Digital Product Lab2

Contents1. Introduction

2. Model description

3. Comparison of postponement strategieso Product redesign strategyo Process reversal strategyo Comparison of two strategieso Case analysis

4. Numerical example

5. Concluding remarks

Page 3: Scm 2

Digital Product Lab3

Introduction Competitive market >> Companies have to extend their

product lines to meet diverse customer demands.

Mass customization >> new competitive paradigm >> companies customise products in response to individual customer orders, while retaining their operational performance (Davis 1987)

Mass customization is generally described as a process by which firms apply technology and management methods to provide product variety and customization at a low cost through flexibility and quick responsiveness (Davis 1987, Pine et al. 1993, Kotha 1995).

Page 4: Scm 2

Digital Product Lab4

Introduction Postponement is one of the practical methods to mass

customization (Kotha 1995, Lampel and Mintzberg 1996, Feitzinger and Lee 1997).

It implies that the process would not commit the work-in-process into a particular finished product until a later point (Lee and Tang 1997).

Postponement strategies >> reduce the risks associated with product variety by exploiting the commonality between items and by designing the production and distribution processes to delay the point of differentiation (Aviv and Federgruen 2001a).

Delaying product differentiation >> increase flexibility, reduce uncertainties and decrease the costs of complexity by reducing the variety of components and processes within the system (Garg and Tang 1997, Yang et al 2004a, Nair 2005).

Page 5: Scm 2

Digital Product Lab5

Introduction/Problem definition

This paper >> consider a manufacturer in search of postponement strategies in mass customization with service guarantees.

Production process consists of several stages. Beginning stages >> manufactures and stocks a common product that can then be customised at the later stages.

Service guarantees >> Manufacturer should deliver customised products within a limited period >> the location of product differentiation point is a significant decision.

Positioning of the differentiation point at the upstream stages >> reduce the investment in the value-added component inventory, but may also impact the company’s responsiveness to customer orders.

Page 6: Scm 2

Digital Product Lab6

Introduction/Problem definition

Example: IBM used to deliver RS6000 server machines later than the customer requested arrival data due to an upstream differentiation point leading to a sizable percentage of late orders (Swaminathan and Tayur 1998a)

By properly designing the product structure and the supply chain process, the product differentiation point in mass customization can be delayed to increase the flexibility and responsiveness to customer demand.

Page 7: Scm 2

Digital Product Lab7

Introduction/Literature Alderson (1950): the first to propose the postponement

concept from a marketing management perspective.

Bucklin (1965): brings postponement into the distribution channel.

Yang et al. (2004b):The scope of postponement has expanded from marketing to the whole supply chain, including purchasing, manufacturing, distribution.

Zinn and Bowersox (1988): propose two different postponement strategies, e.g. form postponement (including manufacturing, assembly, packaging and labelling postponement) and time postponement

Page 8: Scm 2

Digital Product Lab8

Introduction/Literature

Lee and Tang (1997): provide a classification of possible postponement strategies through redesigning products and restructuring process.

Swaminathan and Lee (2003): The ability of a firm to implement a successful postponement strategy depends on how well the firm can tailor its process and product characteristics to the market requirements

Swaminathan and Lee (2003): provide a comprehensive review on analytical models for evaluating postponement alternatives.

Page 9: Scm 2

Digital Product Lab9

Introduction/Literature Lee (1996): presents inventory models that support

product/process design for postponement.

Lee and Whang (1998): explore the postponement model further

by assuming that demands are not independent and identically distributed over time.

Lee and Tang (1997): provide a few analytical models to analyze the costs and benefits of three kinds of postponement strategies (standardization, modular design, and process restructuring)

Garg and Tang (1997): present a model to evaluate postponement strategies for product families with multiple points of differentiation.

Page 10: Scm 2

Digital Product Lab10

Introduction/Literature

Lee and Tang (1998) & Jain and Paul (2001): present the operations reversal model to determine which sequence of operations results in optimal operational performance.

Aviv and Federgruen (2001a): characterize the benefits of postpone-ment in more general setting, where parameters of the demand distributions fail to be known with accuracy or where consecutive demands are correlated.

Aviv and Federgruen (2001b): model the costs and benefits of postponement strategies in capacitated multi-item inventory systems with random and seasonally fluctuating demands.

Page 11: Scm 2

Digital Product Lab11

Introduction/Literature Swaminathan and Tayur (1998a): provide a final assembly

model with production capacity constraints.

Gupta and Benjaafar (2004): adopt queuing approximations to analyze a system where both make-to-stock and make-to-order environments are utilised while delaying the point of differentiation.

