Scheduling of Experiments Christine Clarke, 10 th October 2012 FACET User Meeting.
-
Upload
isabel-hunter -
Category
Documents
-
view
212 -
download
0
Transcript of Scheduling of Experiments Christine Clarke, 10 th October 2012 FACET User Meeting.
Scheduling of Experiments
Christine Clarke, 10th October 2012
FACET User Meeting
2012 Schedule -- FACET User Run 1
3
Shift Schedules
https://slacportal.slac.stanford.edu/sites/ard_public/facet/user/Pages/Schedule.aspx
Weekly pattern:
• Wednesday was an Access Day (PAMM)- When LCLS access (every other Wednesday), FACET beam needs to turn off
• Thursday was Machine Development - MD is a great buffer between PAMM and User shifts
• 5 remaining days for experiments
• Later in run, Friday morning became MD time too- MD time was extremely beneficial to delivering good beam
User Beam-time64%
MD Machine De-velopment
19%
PAMM Planned Tunnel Access + Re-covery17%
4
Part 1A Schedule
Starting Date [Wed]
Run Wee
k
Wednesday Thursday Friday Saturday Sunday Monday Tuesday End Date [Tues]
4/11/2012 O 1 Commissioning MD 4/17/2012
D PAMM Recovery
S PAMM Recovery E-203 (4 hr)
4/18/2012 O 2 E-203 T-501 (2hr) T-501 4/24/2012 D MD S
4/25/2012 O 3 MD E-200 5/1/2012 D PAMM E-202
S PAMM Recovery 5/2/2012 O 4 MD E-202 5/8/2012
D PAMM E-201/E-205 S PAMM Recovery
5/9/2012 O 5 MD E-202 5/15/2012
D PAMM E-200 S PAMM Recovery
5/16/2012 O 6 MD E-202 5/22/2012
S PAMM E-201/E-205 D PAMM Recovery
https://slacportal.slac.stanford.edu/sites/ard_public/facet/user/Pages/Schedule.aspx
Experiment “groups”
• Experiments were grouped together so they could cover 24 hours a day for five days
straight- Group A: E-203 (Smith-Purcell), E-206 (THz), T-501 (CERN BBA)
- Group B: E-201 (DWF), E-205 (Euclid/energy chirp), E-207 (2-channel dielectric), E-204
(Metallic Structures)
- Group C: E-200 (PWFA)
- Group D: E-202 (Ultrafast EM Switching) – one shift/week due to sample change-over
constraints
5
Issues…
Group A:
• Grouping allowed 24 hour coverage but incurred many config changes
• This group lost a week due to power outage
• With single shifts, some experiments in this group were unfairly penalised
by lack of owl shift accelerator physicist
Group B:
• Smaller groups dependent on larger group (E-201) for commissioning
hardware
• E-205 and E-207 didn’t get beam time - How do we transfer knowledge between Group B groups?
• A real strain on a few key players in E-201
Group C:
• No unique issues?
Group D:
• Frequent rescheduling of the single shift based on condition of machine and
plans of other groups.
6
Most common complaint:
No time to think!
