School of Community Government
Works and Works Management
Project and Contract Management 2006
2
TABLE of CONTENTS
PREAMBLE – COMMUNITY SCHOOL OF GOVERNMENT...............................................................................7
COURSE DESCRIPTION AND PURPOSE..........................................................................................8
1 INTRODUCTION TO PROJECT AND CONTRACT MANAGEMENT..........................................9
1.1 INTRODUCTION AND SCOPE....................................................................................................9
1.2 GOALS AND OBJECTIVES......................................................................................................10
1.3 WHAT IS A PROJECT?..........................................................................................................10
1.4 WHAT IS PROJECT MANAGEMENT?........................................................................................11
1.5 THE PROJECT LIFE CYCLE...................................................................................................18
1.6 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................21
1.7 REVIEW AND RESEARCH QUESTIONS.....................................................................................21
1.8 RESOURCES....................................................................................................................... 21
2 PHASE 1: DEFINITION OF A CONTRACT..............................................................................22
2.1 INTRODUCTION....................................................................................................................23
2.2 GOALS AND OBJECTIVES......................................................................................................23
2.3 WHAT IS A CONTRACT?.......................................................................................................24
2.4 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................26
2.5 REVIEW AND RESEARCH QUESTIONS.....................................................................................26
3 PURCHASING METHODS........................................................................................................28
3.1 INTRODUCTION....................................................................................................................28
3.2 GOALS AND OBJECTIVES......................................................................................................29
3.3 METHODS OF PUBLIC PURCHASING.......................................................................................29
3.4 BUSINESS INCENTIVE POLICY (BIP).......................................................................................31
3
3.5 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................33
3.6 REVIEW AND RESEARCH QUESTIONS.....................................................................................33
3.7 CASE STUDY....................................................................................................................... 35
3.8 RESOURCES....................................................................................................................... 36
4 THE TENDERING PROCESS - CONSTRUCTION....................................................................38
4.1 INTRODUCTION AND SCOPE..................................................................................................38
4.2 GOALS AND OBJECTIVES......................................................................................................39
4.3 TYPES OF CONSTRUCTION PRICE AND PAYMENT METHODS.....................................................39
4.4 THE TENDERING PROCESS...................................................................................................42
4.5 BID SECURITY.....................................................................................................................43
4.6 BID DEPOSITORY.................................................................................................................43
4.7 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................44
4.8 REVIEW AND RESEARCH QUESTIONS.....................................................................................44
5 NEW DEAL FOR COMMUNITIES.............................................................................................45
5.1 INTRODUCTION....................................................................................................................45
5.2 GOALS AND OBJECTIVES......................................................................................................46
5.3 CAPITAL AUTHORITY ARRANGEMENTS....................................................................................46
5.4 DISCUSSION AND REFLECTIVE
QUESTIO……………………………………………………………..47
5.5
RESOURCES…………………………………………………………………………………………..48
6 PHASE 2 PLANNING................................................................................................................49
6.1 INTRODUCTION....................................................................................................................50
6.2 PLANNING IS NOT FOR THE FAINT-HEARTED............................................................................51
6.3 CONFLICTS AREN’T NECESSARILY BAD...................................................................................52
6.4 SPECIFICATIONS..................................................................................................................52
6.5 PURCHASING CONSTRUCTION...............................................................................................54
6.6 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................55
6.7 REVIEW AND RESEARCH QUESTIONS.....................................................................................55
6.8 RESOURCES....................................................................................................................... 55
4
7 PLANNING – ESTIMATING......................................................................................................56
7.1 INTRODUCTION....................................................................................................................56
7.2 GOALS AND OBJECTIVES......................................................................................................57
7.3 WHAT IS ESTIMATING?.........................................................................................................57
7.4 CONSIDERING CRADLE TO GRAVE COSTS..............................................................................57
7.5 WHY ESTIMATE?................................................................................................................. 59
7.6 HOW IS ESTIMATING DONE?.................................................................................................59
7.7 NORTHERN ESTIMATING:......................................................................................................60
7.8 PREPARING THE ESTIMATE...................................................................................................60
7.9 THE GENERAL CONTRACTOR’S RESPONSE............................................................................61
7.10 ESTIMATING - SMALLER PROJECT..........................................................................................62
7.11 OVERHEAD, CONTINGENCIES AND PROFIT..............................................................................64
7.12 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................65
7.13 REVIEW AND RESEARCH QUESTIONS.....................................................................................65
7.14 RESOURCES....................................................................................................................... 66
8 PLANNING - SCHEDULING.....................................................................................................67
8.1 INTRODUCTION....................................................................................................................67
8.2 GOALS AND OBJECTIVES......................................................................................................68
8.3 WHAT IS SCHEDULING?........................................................................................................68
8.4 BAR CHART........................................................................................................................ 69
8.5 PERT DIAGRAM / CRITICAL PATH ANALYSIS............................................................................71
8.6 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................72
8.7 REVIEW AND RESEARCH QUESTIONS.....................................................................................73
8.8 RESOURCES....................................................................................................................... 73
9 SIMPLIFY WITH SOFTWARE...................................................................................................74
9.1 INTRODUCTION....................................................................................................................74
9.2 GOALS AND OBJECTIVES......................................................................................................75
9.3 COMPUTERS DON’T MAKE MISTAKES BUT THEY AREN’T SMART..................................................75
9.4 SOFTWARE CAN …..............................................................................................................75
9.5 CHOOSING PROJECT SCHEDULING SOFTWARE.......................................................................76
9.6 CHOOSING PROJECT ESTIMATING SOFTWARE........................................................................76
9.7 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................77
5
9.8 REVIEW AND RESEARCH QUESTIONS.....................................................................................77
9.9 RESOURCES....................................................................................................................... 77
10 PHASE 3 MONITORING & CONTROLLING – IN HOUSE........................................................78
10.1 INTRODUCTION....................................................................................................................79
10.2 GOALS AND OBJECTIVES......................................................................................................79
10.3 MONITORING THE PROJECT..................................................................................................79
10.4 CONTROL IS A GOOD THING.................................................................................................80
10.5 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................81
10.6 REVIEW AND RESEARCH QUESTIONS.....................................................................................81
11 MONITORING THE TRADITIONAL CONTRACT......................................................................82
11.1 INTRODUCTION....................................................................................................................82
11.2 GOALS AND OBJECTIVES......................................................................................................83
11.3 THE PROCESS....................................................................................................................83
11.4 IMPORTANCE OF RECORD KEEPING.......................................................................................85
11.5 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................87
11.6 REVIEW AND RESEARCH QUESTIONS.....................................................................................87
12 HOW TO CONTRIBUTE TO SUCCESSFUL PROJECT COMPLETION...................................88
12.1 INTRODUCTION....................................................................................................................88
12.2 GOALS AND OBJECTIVES......................................................................................................89
12.3 THE PROJECT TEAM............................................................................................................89
12.4 CONFLICT RESOLUTION........................................................................................................90
12.5 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................92
13 PHASE 4: WRAPPING UP THE PROJECT..............................................................................94
13.1 INTRODUCTION....................................................................................................................95
13.2 GOALS AND OBJECTIVES......................................................................................................95
13.3 WHY EVALUATE THE PROJECT?............................................................................................95
13.4 IDENTIFY WHAT YOU DID RIGHT AND WHAT COULD HAVE BEEN DONE BETTER..........................95
13.5 THE FINAL REPORT.............................................................................................................96
13.6 DISCUSSION AND REFLECTIVE QUESTIONS.............................................................................97
13.7 REVIEW AND RESEARCH QUESTIONS.....................................................................................97
6
WEBSITES & RESOURCES.............................................................................................................98
Appendix A: Project Management. A Crisp Fifty- Minute Book....................................................99
7
Preamble – Community School of Government
COMMUNITY SCHOOL OF GOVERNMENT
The School of Community Government is a division within the Department of Municipal and Community Affairs, Government of the Northwest Territories.
The School of Community Government (S of CG) assists community governments by providing training and development opportunities to community governments, their staff and other community organizations. Training is based on assessed community needs, delivered to a recognized standard and upon successful completion provides certification.
WORKS AND WORKS MANAGEMENT
Works and Works Management is one of the programs offered by the School of Community Government. Community Works comprises more than half of a community’s budget and includes mobile equipment, buildings, roads, water and sanitation and work place safety. The School of Community Government recognizes the importance of Community Works and offers a number of programs to help meet the training needs of community works foremen, facility maintainers and many other employees involved in community works.
8
Course Description and Purpose
COURSE DESCRIPTION
This course will give you understanding and help you in project and contract management. It includes information on the administration of projects, the tendering process and estimating and scheduling with emphasis on construction.
This course has been developed to address the learning needs of Community Works Foremen.
PURPOSE
This course has been developed to meet learning needs identified in the NWT Occupations Community Works Foreman DACUM Chart (January, 2002) that was developed by the Departments of Municipal and Community Affairs and Education Culture and Employment. The DACUM process is a way to “Develop A Curriculum”. It is a competency analysis that gives employers, employees, educators and learners a say in developing the curriculum for an occupation. This course may also be of value to other community people who are involved in projects, construction and/or contracting who may be employed by Aboriginal or Community Development Corporations or their subsidiaries.
This course was made in the North and is based on needs specific to the Northwest Territories. If you are attending a course delivery you will have the opportunity to hear presentations made from experts in the area and be able to ask them for general advice as well. The course manual includes many additional sources of information that you can access through the internet or, in some cases, by phone.
This manual was developed by Red Willow Consulting Ltd. with technical assistance from FSC Architects and Engineers and materials developed by Professor Tamer E. El-Diraby of University of Toronto (given with permission), Government of the Northwest Territories, Department of Public Works and other sources. A text called, Project Management by Marion E. Haynes (Crisp Publications) is also used. The project leader was Mike Yakabuski, Senior Researcher, School of Community Government, Municipal and Community Affairs, Government of the Northwest Territories.
1 Introduction to Project and Contract Management
Abbott: Who's on first? Costello: I don't know. Abbott: He's on third, we're not talking about him. Costello: Now how did I get on third base? Abbott: Why you mentioned his name. Costello: If I mentioned the third baseman's name, who did I say is playing third? Abbott: No. Who's playing first. Costello: What's on first? Abbott: What's on second. Costello: I don't know. Abbott: He's on third. Costello: There I go, back on third again!
1.1 INTRODUCTION AND SCOPE
When a Community Works Foreman completes a project it almost always involves other people. It can involve working with staff, council and/or contractors. It helps to know who is responsible for what.
A Community Government (CG) can play many roles in projects and the number of roles seems to be increasing. This affects your job. Regardless of the CG’s role and your responsibility the more you know about project management, the better.
If you are working on a project another thing you can be sure of is that the project will have problems.
Taking this course and studying project and contract management won’t prevent all of the problems from happening but it will help.
By learning project management skills, you will be able to
Free up your own and other people’s time to solve problems before they happen
Reduce frustration
Improve the quality of the completed project
Save money in time and in material costs
In this course we will be studying project and contract management, with emphasis on the specific areas of tendering and construction management including estimating and scheduling.
