School Maintenance Grant Program (SMGP) Instructions for the Final Expenditure Report Effective 07/07/20 Illinois State Board of Education School Business Services Darren Reisberg Chair of the Board Dr. Carmen I. Ayala State Superintendent of Education

Transcript of School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within...

Page 1: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

School Maintenance Grant Program (SMGP)

Instructions for the Final Expenditure Report

Effective 07/07/20

Illinois State Board of Education

School Business Services

Darren Reisberg

Chair of the Board

Dr. Carmen I. Ayala State Superintendent of Education

Page 2: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

1 | School Maintenance Grant Program Instructions

Table of Contents

I. Final Expenditure Report Instructions Page 2

A. School District Role – Creating and Submitting the Final Expenditure Report Page 2

B. ROE Role – Approving and Submitting the Final Expenditure Report Page 8

Page 3: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

2 | School Maintenance Grant Program Instructions

I. Final Expenditure Report Instructions

A. School District Role – Creating and Submitting the Expenditure Report

1. Within 20 days of final project completion, the Final Expenditure Report should be completed and submitted on IWAS. NOTE: Grant funds are subject to the Illinois Grant Funds Recovery Act [30 ILCS 705]. Any funds not expended or legally obligated within two years after disbursement by the State shall be returned to the State Board of Education within 45 days. For grant funds that are legally obligated at the two year mark, a 90 day liquidation period will be given to fully liquidate the funds and get to final project closeout. Any grant funds not obligated within two years and expended within 90 days after the two years shall be returned to the State Board of Education within 45 days.

2. Log in to IWAS & go to System Listing. Under Surveys click School Maintenance Project Grants.

3. Select Final Expenditure Reports from the screen below.

Click here

Click here

Page 4: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

3 | School Maintenance Grant Program Instructions

4. Click the Final Expenditure Report under Create Documents on the Home screen.

5. Find and select the Grant Application for which you are creating an expenditure report.

6. Enter the Current Fiscal Year, along with a description of all work items that were completed with the grant. Click the Save button when complete.

To create final expenditure report, click here

Find and select the grant application for which you are creating an expenditure report

Enter the current Fiscal Year to document the year the final expenditure report was created

Provide a brief

description of all work items that were completed with the grant.

Save when done

Page 5: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

4 | School Maintenance Grant Program Instructions

NOTE: If the final expenditure report has already been started for that application, a yellow highlighted message will appear along with a link to View Existing Expenditure Report.

7. Review the Expenditure Report Header Information on the Expenditure Report Header Page for accuracy, and if needed, make corrections using Edit Expenditure Report Header Information.

8. Under Expenditure Report Data click Final Work Items.

Please note

Use this for corrections

Click here

Page 6: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

5 | School Maintenance Grant Program Instructions

9. Click Open for each work item.

10. List the Total Actual Work Cost, Actual Start Date and the Actual Completion Date. Click

the Save Item button when all information has been entered correctly. Complete this process for each work item.

11. Return to the Expenditure Report Header Page by clicking Grant Expenditure Report.

Click to open each work item and complete required information

Complete all fields to show actual dates and actual cost of project

Save when done

Click here

Page 7: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

6 | School Maintenance Grant Program Instructions

12. Completing the “GATA Final Performance Report.” i. Under “Application Printable Documents,”

1. Open “Instructions for GATA Final Performance Report” 2. Open and Print “GATA Final Performance Report” 3. Use “GATA Final Performance Report Instructions” to complete report Guidance for completing the GATA Performance Report (numbers correlate with report): 6. Project / Grant Period - The “End Date” is two years from the time the State disperses the grant funds 11. Deliverable -Enter each project (work item) 12. Due Date -2 years from the time the State dispersed the grant funds 14. Deliverable explanation -state if it is on schedule to be completed 15. Performance Measure -state “100% of project will be completed during 2 year time frame and when the project started/will start and projected end date” 16. Performance Standard/Frequency -state “project progress will be evaluated quarterly” 17. Results/Accomplishments in Reporting Period -state the “percent” that has been completed during reporting period 18. Required “R” or Inform Only “IO” -state “R” 4. Scan report into computer

ii. Click “Attach Files” under the “Application Required Attachments” 1. Click “choose file.” 2. Locate file on computer. 3. Click “submit.”

Page 8: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

7 | School Maintenance Grant Program Instructions

13. Click District Approval to submit. Once approved, a green box will appear at the top of the screen indicating that the expenditure report has been submitted to the ROE office for approval.

Click here

Page 9: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

8 | School Maintenance Grant Program Instructions

B. ROE’S ROLE – Approving and submitting the Final Expenditure Report

1. Login to IWAS & click System Listing. Under Surveys click School Maintenance Project Grants.

2. Select Grant Expenditures from the screen below.

Click here

Click here

Page 10: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

9 | School Maintenance Grant Program Instructions

3. Find and Open Expenditure Report(s) under District Submitted Grant Expenditure Reports.

4. Click Final Work Items under Expenditure Report Data.

5. Review the Schedule of Final Work Items for accuracy. Click Open on each project to review.

Click here

Click here

Open each item to verify accuracy

Review grant totals

Page 11: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

10 | School Maintenance Grant Program Instructions

6. Review each project and verify that Total Actual Project Costs, Actual Start Date and Actual Completion Dates and are listed correctly for each project.

7. Once all work items have been verified, return to the Expenditure Report Header Page by clicking Grant Expenditure Report.

8. Click the ROE Approval or Rejection button.

Click here

Review data entered by district

Click here

Page 12: School Maintenance Grant Program (SMGP) Instructions for the Final … · 2020-07-07 · 1. Within 20 days of final project completion, the Final Expenditure Report should be completed

11 | School Maintenance Grant Program Instructions

9. If approved, mark the box and click the blue Submit button for the expenditure report to be forwarded for ISBE approval.

10. If disapproved, mark the “Disapproved” box, provide comments and click the blue Submit button for the expenditure report to be returned to the district for corrections or modifications.

If rejecting, must indicate reason for disapproval

Shows that Grant expenditure report has successfully been submitted to ISBE

Then here

If approving, click here

If rejecting, click here

Then here

Shows that grant expenditure report was rejected and sent back to district