0 OVERLEA HIGH SCHOOL
Schematic Design Presentation S. Dallas Dance, Superintendent
October 22, 2013
1 OVERLEA HIGH SCHOOL
Overlea High School - Facility Summary
• Facility Opened:
• Auditorium Addition:
• Activity Room Addition:
• School Rated Capacity (SRC):
• Current Total Enrollment:
• Current Total Area:
• Project Scope:
1961
1968
1973
1,230 Students
921 Students
203,505 sf
Renovation
2 OVERLEA HIGH SCHOOL
Project Vicinity And Site Location – Facility Summary
BALTIMORE
TOWSON
LUTHERVILLE
PIKESVILLE
ELLICOTT CITY
GARRISON
ESSEX
OVERLEA HIGH
SCHOOL
3 OVERLEA HIGH SCHOOL
Existing Site Plan – Facility Summary
0’ 100’ 300’
50’ 200’ 400’
N
4 OVERLEA HIGH SCHOOL
Existing Site Topography:
5 OVERLEA HIGH SCHOOL
Project Objectives
• Provide Appropriate Learning Environments
• Incorporate Facility Upgrades to Support Student Community
• Improve Student and Building Safety
• Upgrade Building Systems
6 OVERLEA HIGH SCHOOL
Summary of Systemic Deficiencies:
Building Envelope Deficiencies
• Building Envelope (Single pane windows – many inoperable windows).
• Security at existing doors.
Code Deficiencies
• Toilet rooms and fixtures not ADA compliant.
• No ADA accessibility to existing classrooms.
• No automatic sprinkler system and out of date fire alarm.
MEP System Deficiencies
• Outdated intercom and clock systems
• Outdated Technology (no infrastructure for WiFi and teaching technology).
• HVAC, no air conditioning.
Building Interior Deficiencies
• Lighting does not meet current BCPS / code lighting standards.
• Kitchen equipment outdated.
• Elevator does not serve all levels and is not ADA compliant.
• No ADA compliant signage.
7 OVERLEA HIGH SCHOOL
Building Envelope Deficiencies:
Single Pane Windows
8 OVERLEA HIGH SCHOOL
Building Envelope Deficiencies:
Exterior Doors
9 OVERLEA HIGH SCHOOL
Code Deficiencies:
Toilet Rooms & Fixtures
10 OVERLEA HIGH SCHOOL
Code Deficiencies:
Handicap Access to Classrooms
11 OVERLEA HIGH SCHOOL
Code Deficiencies:
Fire Protection (Sprinkler) and Fire Alarm System
12 OVERLEA HIGH SCHOOL
MEP Deficiencies:
Outdated Intercom and Clock System
13 OVERLEA HIGH SCHOOL
MEP Deficiencies:
Lacking Infrastructure for Interactive Boards & Wi-Fi
14 OVERLEA HIGH SCHOOL
MEP Deficiencies:
Air Conditioning and HVAC
15 OVERLEA HIGH SCHOOL
Building Interior Deficiencies:
Ceilings and Lighting
16 OVERLEA HIGH SCHOOL
Building Interior Deficiencies:
Kitchen Equipment and Serving Line
17 OVERLEA HIGH SCHOOL
Summary of Systemic Improvements:
Building Envelope Improvements:
• Replacement of window curtain wall system and windows throughout the entire facility.
• Replacement of all exterior doors.
Code Improvements:
• Install sprinkler system throughout the entire building.
• Replacement of all doors and hardware.
MEP System Improvements:
• Upgrade mechanical system to all year round climate control thru central heating and
central cooling.
• Replace all exhaust vents
• Upgrade Plumbing Systems
• Replacement of electrical switchboard, panelboards and branch circuits
• Replacement of all interior lights and all exterior lights
• Replacement of light controls
Building Interior Improvements:
• Renovation of group restrooms to be in compliance with ADA guidelines
• Replace kitchen equipment and serving line layout.
• Replacement of the elevator to access all floors.
• Provide ADA compliant room signs
18 OVERLEA HIGH SCHOOL
Summary of Programmatic Deficiencies:
Career Technology Education (CTE) Program Missing or Undersized:
•Advance Tech Lab.
•Graphics Communication Lab
•Broadcast & Project Lead The Way (PLTW) Bio Lab
Special Ed Classrooms are Undersized:
•No support spaces
•Located in the corridor by gymnasium.
Music Program:
•Undersized
•Lacking the required support spaces.
Physical Education:
•Weight room is located in an unventilated space
•Area is only accessible from outside.
Art program:
• Original to facility
• Lacking support spaces.
19 OVERLEA HIGH SCHOOL
Summary of Programmatic Improvements:
CTE Program:
• Renovation of Advance Tech Lab to meet ED Spec.
• Relocation Graphics Communication program and support spaces.
Special Education:
• Relocation of Special Ed program.
Music:
• Provide full music program.
Art Program:
• Renovation of Graphic Arts program.
Physical Education:
• New Cardio Fitness program located in the Gymnasium wing.
• Weight Room moved inside of building.
General Building Improvements:
• Renovation of the Advance Path Testing.
• Renovation of the Health Suite to comply with MSDE guidelines.