1.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to
Define a project
Describe the various roles that Community Governments have in projects
Describe the project life cycle and the four project phases
Explain project management
1.3 WHAT IS A PROJECT?
A project is an undertaking that has a beginning and an end, and is carried out to meet established goals within cost, schedule and quality objectives. The successfully managed project is one that is completed as it was intended, on/or before the deadline and within budget. Planning combined with quick on the feet (or telephone) response to problems, gives you your best chance for success.
It would be hard to say whether projects or on-going maintenance and program activities are more important: they’re different. If you are constructing a building, you will finish it, but the building’s maintenance is ongoing.
The following chart gives some examples of what is a project and what is not a project.
11
Project Not a Project
Program
Maintenance
Regular Work
Catering for a BBQ for the whole community Making coffee for the office
Installing a water treatment facility Delivering water weekly
Building roads for a new housing area Clearing snow from the streets
Installing a new boiler Inspecting equipment regularly
1.4 WHAT IS PROJECT MANAGEMENT?
Project management is the art of directing and coordinating people and material resources throughout the life of a project by using management techniques to achieve a set of objectives including scope, cost, time, quality and participation satisfaction.
To be a project manager you need to
Use general management skills. You will need to build morale and support staff, direct and organize tasks and motivate people. You will need to review and approve decisions made by others and monitor people’s work and take corrective action when necessary.
Be knowledgeable of the technical aspects of the project, be it the design of a training module (curriculum development), a software program (computer programming) or the construction of a facility. What you need to know about a construction project will depend on its size and complexity but could include engineering, architecture and the trades. A project manager does not necessarily know the details of every area but individuals who manage major projects have made project management their career.
Use project management skills like planning and estimating and scheduling.
Continually strive to improve the process
Chapter Two – Phase One: Definition of a Contract 12
Figure 1.1
Projects are often completed by in-house staff. For instance the Works Department may complete a project such as painting the exterior of the community school building over the summer. This same project could, however, be completed by selecting and entering into a contract with a business that paints buildings.
Whether a project is completed in-house or contracted out, it takes many of the same skills as managing a department. The difference is that in managing the Works department, it is important to ensure that a service will be provided, and staff will be available to complete work, on an on-going basis. With projects, there is always a deadline and the objective is to make sure that specified work is completed.
Chapter One – Introduction to Project and Contract Management 13
Figure 1.2
Chapter One – Introduction to Project and Contract Management 14
Prospective on Objectives and Methods of Construction Project Management
The "life cycle" of costs and benefits from initial planning through operation and disposal of a facility are relevant to decision making. An owner is concerned with a project from the cradle to the grave. Construction costs represent only one portion of the overall life cycle costs.
Optimizing performance at one stage of the process may not be beneficial overall if additional costs or delays occur elsewhere. For example, saving money on the design process will be a false economy if the result is excess construction costs.
Fragmentation of project management among different specialists may be necessary, but good communication and coordination among the participants is essential to accomplish the overall goals of the project. New information technologies can be instrumental in this process, especially the Internet and specialized Extranets.
Productivity improvements are always of importance and value. As a result, introducing new materials and automated construction processes is always desirable as long as they are less expensive and are consistent with desired performance.
Quality of work and performance are critically important to the success of a project since it is the owner who will have to live with the results.
From Project Management for Construction. Fundamental Concepts for Owners, Engineers, Architects and Builders. 2003.
Chapter One – Introduction to Project and Contract Management 15
COMMUNITY PROJECT MANAGEMENT
(The following chart demonstrates how a large construction project is typically completed in a Community.)
Figure 1.3
Community Planning and Design
Usually communities identify the sites for future building in the community plan which is prepared by the municipality and community residents and revised every five years. The community plan is developed with the assistance of professional planners and technical staff. Where community plans are not in place, there is a land use plan.
When the time comes for the construction of the facility the Community Organization, (and in this example, the Hamlet will be the owner of the new building) seeks professional help from as Architect. The Architect and the Hamlet Council and staff will discuss the needs of the community and the Architect will prepare an outline of what will meet these needs.
Before any building design is completed the Hamlet will need to complete a number of surveys and studies of the site so that the building structure will work on the site.
Once there is a clear description of the site, the Architect, with assistance from Engineers will design the building.
Chapter One – Introduction to Project and Contract Management 16
Construction
Usually the Architectural Firm also manages the construction project which the Contractor completes. Throughout the process the project drawings are used for communication among the team. During the design phase, these drawings will likely be revised as the Hamlet and the Architect discuss various ideas and architectural details. The Drawings and Specifications, when finalized, will explain how and what materials will be used. The Construction Contractor builds based on the Drawings and Specifications.
Building Occupancy
When the Hamlet takes up occupancy in the building, there will be a warranty period of about one year when the Contractor will be responsible for nearly all problems that might occur in the building.
Different Schemes for Different Teams
Throughout this course, we will be looking at the different roles that a Community Government (CG) Works Foreman may play in projects or contracts. For instance, if a community-owned facility is being built,
1. The Works Foreman, on behalf of the CG may manage a project with staff completing the work (in-house). This might occur when a new road is constructed
2. The CG may tender a project to build a water treatment facility, receiving bids and selecting a construction firm. The Works Foreman may be the Project Manager.
3. The CG may tender a contract such as building an office building. An architectural and/or engineering firm may design and manage the contract. The Works Foreman may be one of the representatives of the CG on a committee that leads the project.
4. The project may be supervised by the Government of the Northwest Territories (GNWT) and the Works Foreman may have a very limited role.
5. A Community Government can be bid on a contract such as a Department of Transportation road maintenance project and may be awarded the contract. In this situation the Works Foreman may be the project manager.
The following chart shows many of these different roles.
Chapter One – Introduction to Project and Contract Management 17
Owner Designer Project Manager Construction
1. In-houseCommunity Government (CG)
CG or consultantCG Works Foreman
CG Works
2. CG prepares tender
CG CG or consultantCG Works Foreman
Contractor
3. Consultant prepares tender
CG Consultant
Consultant (SAO or Works Manager on behalf of the owner)
Contractor
4. Government of the NWT prepares tender
CG Consultant
Consultant (GNWT representative on behalf of the owner)
Contractor
5 CG bids on tender
Government (Federal or NT)
Government staff or in-house staff
Works Manager (GNWT on behalf of the owner)
CW
Chapter One – Introduction to Project and Contract Management 18
1.5 THE PROJECT LIFE CYCLE
All projects have a similar life cycle which can be broken into four phases:
Defining the project
Planning the project
Implementing the plan
Completing and evaluating the project
Figure 1.4
Chapter One – Introduction to Project and Contract Management 19
PHASE 1: DEFINING & STRATEGIZING THE PROJECT
In this phase, the Community Government determines the objectives and strategizes on how to go about the project.
It recognizes a need for something such as a building or a wharf, a celebration or a new accounting system. It decides on the project and the purposes of the final completed facility or event or system. Chapter 2 is about defining the project.
The community must then work on a strategy as to how it will go about completing the work on the project. Often the process chosen includes contracting. In this manual, in Chapter 2, 3 and 4 we will discuss approaches to contracting for the completion of a project.
PHASE 2: PLANNING THE PROJECT
In this phase
Write specifications
Develop budget
Develop schedule
Three items define a project: Quality, Cost and Time. The following chart shows how these items connect with project tasks.
Webster’s Dictionary defines the noun, quality as “any of the features that make something what it is”, “basic nature; character; kind” and “the degree of excellence which a thing possesses. Similarly quality, in projects, refers to the type and grade of materials used and the method of workmanship. These are identified in the specifications.
Project costs include every cost of the project. Project costs include materials, supplies, labour and other expenses all of which are included in the budget. Project costs don’t include the ongoing costs that a project might create, for instance, the fuel costs to operate a building.
Project time refers to the hours required to complete a project. It also includes the timing of a project; the sequence of project activities and how the project can be fit into the calendar. For instance, painting a school needs to be completed between the end of June and the middle of August and materials, in some communities, must be ordered for barge delivery.
Chapter One – Introduction to Project and Contract Management 20
Figure 1.5
PHASE 3: IMPLEMENTING THE PLAN – EXECUTING THE PROJECT
This phase is when the action starts, when site work begins, materials are delivered and construction follows.
The project manager’s role, although (s)he does not act alone, is to
Monitor performance
Take corrective action
Provide feedback
Resolve differences
In management jargon, these activities are called controlling. The project manager ensures that the plan is followed. Each of these four activities is done in order to stick with the plan. Of course sometimes changes to the plan are necessary and this is why communication is so important.
PHASE 4: COMPLETING AND EVALUATING THE PLAN
This phase is the completion of the implementation of the plan. It includes
Deliver output
Wrap up administrative details
Evaluate the experience
All the items in the plan are completed, files are updated and manuals completed. Finally the project is reviewed to see what has been learned.
Chapter One – Introduction to Project and Contract Management 21
Project
Quality Cost Time
BudgetSpecifications Schedule
1.6 DISCUSSION AND REFLECTIVE QUESTIONS
1. Discuss some of the projects that have been completed in your community and identify who was the owner, the designer, the project manager and who completed the construction.
2. Take a recent project and describe the steps taken to complete it.
3. Review “Community Construction Management” and cross-reference with “The Project Life Cycle”, where applicable.
1.7 REVIEW AND RESEARCH QUESTIONS
1. Of the following list, which items are projects?
Building a shed
Building a new school
Replacing all incandescent lights in a facility in August as part of preventive maintenance
Contracted janitorial services
Using Municipal Maintenance Operations System
2. Define a project and give examples from your work.
3. Explain project management.
1.8 RESOURCES
Crisp Publication, Project Management, pages 1-12.
Chapter One – Introduction to Project and Contract Management 22
2 Phase 1: Definition of a Contract
Chapter Two – Phase One: Definition of a Contract 23
Figure 2.6
2.1 INTRODUCTION
As a member of the community, you and others may be aware of a need in the community. Perhaps people are talking about the need for sidewalks or more playgrounds for children. It may be that it is already in your community plan. Seeing a need is often the first step towards a project.
Phase 1 of a project is developing a clear description of what is required by determining the project objectives and selecting a strategy to complete it. The Crisp Publication, Project Management, Part 2, on pages 15 -22 details this general process.
One of the strategies that must be decided is the way that the project will be completed. If it is to be completed by a contract, the way it is obtained or procured has to be determined. But first we will look at what a contract is.
Figure 2.7
2.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to explain
What a contract is
Differences between hiring and contracting
24
2.3 WHAT IS A CONTRACT?
A contract is a legal definition. It is an agreement between persons which obliges each party to do or not to do a certain thing. Technically, a valid contract requires an offer and an acceptance of that offer, and, consideration.
“I will sell you my motor for $500.00”
“I accept.”
Offer
An offer is a promise made by one party to another to perform or give property, goods or services.
“I will sell you my motor for $500.00”
Acceptance
An acceptance is the agreement of one party to the offer made by another.
“I accept.”
Consideration
A consideration is a benefit gained by the person who makes the offer.
$500 .00
Capacity
Capacity means that both parties in an agreement must be legally able to enter into an agreement. For example, a minor (a person under 19 years of age) cannot legally enter into an agreement.
Both persons are over 19 years of age.
Intention
Intention means that both parties to an agreement must mean to enter into the agreement. For example, a person is inebriated and does not intend to enter into an agreement.
