Transcript of SCCL Corporate safety accident analysis 2006 2011 may
![Page 1: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/1.jpg)
WELCOME TO
WORKSHOP ON DESIGN OF SUPPORT PLAN AND
STANDARDIZATION OF STRATA CONTROL INSTRUMENTS
![Page 2: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/2.jpg)
ACCIDENT ANALYSIS FROM 1-JAN,2006 TO 31-05-2011.
&CAUSES AND STEPS TO CONTROL ROOF &
SIDE FALL ACCIDENTS.
BY
ISO CORPORATE
![Page 3: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/3.jpg)
THE CAUSE WISE ANALYSIS OF ACCIDENTS Jan.06-May.11.Cause
BELOW GROUND OPENCAST ABOVE GROUND Total
F S R F S R F S R F S R
FALL OF ROOF 21 85 143 21 85 143
FALL OF SIDES 9 102 294 9 102 294
OTHER FALLS OF GROUND 1 19 2 1 2 1 20
OVER WINDING OF CAGES/SKIPS ETC
OTHER ACCIDENTS/DANGEROUS OCCURANCES DUE TO WINDING
ROPE HAULAGE 14 226 146 1 14 226 147
CONVEYORS 1 20 10 1 2 2 12 7 4 34 17
DUMPERS 7 16 11 7 16 11
OTHER WHEELED TRACKLESS 1 3 3 1 3 5 4 6 9 5
OTHER NON-WINDING MACHINERY 1 1 1 1
HEMM other than dumpers 7 6 9 1 7 7 9
OTHER MACHINERY 27 30 2 10 3 39 33
EXPLOSIVES 4 4 3 7 4
ELECTRICITY 2 2 4 1 10 1 2 3 3 16
SPONTANEOUS HEATING
OTHER ACCIDENTS/DANGEROUS OCCURRANCES DUE TO DUST/GAS/FIRES 1 1 2
FALL OF PERSONS 1 551 1267 37 33 83 87 1 671 1387
FALL OF OBJECTS 435 1474 1 13 12 80 117 1 528 1603
OTHERS (FALLS OTHER THAN GROUND MOVEMENT) 4 7 4 7
OTHER THAN ABOVE 1 562 1174 1 29 33 3 135 174 5 726 1381
Total 49 2020 4574 23 112 110 8 327 396 80 2459 5080
![Page 4: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/4.jpg)
PLACE WISE FATALITIES/INJURIES UNDER GROUND
FATALITIES- 49, SERIOUS-2022, REPORTABLE-4576
OPENCASTFATALITIES-23, SERIOUS-112,
REPORTABLE-112ABOVE GROUND
FATALITIES-8, SERIOUS-327, REPORTABLE-397
![Page 5: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/5.jpg)
CAUSE WISE UNDERGROUND ACCIDENTS
CAUSE F S RFALL OF ROOF 21 85 143FALL OF SIDES 9 102 294ROPE HAULAGE 14 226 146CONVEYOURS 1 20 10ELECTRICITY 2 2 4FALL OF PERSONS 1 552 1268OTHER THAN THE ABOVE 1 562 1174
TOTAL 49 2022 4576
![Page 6: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/6.jpg)
PERCENTAGE OF CAUSE WISE FATALITIES & SEROUS ACCIDENTS IN
BELOW GROUND CAUSE FATAL SERIOUS
FALL OF ROOF&SIDES 30 61.23% 187 9.25%
ROPE HAULAGE+CONV 15 30.51% 246 12.17%
ELECTRICITY 2 4.08% 2 0.10%
OTHERS 2 4.08% 1289 78.48%
![Page 7: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/7.jpg)
FALL OF ROOF AND SIDES PLACE WISE ANALYSIS
FATAL SERIOUSDEVELOPMENT 4 60DEPILLARING 23 106LONGWALL --- 10OTHER PLACES 3 11 TOTAL 30 187
![Page 8: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/8.jpg)
DESIGNATION WISE ANALYSIS
1. SUPERVISORS/MANAGEMENT 32. LOADERS/COAL FILLERS 83. SUPPORT/TIMBERMEN 94. DRESSORS 15. OTHER BG FACE WORKERS 16. FITTERS 17. OTHER OPERATORS 18. OTHER DESIGNATIONS 6 TOTAL 30
![Page 9: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/9.jpg)
BODY WISE INJURIES ANALYSISHEAD INJURIES 13EYES 1BACK 2CHEST 5SPINAL COLUMNS 1UPPER LIMBS 1LOWER LIMBS 1OTHER PARTS OF BODY 6
TOTAL 30
![Page 10: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/10.jpg)
REASONS FOR ROOF & SIDE FALL
ACCIDENTS.
