be available at site. - 2 Nos. of sensors for individual compressor packages (As per OISD standard 116 & 117).

v. Exhausts of the gas engines are to be insulated with glass wool & covered by Stainless steel sheet to prevent heat radiation to keep the working atmosphere in safe condition for working personnel as per CPCB norms.

vi. Supply / transportation / installation of discharge knock out Drum/ filters. vii. Supply / transportation / installation of inlet gas filter/ intermediate gas filters, if required by

the Contractor. viii. Supply / transportation / installation of Fuel Gas Conditioning System including knock out

drum, pressure reducing control valves, etc as required by the Contractor. ix. Supply of Instrument & starting air supply, as necessary will have to be arranged by Contractor

at his own cost by providing suitable Instrument Air & Starting Air System. Only instrument air is to be used for the field instruments.

x. All other Process & Utility Systems as required. xi. Hook up and termination of inlet gas line, outlet gas line, PSVs relief line, flare line & fuel gas

line at the location designated by PEPL. Approximate distances for each hookup are as follows. Inlet gas line –10 M Outlet gas line – 20 M, PSVs relief line –20 M, Flare line –20 M Fuel gas line – 20 M

xii. Successful commissioning of the compressor packages. xiii. Operation and maintenance of the compressor units including deployment of trained

manpower, supply of all consumables, chemicals, lubricants, spare parts, tool & tackles and replacement of defective equipment’s, components, parts etc.

xiv. Maintaining sufficient inventory of spare parts, consumables, lubricants etc. for smooth and continuous operation.

xv. Any other items / work / services not specifically listed above but required for safe, reliable and desired operations of the compressor packages and delivering the compressed CBM gas at the specified conditions

xvi. Providing adequate Gas compression facilities at Installation including all civil, foundations, civil structure, electrical, instrumentation & piping works etc. in all respects including mechanical completion.

xvii. Providing suitable fuel gas flow metering and totalizing device. xviii. Pre-commissioning & commissioning of Gas compressor package systems with periodic

calibration of gas metering systems jointly with PEPL Representative, including the meter for fuel gas consumption by the Contractor.

xix. INLET-GAS: Low pressure CBM Gas will be made available at one point at the Battery Limit (i.e. at the outlet of KoD).

xx. OUTLET GAS: Compressed and dehydrated gas shall be collected at one point at the Battery Limit (i.e. at the location designated by PEPL for compressor installation within the installation). This is to be hooked up to the inlet manifold of CNG dispensing after gas compression and dehydration.

xxi. FLARE GAS: The flared gas (if any) from the compressor plant shall be collected at one point at the Battery Limit (i.e. at the hookup point with PEPL flare line location at a distance of approx 20m from the Compressor area designated by PEPL at Installation).

xxii. Period of contract will be for five years from the date of acceptance of compressor and dehydration unit at Installation after Third Party Inspection and successful trial runs as per

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

6

terms & conditions of tender xxiii. It shall be Contractor’s sole responsibility to strictly adhere to all statutory regulations &

DGMS norms & use only DGMS approved items wherever applicable including but not limited to Cables, Flow Computers etc.

3.1.2. Sites for Operation & Gas compressor packages features:

Gas compression facilities are to be provided at Installation as mentioned above. (Approximate land provided for the purpose is approx 20x30 meters).

i. The quantity of gas to be compressed at Compressors and other details are as follows:

Parameters Compression Quantity

20,000 standard cubic meter per day (SCMD). Quantity may go upto 30,000 SCMD. Contractor may be asked to install compressor of additional quantity. PEPL will give 4 months mobilization time for commissioning of additional compressor.

Prime mover Gas engine/ Hydraulic/ electric motor driven Suction Pressure 0.75 – 1 kg/cm2g Discharge Pressure Of System

255 barg (After Compression and dehydration at flowmeter installed before CNG dispensing system)

Suction Temperature 05 – 50 deg. C Discharge Temperature Max 55 deg C MSL 400-425 m Ambient Temperature 5 to 50 deg. C

Driver, accessories & auxiliaries

As per Contractor’s Requirement – no electricity will be available to Contractor. Gas available for compression shall be used as fuel for running all equipment

Composition of the gas Given below at 2.3.2 ii Configuration of Offered Compressor Package

Contractor will be required to offer compressors to meet the overall requirement of compression service for compressing 20,000 SCM/ per day. However, PEPL may ask Contractor to provide additional compression capacity of 10,000 SCMD. Contractor shall guarantee 95% availability of equipment for Compression and dehydration thorough out the operating month on prorate basis. Equipment available less that 95% in a month is subject to Liquidated Damages (LD) as per LD clause of the Contract. Contractor at its own judgment and cost may provide standby compressor to fulfill the Contractual commitment.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

7

The compressor capacity should be worked out at the worst set of operating parameters i.e. highest ambient temp, highest inlet gas temperature, lowest inlet pressure etc. and highest discharge pressure with given temperature.

ii. APPROXIMATE GAS COMPOSITION OF GAS TO BE COMPRESSED

Component/ Parameter Unit Avg. Value

Methane % v/v 97.09

Ethane % v/v 0.45

Propane % v/v 0.01

i Butane % v/v Traces

n Butane % v/v Traces

i Pentane % v/v Nil

n Pentane % v/v Nil

Hexane+ % v/v Nil

CO2 component % v/v 1.31

N2 component % v/v 1.12

Real Net Cal Value Kcal/M3 7955.51

Real Gross Cal Value Kcal/M3 8835.00

Real Avg. Mol. Wt. 16.61

Real Specific Gravity at 15 Degree C (Air-1)

0.6-0.7

Note: 1. Above values are average and individual gas component compositions may vary over a period of time depending upon reservoir conditions 2. Gas will be near wet characteristics.

3.1.3. Equipment Acceptance Criteria

i. The offered compressor should be reciprocating type, hydraulic, electric or any

combination ii. The offered gas compressor packages shall have to be certified by Charted

Engineer and verified by any of the 3rd party Inspection agency given clause 4.10 in the tender.

3.1.4. Inspection and testing at Site:

The compressor package shall be run continuously for minimum 72 hrs. TPI Agency shall issue inspection certificate on its letterhead confirming that the compressor meets the tender specifications. The certificate should include minimum but not limited to the followings: i. Suction pressure and rated flow for CBM gas. ii. Discharge pressure and rated flow for CBM gas.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

8

iii. Manufacturer of Gas engines and Compressor with sr. no., make, model, month and year of manufacturing of both engine and compressor are in conformity with submitted documents.

iv. Standards and codes under which engine and compressor have been manufactured are in conformity with submitted documents.

v. Name of the packager, Sr. No. of the package and year of packaging are in conformity with submitted documents.

vi. The equipment is capable of meeting compression capacity at the operating parameters specified in the tender.

3.1.5. Mobilization, Installation & Hook-up:

The Gas compressors package system(s) must be mobilized and made operational within a period of 120 days from the date of issue of the Letter/ email of Award. Mobilization will mean the following: i. Area clearance and civil job required to place Gas compressors package system(s)

and provide access to the unit: PEPL will make area available within 7 days of LOI if required by Contactor. Contactor can make his own assessment on this to complete the job in prescribed period to avoid LD etc.

ii. Gas Metering System is required for metering of gas volume which will be measured

after compression and dehydration using gas flow meter installed by PEPL. However bidder may keep his metering device for his monitoring purpose at a suitable location. The flow meter installed by PEPL will be periodically calibrated by OEM/OES/Certified agency in the presence of ONGC, IOC, PEPL and the Contractor.