Both persons are sober and of sound mind
25
A contract need not be in writing, unless it is with regard to the sale of property, of land. A practical definition of a contract is an agreement that will stand up in court. Given this definition, a written contract has much to be said for it.
Figure 2.8
There are many different types of contracts. An employment contract is very different than a service or construction contract. For instance, if you hire an employee to paint the garage, the employee will be paid a wage, very likely by the hour, and will have the protection of Labour Standards laws and possibly a union contract. The person will be paid overtime for hours worked over forty hours per week. Your Council will be responsible for Workers Compensation for the employee. You will be able to tell the employee what hours to work, exactly how to do the work and the employee will not be able to get someone else to help him or her. The employees will be paid for the hours they came to work, whether they were able to complete the work (for instance, if it rained) or not.
If you contract with a business, the business will be paid upon completion of work, regardless of the time it takes, and the company will be responsible for its Workers Compensation and other insurance. The company, unless specified otherwise in the contract will be able to work whenever they want, i.e. into the evening, on the weekend, and can send various people to do the work. They will be paid the same amount regardless of how long it takes them to complete the work (unless there is a penalty clause for late delivery of a product or service.
In this course we will look primarily at contracts for sale of services and construction.
26
2.4 DISCUSSION AND REFLECTIVE QUESTIONS
1. Which is more difficult: managing a project in-house or being responsible for the completion of a project by a contractor?
2. What are the similarities and differences between contracting and hiring as a means to complete a project?
Hiring employees
Completing the project in-house
Contracting
Contractor completing the project
Payment based on?
Who is responsible for insurance?
Reasons for hiring or contracting
2.5 REVIEW AND RESEARCH QUESTIONS
Match the following
Offer Both parties are of legal age
AcceptanceAre you interested in installing the equipment?
Consideration I agree to install the equipment
Capacity The cost is $500.
Intention Both parties are sober and of right mind
Chapter Two – Phase One: Definition of a Contract 27
The Design and Construction Team
Chapter Two – Phase One: Definition on a Contract 28
3 Purchasing Methods
˜When the Government knows what it wants done and how it should be done (such as a construction project), it will already have its plans and specifications and is looking simply for the best price. On the other hand, when the Government knows what it wants done, but not how to go about doing it, it seeks proposals on methods, ability, and price. Then it can negotiate on the best method to achieve the best value.” (1) Socanav Inc and the GNWT et al., SCNT, Vertes, Aug 5, 1993.
3.1 INTRODUCTION
There are many different kinds of contracts such as contracts for goods and services and construction projects. When public organizations purchase goods, services or projects of significant value they are required to use a public process, either public tender or proposal.
In communities, in some cases, construction and other large contracts may be put out to tender by the Government of the Northwest Territories or some other body outside the community. When the community government is involved, construction contracts, and other service contracts will typically be tendered by the Senior Administrative Officer (SAO). However, the Works Foreman can offer support and assistance on site and building projects, mobile equipment, water delivery, sewage pickup and other matters. In some cases, you may manage the contract once it has been awarded.
As well you and your community may be on the other side of the table. For instance, if you have the mobile equipment necessary for road work that the government or some other agency wants to complete, you may decide to bid on their tender.
In this chapter, we will look at the tender processes that the Government of the Northwest Territories uses. We will review these processes for the following reasons.
The GNWT is the largest public purchasing and contracting agency in the NWT and has an established tendering method that follows accepted practices.
Chapter Two – Phase One: Definition of a Contract 29
In some cases, community organizations are required to follow some of the GNWT’s tendering practices. Community organizations may be bidding on GNWT tenders.
3.2 GOALS AND OBJECTIVES
After studying this chapter you will be able to explain
Methods of purchasing goods and services: Request for Proposals, Standing Offers, and Negotiated Contracts.
Tendering and the tendering process
Business Incentive Policy (BIP)
3.3 METHODS OF PUBLIC PURCHASING
Public purchasing or procurement, as it is sometimes called, is different than purchasing in personal or private sector purchasing. Because the money being spent is public money, raised by taxes, the government seeks the best price but there should be no favouritism to one firm or another. The following methods of procurement are used by public organizations.
Tendering is a method of purchasing goods or services used by government and other organizations in an effort to get a good price and at the same time give all competent suppliers, service providers or contractors an opportunity to bid for the work.
3.3.1TENDERING
Tenders are used when it is clear what is to be done and how to go about doing it. The purchaser knows exactly what goods or service they want and is looking for the best price to deliver it. As with other types of tenders, construction tenders have detailed material and performance specifications. The lowest qualified bidder wins the tender.
When public and other organizations purchase goods, services or construction work, they use a process called tendering. They invite businesses to submit a tender on the goods, service or project. In this way they make an effort to get a good price and at the same time give all competent suppliers, service providers or contractors an opportunity to bid for the work. The bidders make an offer to do the work for a fixed price and if they are the successful bidder they are obliged to follow through with providing the service or completing the work.
Tendering is used to mean a number of related things. Tendering means
30
Calling for tenders
Submitting a tender bid
The process of calling for tenders.
The tendering organization accepts one of the bidders’ offers to do the work outlined in the tender for a fixed (set) price. The bidder with the best bid wins the contract and they are obliged to follow through by providing the goods and/or services or completing a project, for the agreed upon fee or price.
3.3.2THE TENDERING PROCESS
The Government of the Northwest Territories places advertisements in northern newspapers and posts announcements on its web site for tenders (http://www.contractregistry.nt.ca) that are expected to be above $100,000 in value. Before a tender can be advertised, detailed specifications must be completed. Although GNWT tenders use standard terms and conditions, these specifications vary in respect to different goods and services tendered.
Bids are invited on all contracts that are expected to be above $5000. These bids may be requested orally but records must be kept.
3.3.3 REQUEST FOR PROPOSALS
A proposal is different from a tender. A Request for Proposal (RFP) is used when the purchaser is looking for the best value solution to resolve a problem or to deliver a good or service, but is not exactly sure how to achieve it. Detailed specifications are not provided. An RFP is used when
You know what you want done
You may not be clear as to how it should be done
The project (or goods or services) are not specifically defined
There is no detailed material or performance specification
You are looking for a general solution (GNWT PWS Procurement Guidelines).
Unlike a tender, an RFP does not include project specifications but instead includes a Scope of Work or Terms of Reference.
In order to decide which bidder is awarded the work for an RFP the proposals received must be evaluated. Usually they are evaluated based on the following factors
1. Project team – who are the people who are going to complete the work
2. Methodology – how is the bidder is going to go about completing the work
31
3. The Company’s past relevant experience
4. The Project Schedule
5. Past Performance Appraisals
6. Location of the Company and team relative to the site
7. Proposal format and quality
8. Cost
Some of these factors are given more weight in the final decision. A committee reviews the proposals. These factors are weighted and rated by a committee to decide the best proposal.
3.3.1STANDING OFFER AGREEMENTS (SOA)
Standing Offer Agreements (SOA) are put out to bid like other tenders. The GNWT defines a Standing Offer Agreement as
A price agreement between the Government and a supplier, wherein the supplier agrees to provide, on demand, specified goods or services under specified conditions during a set period at a defined price or discount.
The purchasing process is by public tender. Standing Offer Agreements are intended to increase the
Cost-effectiveness and service to users, by:
Reducing the time required to acquire standard goods and services
Reducing the overall administrative costs of acquiring frequently required goods and services
Maintaining competitive, best price expenditures.
You would not likely use a Standing Offer to complete a project.
3.4 BUSINESS INCENTIVE POLICY (BIP)
The Business Incentive Policy (BIP) gives registered northern businesses a preference in tender and RFP awards. As a general rule, if a purchase or a project is funded by the Government of the NWT, in the amount of 51% or more, BIP will apply.
The GNWT’s Business Incentive Policy (BIP) provides an incentive to northern business to
32
Offset the higher cost of operating a business in the NWT and to make them able to compete with southern firms.
Enable them to develop necessary experience and business skills
The GNWT also agrees to develop policies which are easily understood by the business community and which are easy to administer.
The GNWT applies the BIP as follows.
Category Incentive
For contracts valued at over $1,000 and less than $5,000
20% discount applied to northern content (No additional tender adjustment for local content.)
For Construction, Service and Maintenance Contracts
Contracts valued at over $5,000
15% discount applied to northern content and an additional 5% discount for local content.
For contracts for goods, contracts valued at over $5,000
15% discount will be applied to northern content on all contracts and an additional 5 per cent discount will be applied to any local content unless otherwise specified in the contract documents.
33
3.5 DISCUSSION AND REFLECTIVE QUESTIONS
1. Could your community government save time or improve service by tendering out and entering into Standing Offer Agreements with any trade or service companies?
3.6 REVIEW AND RESEARCH QUESTIONS
1. Describe the differences between Request for Proposals and Tenders.
Tender RFP
Product
Price selected
Description of Work
Other
Chapter Two – Phase One: Definition of a Contract 34
2. For the following examples, what tender would be considered the lowest price after BIP was applied?
BIP LocalTotal Fixed
CostAdjusted Amount
1. Number One yes No $39,000
2. Second to None yes yes $42,000
3. Tri- Corporation No No $43,000
4. Quartet yes no $38,000
Chapter Three – Purchasing Methods 35
3.7 CASE STUDY
David Smith, senior purchasing agent for Lynx River Junior High School, has been instructed by the local school board to make the school wheelchair accessible by the first day of school. After contacting the Disabled Association in Lynx River as to what would be required, David drafts an Invitation to Tender with detailed specifications as to the work to be done, the angle of the wheelchair ramps for children being one of the specifications.
When the Invitation and specifications are typed, David gives them a cursory glance and sends them off for photocopying and publishing in the local newspaper. Unknown to David, during typing, a paragraph in the specifications has been deleted from the final copy, which details the angle and location of the wheelchair ramps. Further, the number of wheelchair ramps has been mistyped as “ten” rather than “two”.
In due course, three contractors express an interest in the Tender and obtain copies of the Invitation and detailed specifications. Two submit bids forthwith. The third telephones David several times seeking more information and generally becoming a nuisance. After the sixth phone call, David instructs his assistant, Bruce Ward to field any further questions.
The next day the third contractor calls David and is transferred to Bruce Ward, who assures the contractor he is fully qualified to answer any questions the contractor may have.
The contractor then asks Bruce whether something might be missing or in error in the Invitation or specifications as they appear incomplete. Bruce responds, “Absolutely not! I can assure you all the information is in the specifications. That is exactly what is required. No more, no less.”
The third contractor then advises Bruce they will not be submitting a bid as the job is “obviously too large for us to complete in the time frame specified.”
After Tender closing, David and Bruce sit down to decide who will be awarded the Tender contract. Both Tender bidders have submitted bids which describe construction of the wheelchair ramps as unit priced. One is slightly lower and from a reputable contractor, ABC Construction, who David and Bruce decide is the successful contractor.
After notifying the unsuccessful and the successful bidder, David discovers the numerical error. He decides that time is too short to re-tender so he simply instructs ABC Construction to only build two, not ten, wheelchair ramps. He does not notice the missing paragraph however.
The contract is drawn up in a rush and simply states ABC Construction is to “complete the work described in the Invitation to Tender as per the specifications attached thereto on or before September 2nd, David then goes on holidays.