• Relocation of the Administration to provide surveillance.
20 OVERLEA HIGH SCHOOL
KEY PLAN – First Floor
Educational Space Enhancement Advanced Path Testing & CTE: Advanced Tech. Lab
PLAN
21 OVERLEA HIGH SCHOOL
Educational Space Enhancement CTE: Graphic Communication
PLAN
KEY PLAN – First Floor
22 OVERLEA HIGH SCHOOL
Educational Space Enhancement CTE: Broadcast & PLTW – Bio Medical
PLAN
KEY PLAN – First Floor
23 OVERLEA HIGH SCHOOL
Educational Space Enhancement Special Education
PLAN KEY PLAN – First Floor
24 OVERLEA HIGH SCHOOL
Educational Space Enhancement Music Program
PLAN
KEY PLAN – Ground Floor
25 OVERLEA HIGH SCHOOL
Educational Space Enhancement Art Program
PLAN
KEY PLAN – First Floor
26 OVERLEA HIGH SCHOOL
Educational Space Enhancement Physical Education
PLAN
KEY PLAN
27 OVERLEA HIGH SCHOOL
Summary of Overall Building Deficiencies:
• No Continuity Between 3 Story Academic Wing and Cafeteria/Gymnasium Wing
• Main Entrance Lacks Surveillance and Control.
•Administration is located in rear of main building with no line of sight to the main
entrance, bus drop off and parking lots.
• Health suite spaces shared with guidance.
28 OVERLEA HIGH SCHOOL
Building Deficiencies: Main Entrance Existing
KEY PLAN
29 OVERLEA HIGH SCHOOL
KEY PLAN
Building Deficiencies: Main Entrance Existing
30 OVERLEA HIGH SCHOOL
Building Deficiencies: Lack of Continuity, Topography
KEY PLAN
31 OVERLEA HIGH SCHOOL
Building Improvements
Elevation Change Interconnections
KEY PLAN
Secure Entrance
Administration
3 Story
Academic Wing Student Community Space Cafeteria/Gymnasium Wing
Cross Section Thru Main Entrance and Student Community Space
1st Floor Entry
Gym Level
Cafeteria Level Ground Floor
2nd Floor
32 OVERLEA HIGH SCHOOL
KEY PLAN
Building Improvements: Main Entrance Existing
33 OVERLEA HIGH SCHOOL
Building Improvements New Secure Main Entrance
MAIN ENTRANCE PLAN KEY PLAN – First Floor
34 OVERLEA HIGH SCHOOL
Building Improvements Main Entrance Before
KEY PLAN
35 OVERLEA HIGH SCHOOL
Building Improvements New Secure Main Entrance
KEY PLAN
36 OVERLEA HIGH SCHOOL
Building Improvements Sunshine Alley Before
KEY PLAN
37 OVERLEA HIGH SCHOOL
Building Improvements
Proposed Community Space
KEY PLAN
38 OVERLEA HIGH SCHOOL
Building Improvements Sunshine Alley Existing
KEY PLAN
39 OVERLEA HIGH SCHOOL
Building Improvements Community Space Access to Cafeteria and Gymnasium
KEY PLAN
40 OVERLEA HIGH SCHOOL
Building Improvements Community Space Access from Gymnasium
KEY PLAN
41 OVERLEA HIGH SCHOOL
Building Improvements Gymnasium Entrance Level
KEY PLAN
42 OVERLEA HIGH SCHOOL
Building Improvements Gymnasium Entrance Level
KEY PLAN
43 OVERLEA HIGH SCHOOL
Building Improvements Cafeteria and Gymnasium Entrance
KEY PLAN
44 OVERLEA HIGH SCHOOL
Building Improvements Cafeteria Entrance with Gymnasium Stairs Beyond
Community Space
KEY PLAN
45 OVERLEA HIGH SCHOOL
Building Improvements Aerial Photo of North Facade
46 OVERLEA HIGH SCHOOL
Building Improvements Isometric of North Facade
47 OVERLEA HIGH SCHOOL
Building Improvements Aerial Photo of South Facade
48 OVERLEA HIGH SCHOOL
Building Improvements Isometric of South Facade
49 OVERLEA HIGH SCHOOL
Building Improvements Auditorium Entrance Before
50 OVERLEA HIGH SCHOOL
Building Improvements Auditorium Entrance After
51 OVERLEA HIGH SCHOOL
Building Improvements
Existing South Elevation- 3 Story Academic Wing
52 OVERLEA HIGH SCHOOL
Building Improvements Proposed South Elevation- 3 Story Academic Wing
53 OVERLEA HIGH SCHOOL
Building Improvements Proposed South Elevation- 3 Story Academic Wing
KEY PLAN
54 OVERLEA HIGH SCHOOL
Building Improvements
Exterior Animation
ANIMATION
55 OVERLEA HIGH SCHOOL
Project Schedule:
•Design Sept. 2013 – April 2014
•Bid & BCPS Board Meeting May 2014 – Aug. 2014
•Construction Sept. 2014 – Oct. 2016
56 OVERLEA HIGH SCHOOL
QUESTIONS