Education Committee 30 September 2008 4 Report SCHOOL ESTATE MANAGEMENT PLAN - OPTIONS APPRAISAL - BEATTOCK, ST MUNGO AND MOUSWALD PRIMARY SCHOOLS 1. Reason for Report To advise Members of the results of recent condition surveys carried out on Beattock, St Mungo and Mouswald Primary Schools and outline the range of options available, should Members wish to progress with the upgrading of these schools. 2. Report Summary 2.1 This report provides Members with information from Condition Surveys carried out as a result of these three schools being identified as strategic priorities when the KPls within the updated SEMP were considered in March 2008. 2.2 with the upgrading these schools. 3. Glossary of Terms ASfL Additional Support for Learning ECS Education and Community Services EIP Education Improvement Plan FM Facilities Management KPI It also sets out options to be considered should Members wish to progress Key Performance Indicators- these are collated in each SEMP in respect of each school and measure the following- 0 Condition 0 Sufficiency 0 Suitability 0 Accessibility FM Costs 0 Environmental Impact School Estate Management Plan Design Criteria required for all major school estate projects Site; Capacity; 0 Pre-school provision; ASL provision; 0 Meal provision; 0 Accommodation schedules; 0 0 Estate and Deliverability factors. SE\ P Strategic Hooks Community facilities required - informed by the Communities Estate Management Plan;

Transcript of SCHOOL ESTATE MANAGEMENT PLAN OPTIONS …egenda.dumgal.gov.uk/aksdumgal/images/att15414.pdfSCHOOL...

Education Committee 30 September 2008 4 Report

SCHOOL ESTATE MANAGEMENT PLAN - OPTIONS APPRAISAL - BEATTOCK, ST MUNGO AND MOUSWALD PRIMARY SCHOOLS

1. Reason for Report To advise Members of the results of recent condition surveys carried out on Beattock, St Mungo and Mouswald Primary Schools and outline the range of options available, should Members wish to progress with the upgrading of these schools.

2. Report Summary 2.1 This report provides Members with information from Condition Surveys carried out as a result of these three schools being identified as strategic priorities when the KPls within the updated SEMP were considered in March 2008.

2.2 with the upgrading these schools.

3. Glossary of Terms ASfL Additional Support for Learning ECS Education and Community Services EIP Education Improvement Plan FM Facilities Management KPI

It also sets out options to be considered should Members wish to progress

Key Performance Indicators- these are collated in each SEMP in respect of each school and measure the following-

0 Condition 0 Sufficiency 0 Suitability 0 Accessibility

FM Costs 0 Environmental Impact

School Estate Management Plan Design Criteria required for all major school estate projects

Site; Capacity;

0 Pre-school provision; ASL provision;

0 Meal provision; 0 Accommodation schedules; 0

0 Estate and Deliverability factors.

SE\ P Strategic Hooks

Community facilities required - informed by the Communities Estate Management Plan;

Report Education Committee 30 September 2008

4. Recommendations Members are asked to:

4.1 Primary Schools as strategic investment priorities in view of the revised Condition S u rve ys:

consider if they wish to review the decision to treat St Mungo and Mouswald

4.2 will ensure that future strategic investment decisions are based on up to date Condition information:

note that a programme of Condition Surveys has now been instructed, which

4.3 On the basis that they wish to proceed, agree:-

that Option 1 - Do Nothing, Option 2 - Refurbish as existing and Option 5 - Closure, should not be considered further;

not to provide specific community facilities within each school, as outlined at para 11.3.2, but note that the schools will be available for use by the community under the School Lets policy and the tutorial/library/resource room will be a bookable resource for community planning partners;

that the new schools should not include an extended hall and a MUGA, as outlined at para 11.4.3;

the proposed accommodation schedules for the three schools (Appendix 1 and 2);

that in respect of Mouswald Primary School, Option 4 - New Build on Extended Site is the preferred option, at an estimated cost o f f 1.460M, excluding land purchase and potential capital receipt, on the assumption that the required land can be purchased;

that in respect of St Mungo Primary School, Option 4 - New Build on Extended Site, is the preferred option, at an estimated cost of f 1.439M, excluding land purchase and potential capital receipt, on the assumption that the required land can be purchased;

that in respect of Beattock Primary School, Option 4 - New Build on Existing Site is the preferred option, at an estimated cost of f2.052M;

that a bid for additional funding, amounting to f 3.451 M, is submitted to the Corporate Policy Committee:

that the specification for each school should include a requirement for a BREAM rating ‘very good’, in line with the 2A schools.