Chapter Three – Purchasing Methods 36
ABC Construction does complete the work by September 2nd, but the two wheelchair ramps are located at the wrong doors. In addition, the angles of the wheelchair ramps while appropriate for adults are too steep for children.
David refuses to pay ABC Construction any money claiming they have not lived up to the contract.
ABC Construction insists they did not know the wheelchair ramps were too steep nor did they know the locations were wrong. They claim they built “standard wheelchair ramps at appropriate and reasonable locations”. They further claim they have performed the contract as described and should be paid in full.
The dispute is reported in the local newspaper. The third contractor who chose not to bid discovers David only wanted two ramps, not ten. The third contractor also discovers that had they bid on the contract, their bid would have been substantially lower than the successful tender bid.
REQUIRED: Discuss this case. Identify what was done incorrectly. Suggest means of
correcting. Identify possible lawsuits.
3.8 RESOURCES
CIV320 H1 S Management of Construction. Module 2: Contracting. Tamer E. El-Diraby, PhD. University of Toronto.
GNWT Public Works and Services Web site – Publications – Procurement Guidelines
GNWT Public Works and Services Web site –http://www.pws.gov.nt.ca/pdf/publications/Proj_Mgmt_Manual/PM-%20Introduction/0.2contents.pdf
Chapter Three – Purchasing Methods 37
Chapter Two – Phase One: Definition of a Contract 38
4 The Tendering Process - Construction
4.1 INTRODUCTION AND SCOPE
The largest and most costly projects completed in communities are construction projects. Community projects are funded with tax payer’s dollars. The tendering process is a way to assure the fair, impartial awarding of contracts while at the same time achieving value for tax payer’s dollars. Although tendering is a straight-forward process, it has its complications.
Figure 4.9
39
4.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to explain
Three types of Construction Price and Payment Methods
The tendering process for Fixed Price Contracts
The purpose of Bid Bonds and Performance Bonds.
4.3 TYPES OF CONSTRUCTION PRICE AND PAYMENT METHODS
Contractors use a number of methods to set the cost of a project. Each one is suited to a particular type of work. On larger projects, there may be one contract between the owner and the person who is doing the construction (the contractor), and a second (separate) contract between the owner and the person who is doing the design work (an architect or designer).
4.3.1TYPES OF CONTRACT
A Fixed-Price Contract also called a Lump Sum Contract or Stipulated Price Contract sets out the total price for the work, including all labour, materials, sub trades, equipment rentals and so forth. Fixed-price contracts are suited to small repair or renovation jobs, or those projects that are relatively straightforward and easy to plan. Any changes or adjustments to a fixed-price contract require a written Change Order signed by both parties.
A Cost-Plus Contract is based on the cost actually paid for labour, subcontracted services, materials and other direct expenses, plus a fee to cover the contractor's time managing and coordinating the sub-trades, materials and inspections needed to complete the project. The fee can be either a fixed amount or a percentage of the costs. A cost-plus contract is often used in larger renovation projects when the exact extent of the work to be done cannot be accurately determined in advance. The project budget set out in the contract should provide estimated costs for major elements of the work. To ensure that the project costs are kept under control, a maximum budget is usually set out in the contract.
Design-Build Contracts are a variation on either fixed price contracts or cost-plus contracts. The distinguishing feature of a design-build contract is that instead of the owner signing one contract to design the home, and a separate contract to build it, the whole project is covered in a single document: one firm undertakes to do both design and construction. This approach is more common with custom new construction and large-scale renovation projects. For instance, architects often provide overall management for a custom project, doing the design work themselves and then hiring contractors to carry out the construction. Most often, design-build management fees are calculated as a percentage of all costs and billed separately. However, even if the design-build contract is presented as a "single package
Chapter Two – Phase One: Definition of a Contract 40
deal", the owner should make absolutely sure that they are able to approve the design before work begins on construction.
Figure 4.10
In a Traditional, Fixed Price Contract, the design of the building is completed before the tender is advertised. As contractors pick up tender documents their company name is recorded. As the following illustration indicates, after the tender is advertised, there is usually a pre-bid meeting where interested contractors can ask the owner questions. The answers to any questions will be circulated to all bidders. The contractors need to have sufficient time after the tender is advertised to review the documents and prepare their tender. This is called the tender period. During the tender period, there may be modifications made. If this is the case, these amendments are circulated to every contractor who has picked up tender documents.
In Traditional, Fixed Price Contracts there are three parties involved in the contract, the owner, the consultant (architects and/or engineers) and the construction contractor. The consultant acts on behalf of the owner to manage the project.
Chapter Four – The Tendering Process – Construction 41
Figure 4.11
Chapter Four – The Tendering Process – Construction 42
4.4 THE TENDERING PROCESS
Figure 4.12
A fundamental rule of tendering is that bids must be received by a certain time and date. You cannot accept a bid that is received after the closing time and date. As well, the bidder must advise that he or she has received the amendments, if there were any.
Tender openings are public. They are held in a board room or place with an official clock as soon as practical after the tender has closed. The person receiving the tenders writes down
The name of the firm who submitted the tender
The $ amount of the tender
Whether or not security was given (if required)
It can take up to thirty days for tenders to be awarded. The tenders are reviewed to confirm the following points.
Are mandatory elements of the tender met?
Is the bid qualified?
Is the bid complete?
Are there inconsistencies between owner’s price estimates and the tender?
Chapter Four – The Tendering Process – Construction 43
Are there technical inconsistencies in the tender?
Is the bidder capable in all respects of being able to perform the contract requirements? (This may have been confirmed prior to the tender closing if Pre-Qualification was completed.)
After these points are clarified, the contract signing authority is advised, the contract award is approved and the successful contractor is advised and in some cases, letters of regret are sent to the unsuccessful ones.
4.5 BID SECURITY
For large tenders contractors may be required to provide a bid security in order to demonstrate good faith that they will follow through with the work. A bid security is
4.5.1BID BOND
A Bid Bond is purchased by the contractor when he submits a bid on a tender that requires a Bid Bond. The purpose of the Bid Bond is to guarantee to the Owner the good faith of the contractor. If the contractor’s tender is accepted he will enter into a formal contract with the Owner. If the contractor does not sign a contract then he is obliged to pay the Owner the difference in money between the amount of his tender and the amount it costs the Owner to get someone else to complete the work. If he fails to come up with this money the Surety Company that sold the Bid Bond is obliged to do so. If the Surety is called upon to pay under the terms of the Bid Bond, it will expect to recover such payment from the Principal.
4.5.2 PERFORMANCE BOND
The basic function of a Performance Bond is to protect the Owner up to the amount of the Bond in the event that the Contractor does not go through with the work. Provided the Owner has met his obligations under the Performance Bond and the contract, he will claim against the Surety and will expect to be covered for any loss suffered, up to the total amount of the bond. A Performance Bond is not intended to cover payment of labour and materials claims. Owners and Contractors should not depend on the Performance Bond for payment of such claims. Basically, the function of a Labour and Material Payment Bond is to guarantee that all claimants, likely sub-contractors or suppliers, will be paid for labour and materials furnished to the Principal for use of the project described in the bond.
4.6 BID DEPOSITORY
The Bid Depository is a system for the reception of sealed bids from Trade Contractors to enable those receiving the bids to obtain firm quotations in writing and adequate time to compile their tenders completely and accurately. This fair and equitable process is in the best interests of Owners, Tender Calling Authorities and General and Trade Contractors.
Chapter Four – The Tendering Process – Construction 44
Flowing from this stated purpose is the requirement that General Contractors enter into contract with selected Bidders whose bids have been properly deposited and which will be used for sub-contract purposes. Following the submission of General Contractor tenders, substitution or replacement of such selected Bidders is subject to specific approval of the Tender Calling Authority and/or Owner, based upon valid reason or circumstances which were not reasonable evident or assessable prior to the close of General Contractor tenders.
4.7 DISCUSSION AND REFLECTIVE QUESTIONS
1. Discuss the advantages and disadvantages of the three main types of construction contracts from the Owner’s point of view.
2. Is it worthwhile to send letters of regret to the unsuccessful bidders? Explain.
4.8 REVIEW AND RESEARCH QUESTIONS
1. What are the three main types of construction contracts? Give examples for when you might choose to use each of them.
2. What is the difference between a Bid Bond and a Performance Bond?
Chapter Four – The Tendering Process – Construction 45
5 New Deal for Communties
5.1 INTRODUCTION
Municipal and Community Affairs (MACA) through its New Deal initiative will give community governments more control of community infrastructure planning. Community governments will assume more responsibility for capital projects and project management as a result of this.
Chapter Five – Community Capital Authority Arrangements 46
5.2 GOALS AND OBJECTIVES
After studying this chapter you will be able to explain
The key components of Municipal and Community Affairs’ New Deal for Community Governments as this relates to capital projects.
5.3 A NEW DEAL FOR COMMUNITY GOVERNMENT
The Government of the Northwest Territories continues to ensure that the move to community empowerment is complete by establishing community governments as a fully autonomous third levels of government.
In recent years there has been a gradual increase in community governments’ abilities to manage community affairs. This change is reflected in the way capital construction projects have been managed.
Before 2000 many projects (eg. arenas, fire halls) were funded by the GNWT through MACA, managed by Public Works (PW&S) and the community provided a contribution (often labour). Through the Municipal Capital Assistance Policy, MACA provided arrangements whereby Community Governments could assume more responsibility in the management of projects. Depending on the capabilities of the community, these arrangements included;
1. Full Project Authority
The project was funded by MACA but the community government had full authority over all phases of project management.
2. Partial Project Authority
The project was funded by MACA. The community government participated in project planning and had some project management responsibility.
If a full or partial authority agreement was entered into by the GNWT/MACA and the community government, a contribution agreement was set-up between the two parties.
The practice of allowing for full and partial authority agreements has been discontinued.
The Municipal Statutes Replacement Act approved in Oct 2003 by the legislative assembly sets the stage for community governments to assume more authority and autonomy. As of 2007/08 the New Deal for Community Governments will give Hamlets and Charter Communities complete control over the community infrastructure planning process. MACA will provide advisory support and also assist communities in gaining the capacity to raise or
Chapter Five – Community Capital Authority Arrangements 47
borrow the necessary funds for projects, but essentially these community governments will be responsible for all aspects of community infrastructure planning and project management.
Initial implementation of the ‘New Deal for Communities’ will focus on Hamlets and Charter Communities. Phase 2 of the implementation will consider how best to build capacity in Band and Settlement communities. Should the council of band or settlement communities wish to assume some of the same authority as Hamlets and Charter Communities, it is possible for these communities to become Charter Communities.
This chart illustrates the fundamental change to community infrastructure planning and project management as a result of the New Deal.
Typical Project (Fire Hall Construction)
Pre 2007/08 As of 2007/08
Planning · GNWT identified need for Community with community consultation
· GNWT sets priorities for projects
· Community Identifies need · Community sets priorities for
projects
Funding/Financing · Funded by GNWT · Community Government secures funding through borrowing, financing, leveraging of funds.
