S.C. Srivastava, Professor Departmentof Electrical...
Transcript of S.C. Srivastava, Professor Departmentof Electrical...
S.C. Srivastava, Professor Departmentof Electrical Engineering
Indian Institute of Technology Kanpur Email: [email protected]
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA 1
Contents Recent Changes in Power system Networks
Overview of Indian Power Sector
Grid Integration of Renewable Energy Sources (RES): Key Issues
System Wide Impact of Large Penetration of RES
Impact of Wind Penetration and Dynamic Loads on Stability
Planning SVC to Mitigate Instability
Decentralized Wide Area Damping Controller Development
Concluding Remarks
9 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Recent Changes in Power system Networks
• Use of New Materials - Polymeric, Composite, Nano, Superconducting materials.
• Use of Alternate and Renewable Energy Sources to address Global Environmental Concerns
• Development of New Power Electronic Devices, DSP, Sensors, Information & Communication Technology
• IT Enabled Services for maintaining system Security, Reliability and Resiliency- Modern SCADA, Wide Area Monitoring system, Smart Grid
• Regulatory Changes in the Electricity Sector – Electricity Market.
3 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA 4
PHASOR DATA CONCENTRATOR
APPLICATION SOFTWARE
SYSTEM CONTROL CENTER
MONITORING CONTROL DATABASE
PMU
GPS
PMU
PMU PMU
PDC
PDC SUPER PDC
Synchrophasor based WAMS for Smart Transmission Grid
Time synchronized phasor data with high accuracy
Provides phasors within an interval of 20/40 ms (50 Hz System)
Suitable for observing the system under dynamic conditions
Suitable for real time monitoring, control and protection
5 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Distributed Energy Resources (DERs) Distributed Generations using Renewable Technologies
Photovoltaics
Solar thermal
Small wind systems (upto 50 kW)
Large wind systems (ranging upto 1-2 MW)
Biomass etc.
6
Storage Technologies
Mechanical (Pumped storage, Compressed air, Fly wheel)
Electrical (Super capacitor, SMES)
Chemical (Fuel cell)
Electrochemical Batteries (Lead Acid, Li-Ion, Flow, Sodium/Zinc)
SC Srivastava International Workshop on CPS 25-26 March, 2017 IIT Kanpur
An Overview of Indian Power Sector Installed Gen. Capacity as on 30th April, 2017
Source: www.cea.nic.in
Fuel MW %age
Total Thermal 220569.88 67.0
Coal 194402.88 59.0
Gas 25329.38 7.7
Diesel 837.63 0.3
Hydro (Renewable) 44594.42 13.5
Nuclear 6780.00 2.1
RES** (MNRE) 57260.23 17.4
Total 329204.53
**Renewable Energy Sources(RES) include Small Hydro, Bio-mass/gas, Urban & Ind. Waste
Sector MW %age
State Sector 104447.28 31.7
Central Sector 81167.25 24.7
Private Sector 143590.01 43.6
Total 329204.53
All India Thermal Plant Load Factor : 65.59% (April 2017)
7
North-Eastern
Region
Western
Region
Northern
Region
Southern
Region
Eastern
Region
High Voltage Transmission Capacity (as on 30-04-17)
(220kV & above about 3,69,650 ckt. km)
Capacity MVA Circuit km
765/800 kV 170500 31616
400 kV 243307 159058
220 kV 314503 163420
HVDC 19500 15556
Map of India in Five Regions (regions are shown separated for sake of clarity)
8
Inter-regional capacity: 75,050 MW
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Non Conventional Energy In India (as on 31st March, 2017)
• 3900 MW in 2002 to 57244.23 MW in March 2017 (Grid Connected)
Wind : 32279.77 MW (Onshore potential 49130 MW)
Small Hydro : 4379.85 MW
Bio-power : 8181.70 MW (Biomass, Gasification & Bagasse)
Waste to power : 114.08 MW
SPV : 12288.83 MW (100 GW by 2022)
• Off-grid : 1468.95 MW (Source: http://www.mnre.gov.in/mission-and-vision-2/achievements/)
9 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
System Operation (at present)
10
• At regional level – Five RLDCs viz. NRLDC, SRLDC, ERLDC, WRLDC and NERLDC, and at national level NLDC.