Report Education Committee 30 September 2008 4

5. Plan Links and Contribution 5.1 The proposals in this report are consistent with the Corporate Plan values of:

Customer First; Continuous Improvement; Equality and Diversity; Local decision making and service delivery.

5.2 The proposals in the report support the following Corporate Plan objectives: Smarfer - Provide all children and young people with access to positive

Safer and Stronger - provide facilities fit for purpose and accessible for all Wealthier and Fairer - improve physical and technological infrastructure;

0 Greener - work towards a cleaner, greener environment.

learning environments;

6. ResourcesNalue for Money Assessment 6.1 capital resources to improve the school estate.

The proposals within this report are designed to make best use of available

6.2 three new builds, excluding site purchases and potential capital receipts. The total average projected roll for these 3 schools over the next 6 years, as advised to Members in August 2008, is 108. This equates to f46k per pupil. As a comparison, the current estimated Total Outturn Cost of the three 2A schools is f 16, l l Ok and, based on the total current rolls, this equates to f28k per pupil. However, it should be noted that the price base for the three schools is 2009, compared with a 2007 price base for the 2A schools.

The recommendations in this report would cost approximately f4,951 k for

6.3 environmental performance of schools from design through to management. This method entails the environmental assessment of buildings against performance criteria set by BRE, awarding ‘credits’ based on building’s individual performance. The recommendation in this report is that the three new schools should have a BREEAM rating of “Very Good”, which is performance that reflects industry best practice. This would add to the initial capital cost but would result in not only more environmentally friendly buildings, with a reduced carbon footprint, but also reduced running costs, over the whole life of the asset.

BREEAM for Schools is a comprehensive tool for analysing and improving the

7. Risk Assessment 7.1 needs, in terms of fitness for purpose, delivery on time or on budget. To mitigate against this risk, all major school estate projects are designed having regard to ‘strategic hooks’ which are kept under review during the design stage and, in addition, flexibility is promoted within each design.

There is a risk in any project that the final product may not meet the service

7.2 the School Estate -

The May 2007 INEA report identified the following Action Point in relation to

Finalise and implement plans for improving the school estate, including addressing the challenges of demographic change and falling rolls.

3

Report Education Committee 30 September 2008

The Inspectors will take a view as to progress made against this Action Point during the follow up inspection.

7.3 detailed project plans.

The current Council restructuring process may disrupt the development of

7.4 be available within a reasonable timescale. In August, Members agreed to carry forward f 1.5M from the 2008/09 capital funds available and earmark this as a contribution to the costs of these three schools. If Members agree the recommendations in this report, a bid for the balance of funding, amounting to f 3,451 K, will require to be submitted to the Corporate Policy Committee. This amount does not include site acquisition costs or potential capital receipts.

The funding required to take forward the agreed option in each case may not

7.5 are dependant on the acquisition of additional land adjacent to the existing schools. There is a risk that these acquisitions are not achievable.

The recommendations in respect of St Mungo and Mouswald Primary Schools

8. Authorities and Legal Implications The Standards in Scotland’s Schools Act 2000 imposes a statutory duty on all Education authorities to seek continuous improvement in all aspects of education provision. This includes the school estate.

9. Consultations 9.1 the report -

The following have been consulted and are in agreement with the contents of

Executive Director - Community and Support Services Corporate Director - Combined Services Corporate Director - Planning and Environment Services Group Manager - Community Services Group Manager - Policy and Improvement Acting Director of Finance Operations Manager - Leisure and Sport Interim Operations Manager - Property Services Project Manager - Smarter Schools Group Manager Human Resources Members of the School Services Senior Management Team

9.2 have raised a concern regarding the staffing implications of the policy which has been adopted in relation to the PPP and 2A schools and recent capital refurbishments. This has resulted in the conversion of production kitchens to serveries, in appropriate situations. Unions have expressed concern at the potential job and grade implications of “de-skilling” the workforce.

