Schedule 061302013

2
Project name : YKK INDIA BAWAL FACTORY RENOVATION WORKS 20thMay2013 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 Manufactureing Drawing Manufacturing PH-1 1 Step 1 (S2 shft to PH-1) Piping Work Connection to Existing Main Piping Installation Machine Shifting by YKK GR1 GR2, GR3, GR15 GR5, GR8 2 STEP 2 (N2 shift to PH-1) Machine Shifting by YKK GR4, GR6, GR7 GR9, GR10 GR12, GR13, GR14 3 STEP 3 (S1 to Shift to S2) Piping Work Connection to Existing Main Piping Machine Shifting by YKK GR10, GR8 4 STEP 4 (S1 shft to N2 Temp) Machine Shifting by YKK GR1 5 STEP 5 (N1 shft to S1) Piping Work Connection to Existing Main Piping Piping Work Machine Shifting by YKK GR4, GR2, GR3 GR5, GR6 6 STEP 6 (N1 shift to S2) Machine Shifting by YKK GR7 7 STEP 7 (N2 shft S1) Machine Shifting by YKK GR1 5) 1) 4) 2) Shop Drawing N1 N2 S1 S2 3) Compressed AirBranch Piping Dismantling for N2 Area 1) New Main Compressed AirPiping for N2, S2 Area Drawing Approval 4 Make Quotation Shop Drawing Sep-14 PH-1 AHU Dismantling B Excution Work by YKK Aug-14 Existing Facility Servey Collection of Existing Drawings Design Desing/Equipment Order 5 7 Compressed AirBranch Piping Dismantling for S2 Area PH-1 New Compressed Air Piping 1) 1) Quotation Assesment 5) 4) 3) 6) 2) 1) EVENT New Main Compressed AirPiping for N1, S1 Area New Branch Compressed AirPiping for N2, S2 Area Electrical Distribution Panel Air Condtioning Work PH-1 Electrical Dismantling PH-1 Electrical Installation Material Order Jul-14 Order Jun-13 Jul-13 Aug-13 PH-2 1) Apr-14 Mar-14 Feb-14 May-13 Jan-14 Shop Drawing Material Order Shop Drawing 2) Compressed AirBranch Piping Dismantling for S1 Area New Branch Compressed AirPiping for S1 Area 3) 4) Oct-13 Nov-13 Dec-13 Material Order 1) 1 6 2 3 A 2014 Approval Material Order Air Conditioning Unit 2013 May-14 Jun-14 Sep-13

description

schedule

Transcript of Schedule 061302013

Project name : YKK INDIA BAWAL FACTORY RENOVATION WORKS 20thMay2013

5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30

Manufactureing

Drawing Manufacturing

PH-1

1 Step 1 (S2 shft to PH-1)

Piping Work Connection to Existing Main Piping

Installation

Machine Shifting by YKK GR1

GR2, GR3, GR15

GR5, GR8

2 STEP 2 (N2 shift to PH-1)

Machine Shifting by YKK GR4, GR6, GR7

GR9, GR10

GR12, GR13, GR14

3 STEP 3 (S1 to Shift to S2)

Piping Work Connection to Existing Main Piping

Machine Shifting by YKK GR10, GR8

4 STEP 4 (S1 shft to N2 Temp)

Machine Shifting by YKK GR1

5 STEP 5 (N1 shft to S1)

Piping Work Connection to Existing Main Piping

Piping Work

Machine Shifting by YKK GR4, GR2, GR3

GR5, GR6

6 STEP 6 (N1 shift to S2)

Machine Shifting by YKK GR7

7 STEP 7 (N2 shft S1)

Machine Shifting by YKK GR1

5)

1)

4)

2)

Shop Drawing

N1 N2

S1 S2

3)Compressed AirBranch Piping Dismantling for N2 Area

1)New Main Compressed AirPipingfor N2, S2 Area

Drawing Approval

4 Make Quotation

Shop Drawing

Sep-14

PH-1 AHU Dismantling

B Excution Work

by YKK

Aug-14

Existing Facility Servey

Collection of Existing Drawings

Design

Desing/Equipment Order

5

7

Compressed AirBranch Piping Dismantling for S2 Area

PH-1 New Compressed Air Piping

1)

1)

Quotation Assesment

5)

4)

3)

6)

2)

1)

EVENT

New Main Compressed AirPipingfor N1, S1 Area

New Branch Compressed AirPipingfor N2, S2 Area

Electrical Distribution Panel

Air Condtioning Work

PH-1 Electrical Dismantling

PH-1 Electrical Installation

Material Order

Jul-14

▼Order

Jun-13 Jul-13 Aug-13

PH-2

1)

Apr-14Mar-14Feb-14May-13 Jan-14

Shop Drawing Material Order

Shop Drawing

2)Compressed AirBranch Piping Dismantling for S1 AreaNew Branch Compressed AirPipingfor S1 Area

3)

4)

Oct-13 Nov-13 Dec-13

Material Order

1)

1

6

2

3

A

2014

Approval

Material Order

Air Conditioning Unit

2013May-14 Jun-14Sep-13

Project name : YKK INDIA BAWAL FACTORY RENOVATION WORKS 20thMay2013

5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30

Sep-14Aug-14Jul-14Jun-13 Jul-13 Aug-13 Apr-14Mar-14Feb-14May-13 Jan-14Oct-13 Nov-13 Dec-1320142013

May-14 Jun-14Sep-13

8 STEP 8 (PH-2 PFC shift to N2)

Machine Shifting by YKK GR4, GR2, GR3

GR5, GR6

9 STEP 9 (PH-2 PFC shift to N1)

Piping Work

Machine Shifting by YKK GR5, GR6, GR7, GR8

GR9

10 Dismantle Existing Main Pipe Line

Compressed AirBranch Piping Dismantling for N1 AreaNew Branch Compressed AirPipingfor N1 Area

Material OrderShop Drawing

3)

1)

2)