• All regional power grids are synchronized (NEW grid)
• RLDCs and NLDCs owned by POSOCO New Delhi.
• Two exchange in operation viz. Indian Energy Exchange (IEX), and Power Exchange India Limited (PXIL)
• Frequency linked ABT for Unscheduled Interchange (UI) to improve grid discipline (at regional levels).
• Synchrophasor based WAMS being deployed in Regional grids. (URTDMS Project of PGCIL). About 1700 PMUs planned.
• NSGM to promote Smart Grid activities.
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Renewable Generation: Few Technical Challenges
11 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Intermittent generation dependent on weather, season, time of day–Need accurate forecasting & Power balancing .
Voltage and frequency control; Many of these sources do not have reactive power generation.
Sudden generation loss can lead to angle and voltage instability. Also inertia less generation, e.g. solar.
Power Quality issues-Harmonics, flicker, under voltage ride through capability (IEEE & IEC standards)
Power management and Maximum power point tracking. Requires proper converters and controls.
References: 1. Vignesh V., „Improved Load Modelling and its Impact on Stability of Power Systems having Large
Penetration of Wind Generation‟, Ph.D. Thesis, IIT Kanpur, March 2016.
2. Vignesh V, S. C. Srivastava and S. Chakrabarti, “A Robust Decentralized Wide Area Damping
Controller for Wind Generators and FACTS Controllers Considering Load Model Uncertainties”,
accepted for publication in IEEE Trans. on Smart Grid, , Early access DOI: 10.1109/TSG.2016.2552233.
Region Wise Installed Generation Capacity in
India (CEA Report, April 2017)
Region Installed Capacity in MW
RES Total
Northern 11539.36 90241.59
Western 18304.43 108418.96
Southern 26132.07 91808.36
Eastern 990.74 34752.87
North-Eastern 281.12 3930.19
Islands 12.52 52.57
TOTAL 57260.23 329204.53
12 States like Tamilnadu, Gujarat and Rajasthan have high penetration of wind generation.
Ref: POSOCO Report on “Flexibility Requirement in Indian Power System” , January 2016. 13
Ref: POSOCO Report on “Flexibility Requirement in Indian Power System” ,
January 2016. 14
Few Possible Solutions/RD&D Needs at Grid Level
Transmission planning to cater for renewable generation- Green Corridor in India.
Flexible generation/load management.
Proper planning of Flexible AC Transmission System (FACTS) controllers, SVC/STATCOM.
Regulatory mechanism to promote renewables.
Balancing mechanism, Ancillary service market development.
SCADA with renewable desk.
Synchrophasor technology based Wide Area monitoring and Control, employing Phasor Measurement Units.
15 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Power System Stability
Frequency
Stability
Small-Signal
Stability
Transient
Stability
Short
Term
Long
Term
Large-
Disturbance
Voltage Stability
Small-
Disturbance
Voltage Stability
Voltage
Stability
Rotor Angle
Stability
Considerat-
ion for
Classification
Physical
Nature/ Main
System
Parameter
Size of
Disturbance
Time
Span
Short Term
Short
Term
Long
Term
P. Kundur, J. Paserba, V. Ajjarapu, G. Andersson, A. Bose, C. Canizares, N. Hatziargyriou, D. Hill, A. Stankovic, C. Taylor, T. V. Cutsem, and V. Vittal, "Definition and classification of power system stability IEEE/CIGRE joint task force on stability terms and definitions," IEEE Transactions on Power Systems, vol. 19, no. 3, pp. 1387-1401, Aug. 2004.
16
Study on Impact of Large Wind Penetration on System Stability
The impact of different level of wind penetration (5-20%) on system stability was first studied on NRPG system.
The NRPG system used (400 kV, 765 kV and few 220 kV buses retained) had a total generation of around 17000 MW and total load of around 16500 MW .
Wind Parks assumed at Udaipur, Jodhpur, Banswara and Bikaner of 850 MW, (5% of the total generation).
Constant MVA models for loads were first considered.
DSA tool from Power Tech was used for simulation.
The disturbance simulated was to disconnect the wind generation at these buses.
.