The Group Manager Human Resources has advised that the Trade Unions

10. Background 10.1 In March 2008, Members received a report which summarised the KPI data for each school. This advised that the only three schools with a Condition Rating ‘D’ were Beattock, St Mungo and Mouswald Primary Schools. As a result, it was agreed that these schools should be strategic investment priorities.

Report Education Committee 30 September 2008 4

School Mouswald St Mungo Beattock

10.2 In June, 2008, Members agreed a provisional timetable which proposed that, funding permitting, projects to rebuild or refurbish these 3 schools could be completed in time for the start of the 201 1/12 academic year.

March 2008 KPI June 2008 Condition Survey D C D C D D

10.3 In August 2008, Members agreed that the Option Appraisals for Mouswald, Beattock and St Mungo Primary Schools would be based on the following school sizes:

Beattock Primary School - 3 class bases St Mungo Primary School - 2 class bases Mouswald Primary School - 2 class bases

10.4 Members further agreed to receive a report in September outlining the options available.

11. 1 1.1 Condition Surveys 11 .I .I As a result of these three schools being identified as strategic investment priorities, based on them having a Condition rating ‘D’ in the March 2008 report, a further condition survey was instructed to update the information available. This confirmed the position in relation to Beattock Primary School but amended the condition rating for the other two schools to C. It should be noted that the Condition Survey specification does not allow for certain health and safety issues to be taken into account, as they did not relate wholly to condition.

Key Issues - Option Appraisal

11 .I .2 The March report highlighted to Members that the condition information provided was based on surveys undertaken in 2002, as part of the preparation for PPP. It further advised that, ideally, such surveys should be repeated every 5 years but this had not been possible due to a lack of available funding, In response to this concern, Members have agreed that service reserves should be earmarked to carry out a programme of condition surveys.

I 1 .I .3 Members should consider if the amended condition ratings for St Mungo and Mouswald should result in their priority being revised. The Option Appraisal exercise that follows considers each school in turn. The additional information in respect of these two schools may assist in the consideration of their continued priority. This does highlight that both these school buildings fall considerably short of the SEMP Educational Objectives, with concerns in a number of other KPI areas, and that there is still a proven need to invest in these schools

11.2 The option appraisal process followed has regard to the Scottish Executive’s Option Appraisal - Building Our Future: Scotland’s School Estate document.

11.3 Service Objectives The first consideration of the appraisal process is to define the service objectives. These are split into educational and community objectives.

5

Report Education Committee 30 September 2008

Main General Purpose hall, suitable for a range of community recreational activities (minimum 1 badminton court size)

11.3.1 Educational Obiectives The vision and purpose of Education in Dumfries and Galloway is to raise levels of attainment, achievement and participation through encouraging innovation and creativity, collaboration and a culture of sharing and learning. As many of the schools in this authority are generally smaller than average, we should celebrate the benefits and encourage innovation to overcome the curricular challenges.

1 75m2

The objectives are to: > Provide sufficient new or modernised accommodation suitable for the

effective delivery of A Curriculum for Excellence.

Option 1 - Do Nothing

> Provide a building that is flexible and capable of adaptation to suit either physical or curricular changes.

The SEMP aims to improve all schools to a minimum of Category B on the Condition KPI. This option would mean that the buildings would continue to fall considerable short, in relation to the educational objectives.

> In respect of the SPI for ‘Condition’, remove all Category D rated properties from the School Estate and achieve Category B, as a minimum.

11.3.2 Communitv Obiectives

1 1.3.2.1 The approved recommendations from the Community Facilities Challenge state that, where the population is below 500, the provision of the following facilities should be available within a 10 mile radius.

Base Standard

These facilities are available for each of the communities concerned as follows:

0 Mouswald (with a population of 199) - Dumfries St Mungo (Kettleholm with a population of 178) - Lockerbie Beattock (with a population of 355) - Moffat

11.3.2.2 In light of the above, it is recommended that the requirement for specific community facilities should be discounted from the options appraisal process. Nonetheless, the schools will be available for use by the community under the School Lets policy. In addition, the tutorial/library/resource room could also be a bookable resource for community partners, such as the Health Board and Social Work Services.

