Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin...

16
1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and Elements The following set of landscape zones and elements apply to the Work being undertaken for the “State Highway (Basin Bridge)” designation. The concept plans shown in this Schedule divides the designation into 6 zones with landscape treatments and design elements indicated in each zone. The following plans define the zones: [List of concept plans presented at the Board of Inquiry] The following zone specific principles and detailed design considerations apply to detailed urban and landscape design development and implementation. Comment [YW1]: Each zone needs to refer to the concept plans presented at the Board of Inquiry.

Transcript of Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin...

Page 1: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

1 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Schedule 1

Designation Zones and Elements

The following set of landscape zones and elements apply to the Work being undertaken for

the “State Highway (Basin Bridge)” designation. The concept plans shown in this Schedule

divides the designation into 6 zones with landscape treatments and design elements

indicated in each zone.

The following plans define the zones:

[List of concept plans presented at the Board of Inquiry]

The following zone specific principles and detailed design considerations apply to detailed

urban and landscape design development and implementation.

Comment [YW1]: Each zone needs to refer to the concept plans presented at the Board of Inquiry.

Page 2: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

2 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Zone 1 – Cambridge/Buckle Bridge Interface Zone

Scheme Design Summary Plan

Zone 1 Specific Principles

(Note: Relocation of the former Home of Compassion Crèche and curtilage treatment are

assumed to be part of the NWM Park (Pukeahu) Empowering Act 2012 works which will be

completed in 2015 and form part of the receiving environment)

Zone 1a Develop a landscape interface to the bridge abutment landing and Buckle Street to:

Envelope the bridge abutment landing zone to eliminate any undercroft space lower

than 2.4m;

Provide accessible high open space amenity landscape under the bridge;

Provide a design that responds to and interprets the topography of the site.,;

Incorporate and integrate separate paths for accessible pedestrian and fast easy to

use cycle circulation around and under the bridge; and

Incorporate a, gathering, retention and filtering of surface water from the bridge and

street as a visible component of the landscape.

Zone 1b Develop a landscape interface to Kent and Cambridge Terrace to:

Comment [YW2]: This needs specific plan numbers to define the zones

Comment [YW3]: There are two sub zones in this area and it needs to be referenced correctly

Comment [YW4]: This section needs consistency in language through out it.

Deleted:

Deleted: as a grounded,

integrated landscape condition,

Deleted: eliminat

Deleted: ing

Comment [YW5]: I have undertaken as plain English review removing words that are superfluous and do not help with the understanding of the schedule.

Deleted: design form and

character that integrates visually

with the bridge structure and

connects and extends

Deleted: open space

Deleted: form and character

Deleted: informed by lines of

movement and sight, both

vehicular and pedestrian, across

and to adjacent sites

Deleted: public

Deleted: , as a positive

Deleted: integrated landscape

component,

Page 3: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

3 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Provide a design that responds to and interprets tangata whenua values including

the historical wetland ecology of the former Waitangi Lagoon, now the Basin Reserve

and Kent/ Cambridge corridor;

Design wetland terraces as functional rain gardens, to receive, filter and detain

stormwater from the bridge, adjacent paths and roads;

Contribute a complementary ‘foreground’ landscape to the bridge abutment landing,

the relocated former Crèche, the Carillon and NWM Park beyond in views from Kent

and Cambridge Terrace;

Provide accessible, functional, high amenity landscape spaces that respect the NWM

Park sequence of public space; and

Incorporate separate paths for accessible public pedestrian and fast easy to use cycle

circulation linking with the NWM Park, Buckle Street and Kent/ Cambridge corridor.

Develop a landscape interface to the relocated former Crèche to:

Structure, interpret and reflect the sloping topography of the valley edge and the

former wetland environment of Waitangi Lagoon;

Complement and reinforce the presence of the former Crèche in its new elevated

location adjacent to Zone 1 and include design interpretation that recognises the

former location of the Crèche within the landscape; and

Incorporate public pedestrian and cycle access to the former Crèche, the bridge and

the NWM Park beyond.

Zone 1 Detailed design considerations

This landscape provides an important foreground to the view of the bridge; the Carillon and

the former Crèche building. The quality, finish and detailed design of the built components

of this landscape need to be respect the NWM Park. The wetland planting should define the

ecological setting of the site and the connection though to Waitangi Park planting in order

to make the association from the former Waitangi Lagoon to the sea.