For measurement of fuel gas consumption, one metering system for fuel gas has to be installed by the Contractor for measuring total gas (fuel) consumption for compressor, dehydration and other utilities.

iii. Calibration of all the gas flow meter installed by Contractor shall be carried out in presence of PEPL representative as per norms on the subject at regular intervals.

iv. Providing and fixing all accessories, attachments, instruments etc. and topping up

lube-oil, coolant etc. for operational readiness.

v. Laying of suction pipeline, discharge, flare line and fuel gas pipelines from compressor packages system(s), with hook-up. Contractor shall make his own assessment and design the pipelines as per applicable codes and standards suitable for the application.

vi. Providing all requisite consumables & manpower for pre-commissioning, commissioning and operation of the unit.

vii. The pipelines will be required to be laid mostly over-ground on supports and taken

under-ground for road crossing.

3.1.6. Commissioning:

Commissioning of Gas compressor packages system(s) at site will be as per Gas compressor manufacturer’s recommendations. In addition, the newly laid lines will be required to flush, clean and dried. Pre-commissioning/ commissioning will be done by Contractor’s personnel alone.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

9

Commissioning of the Gas compressor package will be done in presence of PEPL engineers/ PEPL authorized representative with intake of low pressure gas. At this stage, the gas compressor will be run for at least 72 hours without cost to PEPL for checking of system, capacity confirmation.

3.1.7. Operations & maintenance:

The Gas compressor package(s) will be required to operate round-the-clock on continuous basis and any maintenance required to be carried out shall be carried out by the Contractor. The Contractor will ensure presence of qualified and adequate personnel to operate the Gas compressors package(s). The Gas compressors package(s) must be compliant with legal requirements and shall be operated as per requirements of QHSE policy embracing ISO-9000, ISO-14001 and OSHAS-18001 standards as applicable (or any applicable on the subject). Contractor may be required to measure noise levels, monitor exhaust gas emission and follow rules regarding exhaust height location as per law of land. Also, Data regarding fuel, lube consumption etc. may be required to be submitted for QHSE requirements, which Contractor has to comply with. Shutdown of the unit will entail application of Liquidated damages and/or Compensation for Non-compression and/or Termination under the respective clauses.

3.1.8. Non operation

In the event of non-operation of Gas compressor package(s) due to any reason attributable to the Contractor, other than Force Majeure, the same will be recorded by PEPL Shift In-charge in the format at Appendix –B, copy of which will be given to Contractor’s supervisor/ personnel at site. Time period of non-availability of compression services as per this record will be liable for Liquidated Damages and/or Compensation for Non-compression and/or Termination under the respective clauses. Once the Gas compressor package(s) is/are declared fit and ready to operate, Time will be recorded jointly by representative of contactor and PEPL.

During non-operation period of compressors for reasons attributable to Contractor, no payment will be made for dehydration also in addition to LD and other levies which will be applicable as mentioned in tender.

3.2. B Gas Dehydration Package

3.2.1. Capacity of Gas Dehydration Units

INSTALLATION Maximum Installed Capacity of Gas Dehydration Unit (SCMD)

At NK#6 well or designated site

30,000

On any single day during the operation, if the quantity of dehydrated gas is less than the contractual minimum quantity of respective installation due to reasons attributable to

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

10

Contractor, the liquidated damage will be levied as per Clause 4.2 on daily basis and settled at the month end.

The above gas dehydration capacity shall be measured at the outlet battery limit.

3.2.2. Design Basis:

Sl. No.

Installation

Required Installed Capacity of Dehydration Plant (SCMD)

Required Dehydration System

Maximum Temperature at the Inlet of the Dehydration Plant (Deg C)

Requirement of Gas Dehydration

1

NK#6 well or designated site

30,000

Glycol Dehydration/molecular sieve/ Any other suitable technology

55 Deg C as per PNGRB Guideline

Contractor is required to offer dehydration unit to

meet the overall requirement of dehydration

service

GAS COMPOSITION: Gas Compositions of inlet gas to the dehydration unit at Installation may be same as given in Clause 3.1.2 (ii).

PNGRB Gas quality specifications as per Gazette of India (regulations 5(5).8(1) (b) (I) implemented for gas supply through pipeline which is as follows: Parameters Limit Hydrocarbons dew point (Degree Celsius, max) * : 0 Water dew point (Degree Celsius, max) * : 0 Hydrogen Sulphide (ppm by wt. max.) : 5 Total Sulphur (ppm by wt. max.) : 10 Carbon dioxide (mole % max) : 6 Total inert (mole %) : 8 Temperature (Degree Celsius, max) : 55 Oxygen (% mole vol. max) : 0.2 * At the inlet of flow meter installed by PEPL after Compression and dehydration

As per the scope of work for gas dehydration, Contractor to strictly maintain water dew point and temperature of the outlet gas after compression & Dehydration as per PNGRB guidelines. Rest of the parameters will be taken care by PEPL.

3.2.3. Battery Limit Conditions:

The Battery limit conditions of gas at inlet and outlet along with ambient conditions are specified in the data sheets. The Contractor should guarantee delivery of dehydrated gas at the specified outlet conditions.

The Contractor should incorporate necessary facilities required to prevent carryover of free water/oil, if any, on inlet side of Dehydration unit.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

11

The typical composition for CBM gas available at Installation as specified in the table at clause 3.1.2 (ii) above. The gas composition indicated in the table is on dry basis. However, the gas is saturated with water. The gas composition is typical and is subject to variation encountered in CBM fields. No claims would be entertained on account of variation in gas composition. Bidders, at its own cost, may take gas samples for the well and get it analyzed from laboratory of their choice before submission of bids and design the system accordingly.

The data sheets must be duly signed and stamped by Manufacturer/Packager of the dehydration unit as well as the Bidder which confirms bidder’s acceptance to supply / install gas dehydration unit along with all system / subsystems as required in data sheet.

Bidders are required to take note of the variations as follows:

a) Average Molecular weight of gas is 16.61 however, variation in the molecular weight due

reservoir condition may occur. Since the gas is saturated with water, bidders are advised to consider this factor while calculating size of the gas dehydration unit. Standard separation system (inlet KoD) for water removal will be available at Installation before compressor packages. However if bidder feel necessary during design than incorporate necessary facilities required to prevent entry of free water in inlet of dehydration unit.

3.2.4. Scope Of Work for Dehydration Unit

The Contractor is required to dehydrate the CBM Gas available at the inlet of the gas dehydration unit and deliver the dehydrated CBM gas at the specified conditions at Flow meter by providing all necessary facilities, equipment’s, manpower, consumables, lubricants, spare parts, etc.

The Contractor’s scope of work encompasses total engineering, supply, transportation, installation, construction, commissioning, operation and maintenance of a suitable gas dehydration plant complete in all respects.