11.4 Project Options 11.4.1 Five project options are outlined in the table below:

Report

Mouswald Primary School

School St Mungo Primary

4 Education Committee 30 September 2008

Current Proposed Proposed Accommodation Accommodation Increase

(Excl lar er hall) M2 M F1 M2 191 456 265

265 456 191

Option 2 - Refurbish as Existing

Option 3 - Refurbish and Extend - Base Line Case.

Option 4 - New Build on Same/Extended/New Site Option 5 - Closure and transfer to another school.

However, this option may be considered appropriate in the light of the revised Condition Survey information for St Mungo and Mouswald

This is the ‘do minimum option’ involving upgrading of the existing accommodation to address the maintenance and repair needs, as detailed in the June 2008 Condition Surveys only, with no consideration of accommodation and adjacency requirements and the SEMP Educational Objectives. This option is not explored further since the resultant building would not meet the overall SE M P educational objectives Refurbish the existing school and extend to meet the SEMP Educational Objectives. It provides for some improvements but, due to the constraints of the existing buildings, compromises are inevitable. Complete new build, meeting the SEMP Educational Objectives standard and addressing known site concerns. Closure of the existing school and relocation to a nearby school. This may require some alterations and extension to the receiving school. The ECS Committee agreed in March 2008 that no further Small School Reviews be undertaken until the proposed legislation in relation to rural schools is in place. The Scottish Government is currently carrying out a consultation on this issue. In the light of the above, this option is not explored further.

The above table establishes that the project options that are considered further are limited to

Option 1 - Do Nothing for St Mungo and Mouswald, due the new Condition Survey information Option 3 - Refurbish and Extend Option 4 - New Build on Same/Extended/New Site

11.4.2 An initial meeting has been held with the Head Teachers of all three schools to discuss the requirements for a new school, which would meet the SEMP Educational Objectives. Appendices 1 and 2 provides a comparison between the current and proposed accommodation, as summarised below -

Report Education Committee 30 September 2008

Beattock Primary School

532 698 166

11.4.3 The above proposed areas do not include provision for a larger hall, as recommended by Sports Scotland for schools, and the provision of a MUGA at each location. The larger hall would provide sufficient space for two courts and a MUGA would ensure that pupils can enjoy year round sports facilities outdoors. The additional estimated cost of adding the required 75m2 to the hall is f 112K and a MUGA would be f 180k per school. In view of the proximity of each of these schools to alternative provision, both larger halls and MUGA’s, this report recommends that the specifications should not include these additional aspects.

11.5 Mouswald Primary School 11 5.1 Current State 11 5.1 .I In March 2008 Members were advised that the KPI data for Mouswald Primary School was as follows -

0 Suitability - C 0

0 Sufficiency - C 0 Accessibility - C 0 Environmental Impact - D

Condition - D - now updated to C

FMcosts-C

Overall - D - Remains overall ‘D’ due to ‘Environmental Impact’

11 5.1.2 Mouswald Primary School was built in 1866 on a site area of 0.4 Hectares. Subsequent alterations and extensions to the building were undertaken during the 1970’s and 1980’s. Externally the school site consists of tarmacadam surfaces to the playground and car parking area and a grassed sports field to the rear. The existing access route consists of a narrow right of way across neighbouring land.

11 5.1.3 Although the current site is sufficient, it is not level and therefore presents a number of practical issues. The proposed size of the new school is 265m2 larger than the existing building - i.e. 191 m2 to 456m2

11 5.2 Option 1 - Do Nothing This option should be considered in this case in view of the revised grading given in the recent Condition Survey.

11 5.3 Option 3 - Refurbish and Extend 0 This would involve a complete refurbishment of the existing school and an

extension to meet the SEMP Educational Objectives, as detailed in the proposed accommodation schedules (Appendix 1).