Planting of the steeper terraces should also respect the NWM Park details.

The wetland terraces are to be rain gardens, designed to receive, filter and detain

stormwater from the bridge, paths and roads. Therefore integrated stormwater drainage

design will be required.

Maintenance of the wetlands, tree and terrace planting will be critical to ensuring ongoing

success of this space. These need to be designed therefore to ensure good functionality and

considering future maintenance and possible development of future wetland spaces down

Kent and Cambridge Terrace.

Deleted: form and character

Deleted: as a component

Deleted: to

Deleted: greater

Deleted: to Kent/ Cambridge/

Basin Reserve processional

Deleted: fully integrated with

Comment [YW6]: This area is not in the Empowerment Act and therefore not part of the NWM. It has visual and physical links that with the movement of the Creche will be stronger with Cambridge and Kent Terrace.

Deleted: terrace walls, path paving,

balustrades, handrails, lighting and

furniture elements

Comment [YW7]: This planting should not be the same as Waitangi Park as it is in quite a different ecological area.

Deleted: connect to that detailed

for

Comment [YW8]: This area is not in NWM Park and should be a transition zone towards a non-memorialisation space around the fast moving and activity focused Basin Reserve.

Moved (insertion) [1]

Deleted: .

Moved up [1]: The wetland terraces

are to be rain gardens, designed to

receive, filter and detain stormwater

from the bridge, paths and roads.

Therefore integrated stormwater

drainage design will be required.¶

Page 4: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

4 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

A maintenance plan covering methods and programme for maintenance of wetland terraces

will be required.

Provide specific wind shelter at selected locations. at bus stops and traffic lights, without

introducing negative CPTED implications.

Zone 2 – Kent/Cambridge Basin Gateway

Scheme Design Summary Plan

Zone 2 – Specific Principles

Develop a landscape interface to:

Provide a design that responds to and interprets tangata whenua values including

the historical wetland ecology of the former Waitangi Lagoon, now the Basin Reserve

and the Waitangi Stream which now flows in the stormwater pipe under Cambridge

Terrace;

Provide for safe, visible and generous sheltered public access and gathering to the

northern entry of the Basin Reserve;

Provide fast easy to use cycle circulation into the northern entry of the Basin Reserve

Integrate the existing and future Kent/ Cambridge median landscape also known as

Canal Reserve, with adjacent landscapes;

Integrate the pier for the bridge with the ground;

Deleted: Consider providing

Deleted: where it is possible (e.g

Deleted: )

Deleted: form and character

Comment [YW9]: Cycle circulation in and around the Basin Reserve has been left out.

Deleted: the form and character

of

Deleted: with

Deleted: in both design language

and configuration of the

landscape and movement system

on

Comment [YW10]: This needs more work. If you put it in plain English is means nothing more than putting the pier in the ground. What is being said here?

Page 5: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

5 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Structure soft (plant material) and hard (paving, street furniture) landscape

components to define gathering and circulation space in relation to existing median

circulation zones. This will be done through the reconfiguration of pedestrian

crossings, bus stops, and the Basin Reserve Gateway;

Provide landscape elements and built gateway components of the Basin Reserve that

enhance the physical and visual amenity of the undercroft of the bridge, its piers,

adjacent roading.

Integrate the bridge undercroft landscape with the landscape beyond the Basin

Reserve;

Provide appropriate visual mitigation between the Basin Reserve and the bridge by a

combination of additional planting, and/or screening, and/or new building structure.

Zone 2 Detailed design considerations

WCC has indicated the desire to develop the Kent and Cambridge Terrace boulevard to

improve urban design form and function. The design of this space is very much a part of

that boulevard while still respecting other connections such as Waitangi Park to the north

the NWM Park to the west, the Basin Reserve to the south, Government House to the south

and ultimately the open spaces of Wellington College, Wellington East Girls College and the

Town Belt to the east, . The design should:

Integrate the landsape with the Kent and Cambridge Terrace boulevard (aka Canal

Reserve);

Provide safe, visible and generous public and cycle space entry to the Basin Reserve;

Integrate and coordinate the materials used across Zone 2 and with the adjacent

landscapes Basin Bridge Zones including materials, lighting, furniture and detailing;

Join the landscape between the inside and outside the Basin Reserve;

Provide specific wind shelter at selected locations (e.g. at bus stops and traffic lights)

without introducing negative CPTED implications.