Graman and Magazine (2002): develop a single-period, multiple-product, capacitated postponement capacity.

Tibben-Lembke and Bassok (2005): present an inventory model for delayed customization problem in which the company considers using both regular production and postponement.

Page 12: Scm 2

Digital Product Lab12

Introduction/Literature

There are also some papers considering the application of postponement in practice (see Lee et al . 1993, Kotha 1996, Swaminathan and Tayur 1998b, Brown et al. 2000, Thonemann and Brandeau 2000).

There is lack of research on comparison of different postponement strategies in the extant literature.

We assume the expected customer waiting time or service level is determined by market competition; and we find that the processing time and value added at the considered stages are the two main factors determining the choice of postponement strategy.

Page 13: Scm 2

Digital Product Lab13

Contents1. Introduction

2. Model description

3. Comparison of postponement strategieso Product redesign strategyo Process reversal strategyo Comparison of two strategieso Case analysis

4. Numerical example

5. Concluding remarks

Page 14: Scm 2

Digital Product Lab14

Model description Consider a firm that mass customizes products out of generic

components according to customer orders.

Firm produces common modules or components, and then stores them at the differentiation point.

The upstream production process >> forecast-driven. The final downstream from the differentiation point >> order-driven, which differentiates the products to specific customer orders.

Example: A computer manufacturer, which assembles computers to customer orders at its distribution centre (figure 1).

Page 15: Scm 2

Digital Product Lab15

Model description

Page 16: Scm 2

Digital Product Lab16

Model description Assume the mass customization system has N stages,

and the differentiation point is located at the end of stage k (see figure 2).

Customer demand during a single period (D), is a random variable with a continuous distribution represented by the cumulative distribution function (cdf) F(x) and continuous density function f(x).

Assume that demands in different periods are independent.

Page 17: Scm 2

Digital Product Lab17

Model description

Page 18: Scm 2

Digital Product Lab18

Model description Suppose the customization process is flexible and

no capacity limit is imposed on the customization phase.

When a customer order comes >> can start customizing products if the general components needed are available at the differentiation point.

Periodic review based-stock replenishment policy is applied at the differentiation point.

Page 19: Scm 2

Digital Product Lab19

Model descriptionThe sequence of events for the model Beginning of each period >> customer orders arrive.

Then >> generic component inventory is used to customize the products to meet the customer orders.

If there is no sufficient on-hand inventory at the differentiation point

to meet all customer orders >> the excess is backlogged until more inventories are available from upstream production processes.

Next, inventory is reviewed, and production to replenish the component inventory to a given inventory position is initiated.

Finally, all costs and revenues are incurred.

Page 20: Scm 2

Digital Product Lab20

Model descriptionNotation:

Page 21: Scm 2

Digital Product Lab21

Model description Difficult to determine an exact value for stockout costs >>

this model considers service level measures instead of stockout costs.

Service levels generally refers to either the probability of not stocking out or the proportion of demand satisfied directly from inventory, or fill rate (Zeng and Hayya 1999).

This study >> choose two service level measures that are commonly adopted in mass customization operations: expected average customer order lead time & proportion of demand satisfied within target time periods (see Lee 1996).

Page 22: Scm 2

Digital Product Lab22

Model description T: Manufacturer’s response time to customer orders

tw: waiting time for components if there is no enough inventory on-hand at the differentiation point when the customer orders arrive.

Page 23: Scm 2

Digital Product Lab23

Model description An individual order arriving in a particular period

could be satisfied in

periods ( ~ tw = 0) >> best service level

Page 24: Scm 2

Digital Product Lab24

Model description The longest response time is

the total production time of the customized products, where

Page 25: Scm 2

Digital Product Lab25

Model description

Page 26: Scm 2

Digital Product Lab26

Model description

Page 27: Scm 2

Digital Product Lab27

Model description

Page 28: Scm 2

Digital Product Lab28

Model description

o Objective function >> represents inventory holding cost at the differentiation point and the total average WIP inventory cost before the differentiation point. o Constraint (1) defines the average customer waiting time, and constraint (2) defines the fill rate within a target waiting time window. o This paper >> focuses on analyzing the impact of postponement strategies on inventory costs >> ignore the restructuring costs and production costs in the model

Page 29: Scm 2

Digital Product Lab29

Model description

Page 30: Scm 2

Digital Product Lab30

Contents1. Introduction

2. Model description

3. Comparison of postponement strategieso Product redesign strategyo Process reversal strategyo Comparison of two strategieso Case analysis

4. Numerical example

5. Concluding remarks

Page 31: Scm 2

Digital Product Lab31

Product redesign Product redesign strategy >> adopts standardization or modular

design concepts.