0 It should be noted that this is a compromise solution as indicated in para 11.4.1. The construction method of the existing building is solid sandstone with lathe and plaster and this, together with the current layout and the age of the building, means that it does not lend itself to being easily extended. The estimated cost of this option is f 1,487K as detailed in Appendix 3

Report

Advantages . Allows the development of a

4 Education Committee 30 September 2008

Disadvantages High overall capital costs

Advantages . This would be the lowest capital cost . Less additional land would be required . Revenue savings from the reduction of travel to other facilities to provide some activities such as Physical Education.

Disadvantages . Would require the existing staff and pupils to be decanted for a full academic year. (Possible decant to current Lockerbie Primary School, along with St Mungo) . Current site concerns i.e. restricted and not level, would not be addressed . Additional land will still be required to provide suitable hard and soft landscaping . Possible solutions limited due to type of construction of the existing building . Difficult to address accessibility issues to all areas of the building and site due to the topography of the site The major issues of traffic management and safe site access remain and compromise safety. . Educational objectives still compromised in older part of school, in particular . Whole life costs more expensive than new build option . Very Good BREAM rating would not be achieved due to remaining poor insulation in the external walls.

11 5 .4 Option 4 - New build on extended site This would involve building a new school on the same or an extended site and the potential for disposal or demolition of the existing school. No alternative sites have been identified and planning restrictions prohibit ribbon development. The possibility of relocating the school to a new site within Mouswald village or another greenfield site on the main road were considered as part of “informal discussions” with the Planning Officer for this area but were considered to be difficult to justify. Works within the same or an extended site were considered acceptable in timescale, cost and planning terms. The local land owner has agreed that initial site investigations can be carried out with a view to potential purchase. The expectation is that these investigations will confirm that this area is suitable for building. The total outturn cost (excluding land acquisition and possible capital receipt) for a new build at this school is f 1,460k.

Report Education Committee 30 September 2008

option . Addresses known site issues:

and outwith the site

access

. Traffic management within

. Pedestrian and vehicular

. Adequate car parking . Improved drainage . Increased useable playground and playing field area . Addresses access, health & safety

and security issues . Revenue savings from the reduction of travel to other facilities to provide some activities such as Physical Education

sale of existing school. . Potential capital receipt from the

11 5.5 Strategic Hook Impact In light of the above factors, Option 4, new build on an extended site, is

considered the best option to progress. The impact this option will have on the ‘strategic hooks’ is shown on the following table.

Site: > New build on an extended site Capacity: > This Committee agreed on 26 August 2008, that the options appraisal

would be based on a 2 class base. Pre-School Provision: > Provision for this area is provided elsewhere. Additional Support for Learning: > The proposed schedules include a high dependency disabled facility and

facilities are available for adaptation, if a specific ASfL need is identified Meal Provision: P The current servery (3m2) will be upgraded to an enhanced servery (1 5m2) Accommodation Schedules: > As per Appendix 1 -without an extended games hall and MUGA - see

para 11.4.3 Community Facilities: > No additional specific communities facilities will be provided as per para

11.3.2 Estate and Deliverability Factors: > Option is dependent on site being suitable and the land owner‘s agreement

to sale. > The school will continue to operate until the new building is built. Therefore,

no decant arrangements are required.

11.6 St Mungo Primary School 11.6.1 Current State

Report Education Committee 4

30 September 2008

11.6.1 .I In March 2008 Members were advised that the KPI data for St Mungo Primary School was as follows -

0 Suitability - C 0

0 Sufficiency - D 0 Accessibility - B 0 Environmental Impact - D

0

Condition - D - now updated to C

FMcosts-B Overall - D ‘Environmental Impact’

Remains overall ‘D’ due to ‘Sufficiency’ and

11.6.1.2 St Mungo Primary School was originally built as a church circa 1800 using traditional building methods and materials. The building was converted to a school in the 1870’s. Toilet wings were added in the 1970’s. The building is a Category C(S) listed building. The school site has an area of 0.38 Hectare and extends back from the 8723 Public Road. It consists of vehicular access and parking areas at the front (access to an adjoining private house is via this area). Beyond this sits the school building, centrally located between two hard surfaced play areas. This includes a substantial open shelter and the remains of the original outdoor toilets are located to the rear of the school. In addition, a detached building contains the school’s central heating fuel storage tanks. Behind the school there is a grassed playing field, which is in leasehold.