The new Basin Reserve Northern Gateway Building should:

Integrate with new as well as existing landscape and buildings, including the R.A.

Vance Stand, Players’ Pavilion (if kept), and the existing toilet block;

Ensure the design, management and occupation of spaces are in alignment with the

concept design configuration and form, including hierarchy of public interface and

service, degree and location of openings/ glazing, and expression as a gateway

pavilion to the Basin Reserve;

Support the landscape in providing safe, visible, and generous public space entry to

the Basin Reserve;

Ensure the Gate design into the Basin Reserve at the bottom of the building allows

the default setting to be open for public and cycle use, but can be shut through a

Deleted: that shape and

Deleted: facilitate

Deleted: ,

Deleted: ed

Deleted: Reinforce

Comment [YW11]: Not sure if this is refereeing to the Northern Gateway ...

Deleted: integration with, and

Deleted: in

Deleted: relation

Deleted: to

Deleted: new

Deleted: adjusted

Deleted: and

Deleted: <#>Provide for safe ...

Comment [YW12]: What is this? Is this ...

Deleted: As noted previously,

Deleted: connecting

Deleted: and

Deleted: open spaces in an east- ...

Deleted: or allow for integration ...

Deleted: landscape

Deleted: ly

Deleted: proposed

Deleted: and receiving

Comment [YW13]: If this is not explicit ...

Deleted: Integrate

Deleted: built components with

Deleted: interfaces both

Comment [YW14]: Integration of ...

Deleted: <#>Integrate and ...

Deleted: where it is possible

Comment [YW15]: Is this the right ...

Deleted: retained

Deleted: developed

Comment [YW16]: This needs specific ...

Comment [YW17]: What are you ...

Deleted: ways

Deleted: are high quality ...

Deleted: such that

Deleted: is

Deleted: with

Deleted: operable

Page 6: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

6 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

visually permeable gate for security at night, or for events, and additional visually

impermeable ‘shutters’ can be added when there is a cricket match time. The gates

shall be designed to achieve porosity levels of 30-35% when shut, to mitigate

potential wind effects. While the Ground level screens to the east of the public

gateway are not publicly accessible, the requirement for visual permeability in the

default mode applies;

Ensure CPTED principles are used to develop the design and management of the

facility; and

Ensure high quality and enduring materials detailing and colour maintain a clear

articulation between the 3 components of base, mid-layers, and roof form:

Ensure screening elements of the gates are architecturally integrated and of a quality

that is consistent with the building itself;

Ensure that the Northern Gateway Building presents a positive frontage to the

important view from Kent and Cambridge Terraces;

Ensure that the south façade has formal articulation allowing for a occupiable

balcony space developed with a coherent building composition, and which ensure

that the interior of the building and its users engage with the Basin reserve Cricket

Ground;

Express and design the undercroft of the gate area as a high quality entrance space;

Provide effective visual screening that can close off the ground level undercroft

openings of the Northern Gateway Building during matches;

Provide fencing/barrier and gates that will maximise views through to the ground

outside match times, and allow for physical access control as required; and

Provide screening if and as necessary to provide for shelter in excessively windy

conditions in the undercroft.

Zone 3 – Kent/Ellice Street Corner Zone

Scheme Design Summary Plan

Deleted: screen/

Deleted: s

Deleted: with

Deleted: as required at

Comment [YW18]: Is this saying that the east and west gates under the building are different?

Deleted: Utilise

Deleted: in the

Deleted: ed

Deleted: and

Deleted: that

Deleted: s

Comment [YW19]: Are we talking about the gate screening elements? If not there is more detail required here.

Deleted: axial

Comment [YW20]: Are we interested from where?

Deleted: including

Deleted: s

Comment [YW21]: Is the balcony space to hang over the pedestrian area that goes around the Basin?

Comment [YW22]: Undercroft of what area of the building. I presume its in relationship to the gates or are you suggesting the balcony.

Comment [YW23]: Isn’t this a repetition of what has already been said?

Comment [YW24]: Once again repetition

Comment [YW25]: Once again where is the undercroft and why is sheleter required. This is not clear.