![Page 11: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/11.jpg)
PLANNING ISSUES IN DEVELOPMENT
DEVLOPMET WITH OUT CONSIDERING FLOOR CONTOURS.
NOT FRAMING SSR IN SCIENTIFIC WAY. WIDER GALLARIES & INADEQUATE SUPPORTS. STABILITY OF SIDES & SUPPORT DESIGN. VALIDATION OF RMR & SUPPORT PLANS. DESIGN OF SUPPORT SYSTEMS FOR
GEOLOGICALLY DISTURBED AREAS. TRAINING & SKILL IMPROVEMENT.
![Page 12: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/12.jpg)
2.PLANNING ISSUES IN DEPILLARING PANELS
WIDER PANELS /LONGER DIAGONAL LENGTHS. WIDER GALLERIES. MORE HEIGHT OF EXTRACTION. LONGER DURATION OF SLICING /SLOW RATE OF EXTRACTION. INDUCED BLASTING TO PREVENT HANGING GOAF. IMPROPER STOWING SYSTEMS. INFERENCING THE DATA COLLECTED FROM INSTRUMENTATION. NON COMPLAINCE OF PERMISSION CONDITIONS.
![Page 13: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/13.jpg)
3.IMPLEMENTATION ISSUES TESTING AND DRESSING OF ROOF & SIDES
BEFORE & WHILE WORKING. INSPECTION,TESTING,DRESSING & SUPPORT
OF TRAVELLING AND HAULAGE ROADS. INADEQUATE TEMPORARY SUPPORTS. MISS JUDGEMENT BY MINE OFFICIALS. TESTING OF ROOF BOLTS & ROPES. TIGHTNESS OF SUPPORTS. SUPPORT CYCLE IN MINES. MEETINGS WITH MINE OFFICIALS. INTERACTION WITH SUPPORTMEN etc.
![Page 14: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/14.jpg)
CORRECTIVE ACTIONS SUGGESTED
103 CIRCULARS WERE ISSUED TO CONTROL ACCIDENTS FROM ROOF & SIDE FALLS,METHOD OF WORKING etc.
STANDARDIZING ROOF BOLTING METHODS. MECHANIZED DRILLING FOR BOLTING. SWITCHING OVER TO RESIN GROUT IN ALL
PLACES. TESTING GROUT MATERIALS & BOLTS. CALCULATING FRESH RMR OF ROOF AND RE-
DESIGNING SSR SCIENTIFICALLY.
![Page 15: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/15.jpg)
CORRECTIVE ACTIONS SUGGESTED.
SUPPORT REQUIREMENTS OF SIDES. FRAMING OF EFFECTIVE SAFETY
MANAGEMENT PLAN FOR EVERY ACTIVITY IN THE MINE & IT’S IMPLEMENTATION.
REVIEW SOPs PERIODICALLY AND UP-DATE AS SUTUIATION WARENTS.
STANDERDIZATION OF MONITORIG INSTRUMENTS.
UTILIZING THE INFORMATION FROM PREVIOUS EXPERIENCES.
![Page 16: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/16.jpg)
Concern for man and his fate must always form the chief interest of all technical endeavors. Never forget this in the midst of your diagrams and equations. Albert Einstein
![Page 17: SCCL Corporate safety accident analysis 2006 2011 may](https://reader036.fdocuments.us/reader036/viewer/2022082721/58cfa14c1a28ab6b088b4c5b/html5/thumbnails/17.jpg)
Thank you