Contractor’s scope of work shall include all civil / structural / mechanical / piping / instrumentation / electrical works for the gas dehydration plant including but not limited to the following:

i. Supply / transportation / installation of skid mounted gas dehydration unit complete as

per data sheet including skid piping, pressure vessels, instruments and control systems, electrical items, all utility systems including power etc.

ii. Supply / transportation / installation of Fuel Gas Conditioning System if required including knock out drums, pressure reducing control valves, etc.

iii. All other Process & Utility Systems as required. iv. All lines laying, hook up and termination (both inlet & outlet) of gas line to & from the gas

dehydration units, if needed, all PSVs & flare lines, fuel gas line etc. are to be done from & to the PEPL designated points. Ensuring PSVs for all pressure vessels as required by prescribed standards.

v. Supply, installation and maintenance of metering facilities for fuel gas line and Water Dew Point Analyzer

vi. Successful commissioning of the gas dehydration plant. vii. Any other items / works / services not specifically listed above but required for safe,

reliable and desired operation of the gas dehydration plant and delivering the dehydrated CBM gas at the specified conditions.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

12

viii. INLET-GAS: Low pressure CBM Gas will be made available at one point at the Battery Limit

(i.e. at the outlet of KoD). ix. OUTLET GAS: Compressed and dehydrated gas shall be collected at one point at the

Battery Limit (i.e. at the location designated by PEPL for compressor installation within the installation). This is to be hooked up to the inlet manifold of CNG dispensing after gas compression and dehydration.

x. FLARE GAS: The flared gas (if any) from the compressor plant shall be collected at one point at the Battery Limit (i.e. at the hookup point with PEPL flare line location at a distance of approx 20m from the Compressor area designated by PEPL at Installation).

xi. Dimensions of all available pipe lines to be hooked up at battery limit mentioned at ix, x, xi point above are as follows:

INSTALLATION

Present Inlet Gas line to Dehydration Unit (Inch)

Outlet Gas line from Dehydration Plant (Inch)

Flare Gas Line (Inch) from Dehydration Plant (Inch) to hookup with PEPL flare line

NK#6 well or designated site

As per compressor outlet

As per Contractor design

Contractor to decide

PEPL will provide hot work permit during day time (up to stipulated time i.e., up to sun set only) but prior intimation is required for the same. Contractor should also give assurance on fire & safety precautions & abide by the safety standards for the same.

3.2.5. The following systems / sub - systems should form part of the package

The gas dehydration package and its piping arrangement should be designed suitably taking into account the design basis & other parameters (gas composition, dehydrated gas specifications as per PNGRB guidelines etc.) brought out above. Contractor should submit P&ID diagram of the entire arrangement up to tie-in points well in advance and get the same approved by PEPL prior to starting of construction activity. Dehydration package may comprise of the following:

i. Gas Dehydration system ii. Instrument Air System (Air Compressor, Volume bottle etc.) iii. Fuel Gas Conditioning System, if required iv. Outlet Knock Out Drum or filters v. All other items not specifically listed above to make complete package vi. Local Control Panel if required vii. Shut Down Instruments if required viii. Safety valves ix. Piping. (Process, fuel gas, air etc.) x. Inlet knock out drum: Normally, additional Inlet Knock out Drum is not required before

(inlet of dehydration system) dehydration system. However Contactor to decide on the same depending on efficiency of his total system.

xi. Dehydration package should be designed for continuous operation in tropical ambient condition and should be suitable for classified hazardous area.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

13

xii. Outlet Knock-Out Drum/filters to prevent carryover of liquid in pipeline 3.2.6. General Requirement of Gas Dehydration System

i. Gas dehydration plant shall be designed, constructed and operated so as to meet the

requirements of applicable safety codes / standards.

ii. All electrical apparatus, instrumentation items / system shall be suitable for the hazardous area classification as per applicable oil & gas National / International standards and statutory regulations.

iii. All pressure vessels of the gas dehydration units need to be tested and a proof of such test

as certified by a reputed third party agency approved by PEPL, needs to be submitted prior to commissioning of the gas dehydration unit. Similarly, all PSVs should be tested / calibrated and a proof of such test as certified by manufacturer (in case of new PSVs) or certified by a reputed calibration agency for oil & gas industry (in case of old PSVs) needs to be submitted prior to commissioning of the gas dehydration unit.

iv. All systems should be designed, constructed and operated for uninterrupted continuous

operation to supply dehydrated gas at a point in PEPL’s pipe line (as designated by PEPL) at the specified pressure & temperature as per the specification of PNGRB

v. In case Contractor is not able to deliver the Contracted Quantity of dehydrated Gas due to reasons attributable to Contractor at the specified outlet conditions, it shall be treated as failure on part of the Contractor and dealt with in accordance with the Compensation Clause 4.2.3 of Technical Part of Special Conditions of Contract.

vi. All works / systems provided under this contract shall be designed and constructed in accordance with the prevalent Oil & Gas National / International standards, codes and practices.

vii. PEPL shall carryout inspection by itself or by designated third party, the facilities / equipment’s deployed by the Contractor and if any deficiencies are observed by PEPL or by designated third party, the Contractor shall rectify such deficiencies promptly upon receipt of such instructions from PEPL.

3.2.7. Mobilization, Installation & Hook-up:

The Gas Dehydration unit must be mobilized and made operational within a period of 120 days from the date of issue of the Letter/ email of Award. Mobilization will mean the following: i. Area clearance and civil job required to place Gas Dehydration package system(s) ii. No metering device will be required at Gas Dehydration stage, gas volume will be

measured by the flow meter installed by PEPL. However bidder may keep his metering device for his monitoring purpose at a suitable location.

For measurement of fuel gas consumption, one metering system for fuel gas has to be installed by Contractor for measuring total fuel consumption for compressors, dehydration and other utilities installed by Contractor. Calibration of gas flow meter to be carried out in presence of PEPL representative as per norms on the subject.

iii. Providing and fixing all accessories, attachments, and instruments etc. for

operational readiness.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

14

iv. Laying of suction, discharge and fuel gas pipelines between Gas compressors & dehydration package system(s), with hook-up.

v. Providing all requisite consumables & manpower for pre-commissioning, commissioning and operation of the unit.

The pipelines are required to be laid mostly over-ground on supports and taken under-ground for road crossing.

3.2.8. Commissioning:

Commissioning of Gas Dehydration package will be as per packager/ manufacturer’s/ OEM recommendations. In addition, the newly laid lines will be required to flush, clean and dried. Pre-commissioning will be done by Contractor’s personnel alone.

Commissioning of the Gas Dehydration package will be carried out in presence of PEPL engineers/ PEPL authorized representative with intake of gas from Compressors. At this stage, the dehydration package will be run for at least 72 hours without cost to PEPL for checking of system, capacity confirmation. A dew point meter shall be used for checking the dew point of gas. Dew point meter shall be provided by the Contactor.

3.2.9. Operation & maintenance:

The Gas Dehydration package(s) will be required to be operated round-the-clock on continuous basis and any maintenance required to be carried out shall be done by the Contractor. The Contractor will ensure presence of qualified and adequate personnel to operate the Gas Dehydration package Shutdown of the unit due to reasons attributable to Contractor will entail application of Liquidated damages and/or Compensation for Non-dehydrated gas and/or Termination under the respective clauses.