Page 7: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

7 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Zone 3 – Specific Principles

Develop an integrated corner on the Kent/ Ellice Corner to:

Build a building with an active frontage and streetscape on the corner from Kent

Terrace to Hania Street;

Integrate with and complement the historical pattern of buildings along Kent

Terrace;

Use the Bridge substructure and undercroft of the superstructure as an articulated

ceiling and verandah to the public realm. Also maintain the required serviceability to

the bridge structure;

Design the building in a manner that links to the service and car parking area

accessed from Hania Street;

Apply CPTED principles in and around the building on the corner of Kent Terrace. In

particular consider the sight lines, safe activated edges, lighting from the building

itself and good visibility into the service and car park area;

Reinforce the existing built edge alignments of Kent and Ellice, and provide a

generous width footpath and cycle lane that:

Integrate the footpath/ cycle lane extending either side; and

Enbable circulation space for both longitudinal and transverse traffic and for

pedestrian entry to tenancies.

Comment [YW26]: The building and the landscape should be separated in a similar way to Zone 2. This Zone does not describe the principles of the hard and soft landscape components of the zone

Deleted: Repair the built

Deleted: by incorporating a

combined building and

streetscape that presents an

active frontage to the street

Comment [YW27]: How is this possible with this building. I would delete it as I think its fictitious to do this.

Deleted: Incorporate

Deleted: soffit

Deleted: structure of the

Deleted: Configure

Deleted: Contribute to the safety

of pedestrian circulation by the

application

Deleted: of

Deleted: that address

Deleted: and

Deleted: <#>Incorporate a level

of screening at the upper level of

the building between the bridge

and the Grandstand Apartments.¶

Comment [YW28]: Specific plans and or dimensions should be required here.

Deleted: s with

Deleted: Facilitates mixed use

Page 8: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

8 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Zone 3 – Detailed design considerations

The design detail of the building are critical to the achievement of the desired outcomes.

The building is to be of the form, scale and detail indicated with:

High quality, fully glazed shop frontages to Kent Terrace, Ellice and Hania streets;

Capability for public entry on multiple sides;

Fully integrated with the streetscape works, the car park service area and the vertical

landscape screen element;

Fully integrated (as an autonomous element) with the bridge piers (within) and

superstructure over the building;

A management plan encouraging tenancies with amenity or showroom function

supporting street activity for extended hours and the use of inside and outside

lighting throughout the night;

Visibility into and out of the building to be transparent, through the provision of

extensive glazing. This shall be managed to retain transparency;

Integration of lighting that allows for full night time illumination of interior, building

edge and footpaths immediately in front of the building;

Encourage displays with associated lighting that imbue quality and add interest

within the building and to the building frontage;

Maintain clean building edges without recesses off the footpath;

;

Provide a management plan for the corner building to manage tenant use to

support/ maintain intended visual amenity objectives;

Design for the ease of technical servicing, fire, and seismic separation requirements

between the bridge and other components;

Integrate Treat stormwater management into rain gardens at the street edge; and

Consider providing specific wind shelter at selected locations where it is possible

(e.g. at bus stops and traffic lights) without introducing negative CPTED implications.

Integrate signage and lighting to reduce the number of poles in order to avoid visual

clutter in the landscape

Zone 4 – Paterson/Ellice/Dufferin Interface Zone

Scheme Design Summary Plan

Deleted: and screen

Deleted: <#>Integration of public

art with screen; ¶

Integrate the screen with the new

building and the existing

Grandstand Apartments

Deleted: <#>Design the screen

planting system to ensure

appropriate soil type and

capacity, drainage and irrigation

and ability for maintenance;¶

Deleted: <#>Provide a

management plan for the vertical

landscape screen to support and

maintain the structure and green

components;¶

Page 9: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

9 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Zone 4 – Specific Principles

Develop Hania/ Ellice corner landscape to:

Provide a positive continuous ground landscape linking to Cambridge/ Buckle Bridge

Interface Zone and Kent/ Cambridge Basin Gateway;

Integrate spatially and functionally with building under bridge to the west, and with

the Dufferin Street ‘corridor’ landscape to the south;

Minimise effects on the Regional Wines and Spirits building, vehicle and pedestrian

access and the reconfigured carpark;

Incorporate and integrate with the piers supporting the pedestrian/cycle bridge; and

Facilitate accessible pedestrian and fast easy cycle access between Hania, Ellice,

Paterson and Dufferin street pathways.

