SCED Constraint Competitiveness Test ( CCT) Update Review of (10/1/2013 to 11/30/2013)

11
SCED SCED Constraint Competitiveness Test Constraint Competitiveness Test (CCT) Update (CCT) Update Review of (10/1/2013 to Review of (10/1/2013 to 11/30/2013) 11/30/2013) Market Analysis ERCOT

description

SCED Constraint Competitiveness Test ( CCT) Update Review of (10/1/2013 to 11/30/2013). Market Analysis ERCOT. Background of NPRR 520 (SCED CCT). Why Change? SCED over-mitigation issues What Changed? No Monthly and Daily Constraint Competitiveness Test (CCT) - PowerPoint PPT Presentation

Transcript of SCED Constraint Competitiveness Test ( CCT) Update Review of (10/1/2013 to 11/30/2013)

Page 1: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

SCED SCED Constraint Competitiveness Test (CCT) Constraint Competitiveness Test (CCT)

Update Update

Review of (10/1/2013 to 11/30/2013)Review of (10/1/2013 to 11/30/2013)

Market AnalysisERCOT

Page 2: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Background of NPRR 520 (SCED CCT)

Why Change?Why Change? SCED over-mitigation issues

What Changed?What Changed? No Monthly and Daily Constraint Competitiveness Test (CCT) SCED CCT runs every 5 minutes (or whenever SCED is

executed) Less set of Resources get mitigated Minimizing unnecessary Base Point oscillations/QSGR dispatch

January 7, 20142

CMWG

Page 3: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

System Lambda Increase (10/1-11/30)

January 7, 20143

CMWG

Page 4: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Mitigation Ratio

January 7, 20144

CMWG

Page 5: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Increased Peaker Net Margin (PNM)

January 7, 20145

CMWG

Page 6: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Pivotal Players For Each Active Constraint (10/1-11/30)

January 7, 20146

CMWG

Page 7: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Pivotal Players For Each Active Constraint (10/1-11/30) (continued)

January 7, 20147

CMWG

Page 8: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Top 10 Non-Competitive Constraints Based on Frequency (10/1-11/30)

January 7, 20148

CMWG

Page 9: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Constraints with Both Competitiveness Status (10/1-11/30)

CONTINGENCY_NAMECONTINGENCY_NAME CONSTR_NAMECONSTR_NAME FROM_STATIONFROM_STATION TO_STATIONTO_STATION FROM_STA_KVFROM_STA_KV TO_STA_KVTO_STA_KV Competitive_FreqCompetitive_Freq NonCompetitive_FreqNonCompetitive_Freq

UST2STP1 BLESSI_LOLITA1_1 LOLITA BLESSING 138 138 46 55SNEDLON5 MV_YUT_RAYMND1_1 RAYMND2 MV_YUTT 138 138 8 1SNEDLON5 LASPUL_RAYMND1_1 LASPULGA RAYMND2 138 138 779 265

SHOLHLJ5 155T217_1 BELLSO PT 138 138 15 22SGIBSNG5 SNGXGC99_1 GIBCRK SNG 345 345 23 38

SBOSWHT8 OLKW_BOS_1 BOSQUESW LKWHITNY 138 138 87 590SBOSELM5 1030__B BOSQUESW RGH 138 138 234 107DZORHAY5 KENDAL_AT4L KENDAL KENDAL 1 138 397 82

DZORHAY5 75T243_1 KENDAL COMFOR 138 138 10 237

DTB_SNG5 SNGZEN99_A SNG ZEN 345 345 5 226

DSNGZEN5 SNGTB_74_A SNG TB 345 345 594 1458DSALKLN5 610__B TMPSW TMPSE 138 138 49 357

DMARZOR5 428T428_1 SEGUIN SEGUWE 138 138 141 226

DJEWSNG5 JK_TOKSW_1 TOKSW JK_CK 345 345 215 289DGIBSNG5 260_A_1 JEWET SNG 345 345 44 489DGIBSNG5 240__A JEWET SNG 345 345 51 38

DBOEHA58 74T148_1 COMFOR CICO 138 138 59 240

DAUSLOS5 CKT_3122_1 FPPYD2 HOLMAN 345 345 25 2BASE CASE MATA_WEC1_1 MATA WEC 69 69 5 2

January 7, 20149

CMWG

Page 10: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Summary of Impact of NPRR 520

Prior to Implementation of

NPRR 520

After Implementation of NPRR 520

Jul-13 Aug-13 Sep-13 Oct-13 Nov-13

ECI Methodology sf*HSL sf*sf*HSL sf*sf*HSL sf*sf*HSL sf*sf*HSL sf*sf*HSL

ECI Threshold on The Export Side

3,000 N/A N/A N/A N/A N/A

ECI Threshold on The Import Side

2,500 2,300 2,300 2,300 2,300 2,300

Percentage of Mitigated Resources for Each SCED Interval

100% 4.80% 3.08% 5.73% 4.08% 2.42%

Average System Lambda Increase ($/MWh)

N/A 0.20 0.25 1.37 1.57 1.19

Cumulative PNM Increase ($/MW)

N/A 80.63 180.75 979.48 1,169.32 850.7

Total Number of Non-competitive Constraints

100% 95.00% 96.60% 88.20% 90.95% 85.64%

Non-competitive Constraints

ECI >= 2300 N/A N/A 95.6% 88.3% 73.05% 84.08%Pivotal Players Exist N/A N/A 31.1% 34.5% 21.39% 3.49%

No SF <= -0.02 N/A N/A 1.1% 1.9% 10.76% 3.28%

January 7, 201410

CMWG

Page 11: SCED  Constraint Competitiveness  Test  ( CCT)  Update  Review of (10/1/2013 to 11/30/2013)

Thanks!Thanks!