3.2.10. Non operation of Dehydration Unit

In the event of non-operation of Gas Dehydration package(s) due to reasons attributable to the Contractor, the same will be recorded by PEPL Shift In-charge in the format at Appendix –B, copy of which will be given to Contractor’s supervisor/ personnel at site. Time period of non-availability of dehydration services as per this record will be liable for Liquidated Damages and/or Compensation for Non-dehydration and/or Termination under the respective clauses. Once the Gas Dehydration package is declared fit and ready to operate, Time will be recorded jointly by representative of contactor and PEPL.

During non-operation period of dehydration unit, no payment will be made for compression also in addition to LD and other levies etc. will be applicable as mentioned in tender.

4. TECHNICAL PART OF SPECIAL CONDITIONS OF CONTRACT

4.1. General:

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

15

4.1.1. These “Special Conditions of Contract" shall over-ride the "General Conditions of Contract" and "Technical specifications", wherever required.

4.1.2. The work may have to be carried out in restricted area/conditions, the Contractor shall have to carry out such works without any extra payment as per instructions of Engineer-In-Charge ensuring and complying with all safety regulations and requirements. A flame arrester, attached to the equipment/vehicles run by petroleum products, is mandatory in such circumstances.

4.2. Failure & Termination / Liquidated Damages / Recovery / Compensation:

4.2.1. Delay in Mobilisation and Liquidated Damages:

i. CONTRACTOR (successful bidder) shall mobilize and deploy the required

manpower and complete CBM gas Compressor and Dehydration unit, so as to commence the services at the specified site within a maximum of 120 days from the date of email order / LOA.

ii. If the CONTRACTOR (successful bidder) fails to mobilize and deploy the

required manpower /equipment and / or fails to commence the services within the period specified in sub clause (i) above, PEPL shall have, without prejudice to any other right or remedy in law or contract including sub clause (iii) below, the right to terminate the contract.

iii. If the CONTRACTOR is unable to mobilize / deploy and commence the services

within the period specified in sub clause (i) above, it may request PEPL for extension of the time with unconditionally agreeing for levy and recovery of LD. Upon receipt of such a request, PEPL may at its discretion, extend the period of mobilization and shall recover from the Contractor, as an ascertained and agreed Liquidated Damages, a sum of equivalent to ½% of the total contract value, for each week of delay on prorata basis , subject to a maximum of 10% of the total Contract value.

iv. Delay in mobilization of additional compressor (10,000 SCMD): If the

CONTRACTOR is unable to mobilize / deploy and commence of additional compressor within the period 120 days, it may request PEPL for extension of the time with unconditionally agreeing for levy and recovery of LD. Upon receipt of such a request, PEPL may at its discretion, extend the period of mobilization of additional compressor and shall recover from the Contractor, as an ascertained and agreed Liquidated Damages, a sum of equivalent to ½ % of the calculated total contract value for additional compressor, for each week of delay on prorata basis, subject to a maximum of 10% of the total Contract value for additional Compressor.

Example: If Contractor quotes total contract value of compression and dehydration charges of 20,000 SCMD gas as ‘X’. After award of Contract, PEPL give callout for mobilization of additional compressor 10,000 SCMD after 14 months. However, contractor delays mobilization of equipment by 10 days for initial mobilization and 12 days for subsequent (additional mobilization). The procedure for calculating the LD for initial mobilization and additional mobilization will be as follows:

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

16

Calculation of LD for Initial Mobilization Total Contract Value– X Contract Period – 5 years Delay in Mobilization – 10 days LD on Mobilization = X * ½% * 10 / 7 Calculation of LD for additional Mobilization Total Contract Value– X Contract Period – 5 years Delay in Mobilization – 12 days Call out given after 14 months LD on Mobilization = (Total contract period (yrs) – time after callout for mobilization of additional compression given/12) * X * ½% * 12 / 7 *compression capacity of callout/compression capacity of as per contract LD on Mobilization = (5 – 14/12) * X * ½% * 12 / 7 * 10000 / 20000

v. Liquidated Damages for Delay in Demobilization: In case Contractor fails to demobilize, or delays in demobilization of Gas compressor package and dehydration system beyond 30 days’ time permitted for the same, liquidated damages will be charged @ Rs. 10,000 per day, subject to a maximum 10% of annualized total Contract value.

vi. The parties agree that the sum specified above is not a penalty but a genuine pre-estimate of the loss/damage which will be suffered by PEPL on account of delay on the part of the Contractor and the said amount will be payable without proof of actual loss or damage caused by such delay.

4.2.2. Breakdown/Shutdown of Equipment Contractor shall insure 95% availability of equipment installed for compression and dehydration of CBM gas. In the event, Contractor equipment is available less than 95% in a month for reasons attributable to the Contractor, Contractor shall pay compensation to PEPL equal to the daily fixed charged as per price bid on prorate basis. The total liability due to liquidated damages and/ or compensation due to non- dehydration of gas shall not exceed 50% of the annualized Contract value.

4.2.3. Compensation for Non-Compression and non-Dehydration of Contracted Quantity of Gas

During the operations period of the Contract (after 72 hrs trial run), in the event Contractor fails to deliver the contracted quantity of compressed gas at the specified outlet for reasons attributable to the Contractor, the Contractor shall pay compensation to PEPL equal to the gas compression & dehydration charges as per

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

17

the price schedule for non-compressed quantity of the gas calculated on per day basis to be settled on monthly basis. The total liability due to liquidated damages and/ or compensation due to non- dehydration of gas shall not exceed 50% of the annualized Contract value.

4.2.4. Liquidated Damages for Not Achieving the Specified Quality (PNGRB) of the

Dehydrated Gas

i. During operation period of the contract, water dew points & other specified parameters shall be measured two times in every 24 hours of operation at mutually agreed time between PEPL & Contractor. Average values of all specified outlet parameters will be calculated for the last 48 hours measured values (four results) of each parameter.

In the event Contractor fails to deliver the contracted quantity of dehydrated gas of specified quality (PNGRB specifications) at the specified outlet (average value of last 48 hours) for reasons attributable to the Contractor, the Contractor shall pay compensation to PEPL on the basis of prevailing present Gas price fixed at Rs. 12.28/ SCM payable to PEPL or equal to the compression and dehydration charges as per the price schedule whichever is higher for non-dehydrated quantity of the gas calculated on per day basis to be settled monthly. During this event, Contractor will not be paid any compression and dehydration charges subject to maximum of 50% of annual Contract value.

4.2.5. Other General Conditions i. Both Contractor and PEPL agree that this is a genuine pre-estimate of the

loss/damage which will be suffered on account of delay / breach on the part of the Contractor and the said amount will be payable to PEPL without there being any proof of the actual loss or damages caused by such delay / failure / breach.

ii. Liquidated damages as per clause 4.2.1, 4.2.2, 4.2.3 & 4.2.4 above, thus accrued will be recovered by PEPL from the bills / invoices submitted by the Contractor, in accordance with terms & conditions of the Contract.

iii. PEPL may without prejudice to its right to effect recovery by any other

method, deduct the amount of liquidated damages and / or compensation for non- compressed gas and non dehydration of contracted quantity of Gas from any money belonging to the Contractor in its hands (which includes PEPL’s right to claim such amount against the Contractor’s Bank Guarantee (s)) or which may become due to the Contractor from the Contractor’s monthly bills.

iv. Any such recovery of Liquidated Damages and / or compensation for non-

compressed gas and non- dehydration of contracted quantity of Gas shall not relieve the Contractor from any other of his obligations / liabilities under the Contract.