Develop Dufferin/ Ellice landscape zone to:

Provide a positive integrated wetland landscape, incorporating collecting, filtering,

retention and discharge of stormwater from the bridge and adjacent paths and

roads;

Integrate the main bridge pier and the elevated pedestrian/ cycle lane substructure;

Provide a new laneway to accommodate pedestrians, cyclists and vehicles travelling

from Ellice Street to Dufferin Street, the schools frontage and Newtown;

Consider, respond and interpret tangata whenua values including the historical

Hauwai cultivation area in this vicinity;

Deleted: formally and spatially

with

Comment [YW29]: This definitely needs more design principles!

Page 10: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

10 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Envelope the bridge abutment landing zone to eliminate any undercroft space lower

than 2.4m; and

Reinforce the structure of tree planting around the eastern side of the Basin Reserve.

Develop St Joseph’s Church car park and Ellis Street Residents to:

Retain existing parking provision with improved landscape amenity that compliments

the existing landscape treatment; and

Provide extensive landscape visual and audial screening of the bridge from St

Joseph’s and Ellice Street residential buildings.

Zone 4 Detailed design considerations

The levels and junctions of pathways, lane, rain gardens, gardens and abutment need to be

carefully considered to achieve a high quality ground plane landscape.

Integrate signage and lighting to reduce the number of poles in order to avoid visual

clutter in the landscape;

Provide substantial pedestrian lighting a the laneway of pedestrians to use that is at

a level that there is not a perception that this is not a path to unsafe.

Plant low indigenous plantings to ensure appropriate cultural connections to the

historical landscapes of Waitangi Lagoon and Hauwai cultivations while maintaining

good visibility throughout the area;

Provide interpretation of cultural heritage of this area; and

Provide wind shelter at at bus stops and traffic lights without introducing negative

CPTED implications.

Zone 5 – Dufferin/Rugby Streets, Schools / Church / Govt

House Interface Zone

Scheme Design Summary Plan

Deleted: Envelope the bridge

abutment as a grounded

landscape condition, eliminating

undercroft space lower than 2.4m

Comment [YW30]: This needs to be strengthened with more appropriate principles. The lack of principles suggest the applicant has not thought about this enough or in detail.

Deleted: some

Comment [YW31]: What rain garden?

Comment [YW32]: More information is required on the soft and hard landscape of this area.

Deleted: Consider providing

specific

Deleted: selected locations where

it is possible (e.g.

Deleted: )

Page 11: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

11 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Zone 5 – Specific Principles

Develop Dufferin Street, St Mark’s Church and schools drop-off zone in order to:

Incorporate and structure circulation and gathering space for pedestrians and

cyclists that link to the schools and church frontages;

Incorporate and structure zones for car drop-off, bus drop-off and waiting zone that

is safe and minimises congestion to schools, St Mark’s Church, Government House

entry and the street;

Consider, respond and interpret tangata whenua values including the historical

Hauwai cultivation area in this vicinity;

Develop a strong landscape corridor that extends the landscape of Government

House and the Basin Reserve through to Ellice Street, that promotes connectivity and

screens the Bridge structure particularly when viewed from Government House entry;

Provide a legible landscaped entry to Government House; and

Reinforce the structure of tree planting around the Basin Reserve’s ‘outer square’.

Integrate signage and lighting to reduce the number of poles in order to avoid visual

clutter in the landscape

Develop the Rugby Street zone in order to:

Incorporate a rationalised bus waiting and pick up area; and

Provide pedestrian/ safe cycle circulation and gathering spaces linking bus stop area

with schools and Adelaide Road.

Deleted: integrates with

Comment [YW33]: This is what the photomontages are doing.

Comment [YW34]: What are you meaning by this?

Formatted: Indent: Left: 1.27 cm, No bullets or numbering

Deleted: Incorporate

Page 12: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

12 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Develop the southern gateway zone in order to:

Provide a clear, legible and accessible link between Adelaide Road and the southern

gateway to the Basin Reserve;

Provide for safe, generous and sheltered public access and gathering to the southern

entry of the Basin Reserve;

Provide fast easy to use cycle circulation into the southern entry of the Basin Reserve

and

Respect the existing J.R. Reid Gate when you are relocating the existing C.S.

Dempster Gate with to provide a setting for both structures while providing an

enlarged improved southern gateway to the Basin Reserve.