Standardization: Replace some customized components with common components.

Modular design: Decompose the complete product into submodules that can be easily assembled together

Through product redesign >> manufacturer can delay the customization operations.

Companies adopting product redesign approach: Xilinx (Brown et al. 2000), Lucent Technologies (Hoyt and Lopez-Tello 2001) and IBM (Swaminathan and Tayur 1998a).

Page 32: Scm 2

Digital Product Lab32

Product redesign To implement product redesign strategy to delay the point of

differentiation >> assume the firm redesigns the product structure to replace specific components at stage k + 1, so customization operations start at stage k + 2 and the differentiation point is postponed from the end of stage k to the end of stage k +1 (figure 3).

Page 33: Scm 2

Digital Product Lab33

Product redesign

Page 34: Scm 2

Digital Product Lab34

Product redesign

Page 35: Scm 2

Digital Product Lab35

Product redesign

Page 36: Scm 2

Digital Product Lab36

Product redesign Value of component standardization and modularization to

postpone the differentiation point may be different at different stages in the production process.

Proposition 2 implies >> the benefit of component standardization and modularization decreases as the costs of standardized or modularized components increase.

~> It is not beneficial to standardize or modularize components to postpone the point of product differentiation if the components have high values.

In contrast, if the components have low value, inventory costs may be reduced through component standardization or modularization.

Page 37: Scm 2

Digital Product Lab37

Product redesign Product redesign approach, vanilla boxes (common semi-

finished products used to produce different products) can be designed to postpone the point of differentiation.

IBM introduced the vanilla boxes in one of the two assembly plants for RS6000 server machine production considering the increasing in service time expectations and the costs in terms of vanilla boxes (Swaninathan and Tayur 1998a).

Our results indicate >> under the condition that service can be guaranteed >> the benefits of designing vanilla boxes in the production process are associated with the costs of the vanilla boxes.

Page 38: Scm 2

Digital Product Lab38

Process reversal Process reversal approach: Re-sequences process steps

in making a product or in the supply chain operations so that common process steps shared by customized products are performed before customization process steps.

Well known cases of process reversal for postponement include HP (Kopczak and Lee 1993) and Benetton (Aviv and Federguen 2001).

Page 39: Scm 2

Digital Product Lab39

Process reversal Early 1990s >> HP Europe sold different DeskJet printers in many

markets, differentiated in terms of the power supply module, power cord terminator, and manual.

Traditionally, localization took place in the Vancouver plant. In order to solve the inventory and shortage problems incurred at the European distribution centre, HP Europe reversed localization operation and transportation operation.

It demonstrates the benefits of postponing localization until the printers arrive at the European distribution centre.

Benetton, an Italian apparel manufacturer improved its ability to meet market demand with fewer inventory by reversing the dyeing and knitting stages.

Page 40: Scm 2

Digital Product Lab40

Process reversal To implement process reversal approach to delay the

point of differentiation >> assume stage k + 2 is a common process for all customized products and stage k + 1 and k + 2 can be reversed.

The firm redesigns the processes to reverse stage k +1 and stage k + 2 (figure 4).

Page 41: Scm 2

Digital Product Lab41

Process reversal

Page 42: Scm 2

Digital Product Lab42

Process reversal

Page 43: Scm 2

Digital Product Lab43

Process reversal

Page 44: Scm 2

Digital Product Lab44

Comparison/Process reversal From proposition 3, if stage k + 2 is a short operation and adds high

value, it is not beneficial to reverse stage k + 1 and stage k + 2.

If stage k + 2 is a long operation and adds little value, then the reversal of stage k + 1 and k + 2 would yield great benefits. The longer is stage k + 2, the greater benefits the operations reversal would yield.

It is probably intuitive as to why HP Europe could benefit from the operations reversal of localization and shipping. In this case, the reversal of localization and shipping delays the point of product differentiation.

The benefits of HP Europe’s operations reversal strategy largely depends on the shipping process.

The localization process is relatively short. But the shipping process takes about 4 weeks and adds no value to the printers.

Page 45: Scm 2

Digital Product Lab45

Compare strategies In this paper >> analyze the situation where it is possible

to either standardize the components or change the sequence of operations in a process so that products get differentiated later.

For delaying the point of differentiation >> which approach is better?

We compare the inventory costs of these two postponement strategies.

Page 46: Scm 2

Digital Product Lab46

Compare strategies

Page 47: Scm 2

Digital Product Lab47

Compare strategies

Page 48: Scm 2

Digital Product Lab48

Compare strategies From proposition 4, if the lead time of stage k + 1 is longer than that

of stage k + 2, and the value added at stage k +1 is lower than that at stage k + 2, it is better to adopt product redesign approach to postpone the point of differentiation from stage k to stage k + 1.