11.6.1.3 The current site is sufficient but it is not level and presents a number of practical issues. The existing school is Grade C(S) listed building -this limits the potential for physical alteration. The following planning factors require to be taken into consideration:

Local landmark - local resistance. The building was originally a church and difficult to appropriately adapt sympathetically. Planning resistance Preservation

0 Historic Scotland considerations

The proposed size of the new school is 191 m2 larger than the existing building - i.e. 265m2 to 456m2

1 I .6.2 Option 1 - Do Nothing This option should be considered in view of the revised grading in the recent Condition Survey.

1 I .6.3 Option 3 - Refurbish and Extend This would involve a complete refurbishment of the existing school and an extension to meet the SEMP Educational Objectives, as detailed in the proposed accommodation schedules (Appendix 1). It should be noted that this is a compromise solution. The age and construction of the existing building does not lend itself to being extended to provide the accommodation required. The estimated cost of this option is f 1,317K as detailed in Appendix 3

Report Education Committee 30 September 2008

Advantages . Allows the development of a purpose designed facility which meets the SEMP Educational Objectives . Most environmentally efficient option . Addresses known site issues

P Traffic management within and

Advantages This would be the lowest capital cost . Less additional land would be required

Disadvantages . High overall capital costs . High cost per pupil in comparison to larger primary schools

Disadvantaaes . Would require staff and pupils to be decanted for a full academic year. Lockerbie Primary School could be used, once vacated, but there would be additional travel costs and it would be disruptive. . The site of the current Lockerbie Primary School would not be available for disposal until completion of works at St. Mungo. This would delay the potential capital receipts . Current site is restricted -this option would be a compromise on accommodation

9 Additional land will still be required to provide suitable hard and soft landscaping . Possible solutions are seriously limited due to building layout, particularly as it was originally a church, and the type of construction . Whole life costs more expensive than new school option . Very Good BREAM rating would not be achieved.

11.6.4 Option 4 - New build on extended or new site If Members wish to consider this option there are 2 alternative locations for a new school.

There is currently a lease agreement in place with Castlemilk Estate for part of a field at the rear of the school, at present being used as the school playing field. If additional land could be made available and a clear title secured, the new school could be situated here. There are some site access issues that remain to be resolved. A site has been identified near the village hall and tennis courts. These facilities are at present used by the school but distance restricts use. This ground is also owned by the Castlemilk Estate. However, initial desktop investigations indicate that this site may be in the local flood plain. Investigations are ongoing. In light of the above, the option to build a new school on an extended site is the preferred option. The estimated total outturn figure for this option is f 1,439k

Report Education Committee 4

30 September 2008

outwith the site > Pedestrian and vehicular access > Adequate car parking > Improved drainage > Increased useable playground

and playing field area . Addresses access, health & safety and security issues . Considers its location in relation to known and in use community facilities . Revenue savings from the reduction of travel to other facilities to provide some activities such as Physical Education. . Potential capital receipt from the sale of existing school.

11.6.5 In light of the above, Option 4, new build on extended site, is considered the best option to progress. The impact that this option will have on the strategic hooks is shown on the following table.

I Strateaic Hook ImDact Site: > New build on an extended site Capacity: > This Committee agreed on 26 August 2008, that the options appraisal

would be based on a 2 class base. P re-School Provision : > Pre-school provision is provided from elsewhere. Additional Support for Learning: > The proposed schedules include a high dependency disabled facility and

facilities are available for adaptation if a specific ASfL need is identified Meal Provision: P The current servery (9m2) will be upgraded to an enhanced servery (1 5m2) Accommodation Schedules: > As per Appendix 1 - without an extended games hall and MUGA - see

para 11.4.3. Community Facilities: > No additional specific community facilities will be provided as per para

11.3.2 Estate and Deliverability Factors: > Option on site is dependent on access issues being resolved, site being

suitable and land owner’s agreement to sale. P The school will continue to operate until the new building is built. No

decant arrangements are required.