17 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
18
Study System-WPP Considered in Rajasthan
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Generator Angles and Bus Voltages for 15 Percent
Wind Penetration
19
0 10 20 30 40 50 60 70 80 90 100-80
-60
-40
-20
0
20
40
60
Time (sec)
Ge
ne
rato
r A
ng
les
in
de
g
Generator Angles with 15% Penetration
Hardwaganj
Tanakpur
Chamera
Uri
Bhakra RL6
Bhakra RL2
Bhakra RR2
Dehar 2
Siul
Dehar 4
pong
Theing
Dadri
Paricha
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
0 10 20 30 40 50 60 70 80 90 1000.5
0.6
0.7
0.8
0.9
1
1.1
1.2
Time (sec)V
olt
ag
e M
ag
nit
ud
e (
p.u
.)
Bus Voltage Magnitude with 15% Penetration
Ajmer
Bhiwandi
Bhilwara
Bikaner
Bilara
Jaipur
Jodhpur
Ketri
Kota
Siron
Paricha
Generator Angles and Bus Voltages for 18 Percent
Wind Penetration
20
0 10 20 30 40 50 60 70 80 90-200
0
200
400
600
800
1000
1200
1400
1600
1800
Time (sec)
Ge
ne
rato
r A
ng
les
in
de
g
Generator Angles with 18% of Wind Penetration
Hardwaganj
Tanakpur
Chamera
Uri
Bhakra RL6
Bhakra RL2
Bhakra RR2
Dehar 2
Siul
Dehar 4
Pong
Theing
Dadri
Paricha
With 18 % penetration of the wind, after the
disturbance the generator at Paricha goes into
instability
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
0 10 20 30 40 50 60 70 80 900.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
Time (sec)
Vo
lta
ge
Ma
gn
itu
de
(p
.u.)
Bus Voltage Magnitude with 18% Wind Penetration
Ajmer
Bhiwandi
Bhilwara
Bikaner
Bilara
Jaipur
Jodhpur
Ketri
Kota
Siron
Paricha
Generator Angles and Bus Voltages for 13% wind penetration
and detailed load models (dynamic and static loads)
21
0 10 20 30 40 50 60 70 80-200
0
200
400
600
800
1000
Time in Seconds
Ge
ne
rato
r A
ng
les
in
de
gre
es
Generator Angles for 13% Wind Penetration with detailed load models
Paricha
Uri
BhakraRL6
BhakraRL2
Hardwaganj
Siul
Chamera
Pong
Theing
Dadri
BhakraRR2
Dehar2
Kota
Dehar4
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
0 10 20 30 40 50 60 70 800.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
Time in seconds
Vo
lta
ge
in
p.u
.
Voltage magnitude for 13% penetration with detailed load models
Kanpur
Allahabad
Jaipur
Noida
Kota
Ballabhgarh
Ratangarh
Auriya
Paricha
Jaisalmer
Agra
Jalandhar
Amritsar
Ludhiana
Effect of Control Actions
To restore the system stability, measures adopted are:
1. Ramp up of real power output of other generators
2. Reactive power management to mitigate voltage
stability issues.
3. Load shedding.
Initially ramp up of real power and load shedding controls were considered.
The ramp up of real power was done by changing the reference setting of the governor.
The output of generators at Thankpur, Urig, Chamra, Bhakranagal, Ropar, Dadri, Siul, Theing were ramped up.
22 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Generator Angles and Bus voltages after Power Ramp-up
for loss of 18% wind generation
23
0 50 100 150-80
-60
-40
-20
0
20
40
Time (sec)
Ge
nra
tor
An
gle
s in
de
g
Generator angles after power ramp up
Hardwaganj
Tanakpur
Chamera
Uri
Bhakra RL6
Bhakra RL2
Bhakra RR2
Dehar 2
Siul
Dehar 4
Pong
Theing
Dadri
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
0 50 100 1500.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
Time (sec)
Volta
ge
Ma
gn
itud
e (
p.u
.)
Bus voltage magnitude after generator ramp up
Ajmer
Bhiwandi
Bhilwara
Bikaner
Bilara
Jaipur
Jodhpur
Ketri
Kota
Siron
Case Study-Shedding of the loads
Both real and reactive loads were shed at all the buses.
The loads were shed till the system voltage and generator angles stabilized.