· MACA supplies some funds through block capital funding
Project Management
(inc. planning, design, tendering, construction, warranty)
· GNWT hires consultant· GNWT approves design,
community has some input
· GNWT manages· Community manages with
support of MACA/PW&S
· Community hires consultant· Community approves design· Community manages
5.4 DISCUSSION REFLECTIVE QUESTIONS
1. How can Community Governments gain the capacity to effectively manage capital projects?
2. Will having communities assume more responsibility for capital projects mean less or more capital projects being planned and completed?
3. Will the community government staff workload increase when the community government assumes full responsibility for community infrastructure planning?
Chapter Five – Community Capital Authority Arrangements 48
5.5 RESOURCES
New Deal for Community Governments
Municipal and Community Affairs
Government of the North West Territories
Chapter Five – Community Capital Authority Arrangements 49
6 Phase 2 Planning
~ Quality should be designed into the product and not inspected into it. – Dr. Genichi Taguchi.
Chapter Six – Phase 2: Planning 50
Figure 6.13
6.1 INTRODUCTION
Planning is important in Community Governments. CG’s do various kinds of planning. They make business plans to ensure they provide the best services they can to residents. They schedule their annual activities and then prepare their annual budgets. They make plans for community growth, site and building development in their community plan that is revised every five years. Planning improves the
Efficiency and effectiveness of the organization
Quality of decisions made
Ability of groups to work as a team
Chapter Six – Phase 2: Planning 51
Ownership employees feel about their work and community residents feel about community activities and projects, especially when they are involved in the planning.
The CG’s business plan, budget and community plan include projects. Each of these projects requires planning. Planning saves time, effort and money and is the most important part of a project. It lets the CG make mistakes on paper.
In this chapter we will discuss project planning in CG.
Goals and Objectives
In this chapter you will learn about
The challenges of planning
The function of planning
Specifications
6.2 PLANNING IS NOT FOR THE FAINT-HEARTED
It’s all very well to say that planning includes preparing specifications, a budget and a schedule. However the nature of people is to want more so it’s not surprising that governments of all kinds can never satisfy people. We all have to juggle quality, cost and schedule. People want all the bells and whistles, the budget is never enough and desired completion is next week. Priorities must be decided and tradeoffs made.
However, the better the plan, the closer you can come to pleasing people. You can be more efficient in ordering materials, arranging equipment and getting people working on the project. This is equally important whether your complete the project in-house or contract out the work. The contractor will face similar issues and problems as you face when you complete a project.
Chapter Six – Phase 2: Planning 52
Figure 6.14
6.3 CONFLICTS AREN’T NECESSARILY BAD
Underneath a conflict situation might be a discussion of a better way to do things. Once the work has started a conflict can slow it down, increase the budget and make the project manager look bad. That’s not good but it may be worthwhile because it may contribute to improving the final product. Even better is to sort out the problem and make a change in the defining or planning phase, when you are just dealing with words and numbers rather than later when it can mean costly change orders to cover the cost of replacement materials and additional labour.
6.4 SPECIFICATIONS
Specifications are a list of requirements for a project. Specifications identify the quality, the type and grade of materials used and the method of workmanship.
6.4.1 PURCHASING GOODS
In a contract to purchase a product the specifications are a description of the item to be purchased. For instance:
Chapter Six – Phase 2: Planning 53
40 boxes (10 packages to a box) of white 8 ½ x 11” paper, standard grade, Delivered by truck.
6.4.2 PURCHASING SERVICES
When you write a contract for the provision of a service, the specifications are a description of the service to be provided. For instance:
Chapter Six – Phase 2: Planning 54
Janitorial Services
This school is attended by children from Kindergarten to Grade 10 and consists of 20,000 square feet.
Specifications
1. The Contractor will supply all equipment necessary including all supplies including garbage bags, germicides, disinfectants, detergents and other cleaning supplies as necessary; and washroom supplies including washroom soap, two-ply toilet paper, high quality paper towels and any other supplies not mentioned here but assumed to be necessary in providing a clean and sanitary school.
2. Janitor Supervisor
The Contractor must identify a janitor supervisor in each school and the contractor must supply a list of employees who will be performing the work to the Board Superintendent and must assure that only these employees are granted access to the schools. This listing of employees shall be provided monthly.
3. Insurance
Provide the Board with evidence of compliance with the following:
a) Workers' Compensation Coverage
b) Northwest Territories Business license
c) Liability Insurance in the amount of one million dollars ($1,000,000)
d) Proof of bonding of all employees that will be working in the school.
4. Security
All safety measures respecting personnel and fire hazards recommended by National and Territorial codes.
5. Special Equipment
Word processing equipment and computers and terminals and telephone answering/message devices will have only the floor, chair and desk cleaned. The glass viewing screen and the equipment itself will be cleaned by the operators and is not included in this contract. These machines may be left on to process work automatically, in which case NO cleaning is to be carried out in the surrounding floor or furniture at the machine to avoid possible static discharge. Power plugs at these machines must NOT be unplugged regardless of whether the machine has been left "on" or "off". Adequate power outlets are located nearby for vacuum cleaners or other similar use.
National Master Specifications (NMS)
Selected Divisions
Division 00 – Procurement and Contracting Requirements
Division 1 – General Requirement
Division 2 – Existing Conditions
Division 3 – Concrete
Division 4 – Masonry
Division 5 – Metals
Division 6 – Wood and Plastics and Composites
Division 7 – Thermal and Moisture Protection
Division 8 – Openings
Division 9 - Finishes
Division 10 – Specialties
Division 11 – Equipment
Division 12 – Furnishings
Division 13 – Special Construction
Division 14 – Conveying Systems
Division 21, 22, 23, 25 – Mechanical
Division 26 – Electrical
Division 31 – Earthwork
Division 32 – Exterior Improvements
6.5 PURCHASING CONSTRUCTION
Construction projects can be very complicate and preparing specifications for large and complicated projects requires a team of people with great deal of knowledge and skill. Fortunately there are standardized, established methods of preparing these specifications. When an engineering and architecture firm plans a construction project, it must first complete the breakdown of the work that must be done and this is how the specifications are determined.
The specifications follow a standard numbering system. The National Master Specifications (NMS) is a large text that gives every procedure, product or method a number. The numbers are grouped
Divisions
Sections
o Procedure, product or method.
Some of the divisions are listed in the following chart.
Chapter Six – Phase 2: Planning 55
When the Owner or Consultants prepares the estimate for the work to be tendered the consistent numbering helps simplify the process. The General Contractors who bid are familiar with the system as are the sub-trades who will submit estimates to the General Contractor. Using the NMS system helps to clarify what items each trade will be responsible for and this helps to eliminate gaps or overlaps in the cost estimates and in the division of work between the sub-contractors and contractor.
6.6 DISCUSSION AND REFLECTIVE QUESTIONS
1. Review specifications for a current government tender call or call for proposal. List all the steps required to respond to the call.
2. What project do you have in mind to complete? Brainstorm. List all the necessary steps to complete the project. Arrange them in the order that they will need to be done.
6.7 REVIEW AND RESEARCH QUESTIONS
1. Refer to Crisp Publication, Project Management. Pages 25-27.
6.8 RESOURCES
An example of Specifications and Drawings from a Call for Proposals and/or Tender.
Chapter Six – Phase 2: Planning 56
7 Planning – Estimating
~As the owner of a completed construction project, you are concerned with the project from “cradle to grave.” The total "life cycle" costs and benefits are important to you right from the costs of initial planning through to its use and even to its final demolition. Construction costs represent only one portion of the overall life cycle costs. Christ Hendrickson (summary)
7.1 INTRODUCTION
The word, estimating, in general conversation means guessing the measure of something, but in the business of preparing tender documents and submitting bids estimating is just the opposite. It is a careful, precise method whereby an organization figures out what the budget will be for a project. It is also the method a general contractor uses to come up with its bid on a tender. The contractor figures out the price that will provide an opportunity to win the contract and make a profit.
Figure 7.1
7.2 GOALS AND OBJECTIVES
In this chapter you will learn
Why estimating is necessary
Estimating methods
7.3 WHAT IS ESTIMATING?
After a Community Government, or its consultant, has drafted project specifications, estimates of all costs associated with the project are prepared. If the total of estimated costs is over budget, then the specifications must be reviewed and either quality factors changed or more money found.
Estimating is the process of carefully figuring out project costs. The goal of estimating is to be as realistic as possible and include all the necessary costs.
It includes determining what is necessary to complete the work and costing this out. It can include:
Labour
Materials such as cement and wood
Supplies such as fuel
Rental equipment such as a back-hoe
Freight
The bid that a contracting company submits on a tender or call for proposal, is based on its estimate. Sub-contractors prepare prices in this way as well.
7.4 CONSIDERING CRADLE TO GRAVE COSTS
As you know, Community Government’s are responsible for the cost of the maintenance of their facilities. Thus the forecasted operation and maintenance costs are very important when considering how a facility is designed. You are in a good position to review the design of the project to ensure ongoing maintenance costs are considered when specifications are developed. Sometimes cost-saving measures in construction will lead to very expensive maintenance cost over the lifetime of the building.
The capital cost for a construction project includes the following expenses:
Land
Permitting
Planning and feasibility studies
Architectural and engineering design
Construction, including materials, equipment and labour
Field supervision of construction
Construction financing
Insurance and taxes during construction
Owner's general office overhead
Equipment and furnishings not included in construction
Inspection and testing
Disposal of scrap materials from construction project.
The operation and maintenance cost in subsequent years over the project life cycle includes the following expenses:
Community Works staff hours
Labour and material for maintenance and repairs
Periodic renovations
Insurance and taxes
Financing costs
Utilities
Owner's other expenses
Chapter Seven – Planning – Estimating 59
7.5 WHY ESTIMATE?
If you are completing a project in-house, you need to know how much it will cost. If it is a small project the money may come from within your operating budget. If it is larger, you may be required to identify the cost to include in the budget for the next year.
The same applies for projects that the Community Government put out to tender or Call for Proposal. As well, in the case when you contract a project out, you will want to know what price you can anticipate. A price that is very high or very low is cause for careful review to ensure that the bidder is capable of performing fully the contract requirements.
Although a tender is awarded to the lowest price, a Call for Proposal, is awarded based on how it measures up to the Scope of Work. When you receive a price that is much lower than the estimate, it must be reviewed carefully as it possible that the proponent has underestimated the work and will not complete it fully.
7.6 HOW IS ESTIMATING DONE?
When a project is completed in-house you may be responsible for estimating its cost. In other projects the consultants, engineers and architects, will complete the cost estimates.
In order to estimate construction costs you must review many areas to
Determine the user's requirements
Identify building code, fire code, electrical plumbing code and Workers Compensation Board (WCB) requirements/
Develop the concept which will meet the user's requirements, and all applicable Codes.
You must
Use standard construction cost estimating procedures, define cost per unit extending to basic cost to construct (take-off sheets).
Review the completeness of the specifications and include a suitable contingency amount (varies from 5% to 25%)
Establish other costs associated with the project (project management fee, consultants, decorators, and so on)
Provide estimate reflecting total project cost and items not included in the project
Chapter Seven – Planning – Estimating 60
7.7 NORTHERN ESTIMATING:
In the past, contractors and owners relied on historical information for construction material costs. Today, with variable prices, such as the increase in the price of steel, you need to check prices for every new project.