• Access day too rushed
• Too little time between weeks on shift- Can’t engineer good solutions
- Can’t solve what is going wrong
7
Beam time allocation 2012
Aim was to give PWFA ~50% of beam-time, group B ~30%
and group C+D ~20%• Similar to beam
request (time
requested PWFA >
time requested
group B > time
requested group
C+D)
• Perceived to be in
line with FACET’s
goals
• Given relative sizes
of the groups, this
was what the
personnel could
support
E-200 Plasma Wakefield Acceleration
45%
E-201 Dielectric Wakefield Studies
31%
E-202 Ul-trafast
EM Switching
8%
E-203 Smith Purcell
7%
E-204 Metallic Struc-tures1%
E-206 THz
Source Studies
3%
T-501 CERN BBA4%
T-502 Intra-Pulse Multi-Energy Mode in RF Linac
1%
Hours Scheduled
Future Schedule -- FACET User Run 2 and beyond
9
Proposal 1.1 – Moving PAMM
• As proposed in User Brown Bag in June…
• PAMM one day a week (User’s suggested Tuesday)
• But there aren’t enough Operators on a Tuesday to regularly support
the search and subsequent recovery
• Large experiments given a block 3 or 5 days
• Preceded by ~2 days PAMM recovery, POMM and MD time
• Note set-up time can be longer if next experiment requires itStarting Date
[Wed] Wednesday Thursday Friday Saturday Sunday Monday Tuesday End Date
[Tues]
6/20/2012 00:00-04:00 SOPs + BCS Recovery Set-up SOPs + BCS 6/26/2012
04:00-08:00 PAMM Recovery Set-up PAMM
08:00-12:00 PAMM POMM Set-up User Group PAMM
12:00-16:00 PAMM MD PAMM
16:00-20:00 Recovery MD Recovery
20:00-24:00 Recovery MD Recovery
6/27/2012 00:00-04:00 Recovery Set-up 7/3/2012
04:00-08:00 Recovery Set-up
08:00-12:00 POMM Set-up
12:00-16:00 MD User Group
16:00-20:00 MD
20:00-24:00 MD
10
Proposal 1.2 – Moving PAMM take 2
Starting Date [Wed]
Wednesday Thursday Friday Saturday Sunday Monday Tuesday End Date [Tues]
6/20/2012 00:00-04:00 SOPs + BCS Recovery Set-up 6/26/2012
04:00-08:00 PAMM Recovery Set-up
08:00-12:00 PAMM POMM Set-up User Group
12:00-16:00 PAMM MD
16:00-20:00 Recovery MD
20:00-24:00 Recovery MD
6/27/2012 00:00-04:00 SOPs + BCS Recovery 7/3/2012
04:00-08:00 PAMM Recovery
08:00-12:00 PAMM POMM
12:00-16:00 PAMM MD User Group
16:00-20:00 Recovery MD
20:00-24:00 Recovery MD
• There are enough Operators to support a Thursday PAMM
• Friday has enough Operators but a PAMM just before a weekend brings risk if there is a bad recovery
11
Proposal 2 – Double-up
• PAMM once a fortnight (at the same time as LCLS)
• Longer PAMM
• More MD time and more set-up time likely to lead to better
delivery
• Set-up time could be longer still if next experiment requires itStarting Date
[Wed] Wednesday Thursday Friday Saturday Sunday Monday Tuesday End Date
[Tues]6/20/2012 00:00-04:00 SOPs + BCS PAMM Recovery MD Set-up 6/26/2012
04:00-08:00 PAMM PAMM Recovery MD Set-up
08:00-12:00 PAMM PAMM POMM MD Set-up
12:00-16:00 PAMM Recovery MD MD Set-up
16:00-20:00 PAMM Recovery MD MD Set-up
20:00-24:00 PAMM Recovery MD MD Set-up
6/27/2012 00:00-04:00 7/3/2012
04:00-08:00
08:00-12:00
12:00-16:00 User Group
16:00-20:00
20:00-24:00
12
Combinations, Variations and Further Ideas
• Two-day PAMMs with a one week schedule - Is less beam time what we want?
• One-day PAMM once a fortnight- Beam quality will improve and there will be more beam time for
Users
• Interleave MD and set-up with User Time- Scheduling configuration changes during the User Run 1 proved
difficult but it is necessary
• Schedule beam tuning- Problems arise over time and it may be beneficial to hand over to
the Sector0-20 team on a regular and scheduled basis for
improved delivery
13
What’s up with those 8 hour shifts anyway?
8 hour shifts:
• Owl: midnight-8am
• Day: 8am-4pm
• Swing: 4pm-midnight
Some experiments want less beam time in a single block
(E-202) ~4 hour shift. And some operated on 12 hour shift
rota (E-201).
SSRL has 11pm-7am, 7am-3pm, 3pm-11pm shifts.
• We should not be hung-up on the 8 hour rota if this doesn’t
work for us
14
20 minute discussion
Talking Points:
• Group A, B, C and D: how did that work?
• How long should PAMMs be?
• Can we have fewer PAMMs or do we need to have more PAMMs?
• How long should blocks of experiments be?
• How much time should we have for MD?
• How do we schedule the set-up time?
• Should experiments be interleaved more or less?
• Should we schedule beam tuning or leave it to User request?
• How do we best schedule the configuration changes? Can we get
away without any over owl shifts?
• Length and pattern of “shifts” - Better to avoid operator shift change-over?
- Can we stagger User shifts with accelerator physicist shifts so we
don’t have a User shift that never sees an accelerator physicist?