4.3. Conditions of Work Performance:

4.3.1. Contractor shall maintain its equipment in sound, safe and efficient operational

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

18

condition at all times. Should the performance of Contractor’s Compressor packages and dehydration unit become unsatisfactory, PEPL shall give Contractor written notice specifying the causes of its dissatisfaction and Contractor shall have a reasonable time specified by PEPL for rectification of deficiencies failing which PEPL shall have the right to temporarily suspend the operation and recover the cost till such time the situation is rectified to the satisfaction of PEPL. Contractor shall not be entitled to any payment during such suspended period. If the situation is not rectified and continues for a period up to 30 days or repeated frequently, then PEPL shall have the right to terminate this Contract by giving 15 (fifteen) days advance written notice without prejudice to PEPL’s right to levy liquidated damages in accordance with clause No. 4.2 above

4.3.2. The safety of the PEPL Installation, Gas compressor packages and Gas dehydration

plant as well as that of operating personnel deployed by the Contractor is of prime importance. In case at any point of time it is found that the operational personnel deployed by the Contractor do not have the requisite experience of operations of Gas Compressor packages and Gas dehydration unit or abide by safety rules, PEPL may ask Contractor to replace those persons with experienced person as required in the agreement. Contractor shall replace them immediately with experienced person(s).

4.3.3. Contractor shall be responsible for all statutory approval including that of DGMS etc

for its equipment.

4.3.4. Contractor shall provide PEPL all such documents and papers required for approval from DGMS/ statutory bodies for setting up facility at installation.

4.3.5. Contractor shall be responsible for providing First aid medical attention for

Contractor’s personnel at the Site and medical services for Contractor’s personnel.

4.3.6. Contractor shall be responsible for keeping and furnishing to PEPL an accurate record of the Work performed on a Daily Progress Report Form acceptable to PEPL both during installation & commissioning period and plant operating period (contract period).

4.3.7. Contractor shall be responsible for maintaining gas compressor and gas dehydration packages & other equipment including safety equipment in good condition at all times and using all reasonable means to control and prevent fires and accidents.

4.3.8. Contractor shall be responsible for maintaining, at its cost, adequate stock levels of Contractor’s items and replenishing as necessary, repairing of all Contractor’s items and providing adequate spare parts and materials required thereof.

4.3.9. Contractor shall be responsible for furnishing, all lubricants chemicals, consumables & spares for use in the gas dehydration unit etc.

4.3.10. The above obligations are in addition to any other obligations set out in other terms & conditions of this Contract Document.

4.4. Measurement:

4.4.1. The volume of CBM gas compressed during compression shall be measured by the

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

19

gas flow meter installed by PEPL.

Note:-The fuel gas is free of cost, up to rated consumption indicated by the Contractor in the bid. Fuel gas conditioning system including metering facility shall be installed by the Contractor at one place for measuring total gas (fuel) consumption for compressor, dehydration and utilities as mentioned in Scope of Work. Installation of Fuel gas conditioning system is optional to the Contractor but installation of one Fuel gas meter is mandatory. The fuel gas meter should be calibrated by the Contractor as & when required as per schedule/ instruction of PEPL.

4.5. Equipment Acceptance:

In case new compressor packages and gas dehydration unit is not offered, the bidder must submit prior to the mobilization of compressor/ dehydration package equipment a proof from the manufacturer / packager in support of date of manufacture of the compressor, gas dehydration unit and declared fuel gas consumption etc. and submit certificates from reputed third party inspection agency (as per list given in clause 4.11) for conformance to tender specifications as mentioned in Scope of Work. PEPL shall provide its approval for mobilization of the said equipment.

4.6. Inspection Conditions and Its Compliance Mechanism for Compression and Dehydration Package

The bidder shall have to carry out the Third party Inspection (TPI) of the following stages and submit the documents/certificates on TPI’s letterhead issued after the date of opening of tender and should be signed and stamped.

i. OLD GAS COMPRESSOR AND DEHYDRATION UNIT

In case bidder has offered the old GAS COMPRESSOR AND DEHYDRATION UNIT, the TPI should certify the following: a. Along with the bid: Bidder to submit the following documents along with bid for the mobilization of compressors and dehydration package having a capacity of 20,000 SCMD for compressing and 30,000 SCMD for dehydrating of CBM gas. Contractor shall also provide all following data within 15 days from the date of mobilization of additional compressor for approval of the Company.

Inlet pressure and rated flow for CBM gas.

Outlet pressure and rated flow for CBM gas.

Manufacturer of with make, model, month and year of manufacturing and

residual life of the gas compressors & dehydration unit.

Standards and codes under which gas compressor and dehydration units are

manufactured.

Name of the packager, Sr. No. of the package and year of packaging, if

applicable

To certify the suitability of the gas compressors and dehydration unit as per

tender specifications.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

20

Consumption of fuel gas to operate the gas compressors and dehydration unit.

The equipment is capable of meeting the specified gas compression and

dehydration capacity & quality of gas compressed and dehydrated gas at the

range of operating parameters specified in the tender.

b. Inspection and testing at Site:

TPI should do inspection of testing and commissioning of the gas compressor and dehydration unit at site as per PEPL specifications, meeting all safety and statutory norms and tender requirements.

The gas compressors and dehydration unit shall be run continuously for minimum 72 hrs.

TPI Agency shall issue inspection certificate on its letterhead confirming that the gas compressors and dehydration unit meets the tender specifications. The certificate should include minimum but not limited to the followings:

I. Inlet pressure and rated flow for CBM gas.

II. Outlet pressure and rated flow for CBM gas. III. Achieved Water Dew Point ( for dehydration unit) IV. Manufacturer of gas compressors and dehydration unit with type, make,

model, capacity, month and year of manufacturing is in conformity with submitted documents.

V. Standards and codes under which gas compressors and dehydration unit has been manufactured are in conformity with submitted documents.

VI. Name of the packager, Sr. no. of the package and year of packaging are in conformity with submitted documents , if applicable

VII. The gas compressors and dehydration unit is capable of meeting gas compression and dehydration capacity & quality of compressed and dehydrated gas at the operating parameters specified in the tender.

ii. NEW GAS COMPRESSORS AND DEHYDRATION UNIT

In case bidder has offered the new gas compressors and dehydration unit, the following certificates from TPI are to be submitted:

a. Along with the bid:

A certificate from the TPI/ OEM/packager confirming the suitability of the gas compressors and dehydration unit as per the tender specifications for the initial mobilization of compressors and dehydration package having a capacity of compressing 20,000 SCMD and dehydrating 30,000 SCMD of CBM gas.

b. After placement of order / Inspection and testing at Site:

TPI should do inspection of testing and commissioning of the gas compressors and dehydration unit at site as per PEPL specifications, meeting all safety and statutory norms and tender requirements.