There are catalogues of data available, such as Sweets’ Catalogue and Dodge Manual for Building Construction, published by McGraw-Hill but they become outdated as soon as they are published. This information is also based on Southern Canadian or American costs, and is often not applicable to the north. Labour costs and freight and delivery are also typically higher in the north than in the south.
When you are estimating the price of materials you need to consider freight. When you order materials from the south, shipping costs must be added. Usually northern suppliers include shipping to the location of the supplier in the price. However, always confirm whether freight is included or not.
If you are estimating projects you should keep a file of costs and expenses on each project. Of course, the prices will change but your files can be a starting point. Keeping a record of supplier names and address will also be helpful. (If you have not kept these addresses you should be able to get them from your Finance Officer.)
7.8 PREPARING THE ESTIMATE
Whether you are the Contractor and you are preparing a tender or responding to a tender there is always a deadline that must be met. It’s important to
Treat developing the estimate as a project and make up a schedule for the completion of the tender estimate or submission
Complete the various parts of the estimate as soon as possible.
Keep careful records of your prices and calculations
Chapter Seven – Planning – Estimating 61Figure 7.15
7.9 THE GENERAL CONTRACTOR’S RESPONSE
As mentioned earlier construction tenders, follow the order of The National Master Specifications numbering system. The General Contractor will collect quotations and bids from materials, supplies and equipment suppliers and from sub-contractors.
The sub-trades prepare estimates which they give the General Contractor or in the case of a bid depository system the sub trades provide sealed bids to a central location advising what contractor(s) they are willing to work for and contractors pick up these bids.
As well, the General Contractor will complete its own estimates. Some of these estimates will be for comparison to what the sub contractors submit and others will be for parts of the contract for which it is completing the work.
For the contractor preparing a bid, it is important to allow time in the tender preparation schedule for final adjustments. The General Contractor must be very organized to estimate the project and
Reviews documents before the decision is made to bid. The first decision is whether to bid on the tender and if it is decided to go ahead more detailed review will be necessary. When preparing bids contractors use the Construction Documents - the working drawings and job specifications - to determine what must be estimated. Plans normally show the scope of work but the specifications tell how the work is to be done. For example, the plans may call for “paint”. The specifications may call for “one coat of primer, one coat of finish paint”.
Makes a site visit early in the process, preferably prior to estimating on excavation costs to get a picture of the project and what it will require.
Maintains a complete copy of the tender package adding in any addenda as soon as received
Complete and enter sub-bids and sub-trade sheets the day before the tender closes.
Chapter Seven – Planning – Estimating 62
Figure 7.16
7.10 ESTIMATING - SMALLER PROJECT
If you are planning a relatively straight-forward project like painting some houses you could use the following forms, either by hand or using spread-sheet software, to calculate your needs.
7.10.1 PRICING OF MATERIALS
Material Quantity Cost per Sub Total Discount Total
Chapter Seven – Planning – Estimating 63
7.10.2 COST OF LABOUR
NameRatePer
HourHours
Sub Total
UICEmployers
Share
CPPEmployers
Share
VacationPay
Other Total
Grand Total
Chapter Seven – Planning – Estimating 64
7.11 OVERHEAD, CONTINGENCIES AND PROFIT
7.11.1 OVERHEAD
Overhead is costs needed to support and administer the project but which are not used directly in its production. When you complete a project there are always expenses over and above those directly related to the project itself. For instance, when a Community Government is tendering for a new garage to be built, there will be additional work and material costs such as
Arranging advertising for the tender
Accounting for the funding as it is received and expended
Costs for newspaper advertisements, paper, courier and photocopying
Costs for legal or survey costs.
7.11.2 CONTINGENCIES
In most construction budgets, there is an allowance for contingencies or unexpected costs occurring during construction. This contingency amount may be included within each cost item or be included in a single category of construction contingency. The amount of contingency is based on historical experience and the expected difficulty of a particular construction project. Contingent amounts not spent for construction can be released near the end of construction.
7.11.3 PROFIT
In order for a corporation such as a construction company to survive, the company must make something more than covering its costs. Profit is the sum left after all expenses are paid. In order to keep in business, a construction firm must not only budget for a profit, but make one. It isn’t normal for Community Governments to budget to make a profit but if they are bidding on completion of tendered work they must ensure all their administrative work, overhead, additional staff and overtime is covered.
Chapter Seven – Planning – Estimating 65
7.12 DISCUSSION AND REFLECTIVE QUESTIONS
1. What are the consequences of too high or too low a bid?
2. When the Community Government has tendered for a Traditional, Fixed Price Contract to complete a facility in the community, what is the CG’s role, if any, in estimating costs?
3. What reasons might lead the General Contractor to making final adjustments to a tender bid?
7.13 REVIEW AND RESEARCH QUESTIONS
Exercises and Questions
1. Determine how much blue paint is required for two coats on the exterior of a 25 metre by 15 metre by 4 metre high shop that has a 3 metre by 3 metre overhead door? (ONE gallon COVERS 75 square meters).
2. Estimate the cost for materials required completing the painting project.
3. For this painting project, determine the cost of labour.
Chapter Seven – Planning – Estimating 66
7.14 RESOURCES
National Master Specifications (NMS):
www.raic.org/practice/ specifications /index_e.htm
Information on National Master Standards:
http://www.pwgsc.gc.ca/nms/content/user_guide_sect1-e.html#1.5
For a simple calculator to determine the amount of paint you require go to
http://www.behr.com and click “Expert Advice.”
Chapter Seven – Planning – Estimating 67
Figure 8.1
8 Planning - Scheduling
~There cannot be a crisis next week. My schedule is already full. Henry Kissinger.
8.1 INTRODUCTION
Would that project scheduling be as simple as assigning work over the project time span? Alas, there are other matters to schedule of equal importance. You must have equipment available and on site at the precise time is required and you must have construction materials on site when they are needed. Northern scheduling is complicated by transportation methods. Ice roads, ferries, barges are all seasonal and their access is not entirely predictable. Still, you can’t blame all scheduling problems on the weather.
Scheduling comes in many varieties, from the critical path method of scheduling which has been taught in universities for over two decades but is often thought of as impractical to "seat-of-the-pants" scheduling that can be good or can be very bad. Formal scheduling is needed whenever work tasks are complex and whenever workers with different trades or skills must be coordinated.
8.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to
explain what scheduling is
To prepare a bar chart
To prepare a basic critical path chart
Figure 8.2
8.3 WHAT IS SCHEDULING?
Scheduling is a very important process. Developing charts to complete schedules is quite simple. However the charts are only as useful and accurate as the thinking that went into them. So many elements need to be considered. For instance:
What is the lead time between order and receipt of different materials and supplies? How long does the supplier need to provide stock?
When will there be black-out periods when materials cannot be shipped?
What tasks must be done first?
How much time does it take to complete each task?
How many hours are workers available to work on the project?
What tasks can progress when one activity is delayed?
Although it is difficult and there will never be a perfect schedule, only the smallest projects will succeed without a well thought out plan.
Scheduling is the process of figuring out the time it will take to complete a project. In order to do so, you must break the work into steps and determine
1. How long each step will take.
2. The sequence of the steps
3. How external events will effect the timing
For example, if you needed to schedule the interior painting of a school, you would have to consider many things such as,
1. It may take two weeks to get the paint delivered
2. The surface preparation cannot start until the date school session is over.
3. The school must be completely painted one week before school opens in order that it will be dry and the site tidied up.
4. Teachers need to be advised and given time to remove posters, etc. from classroom walls before they leave in June.
8.4 BAR CHART
Sometimes called a Gantt chart or a time line chart, a bar chart graphically displays the relationship of the steps in a project. To create one, list the steps required to finished the project and estimate the time required for each step. Then list the steps down the left side of the chart with dates shown along either at the top or bottom. The bars indicate when a task is to start and when it is scheduled to be completed.
Bar charts are used primarily to inform the client, in an easy-to-read, but general way, about the plans for the project. A bar chart makes it easy to see, at a quick glance, what the project schedule is planned to be, in general terms. Other information can also be included in a bar chart. An example of the schedule of the construction of a school is provided in Appendix A.
The following example outlines the time required to frame in a building
Chapter Eight – Planning – Scheduling 70
Framing Project Exercise
Gantt Chart
Figure 8.3
Chapter Eight – Planning – Scheduling 71
8.5 PERT DIAGRAM / CRITICAL PATH ANALYSIS
PERT stands for Program Evaluation and Review Technique. It is a planning technique that is very popular in courses offered to engineers and other project managers. Although it isn’t actually used that much in the North, except for mega-projects, understanding PERT diagrams helps you to understand more about scheduling itself.
PERT is a type of network drawing and adds dimension to the planning process. To draw one, list the steps required to finish a project and estimate the time required to complete each step. Then draw a network of relationships among the steps. The number of the step is shown in a circle, and the time to complete the step is shown on the line leading to the next circle. Steps that must be completed in order are shown on one path to clarify proper sequencing. Steps that can be underway at the same time are shown on different paths.
A PERT Diagram not only shows the relationship among various steps in a project, but also serves as an easy way to calculate the critical path. The critical path is shown as a broken line in the example below. It is the longest time path through the network and identifies essential steps that must be completed on time in order to not delay completion of the total project.
The usefulness of the PERT Diagram can be increased by colouring each step as it is completed. Actual time may be written over the estimated time to maintain a running tally of actual versus planned time along the critical path.
Example: PERT Chart: Prepare Maintenance Manual
ActivityDuration in days
Immediate Predecessor
1 Write draft 15
2 Revise and refine draft 10 1
3 Edit 5 2
4 Draw Cover 5 none
5 Request peer review & 10 2
revise
6 Proofread 3 5
7 Make corrections 2 6
8 Draw figures 5 6
9 Reproduce 1.5 4,7,8
10 Deliver
PERT Chart
Figure 8.4
A critical path chart allows the superintendent and project manager to detail exactly what needs to be accomplished by what dates, in order for the project to be completed on schedule. It makes it easy to see which tasks are the most critical, the tasks that if not completed will hold up progress on the entire project. This chart shows everyone knows not only what is coming up, but which tasks need the most attention.
8.6 DISCUSSION AND REFLECTIVE QUESTIONS
1. With regard to the painting project in Section 8.3, what other factors should be considered in scheduling the work.
8.7 REVIEW AND RESEARCH QUESTIONS
Refer to Crisp Publication, Project Management. Pages 27-40.
Chapter Eight – Planning – Scheduling 73
1. pp. 25 – 40, completing all exercises including
Making a Work Breakdown Structure
Practice Estimating Time
Practice Drawing a Gantt Chart
Practice Drawing a PERT Diagram
8.8 RESOURCES
Crisp Publication, Project Management.
Chapter Eight – Planning – Scheduling 74
9 Simplify with Software
~A schedule defends from chaos and whim. It is a net for catching days. It is a scaffolding on which a worker can stand and labour with both hands at sections of time. Annie Dillard
9.1 INTRODUCTION
Using pencil or pen for scheduling and budgeting in project management is a lot of work. But relying on guesswork and hunches doesn’t work either.
Thanks to the personal computer (PC) you can use software to help you schedule and budget for your projects.