If the lead time of stage k + 1 is shorter than that of stage k + 2, and the value added at stage k + 1 is larger than that at stage k + 2, it is better to adopt process reversal approach.

Proposition 4 indicates that processing time and value added at the considered stages are two main factors determining the choice of postponement strategies.

We further discuss about the comparison of product design and process reversal in the following case.

Page 49: Scm 2

Digital Product Lab49

Case Analysis Anny: Chinese biological and medical product

manufacturer, addresses the problem of postponement.

One of its main products is Anny Liquid, which contains a live bacteria type of ecological dietetic liquid. The products are distributed by 10 subsidiary companies which are responsible for different regions.

To avoid horizontal channel conflict that one distributor sells the products to other markets, Anny distinguishes the products distributed by different subsidiaries with different product packing.

Page 50: Scm 2

Digital Product Lab50

Case Analysis Traditional production process of Anny Liquid >> 6 stages: mixing,

fermenting, transfusing, inspecting, packaging and shipping (see table 1).

Page 51: Scm 2

Digital Product Lab51

Case Analysis The manufacturing process is guided by the orders from the

10 subsidiary companies.

The subsidiary companies place orders every week based on their sales forecasts and inventory.

Once receiving orders from different subsidiary companies, the manufacturer decides how much to produce and place an order for different packing materials from an outsider supplier.

The original product differentiation takes place at the mixing

stage (see figure 5a). The purchasing lead time of packing materials is 2 days.

Page 52: Scm 2

Digital Product Lab52

Case Analysis

Page 53: Scm 2

Digital Product Lab53

Case Analysis It is usually difficult for the subsidiary companies to

accurately forecast their sales demands.

The dynamic and intensely competitive market >> challenged Anny’s operations.

To reduce the problem of stockout level and excess inventory faced by the subsidiary companies >> Anny decides to adapt its operations strategy to reduce average order lead time from 25 days to 6 days.

Two solutions are considered by the management.

Page 54: Scm 2

Digital Product Lab54

Case Analysis Solution A: postpone the

differentiation point from the mixing stage to the end of packaging stage (figure 5b).

Stages from mixing to

packaging are all standardized and products destined to different regions are differentiated by sticking different stamps on the products just before delivery to the distribution centre (DC).

Page 55: Scm 2

Digital Product Lab55

Case Analysis Solution B: postpone the

differentiation point by standardizing all stages before packaging and reversing the operations of packaging and shipping to DC (figure 5c).

In this solution, packaging operations are carried out at the DC.

Page 56: Scm 2

Digital Product Lab56

Case Analysis Two solutions have different impact on the company’s operations.

In solution A, the manufacturer holds high value finished products from packaging stage to DC.

But in solution B, the manufacturer holds no finished products and packages the products just before delivery to the regional distribution centres (RDCs).

In the case of Anny, packing materials cost 56% of total costs. Considering the packing material costs, the company adopts solution B.

Due to postponing the differentiation point to the packaging stage at the DC through reversing the operations of shipping to DC and packaging, the company significantly reduces its inventory levels and inventory costs meanwhile improves the responsiveness to market.

Page 57: Scm 2

Digital Product Lab57

Case Analysis This paper’s model explains the results well.

According to proposition 4, solution B is preferred to solution A because value added at packaging stage is larger than value added at the shipping stage and the operations time at packaging stage is shorter than the shipping operation.

Page 58: Scm 2

Digital Product Lab58

Contents1. Introduction

2. Model description

3. Comparison of postponement strategieso Product redesign strategyo Process reversal strategyo Comparison of two strategieso Case analysis

4. Numerical example

5. Concluding remarks

Page 59: Scm 2

Digital Product Lab59

Numerical Example We analyze numerical examples comparing the product

redesign and process reversal strategies

The mass customization system in this example has 3 stages with stable processing times at each stage.

The manufacturer produces generic components at stage 1 and processes them at stage 2 and stage 3 to provide customized products (figure 6a).

All one-period demands are normally distributed with mean demand μ = 100 and standard deviation of σ = 50. Demands at different periods are independent.

Page 60: Scm 2

Digital Product Lab60

Numerical Example

Page 61: Scm 2

Digital Product Lab61

Numerical Example The manufacturer can either standardize the process

of stage 2 (figure 6b) or reverse stages 2 and 3 to make stage 3 a common process (figure 6c).

We examine three settings of processing times ti , namely ( t1 , t2 , t3 ) = (4, 1, 3), (4, 2, 2), (4, 3, 1).