The gas compressors and dehydration unit shall be run continuously for minimum 72 hrs.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

21

TPI Agency shall issue inspection certificate on its letterhead confirming that the gas compressors and dehydration unit meets the tender specifications. The certificate should include minimum but not limited to the followings:

I. Inlet pressure and rated flow for CBM gas.

II. Outlet pressure and rated flow for CBM gas. III. Water Dew Point ( for dehydration unit) IV. Manufacturer of gas compressors and dehydration unit with type, make,

model, capacity, month and year of manufacturing is in conformity with submitted documents.

V. Standards and codes under which gas compressors and dehydration unit have been manufactured in conformity with submitted documents.

VI. Name of the packager, Sr. no. of the package and year of packaging are in conformity with submitted documents, if applicable

VII. The gas compressors and dehydration unit is capable of meeting gas compression and dehydration capacity & quality of compressed and dehydrated gas at the operating parameters specified in the tender.

The compressor packages and dehydration unit data sheets must be duly signed and stamped by the Gas compressor package and dehydration units Manufacturer / Packager as well as the bidder.

4.7. The Contractor shall not be allowed to use any of the existing facilities such as

structural/mechanical/piping/instrumentation/electrical works of PEPL. Contractor is required to build up all the related facilities on his own.

4.8. PEPL, at any point of time may depute Site-In-charge/Representatives for inspection of the

works being carried out for installation of the compressor package and gas dehydration unit by Contractor.

4.9. Concessions permissible under statues: Contractor must take all necessary steps in order to

equip themselves to avail all concessions permissible under statutes including benefit under any Tax Act of Government, failing which he will have to bear extra cost where Contractor does not avail concessional rates of levies like custom duty, any other taxes etc.,

4.10. Equipment Condition

Compressors and dehydration package and other major equipment mobilized by the Contractor should have the residual life and worthiness of more than 7 years certified by Charted Engineer and verified by Third Party Inspection agency.

The offered Compressor packages and gas dehydration Units shall have to be certified by any of the 3rd Party Inspection agency listed below. 1. BUREAU VERITAS (INDIA) PRIVATE LIMITED 2. PROJECTS & DEVELOPMENT INDIA LIMITED, NOIDA 3. ABS INDUSTRIAL VARIFICATION (INDIA) PVT.LTD 4. VCS QUALITY SERVICES PVT. LTD 5. INTERNATIONAL CERTIFICATION SERVICES PVT. LTD, MUMBAI 6. SGS INDIA PVT. LTD, GURGAON7. DNV GLAS 7. IRCLASS SYSTEMS AND SOLUTIONS PRIVATE LIMITED 8. TUV SUD SOUTH ASIA PVT LTD 9. TUV INDIA PRIVTE LIMITED

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

22

10. DNV GL AS, MUMBAI The bidders shall furnish the same along with Techno-commercial (un-priced) bid wherever mentioned. No gas compressor and dehydration unit will be accepted without the 3rd party Inspection certificate wherever mentioned. The 3rd party Inspection and certification shall be applicable also for all Gas compressor packages and dehydration units proposed to be mobilized.

5. Other Conditions of the Contract

5.1. The Contractor will fully acquaint with latest mines Act- 1952, Mines rules 1955, Mines Vocational Training (MVT) rules, 1966 and Oil Mines regulations OMR) 2017 (available on DGMS website), along with other regulations as applicable for Oil Mines before bidding. All cost implications for compliance of the regulations shall be borne by the Contractor.

5.2. The Contractor shall obtain copies of relevant parts of statute, health & safety management system and acquaint before start of work.

5.3. Contractor shall issue & ensure use of PPE, safety belts, ear protection Safety gadgets etc. by his workers during working in mines and high noise area as mentioned in OMR – 1984/2017.

5.4. Contractor shall maintain all records, registers & token ID/ Cards etc. for his workers as prescribed in said act / rules. The same to be updated and keep ready for verification / inspection by PEPL/ DGMS authorities.

5.5. Contractor shall insure availability of approved & updated safe operating procedure (SOP), at site before start of work and safety briefing / safety talk etc. have been given to make workers aware of risks, before deployment in oil mine.

5.6. Safety Regulations:

i. In respect of all labour, directly or indirectly employed in the Work, the Contractor shall at his own expense arrange for all the safety provisions as per safety codes of Central Public Works Department, Indian Standards Institutions, the Electricity Act, the Mines Act, Regulations, Rules and Orders made there under and such other Acts as applicable.

ii. The Contractor shall observe and abide by all fire and safety regulations of consultant and the Company before starting construction work. Contractor shall consult safety engineers of consultant or the Company and must make good to the satisfaction of Company any loss or damage due to fire to any portion of the work done or to be done under this Contract or to any of the existing property of the Company.

iii. Safety Practice: The Site is located in an area adjacent to operating plant. As such, the WORK shall be carried out as per the safety practices enforced, by the Safety Engineer of the PEPL and instructions of Installation Manager issued from time to time. Safety is the essence of this Contract. Many times it may happen that the working hours shall be drastically reduced or increased to meet certain safety requirements and Contractor shall meet these requirements without any hesitation or argument.

5.7. Work Permit System:

i. In adjoining areas to the operating plant, the Work shall be carried out on hot

work permit basis. Obtaining hot work permit and satisfying all conditions laid

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

23

down therein, by the Safety engineer shall be the responsibility of the Contractor. No claim for idling of machinery, plant and man-power for safety reasons or non-issuance of safety permit by the safety engineer shall be considered. The Contractor shall abide by all safety regulations of the plant as well as ensure that safety equipment as stipulated in the Factory Act (latest edition) is issued to his employees during the execution of the Work. Failure to use safety equipment’s as required by Engineer will be sufficient reason for cancellation of this Contract. The Engineer may also suspend all Work at Site, if he finds Contractor's workmen adopting unsafe practices. Suspension / stoppage of such work and cost & time effect thereof shall be to Contractor’s account. Only steel scaffolding shall be used wherever required.

ii. Movement of vehicles and parking shall be strictly as per Company's safety requirements.

iii. To ensure that none of the personnel carry any type of cameras and do any photography in or around any of our projects, photography on or around work locations is completely prohibited.

iv. To ensure that all personnel display the Non-employee duty passes issued by the security section, while on work.

v. To ensure that all the personnel engaged by them, abide by the security and discipline rules prescribed from time to time by the security section.

5.8. Mines Vocational Training (MVT): To enforce safety regulations it is essential that all

workers, engaged in the construction activities, should be well equipped with the safety aspect of the work. To achieve this objective Mines vocational training is to be provided to the all workers, who are engaged in the construction activities at site by the Contractor. The expense incurred on account of arranging MVT shall be in borne by Contractor.

5.9. Initial Medical Examination (IME): During the execution of the project, DGMS Guidelines

have to be followed by the Contractor. As per DGMS guidelines worker/employees of the Contractor are required to undergo through Initial Medical Examination at the cost of Contractor

5.10. Environment protection: Contractor shall take all necessary measures to protect the

environment and shall observe and comply with all Governmental environmental regulations as well as Company’s and accepted industry environmental practices as required for this work including safe disposal of waste.

5.11. Working Hours: Work shall be performed on a 24 hours per day (7.00 AM to 7.00 AM), 7

days per week basis throughout the term of this Contract. Day for all purposes including reporting shall mean a continuous period of 24 hours commencing from 07:00 AM to 07:00 AM of next day or as mutually agreed.