Figure 9.1
9.2 GOALS AND OBJECTIVES
After studying this Chapter you will be familiar with
What software can do to help your project
What software can’t do
Choosing software for project scheduling and estimating
9.3 COMPUTERS DON’T MAKE MISTAKES BUT THEY AREN’T SMART
There are many things the computer cannot do. Project management software cannot
Collect the information you need to manage the project. You will still have to develop specifications and collect prices and figure out time requirements.
Make decisions and it doesn’t take responsibility for your decisions. You can’t blame it.
Solve problems which call for judgement. It doesn’t know when the ice road goes out or that there will be a couple of weeks of bad weather.
Communicate with project team members, it doesn’t check whether they have completed the work on time, it doesn’t remind them of the importance of the deadline
Doesn’t replace staff.
9.4 SOFTWARE CAN …
Software can help you prepare charts, graphs, schedules and more. Some of these will be useful to present to your Council to describe your plans. Another really handy thing about computers is its ability to do a “What if?” model. When you change one cost element, you do not need to correct every total in a budget so you can compare costs of different design features or materials easier than you can with a calculator.
There are also software programs for construction estimating. If you use these, or even a regular Excel (or other) spreadsheet it is very helpful. When a change in a unit cost is made, the subtotals and totals are entered automatically.
The National Master Specifications (NMS) which were discussed earlier are used on a computer. Innovative Technology Inc. creates software to edit and format to create
professional project specifications. This is a product that engineers and architects who work for you will likely use.
9.5 CHOOSING PROJECT SCHEDULING SOFTWARE
There are project management programs for projects of all sizes and complexities that run on personal computers. Choose the project management software that best suits your needs. Bigger isn’t necessarily better. Keep in mind the purpose of the software is to simplify not to complicate the project.
There are four categories of software programs
Scheduling programs that offer Gantt charts
Single-projects programs that offer network diagrams, tracking and actual vs. planned reports
Corporate-level programs for multiple projects, with more than 200 tasks per project
Mega-Project Programs for use with in-house Mainframe programs and cost accounting.
When choosing software one of your first considerations should be what other people who you are working with are using. It is usually helpful to be able to work together on the same programs. Notwithstanding the above comment, here is some software you might products you might consider.
9.5.1FASTTRACK SCHEDULE
FastTrack Schedule is a scheduling program that is used to organize project details into clear, graphical timelines on Gantt charts. You can prepare a presentation-quality project schedule, a bar chart time line quite easily. You cannot make PERT charts in FastTrack Schedule.
The Schedule Appendix 9A, is done in FastTrack Schedule 7
9.5.2MICROSOFT PROJECT
Microsoft Project is a single-project program helps project managers coordinate tasks within a specific timeframe for a set amount of money. It includes Gantt charts, PERT charts and estimating tools.
Chapter Nine – Simplfy With Software 77
9.6 CHOOSING PROJECT ESTIMATING SOFTWARE
In order to complete estimates you can use a standard spread sheet program such as Microsoft Excel. Microsoft Excel (or Quattro Pro) will allow you to accurately add up estimates, make edits easily and accurately and print our professional quality sheets.
There are more specialized programs available for estimating.
9.7 DISCUSSION AND REFLECTIVE QUESTIONS
1. Review School Construction schedule – Appendix 9A.
2. What software, if any, would be useful to you for preventive maintenance projects? For renovations?
9.8 REVIEW AND RESEARCH QUESTIONS
1. If possible, test at software available on the World Wide Web
2. Refer to Crisp Publication, Project Management. Page 90.
9.9 RESOURCES
Test FastTrack by downloading software on a trial basis.
http://www.aecsoftware.com/downloads/documents/pdf/fasttrack_8_desktop_guide.pdf
Test Microsoft Project by downloading software on a trial basis
http://www.microsoft.com/office/project/prodinfo/trial.mspx
Hardwood board feet required calculator:
http://www.hardwoodstore.com/bd_ft.html
Board feet and optional cost calculator:
http://www.csgnetwork.com/boardftcalc.html
Gallons of paint required calculator:
http://www.behr.com (click “Expert Advice.”)
Chapter Nine – Simplfy With Software 78
Schedule Appendix 9A: FastTrack Schedule 7
Chapter Nine – Simplfy With Software 79
10 Phase 3 Monitoring & Controlling – In House
~ Never make the mistake of confusing activity with progress.
Figure 10.17
10.1 INTRODUCTION
Have you ever been on a committee where nothing seems to happen – people talk about projects but they never move forward with them? They may get stuck on the planning, if they get that far.
Phase 3 of Project Management is Implementation and this is where the rubber hits the road. If you are installing a new energy-efficient boiler system, building a 2 bay garage or preparing streets for a new neighbourhood at the end of this phase the project will be done. (The project is done but of course, as you work in maintenance, another way to look at it is your job has just begun.)
10.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to
Explain what
Monitoring the Project
Controlling the Project
Importance of Record Keeping
10.3 MONITORING THE PROJECT
For things to run smoothly in the project implementation need to monitor the project, to watch how the plan responds to reality. You need to compare the planned schedule of work to actual work completed,
You can track the project’s schedule against the original plan on a Milestone (Gantt) chart.
You can track the budget on a spreadsheet, keeping track of whether you are over or under on each item and in total.
Item Budget Actual Variance Balance
81
Culverts $3000 $3400 - $400 -$400
Fill $4000 $3500 + $500 +$100
Gravel $3000 $2800 - $200 +$300
You also need to compare the materials, equipment and workmanship to the quality stated in your specifications.
When goods are received, they should be immediately checked. If items are missing or damaged they could stall the progress of work. Check for the following:
Do descriptions and quantities match the invoice?
Is anything damaged and needing to be replaced?
Is documentation of equipment included?
10.4 CONTROL IS A GOOD THING
Frequently in general conversation, we use the word, controlling, to describe a person who is head strong and interfering and someone who is trying to get us to do something we don’t want to do. In the management sense, controlling is about ensuring assigned work is completed. With regard to project management, the people who are completing the work are told what their job is - they may have been involved in the decision - and it is up to the Project Manager to ensure that they stick to the plan. However, problems always come up and it’s also up to the Project Manager to sort these out. You steer the project by staying on top:
By gathering information, by monitoring progress and consistently updating the plan.
By communicating to workers and suppliers (both in writing and talking) to ensure they know what is required of them.
By listening to workers and suppliers and to find out how the project is going, about problems and potential problems
By being involved, by sharing the workload and seeing the problems yourself.
82
10.5 DISCUSSION AND REFLECTIVE QUESTIONS
1. What do you think is most helpful in keeping projects on schedule?
10.6 REVIEW AND RESEARCH QUESTIONS
The schedule for House A is below. The foundation was not completed until 09/05/03.
Figure 10.18
The same schedule applied to House B. The foundation of House B was completed on time and all sub trades started work on schedule. However, the Heating and AC took two weeks longer. Chart the schedule change and the project’s completion
Figure 10.19
1. Discuss project delays within a project and when delays in key activities will or will not affect the overall project schedule.
2. Compare House A to House B in terms of possible project delays.
3. Complete new GANT Charts for House A and B which includes delays in foundation and heating and air conditioning work.
11Monitoring the Traditional Contract
~Contract administration may be defined as the art of obtaining and managing
contracts to ensure acceptable results.
11.1 INTRODUCTION
The tender and award process has been completed. There will be a school built in your community this year. Consultants are in town and a construction firm is booking space at a local motel and looking for local workers.
The contract is signed between the Community Government and the contractor. This will be the first time your CG manages such a large project. The Senior Administrative Officer is representing the CG but she said she would keep you informed and might be needing information from you.
Figure 11.20
85
11.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to explain
The Contract Administration process
Importance of Record Keeping
11.3 THE PROCESS
11.3.1 MEETINGS
Probably the most important meeting in the project is the Start-up meeting. The meeting should be held as soon as practical after the contract has been signed and prior to any work being done. All key players from both the owner and the contractor should be there. You will be in attendance. In the meeting
The names of contacts from both the owner, the consultant representing the owner and the contractor, including names, titles, addresses, phone numbers, fax numbers and email. This list will be distributed
The lines of communication will be identified.
The people who have authority to approve payments, claims and change orders will be identified.
The schedule and working hours will be set
The schedule for meetings and inspections will be set.
Payment procedures and change order procedures will be set.
Safety issues
Insure requirements
Minutes of the start-up and following meetings are prepared by the consultant and distributed to those on the list.
11.3.2 PROGRESS PAYMENTS
On larger contracts, payments are often made on an interim basis, usually monthly and called Progress Payments. No payments are made before the contract is signed. Before payment is released the consultant will approve the completion of the work. In
some cases, equipment and materials, though not yet used, may be paid. In the case of a hamlet, the Senior Administrative Officer must ensure the required securities and insurance certificates are received. No progress payments are made without a certificate for Workers Compensation Board indicating insurance is in place for all workers employed by the contractor and the subcontractors. Typical payment terms are 30 days.
If your SAO and you review a progress payment request which is incorrect in any way, you should speak to the consultant and/or the contractor. Don’t hold up the whole payment for a small dollar error. When contractors don’t get paid they sometimes don’t pay their subcontractors or suppliers. The project may suffer.
11.3.3 CHANGE ORDERS
A change order is a written agreement between the Contractor and the CG to modify, add to, or otherwise alter the work from that originally specified in the contract documents. It is the only legal means available to change the contract conditions after the award of the contract. Change orders may be used to change the contract plans and/or specifications, to order extra work and to cover adjustment to contract unit prices. Change orders may or may not have an effect on the time and/or cost of the contract. When approved by both parties, the provisions of a contract change order become part of the contract.
As an example, assume the Community has a contract with a local contractor to build a school. Halfway through the construction the Community decides to add a parking lot. The Community’s consultant will normally prepare a design for the parking lot. They will ask the contractor what effect this added work will have on the project schedule. Assuming the Community and the Contractor reach an agreement on the added cost and time, a contract change order will be prepared for both parties to sign. This change order will increase the contract price and may extend the contract completion date.
Every change order is different but the following principles apply to all types of change orders:
Change orders should be consistent with the general intent of the original contract. In the example of the parking lot, it w within the general intent of building a school.
All change orders must be in writing and must be approved by the CG’s signing authority (the SAO); the Contractor should sign the change order to indicate his acceptance.
Change orders should be approved by the CG before any of the extra work is started.
Chapter Eleven – Monitoring the Traditional Contract 87
11.3.4 HOLDBACK FUNDS
In accordance with NWT Builder’s Lien Legislation, 10% of all construction contract payment is retained by the Owner. This holdback is released 45 days after substantial completion of the project unless someone files a lien, a claim for money owed to them. Although lien legislation does not apply to communities it is wise to withhold the 10% as a security to ensure work is completed.
11.3.5 SUBSTANTIAL COMPLETION / INTERIM CERTIFICATE OF COMPLETION
A construction project is considered to be “Substantially Complete” when in the opinion of the Consultant, the facility can be safely used for the purpose it was intended.
The Contractor, the Engineer and Community Works staff representative(s) attend this inspection.
In the Interim Certificate of Completion, the Engineer lists all work not completed as specified. These are the defects and faults. The Engineer also lists all uncompleted work or missing equipment. One item this must be provided, or will show in this list is the “Turn-over manuals”. “Turn-over manuals” include a complete set of manuals for all of the systems and equipment in the new building.