11.7 Beattock Primary School 11.7.1 Current State 11.7.1 .I In March 2008, Members were advised that the KPI data for Beattock Primary School was as follows -

Report Education Committee 30 September 2008

Suitability - C 0 Condition - D - confirmed in recent Condition Survey as D

Sufficiency - C 0 Accessibility - C

Environmental Impact - C

Overall - D FMWsts-D

11.7.2.2 Beattock Primary School has an area of 0.6 Hectare and is located on the corner site at Craigielands Park, Beattock. It was originally constructed circa 1970.

11.7.2.3 The current site is sufficient for the proposed accommodation and it does not present any particular difficulties in relation to access or ground conditions. However, the main elements of the building fabric and services infrastructure are in poor condition. The roposed size of the new school is 31 % larger than the existing building - i.e. 532m increasing to 698m2. ;p.

11.7.3 Option 3 - Refurbish and Extend This would involve a complete refurbishment of the existing school and an extension to meet the SEMP Educational Objectives, as detailed in the accommodation schedules (Appendix 2). Due to the aforementioned fundamental fabric and infrastructure condition issues, this option is not feasible. It is therefore not given further consideration.

11.7.4 Option 4 - New build on same site This involves the construction of a new school on the same site. Notwithstanding the infrastructure concerns, the actual site does not give rise to any issues from a health and safety or accessibility point of view. The total outturn cost of a new build option at this school would be f 2,052K.

Advantages . Allows the development of a purpose designed facility which meets the SEMP Educational Objectives in all aspects . Resultant building will be environmentally efficient . Addresses known infrastructure issues

Disadvantages . Would require staff and pupils to be decanted for a full academic year. Moffat Primary School could be used, once vacated, but there would be additional travel costs and it would be disruptive.

capital receipt for the site of Moffat School

. Delay in the potential

11.7.5 The impact that this option will have on the strategic hooks is shown on the following table.

Strategic Hook Impact Site: k The existing site is considered suitable for a new build

14

Report Education Committee 4

30 September 200,

Capacity: > This Committee agreed on 26 August 2008, that the options appraisal

would be based on 3 class bases. Pre-School Provision: > Based on current demand and taking into account the recent and proposed

house building in the area, a nursery with a 20/20 capacity i.e. can accommodation 20 children in the morning and afternoon, is recommended. This is comparable with the current provision.

Additional Support for Learning: P SfF schedules include a high dependency disabled facility and facilities are

available for adaptation if a specific ASfL need is identified Meal Provision: Enhanced Servery Provision. The school currently has a production kitchen. However, in line with recent SEMP decisions, including the PPP and 2A schools, it is recommended that an enhanced servery is provided, with meals provided by the new Moffat PPP School. Accommodation Schedules: > As per Appendix 2 -without an extended games hall and MUGA - see

para 11.4.3 Community Facilities: P No specific additional community facilities will be provided as per para

11.3.2 Estate and Deliverability Factors: P The demolition and new build would require the use of the former Moffat

Primary School as a decant facility, after the completion of the PPP school.

Caroline M Taylor Group Business Manager

Peter Nelson Service Manager - Property (ESWCS)

Date of Report: 23 September 2008

APPENDICES - 3

Background Papers:

Colin Grant Service Director Schools Services Education and Social Work Services Woodbank, 30 Edinburgh Road DUMFRIES, DGI 1NW

26 August 2008 27 May 2008 29 April 2008 25 March 2008 29 January 2008

School Estate Management Plan Update - August 2008 School Estate Management Plan Update - May 2008 School Estate Management Plan Update - April 2008 Investing in the School Estate : Revised Priorities Schools Service Capital Programme 2007108

APPENDIX 1

School Estate Management Plan - Options Appraisal - Mouswald and St Mungo Primary Schools

Projected Costs

Estimated Build Costs - - Mouswald - 456sq m @ f 1,880 - St Mungo - 456 sq m @ f 1,840

Site Works Drainage External Services Preliminaries Contingencies Construction Costs Fees and Statutory Approvals @ 15% TOTAL COSTS