5.12. Personnel:

i. Contractor shall submit the organization chart along with the bid.

ii. Contractor shall submit resumes of all the personnel 15 days prior to the mobilization for PEPL approval for execution of work at site.

iii. Composition and timing of crew changes will need Company approval prior to mobilization as per the laws of land.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

24

6. The Contractor will be required to demonstrate that:

6.1. General: i. The potential hazards of the erection and the risks to personnel and environment

have been identified and appropriate controls provided; ii. Adequate provision is made for ensuring, in the event of a major emergency

affecting the installation, the safe evacuation and rescue of personnel and iii. The statutory and Company requirements relating to safety and pollution control

measures are complied with.

6.2. Watching and Lighting: The Contractor shall, in connection with the works, provide and maintain at his own cost all lights, guards, fencing, markers and watching when and where necessary or required by the Company for the protection of the Works or for the safety and convenience of the Public or others.

6.3. Safety Audits: Contractor shall within 30 days of commencement of Contract and also

once every three months thereafter submit a safety report to the Head HSE of the work centre with a copy to the Project Coordinator. Contractor shall maintain a record of the relevant statutory and Company requirements relating to safety and pollution control measures and compliance.

6.4. Accident/ incident reporting: In the event of any accident or dangerous occurrence, the Contractor shall forthwith send a notice of accident to the Head HSE of the work center with a copy to the Project Coordinator. Contractor shall also arrange for pickup and immediate medical attention for the injured personnel. In case of death, the Contractor shall be responsible for immediately notifying to the nearest police station as well as to the Labour Officer. Near misses shall also be reported as well as analyzed.

6.5. Safety procedure: Contractor should submit a safety procedure prior to start of the activities for Company review. The procedure should include the safety measures to be taken during the work, firefighting / safety equipment available/ which will be provided, in case of any emergency, number of safety / fire officers and their role, periodical exercise on awareness of workers towards safety, Familiarization of workers with safety equipment, teams for firefighting etc.

6.6. Permit to Work: Contractor shall obtain permit to work as per the statutory & PEPL

guidelines and shall strictly comply with all safety requirements of the work permit during permit duration failing which Company's representative will have the right to stop the work and all cost and time effect thereof shall be to Contractor's account.

6.7. Statutory Compliances: Contractor shall maintain all records and fulfill all the statutory

compliance required for carrying out the work at site including but not limited to labour laws, DGMS, OMR etc. Company may ask Contractor to furnish the records as and when required.

6.8. Experience of Crew: The bidder should confirm to deploy, in each shift at least Four

persons (minimum 2 each for compressor packages and 2 for dehydration unit) having 3 years’ experience of operation and maintenance of Gas Compression and Gas Dehydration Units/ Oil & Gas production / Gas compression facilities and having minimum ITI certificate. Confirmation in this regard is to be submitted along with un-priced bid. Any additional manpower required for smooth and safe operations of the

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

25

plant shall be provided by the Contractor at no extra cost to PEPL. However, the details of all personnel i.e. Bio-Data, proof of qualification etc. shall be submitted and got approved by PEPL before commencement of work.

7. Facilities to be provided at site by PEPL:

7.1. LAND: PEPL will provide generally level ground, approachable through road, reasonably illuminated and surrounding area guarded by Local security. However Bidder will have to do all needful for install of the compressors and dehydration units as mentioned above including civil and electrical works etc.

7.2. UTILITIES

i. Fuel Gas: Fuel gas shall be made available at specified conditions free of cost up to the

declared total consumption limit for compressor/ Dehydration/ Gas Genset operations : Total gas consumption: ______SCM per 1000 SCM gas Compressed and dehydrated (quantity to be provide in the technical bid)

Consumption of fuel gas beyond the above total gas quantity shall be chargeable @ Rs.12.28 per SCM.

Contractor will have to install one flow meter with totalizer on fuel gas line for monitoring and regulation of payment on account of fuel gas consumption beyond the total gas consumption as indicated above.

ii. The Contractor has to install flow meter at the time of mobilization for measuring fuel gas. For meters calibration purposes which may be required at any point of time during contract duration, necessary technical support will be required to be provided by Contractor.

Calibration of the meters will be done by Contractor’s instrument technician and shall be witnessed by PEPL representative. In case PEPL representative is not satisfied, calibrations will have to be redone.

In case meter(s) is/ are not of proper/ requisite nature/ quality, PEPL representative may ask the same to be changed which will require replacement and recalibration of the meter(s) to be done again without cost to PEPL. The same will be required to be repeated, if required till meter(s) is/ are proper & calibrated to the satisfaction of PEPL representative.

iii. Service Water: Service water will not be made available by PEPL. Contractor shall

make necessary arrangement to ensure uninterrupted operation of Compressor and Dehydration plant. However, Contractor will be permitted to drill bore well for service water requirement if statutory requirement permits. PEPL will provide NOC for availing water connection, if any, from local authority on bidder’s request.

iv. Electric Power: PEPL will not provide any electrical power required for gas

compression and dehydration operations. Contractor shall be responsible providing suitable power source and hooking up its equipment from the power source at its own cost including but not limited to cables, junction box, MCCB/MCB, laying of cables and installation of electrical equipment by its own and its cost. Contractor shall make necessary arrangement to ensure uninterrupted operation of gas Compressor and dehydration plant.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

26

Compressor/ Dehydration Area lighting and illumination including provision of lighting distribution board, etc. and arrangement for regular & emergency power (DG Set & UPS etc. as necessary) has to be provided by contactor.

v. Supply of Instrument & starting air supply, as necessary will have to be arranged by

Contractor at his own cost by providing suitable Instrument Air & Starting Air System. Only instrument air is to be used for the field instruments. Small quantity of this air will be used for some instrument installed by PEPL also as per requirement.

8. Other responsibility of contactor: 8.1. Disposal of flared / vent gas through a flare line and integration to existing (PEPL’s) flare

header. 8.2. Maintaining sufficient inventory of spare parts, consumables, lubricants etc. for smooth

and continuous operation of the plant. 8.3. Obtaining statutory approvals including the DGMS approval of its equipment and

performing work in accordance with such approvals 8.4. Providing and maintaining adequate firefighting and gas detection equipment viz. Fire

extinguisher, sand buckets, portable trolleys etc. 8.5. Making all necessary arrangements for lodging, boarding and transportation of

Contractor’s personnel.

9. Safety aspects & Shut-down requirements:

In case of safety requirements, PEPL may ask Contractor to stop operations which will be orally conveyed, followed by written communication from Installation Manager. In such event, Liquidated damages will not be applied nor any charges for compression and dehydration will be payable by PEPL. It may be understood that such step shall be taken in case of emergency only. However, in case Contractor is operating the Gas compressor and dehydration plant in an unsafe manner, Installation Manager may ask Contractor for Gas compressor packages and Dehydration plant to be shut down by oral instruction, followed by written instruction later, and ask for rectification of the unsafe condition. The period of shutdown, in this case, will be liable for Liquidated Damages under the Liquidated damages clause.

10. Excess gas compression: In case gas compression or Dehydration quantities are in excess of contractual quantity, gas compression or Dehydration charges payable shall be equal to the contracted unit rates under the contract.