Payment on the interim Certificate is due 60 days after the completion date. The Contractor must submit an invoice and include a statutory declaration regarding payment of his lawful obligations. As noted before, the holdback is released.
11.3.6 FINAL CERTIFICATE OF COMPLETION
When the Contractor is satisfied that all work in the Interim Certificate of Completion is completed, after making his own inspection, he will request an inspection by the Owner.
11.3.7 WARRANTY PERIOD
Under the terms of the generally-used contract, the Contractor must make good any defect or fault that appears in his work with 12 months from the date of the Final Certificate of Completion. This warranty is in addition to any other warranties or guarantees imposed by law or contained in the contract documents. During the warranty period the Contractor is responsible for fixing problems; replacing faulty work or equipment and replacing parts for the warranty period.
About ten months into the warranty period the Consultant may do a warranty inspection. Community Works staff representative(s) attend this inspection.
Chapter Eleven – Monitoring the Traditional Contract 88
11.4 IMPORTANCE OF RECORD KEEPING
There are large quantities of records when a construction project is completed. The CG finance department will be responsible for many of these records
All financial records, including Progress payments, Final payment, release of holdback and supporting documentation.
Change orders, appropriately signed, and supporting documentation
Relevant insurance
The contract and supporting documentation.
Where other items are kept will depend on the size of the community. The following documents may not be filed in Community Works but the following documents are very important.
As-Built Drawings
Turn-over Manuals
As-built drawings, Turn-over Manuals and site drawings may be very useful over the life of the building for problems such as the following.
To figure out a problem such as slanting foundation or a cold draft.
To provide information if electrical rewiring is required.
To provide information if an architect is hired to complete an addition.
To repair equipment. To find the original supplier to order spare parts or repair equipment or follow up on a warranty.
Figure 11.21
Chapter Eleven – Monitoring the Traditional Contract 89
Records
Based on several construction projects, Maged Abdelsayed of Tardif, Murray & Assoc (Quebec, Canada) estimated the following average figures for a typical project of US$10 million:
Number of participants (companies): 420 (including all suppliers and sub-sub-contractors)
Number of participants (individuals): 850
Number of different types of documents generated: 50
Number of pages of documents: 56,000
Number of bankers boxes to hold project documents: 25
Number of 4 drawers filing cabinets: 6
Number of 20inch diameter, 20 year old, 50 feet high, trees used to generate this volume of paper: 6
Equivalent number of Mega Bytes of electronic data to hold this volume of paper (scanned): 3,000 MB
Equivalent number of compact discs (CDs): 6
11.5 DISCUSSION AND REFLECTIVE QUESTIONS
1. Where are the following records kept in your work-place?
As-built drawings
Site plans
Turn-over manuals
2. What methods have you found successful for record-keeping?
11.6 REVIEW AND RESEARCH QUESTIONS
1. What is the purpose of keeping As-built drawings?
2. When would you refer to Turnover-documents?
Chapter Eleven – Monitoring the Traditional Contract 90
12 How to Contribute to Successful Project Completion
~If you kick the project off, be sure to follow through with the next play. The Complete Idiot’s Guide to Project Management
12.1 INTRODUCTION
For success in a project, it’s important to form a team and work together. You need to create trust, listening to everyone, allowing for people to disagree and recognizing what key skills and knowledge each person has. Sometimes you need to encourage bizarre ideas – joking and laughter – as bizarre ideas are often the seed of the answer to a problem.
12.2 GOALS AND OBJECTIVES
Be able to explain
Importance of project team communications
Information every team member needs for a project
Methods of sorting out conflicts with positive results
12.3 THE PROJECT TEAM
When you think of it, every member of a project team contributes to its management. Each member contributes by completing the work they are assigned and may also direct the work of others. They can also contribute by offering their observations and ideas to the Project Manager. However people do not share ideas or tell their superior problems if they know they will be rebuked or “shot down.” The project manager must listen carefully to problems, observations and ideas as the solution to a problem may be given to him or information from multiple sources will provide an opportunity to correct a problem. Communication is very important.
In order for team members to be able to contribute their best to a project they need to know the following information:
Summary of project objectives and milestones
An organization chart of the project
A description of key personnel on the project and their roles
Their personal task list
Enough authority to do the job and an understanding the limits of the authority
The schedule
Due dates for reports, meeting and other activities
Samples of required reports, forms and other documents
Procedures for reporting problems and suggesting changes to the project
Contact information for key project personnel and vendors.
12.4 CONFLICT RESOLUTION
We have talked about the predictability of problems and the same is true with conflict. One of the many hats that a project manager wears is that of conflict manager. Conflict can be a good thing, for instance in a situation when the energy of a heated discussion results in an innovative solution.
You need judgement to determine where to spend your energy. Almost all problems can be solved and many must be sorted out. If materials do not arrive on time and work is stopped, you need to act, to press for immediate delivery of the goods, or purchase stock locally or send workers to another task.
Some petty issues are sometimes not worth trying to resolve and they may even just go away. If workers are squabbling on Friday, they may settle their differences on Monday. Sometimes you can invent a way around the problem, for instance, by shifting persons from one work project to another.
A project conflict occurs when people or priorities or problems interfere with the satisfactory completion of a project. When you try to manage a conflict, make sure you know exactly what the issues are. You will need to answer the following questions
1. Do I have information about the source of the conflict?
2. Can I resolve it?
3. Can the conflict be sorted out by a meeting of two or more team members?
4. Will the conflict go away without intervention?
There are four kinds of people-conflict:
1. A person is disappointed in their own performance.
2. One or more persons can’t get along with each other.
3. People working on the same part of a project are bickering.
4. Different groups are feuding with each other.
Chapter Twelve – How to Contribute to Successful Project Completion 93
Some issues that can cause these problems are:
Problem Solution
People have different goals for the same project.
Encourage discussion including discussion on disagreements in Phase 1 of the project. Make agreed-upon project goals clear
The tasks people have been given are unclear
Provide detailed instructions
Role uncertainty – Am I supposed to manage this task?
Make sure everyone knows the management structure and their tasks.
Schedules: never enough timeRefer to the master plan and negotiate changes, if necessary
Personality clashes Keep communication open, develop trust: mediate (play referee) if necessary
As manager, you have some choices when it’s necessary to resolve a problem
1. You can withdraw and retreat. This is a good option if the conflict is silly and not worth spending time on.
2. You can smooth out the problem by focussing on areas of agreement and avoiding areas of disagreement. This is all right when the conflict is unimportant but chances are the conflict will bubble up again.
3. When you compromise, you negotiate a solution. Wait till both parties cool down and try to come up with a win-win solution.
4. When you use force, you command a person or persons. It’s not recommended as it doesn’t foster a team approach which is so important for successful projects.
5. You can facilitate, confronting the people involved, laying out the problem and getting them to face it and work through the issue(s)
Chapter Twelve – How to Contribute to Successful Project Completion 94
12.5 DISCUSSION AND REFLECTIVE QUESTIONS
1. Discuss examples of
A person is disappointed in their own performance.
One or more persons can’t get along with each other.
People working on the same part of a project are bickering.
Different groups are feuding with each other.
2. What methods could be used to get around an example of each of these problems?
3. What method could be used to resolve an example of each of these problems?
Chapter Twelve – How to Contribute to Successful Project Completion 95
13 Phase 4: Wrapping up the project
~Those who cannot remember the past are condemned to repeat it. Santayana
Figure 13.22
97
13.1 INTRODUCTION
Each project is a learning experience. When you finish a project you need to take an honest look at what you did well and what you could have done better. You can see what you still need to learn.
You have now finished a complete course on project and contract management. You have learned about defining projects, how to tender or call for proposals on a project and you have learned about planning and monitoring an in-house or contract project.. Good luck in your role in project management in the future!
13.2 GOALS AND OBJECTIVES
After studying this Chapter you will be able to
Explain why
Why a final evaluation is a good idea
Prepare a report on s project.
13.3 WHY EVALUATE THE PROJECT?
The purpose of evaluating is to review the process you have used over the life of the project. Probably the most important aspect of the evaluation is to remind you and your team of the history, the experience of the project. You need to know what you did right and what you did wrong so that you will repeat the former and correct the latter. However every project is different and the important learning is not what you did wrong or right but learning to anticipate problems in advance the next time you complete a project
13.4 IDENTIFY WHAT YOU DID RIGHT AND WHAT COULD HAVE BEEN DONE BETTER
Talk about the project with your team. Listen to everyone’s thoughts. At that time, you may learn some of the answers to the following questions.
What went right?
98
In the planning stage?
In the project completion stage?
In our communications?
In sorting out problems?
What went wrong? Or you can ask, what could we do better?
In the planning stage?
In the project completion stage?
In our communications?
In sorting out problems?
Add your own thoughts and opinions. Avoid the tendency to blame exterior agencies or “Acts of God”. Errors are a fact of project life and thus look at your response to the problem and describe and assess this response.
13.5 THE FINAL REPORT
You may be required to present or prepare, or help with a final report to your Council either orally or in writing. Consider including the following topics, some of which may come from your Community finance division.
An overview of the original project plan and the revisions that were made.
A summary of major accomplishments
A comparison of achievements and original goals (quality, budget and schedule)
Final financial accounting and explanation of variance
Evaluation of administrative and management performance. (Information on individuals should be confidential.)
Issues or task that must still be sorted out.
Recommendations for future projects of this type.
Special acknowledgments to team members.
99
13.6 DISCUSSION AND REFLECTIVE QUESTIONS
What do you think is most helpful in keeping projects on schedule?
What have you learned in this course that can help you with your next project?
Refer to Crisp Publication, Project Management. Pages 79-83.
13.7 REVIEW AND RESEARCH QUESTIONS
See Crisp Publication. Project Management. Page 84.
Websites & Resources
National Master Specifications:
www.raic.org/practice/ specifications /index_e.htm
Project Management Glossary:
http://www.welcom.com/content.cfm?page=136
http://maxwideman.com/pmglossary/
Project Management for Construction: Fundamental Concepts for Owners, Engineers, Architects and Builders by Chris Hendrickson, Department of Civil and Environmental Engineering, Carnegie Mellon University, Pittsburgh, PA l52l3 Copyright C. Hendrickson 1998
Second Edition prepared for World Wide Web publication in 2000.
Version 2.1 prepared Summer, 2003:
http://www.ce.cmu.edu/pmbook
GNWT Public Works and Services Web site – Publications – Procurement Guidelines – scroll down:
http://www.pws.gov.nt.ca/publications/index.htm
CIV320 H1 S Management of Construction. Module 2: Contracting. Tamer E. El-Diraby, PhD. University of Toronto.
Community Contracting Process. Capital Authority Agreements. Municipal & Community Affairs. Camillus Engineering Consultants Ltd.
Sunny and Kim Baker. The Compete Idiot’s Guide to Project Management. Alpha Books. 1998. (“Whether you’re on your own or managing a mega project involving thousands of people, this book offers practical project techniques that are easy to understand and fun to read.”)
Chapter Thirteen – Phase 4: Wrapping up the Project 101
Appendix A: Project Management. A Crisp Fifty- Minute Book