Zone 5 – Detailed design considerations

Detailed design in consultation with schools, churches, Government House and bus

operations;

Co-ordinate design with WCC street and precinct aspirations;

Develop design for interpretation of the Hauwai cultivation area in consultation with

tangata whenua;

Integrate streetscape works with proposed future developments along Rugby Street;

Integrate the relocated C.S. Dempster Gate with the J.R. Reid Gate in conjunction with

reconfiguration of local existing landscape and service structures, to form an

enhanced southern gateway to the Basin Reserve, in consultation with the Basin

Reserve Trust; and

Provide wind shelter at locations by bus stops and traffic lights without introducing

negative CPTED implications.

Formatted: Tab stops: -5.4 cm, Left+ Not at -2.86 cm

Comment [YW35]: Cycle circulation in and around the Basin Reserve has been left out.

Deleted:

Deleted: Integrate

Deleted: the relocated existing

C.S. Dempster Gate with

Deleted: respectful

Comment [YW36]: Has WCC got aspirations for other parts of the street precinct. And what are they and shouldn’t they be put in this schedule as they may change otherwise.

Deleted: Consider providing

specific

Deleted: selected

Deleted: where it is possible (e.g.

at

Deleted: s)

Page 13: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

13 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Zone 6 – The Bridge Element

Scheme Design Summary Plan

Zone 6 - Element Specific Principles

An over-riding design objective is integration. To achieve integration with its broader

context the bridge shall:

Be aligned horizontally:

With the alignment of the existing streets and buildings (the city grid), in particular

the Ellice/ Buckle corridor;

With the outer edge of the Basin Reserve ‘Square’ such that it maintains the existing

space around the Basin Reserve and reinforces the form of the historical built edge

to the Square;

To provide a straight and perpendicular crossing of the Kent/ Cambridge corridor;

To optimise a clear and legible journey for vehicles, pedestrians and cyclists along

the bridge route; and

To optimise clear and legible journey and physical connections for vehicles,

pedestrians and cyclists under the bridge.

Be aligned vertically:

Comment [YW37]: Integration with what? This is redundant and needs deleting.

Deleted:

Page 14: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

14 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

To provide an elevated valley crossing in a manner that accentuates the reading of

existing topography;

To provide sufficient height to allow for the necessary head height for traffic

crossing under, but still be of the right height to visually within the Basin Reserve

fringe planting canopy, and the historical building scale of Kent/ Ellice corner; and

Be of a design language (form, material, character) that, while incorporating specific

local character responsive to local conditions that it traverses, also has recognisable

consistency across its length as a single element.

To achieve integration with its local context the bridge shall be considered and expressed as

5 different sub-components complementing a sequence of spaces and experiences,

including:

1. The Zone 1 landing - where abutments and bridge structure are integrated and

grounded in the form and material of the landscape terracing in this zone;

2. The Kent/ Cambridge crossing- where the bridge is a minimal and elegant ‘flying’

element crossing the Kent/ Cambridge corridor;

3. The Kent/ Ellice corner- where the bridge is integrated within the city block structure

along with new corner building and verandah to the footpath below;

4. The Hania/ Ellice/ Dufferin zone - where the bridge is an elevated curving transitional

element spanning between the corner of Kent Terrace and the Dufferin landing zone;

5. The Dufferin landing zone where abutments and structure are integrated and

grounded in the landscape;

6. The pedestrian and cycle clip-on provides access onto the bridge for these modes.

This addition allows the bridge to have a thin edge along the northern face thus

reducing its visual impact from the Kent Terrace and NWM Park approaches. Ensure

safe and functional access is provided for pedestrian & cyclists from Paterson Street

to connect with the NWM Park and into the city via Tory/ Taranaki Streets; and

7. The pedestrian and cycle clip on lands at Paterson Street on a solid retained

structure. The St Joseph’s Church side is planted with a climber to form a green wall.

The retaining wall extends up to provide the balustrade.

Zone 6 – Detailed design considerations

The design mechanisms to achieve integration, and contribute positive effects in terms of

visual amenity, quality of space (above and below bridge), and quality of experience (above

and below the bridge) includes:

Consistent design language in form, material and surface of constructed

components and adjacent constructed landscape/ building components.

Ground transition/ abutments to be designed in a manner that:

Read as extended (solid) landscape components capturing the flying end of the

bridge;

Comment [YW38]: This isn’t possible and needs deleting. It suggests some other forms on the bridge to do this that are not in the design.