11. De-commissioning, Demobilization & Transport-out:

At the end of the contract, the Gas compressor packages and Dehydration units will be required to be safely decommissioned by Contractor’s personnel in presence of PEPL engineers.

It will be Contractor’s responsibility to arrange for safe transportation of Gas compressor packages and Dehydration units out from site within 30 days from the date of completion/closure/termination of contract.

Any delay beyond 30 days in transporting the Gas compressor packages and Dehydration units will entail application of charges similar to demurrage charges spelt out under Liquidated damages clause. Contractor to confirm owing single point responsibility.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

27

PEPL will not pay any amount towards demobilization of the equipment during the Contract period or after the expiry of Contract period.

12. Time Schedule

S NO. DESCRIPTION TIME SCHEDULE

1 Mobilization Period: Mobilization, Commissioning and 72 hrs test run of compressor packages and gas dehydration Plant complete in all respects and commencement of compression and dehydration of CBM Gas in accordance with Tender Document.

Within 120 days from the date of issue of email Order/LOA for Award of Work or within 120 of call out given by PEPL after award of work/ LOA whichever is later.

2 Operations Period: The operations Period of Contract shall be for a period of 5 years from the actual date of initial mobilization & commissioning of compression and dehydration package after 72 hours run test.

3 Extension of Operation Period: PEPL shall have the right to extend the duration of the Contract by two (2) further extension of 6 (six) months each, under the same rates, terms and conditions by giving Contractor at least fifteen (15) days written notice prior to the completion of initial term of the Contract

Date: Bidder’s Signature.

Bidders Name: Bidders Seal.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

28

APPENDIX A - DATA SHEET

Data Sheet for Skid Mounted Gas Engine Driven Compressor Package and Gas Dehydration Package

PART B (Service Requirements)

1.0 OPERATING CONDITIONS

1.1 Gas Handled: LP Gas (Refer Sr. No. 3.0 for composition)

1.2 Inlet Temperature (Min/Max) : 50 (oC)

1.3 Inlet Pressure: 0.75 to 1.0 (Kg/cm2g)

1.4 Outlet Pressure: 255 Barg (at PEPL Flowmeter)

1.5 Outlet Temperature (Max): 55 (oC) (at CTM)

1.6 Capacity Required: 20,000 SCMD for Compressors and 30,000 SCMD for Dehydration Unit

1.7 Standard Conditions referred to: 760 mm Hg & 15.6 0C (SI units)

2.0 SITE CONDITIONS

2.1 Place: Tropical, Dusty

2.2 Site Temperature (Min. / Max) : 05 / 50 (oC)

2.3 Area Classification: Zone-2, Gas Group IIA/IIB, Temp. Class: T3

3.0

TYPICAL GAS COMPOSITION (% V/V ON DRY BASIS)

Nitrogen 1.12

Carbon Dioxide 1.31

Methane 97.09

Ethane 0.45

Propane 0.01

I-Butane Tr.

N-Butane Tr.

I-Pentane Nil

N-Pentane Nil

Hexane+ Nil

Average Mol. Wt. (Dry Basis) 16.61

Notes: 1.Composition indicated is typical and is subject to variation encountered in CBM. 2. No claims would be entertained on account of variation in gas composition. 3. Gas is saturated with water at inlet condition with occasional carryover of water.

Prabha Energy Private Limited

Compressor Package (Gas Engine Driven) and Gas Dehydration Package On Hiring Basis

Data Sheet No. Rev.

NKCBM/COMP-PACK/H

Sheet No.

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

29

Data Sheet for Skid Mounted Gas Engine Driven Compressor Packages and Gas Dehydration Package

PART B (BIDDER DATA)

1.0 GENERAL

1.1 Name & Address of the Bidder

1.2 Confirm suitability for continuous operation in tropical ambient conditions

1.3 Confirm suitability of complete package for classified Hazardous Area

1.4 Confirm that complete package would conform to applicable code

1.5 Make & Model of compressors

1.6 Month & Year of Manufacturing of compressors

1.7 Serial Numbers of the offered compressors

1.8 Make & Model of engines/ Motors

1.9 Month & Year of Manufacturing of engines/ Motors

1.10 Serial Numbers of the offered engines

1.11 Whether Certificate for soundness of compressors package

1.12 Make & Model of dehydration package

1.13 Month & Year of Manufacturing of dehydration package

1.14 Serial Numbers of the offered dehydration package

1.15 Whether Certificate for soundness of dehydration package is enclosed

1.16 Number of compressors proposed WORKING : STANDBY :

1.17 Guaranteed capacity (each compressor)

1.18 Number of Dehydration unit proposed WORKING : STANDBY :

1.19 Guaranteed capacity (each unit)

2.00 ADDITIONAL DATA / INFORMATION

2.1 Compressor-package performance data sheet should include all pressure drops across all vessels e.g. Inlet separator/ filters valves pipelines/ dehydration units etc.

2.2 Catalogues for compressor & engines/ motors are attached

2.3 Catalogues for dehydration packages attached

Prabha Energy Private Limited

Compressors Package and Gas Dehydration Package On Hiring Basis

Data Sheet No. Rev.

NKCBM/COMP-PACK/H

Sheet No.

(SIGNATURE & SEAL OF BIDDER)

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

30

Appendix B

LOG RECORD FOR GAS COMPRESSOR & DEHYDRATION PACKAGE(S)

Name of Contractor: Location: DPR Date:

TIME (Hrs)

INLET PRESSURE (kg/sq cm)

OUTLET PRESSURE (kg/sq cm)

TOTALIZER READING

(SCM)

COMPUTED RATE OF COMPRESSED GAS (SCMD)

07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00

Water Dew Point (Deg C) __________ at _________Hrs. Signature of Contractor’s shift representative with name & designation

Total Gas compressed & Dehydrated as per PEPL CTM

Signature of PEPL Shift in charge with name & designation

TIME (Hrs)

INLET PRESSURE (kg/sqcm)

OUTLET PRESSURE (kg/sqcm)

TOTALIZER READING

(SCM)

COMPUTED RATE OF COMPRESSED GAS (SCMD)

20:00 21:00 22:00 23:00 24:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00

Water Dew Point (Deg C) __________ at _________Hrs. Signature of Contractor’s shift representative with name & designation

Gas compressed & Dehydrated as per PEPL CTM

Signature of PEPL Shift in charge with name & designation

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

31

Appendix C

NOT IN USE

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

32

Appendix D

Documents

P&ID – Contractor to provide drawing and layouts along with the bid

Process Flow Diagram - Contractor to provide drawing and layouts along with the bid

PEPL/CBM/INTR/LC/GCDGU/06-R/2019

33

Appendix E REFERENCE FOR COMPRESSOR PACKAGE AND DEHYDRATION UNIT:

(All latest version available should be applicable) COMPRESSOR:

The offered compressor should be reciprocating type/ hydraulic/ electric motor driven

The water (prevention and control of pollution) Cess (Amendment ) Act, 2003

Emission regulation for DG sets

The Noise (Regulation and control) Rules, 2000

Environment (Protection) Act, 1986

Pollution Control Board norms for exhaust

DEHYDRATION UNIT:

Environmental Rules-1986 (1989)

Oil Mines Regulations

PNRB Guidelines

Pollution Control Board Norms for exhaust