Cost per Sq M

Educational Accomodation Classroom (inc activity area) Fully Accessible Classroom Tutorial/Library/Resource Room Central Store Multi Purpose Hall/Gym/Dinina Multi Purpose Hall Store Sub-Total - Educational

Non-Educational Accomodation Head Teacher Office Administration Office and Reception Staff Room Servery Staff Toilets Gym Changing and Pupil Toilets High Dependency Changing Room Sub Total - Non-Educational

Total

Service Accomodation Circulation/Main Entrance @10% Janitor Cleaners PlanVSprinkler Pumps etc Switchroom/Elect Cup'ds Hub Server School Grounds Sub Total - Service

ITotal Area

f

857,280

92,575 27,000 20,000

196,832 75,452

1,269,139 190,371

1.45931 0

3,201

Mouswald

Existina Pronosed sq m sq m

90 60 0 65 23 24 4 20 28 75 0 20

145 264

7 0 7 3 3 13 0 33

12 15 10 15 10 28 15 105

178 369

12 37 0 10 1 4 0 25 0 6 0 5 Y Y 13 87

191 456

St. Mungo

Existina Pronosed sq m sq m

100 60 0 65 6 24 15 20 32 75 0 20

153 264

9 12 0 15 17 10 9 15 4 10 21 28 0 15

60 105

213 369

39 0 6 7 0 0 Y 52

37 10 4

25 6 5 Y 87

265 456

f I

839,040 92,575 27,000 20,000

196,832 75.452

1,250,899 187,635

1.438.534

3.1 55

APPENDIX 2 4 School Estate Management Plan - Options Appraisal - Beattock Primary School

I Educational Accomodatlon Classroom 2 (inc activity areas) Classroom 3 Fullv Accessible TutoriaKibrarylResource Room Central Store Multi Purpose Hall/Gym/Dining Multi Purpose Hall Store Sus Total - Educational

Pre School Accommodation Pre-5 Playroom (20l20) Pre-5 Toilets/Cloaks/Entrance Pre-5 Outdoor Soft Play Pre-5 Outdoor Play Wraparound Care Space Office - Pre-School Kitchen - Pre-School Sub Total - Pre-School

Non-Educational Accommodation Head Teacher office Administration Office and Reception Staff Room Kitchen Servery Staff Toilets Gym Changing and Pupil Toilets Hiah DeDendencv Chanaina Room Sub Total - Non Educational

Total

Service Accommodation CirculationlMain Entrance @I 0% Janitor Cleaners PlantlSprinkler Pumps etc SwitchroomlElect Cup'ds Hub Server Slave Server School Grounds Sub Total - Service

ITotal Area

Existing sq

I19 0 0 2

141 9

271

58 32

90

9 0 13 44 0 2 22 0 90

451

51 0 5 23 2 0 0 Y 81

532

~

Proposed sq m

120 65 24 20 75 25 329

52 30 Y Y 45 I 0 10

147

12 15 10 0 15 10 28 15

105

581

58 10 4 30 6 5 4 Y

117

698

Projected Costs €

Estimated Build Cost - 698 sq m @ E l ,833 per sq m Demolish existing schoollsite clearance Site Works Drainage External Services Preliminaries Contingencies Construction Costs Fees & Statutory Approvals @ 15% Total Costs

1,279,434 35,000 92,575 35,000 20,000

232,978 89.308

1,764,295 267,644

2,051,939

lcost per sq U 2,9391

Appendix 3

Professional Fees and Statutory Approvals @ 15% 193,991

Total 1,487,262

Cost per Sq M 2,866

School Estate Management Plan - Options Appraisal - Mouswald and St Mungo Primary Schools

Costs to Upgrade Existing School and Extend

171,809

1,317,201

2,509

Upgrade existing school Demolitions New extensions Site Works Drainage External Services Preliminaries Contingencies Construction Costs

Mouswald

Area Rate cost f

St Mungo

Area Rate cost f

168 1,300 21 8,400 15,000

351 1,850 649,350 98,485 10,000 55,000 178,580 68,456

51 9 1,293,271

253 1,300 328,900 8,000

272 1,850 503,200 47,050 10,000 5,000

175,838 67,404

525 1,145,392