Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations

4
1 Scope 1. 18km of sewers (0.5m to 3.0m dia) 2. 2 lift stations 3. Demolition of 4 pumping stations – Jurong West, Jalan Bahar, Corporation and International Road pumping stations 4. Grouting of 18km of twin pumping mains (0.66m to 0.95m dia) Sewerage Schemes to serve Developments in Sewerage Schemes to serve Developments in Jurong Eastern Catchment and Jurong Lake Jurong Eastern Catchment and Jurong Lake District District Objective Extend sewers to serve new developments & phase out 4 pumping stations

description

Sewerage Schemes to serve Developments in Jurong Eastern Catchment and Jurong Lake District. Objective Extend sewers to serve new developments & phase out 4 pumping stations. Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations - PowerPoint PPT Presentation

Transcript of Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations

Page 1: Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations

1

Scope

1. 18km of sewers (0.5m to 3.0m dia)

2. 2 lift stations

3. Demolition of 4 pumping stations – Jurong West, Jalan Bahar, Corporation and International Road pumping stations

4. Grouting of 18km of twin pumping mains (0.66m to 0.95m dia)

Sewerage Schemes to serve Developments inSewerage Schemes to serve Developments inJurong Eastern Catchment and Jurong Lake Jurong Eastern Catchment and Jurong Lake

DistrictDistrictObjective

Extend sewers to serve new developments & phase out 4 pumping stations

Page 2: Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations

2

Jurong Eastern Catchment SchemeJurong Eastern Catchment Scheme

Page 3: Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations

3

Jurong Lake District SchemeJurong Lake District Scheme

Page 4: Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations

4

Important Notes for Interested Partners:

1. Tenders for Consultancy Services – end Mar 2010

2. Tenders for Works – Nov 2010

3. Very tight schedule, sewers and lift stations – complete by 2nd half of 2013

4. Potential Tenderers – prepare early, source for suitable pipe jacking machines, and familiarise with site conditions

Sewerage Schemes to serve Developments inSewerage Schemes to serve Developments inJurong Eastern Catchment and Jurong Lake Jurong Eastern Catchment and Jurong Lake

DistrictDistrict