Base stock policy is applied at the differentiation point.

The manufacturer sets service levels with expected customer order lead time of τ and the fill rate of θ in τ0 periods.

Page 62: Scm 2

Digital Product Lab62

Numerical Example

Page 63: Scm 2

Digital Product Lab63

Numerical Example The corresponding inventory policies for scenario

without postponement and scenarios with one-period, two-period and three-period postponement are given in table 2.

Page 64: Scm 2

Digital Product Lab64

Numerical Example

Page 65: Scm 2

Digital Product Lab65

Numerical Example As shown in table 2, the optimal base stock level and

inventory on-hand at the differentiation point in each scenario is non-decreasing with the fill rate in τ0 periods and non-increasing with expected customer order lead time.

When the expected customer order lead time is short and the target fill rate is relatively low, constraint of the fill rate is loose and base stock level is mainly determined by the expected customer order lead time.

Page 66: Scm 2

Digital Product Lab66

Numerical Example Figure 7 shows that when the service levels are

unchanged, the base stock levels are non-increasing with the postponed time periods.

For instance, the base stock levels keep constant at the service level of τ = 4.2 and θ = 99%, and decrease when postponement strategies are adopted at the service level of τ = 4.2 and θ = 92%.

Page 67: Scm 2

Digital Product Lab67

Numerical Example

Page 68: Scm 2

Digital Product Lab68

Numerical Example As expected from proposition 1, figure 8 shows that when

the service level keeps unchanged, postponement can reduce the inventory level at the differentiation point and the inventory level decreases with the postponed time periods.

Page 69: Scm 2

Digital Product Lab69

Numerical Example In order to compare the different postponement strategies, we fix the

service level parameter τ at 4.2 and θ at 96% in 5 periods. Table 3 reports numerical examples of total inventory costs of

product redesign strategy and process reversal strategy in the three scenarios with different values of Δh2 and Δh3 .

Page 70: Scm 2

Digital Product Lab70

Numerical Example In the 3 scenarios, we find that it is not always beneficial to

postpone the differentiation point.

In product redesign strategy, the benefits of postponement decrease with Δh2.

We further find that the benefits of postponement increase with the processing time of stage 2 when Δh2 is fixed.

In process reversal strategy, the benefits of postponement increase with Δh2 and decrease with t2 when the total value added in stage 2 and 3 is fixed.

Page 71: Scm 2

Digital Product Lab71

Numerical Example In scenarios I and II, where t2 is longer than or equal to t3,

the cost increment of product redesign strategy relative to process reversal strategy is positive when Δh2 is lager than Δh3. As expected from proposition 4, process reversal strategy is preferred.

In scenario III, where t2 is shorter than t3 , the cost increment of product redesign strategy relative to process reversal strategy is negative when Δh2 is smaller than Δh3. Therefore product redesign strategy is preferred.

Page 72: Scm 2

Digital Product Lab72

Contents1. Introduction

2. Model description

3. Comparison of postponement strategieso Product redesign strategyo Process reversal strategyo Comparison of two strategieso Case analysis

4. Numerical example

5. Concluding remarks

Page 73: Scm 2

Digital Product Lab73

Concluding remarks In this paper, we introduce and develop a model for evaluating two

different postponement strategies in mass customization with service guarantees.

Delaying product differentiation point through product redesign and process reversal lowers the inventory levels. But such strategies may increase inventory costs.

We evaluate and compare the postponement strategies by considering the total inventory cost.

When considering the inventory costs, it is not beneficial to delay the point of differentiation if the considered stage is a high value-added process.

However, it is better to delay the point of differentiation if the considered stage has a relatively long time operation and adds little value.

Page 74: Scm 2

Digital Product Lab74

Concluding remarks Our results show that processing time and value added

at the considered stages are two main factors influencing the decision of postponement strategies.

The case study and numerical examples demonstrate that cost savings can be realised when the right strategy is considered.

Our research provides guidance for managers regarding application of mass customization to cost-effectively meet customer demand with service time constraints.

Page 75: Scm 2

Digital Product Lab75

Concluding remarksFurther works in the future: Production congestion should be incorporated.

Further research should apply queuing models to consider the waiting time in the mass customization system.

Production costs, restructuring costs and competition should be considered.

Page 76: Scm 2

Digital Product Lab76

Concluding remarks/Future Future research should consider the impact of the order

lead time competition on the decision of postponement strategies.

More general postponement structures should be analyzed. In practice, different postponement strategies may have different unit production time and cost.

Future research should consider other postponement strategies such as time postponement, and extend the model to consider different unit production time to find the more general results.