Comment [YW39]: Need to know what the height is.

Deleted: integrate

Comment [YW40]: Not the right word

Comment [YW41]: Needs significant rewording to make sense.

Deleted: NWM Park

Comment [YW42]: Refer to specific zones in each of these sections so that there is an relationship with the rest of the schedule.

Comment [YW43]: ?

Comment [YW44]: What is this and why is not mentioned in this zone?

Comment [YW45]: Why is this not mentioned in this zone. This is a new element from the applicants existing design submission.

Comment [YW46]: This needs considerable more work.

Page 15: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

15 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Avoids undercroft under minimum 2.4m and forms high amenity accessible

circulation spaces adjacent to the abutment integrated with the landscape;

Are formed in response to lines of view and movement through and under the

bridge; and

Provide a design character that is integrated with the adjacent landscape.

Piers to be designed in a manner that:

Are sculptured as dynamic forms perceived and experienced ‘in the round’ at

different proximities and velocities;

The alignment and form is specifically responsive to sightlines and lines of

movement through and around the piers;

Express a design relationship to the landscape elements and abutments; and

Considers potential to incorporate seating as an integrated component.

Superstructure designed in a manner that:

Provides for long spans (approx 38 - 40m) reducing the number of piers, creating a

visually open and uncluttered groundscape;

Provides for minimal structural depth- and the ability to reduce the edge thickness to

achieve a fine perimeter profile- reducing the perceived visual width and depth;

Provides for articulated expressed form and texture to the undercroft; and

Provides for differentiated articulated expressed form at the transitions (i.e. curves,

connections to buttresses/ piers between pedestrian/ cycle and main bridge)

Perimeter elements/ top surface components (balustrades/ barriers/ screens), while

providing for necessary safety functions, shall be designed in a manner that:

Are visually integrated with the formal design and modulation of the superstructure,

while designed as low (visual) mass to achieve a fine perimeter profile;

Design infrastructure elements such as downpipes, electrical conduits etc, to

integrate into the structure of the bridge;

Minimise the interruption of outlook from the pedestrian bridge/ perception of

activity and life on the bridge;

Minimise the visual separation of vehicles and pedestrians/ cycles; and

Promotes the perception of bridge as ‘elevated street’- rather than motorway flyover,

by accentuating human scale elements and continuity with Buckle Street.

Provide for safety and give a strong perception of safety for the vehicles, pedestrians

and cyclists that use the bridge.

Lighting the bridge shall be designed in a manner that:

Provides lux levels in accordance with AS/NZS 1158 Lighting for Roads and Public

Spaces for the trafficable areas on the bridge surface and according to CPTED

principles but minimises glare to adjacent areas;

Comment [YW47]: What does this mean? Wouldn’t it be better to state a plan number for this?

Comment [YW48]: From the footpath from the road from the what sightlines?

Comment [YW49]: No relationship to the rest of the bridge?

Comment [YW50]: What does this mean?

Comment [YW51]: What about decent lux for the pedestrians and cyclist on the bridge?

Page 16: Schedule 1 Designation Zones and Elements...1 Proposed Conditions Lindsay Daysh v5 22.2.2014 Basin Bridge Project Wellington Northern Corridor RoNS Schedule 1 Designation Zones and

16 Proposed Conditions Lindsay Daysh v5 22.2.2014

Basin Bridge Project

Wellington Northern Corridor RoNS

Is integrated with the formal design and modulation of the bridge; and

Is integrated with the structure of boulevard lighting of the adjacent NWM Park and

undergrounding of Buckle Street. Pole and light fitting to match if possible.

Lighting below the bridge should be designed in a manner that:

Provides lux levels in accordance with AS/NZS 1158 Lighting for Roads and Public

Spaces for the trafficable and public space areas. Lux levels to meet CPTED principles

while minimising glare; and

Incorporates architectural lighting that highlights forms, surfaces and textures of the

superstructure, undercroft, piers and abutments in a manner that contributes

positive amenity to public areas from where the bridge can be seen and experienced.

Comment [YW52]: This is not the NWM Park. The park vehicle lighting will go into a tunnel. Are we meant to integrate with tunnel lighting.? Is there no integration with the lighting on Kent and Cambridge Terrace?