It was observed that even without shedding of loads completely to compensate for 3000 MW of wind power loss (18 % of total generation), the system stabilized.
It was observed that the amount of load to be shed to stabilize the system for 18% loss of wind generation was around 1700 MW( 11% of the total load)
24 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
25
0 50 100 150-80
-60
-40
-20
0
20
40
60
80
Time in Seconds
Ge
ne
rato
r A
ng
le in
de
gre
es
Generator angles after Load Shedding
Paricha
Dehar4
Uri
Bhakra RL6
Bhakra RL2
data6
Hardwaganj
Siul
Chamera
Pong
Theing
Dadri
BHAKRA RR2
Dehar2
Tanakpur
Generator Angles and Bus Voltages after load shedding
SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
0 50 100 1500.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
Time (sec)
Vo
lta
ge
Ma
gn
itu
de
(p
.u.)
Bus Voltage Magnitude with load shedding
Ajmer
Bhiwandi
Bhilwara
Bikarner
Bilara
Jaipur
Jodhpur
Ketri
Kota
Siron
Paricha
Bus Voltages stabilize after
the load shedding
Planning of SVCs to Mitigate Voltage Instability with High Wind Penetration
1. Static Var Compensators (SVCs) are shunt dynamic reactive power
compensators.
2. Methodologies proposed to determine the location and sizes of the
SVCs in presence of wind power plants and dynamic loads.
3. A sensitivity index for determining the effective locations of the
SVCs, to enhance the damping of the voltage modes, is proposed.
4. The optimal sizes of the SVCs were determined by a hybrid
optimization technique in order to mitigate voltage instabilities.
5. Supplementary controller for the optimally placed SVCs was
designed to improve the damping of the electromechanical modes.
6. Tested on three systems
26 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Composite Load Model Used
Primary distribution level
Transmission level
j
Bss
LM
MM
AC motor
R+jX
2
B1 jB
Static
27 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Steps Used:
• Determination of set of critical contingencies- damping ratio based index
• Determination of optimal locations of SVCs-sensitivity approach
• Determination of sizes of SVCs –Optimization approach
• Design of supplementary damping controller-Optimal algorithm
Simulation Studies
• The proposed method is implemented on three test systems. • The results for NRPG system is presented.
• NRPG system is a reduced network of a practical power system in India, containing 220 and 400 kV networks with 246 buses,376 branches (lines/transformers), 42 generating stations with 60 machines, and 40 reactors.
• A total wind penetration of 25 % is assumed, with the wind turbines placed at the buses 160, 161, 162, 163, 164, 165, 168, 174, 177, and, 178, each of 500 MW capacity.
• 10 critical contingencies were identified, method gave 10 optimal locations of SVCs
28 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Table : Most critical contingencies in NRPG System
S.N0. Contingency Rank
1 Ballabgarh-Kanpur line (233-239) outage 1
2 Rihand generator outage (Bus 41) 2
3 Dadri generator outage (Bus 38) 3
4 Ballabgarh- Dadri line (233-235) outage 4
5 Ropar generator outage (Bus 13) 5
6 Agra-Kanpur line (234-239) outage 6
7 Lucknow- Sultanpur line (211-217) outage 7
8 Bhakranangal generator Outage (Bus 6) 8
9 Sitapur-Lucknow line (188-190) outage 9
10 Udaipur- Chithorgarh line (168-170) outage 10
29 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Table: Critical eigenvalues for the outage of Agra-Kanpur line
(234-239) in NRPG System
S.N0 Eigenvalue Damping (%) Frequency(Hz)
1 0.6824+j56.86 -1.20 9.05
2 0.5852+j55.7319 -1.05 8.87
3 0.54460+57.3278 -0.95 9.18
4 0.4043+j57.8363 -0.78 8.25
5 0.2865+j55.1035 -0.52 8.77
6 0.1321+j55.0407 -0.24 8.76
7 0.0559+j55.8579 -0.10 8.89
8 -0.0802+j57.3027 0.14 9.12
30 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Simulation Studies (without and with SVCs)- Three Phase Fault
(a) 1.5
1
0.5
0 0 5 10 15 20 25 30 35
(b) 1.2
1
0.8
0.6
0.4 0 5 10 15 20 25 30 35
Time in s
Figure: Few load bus voltages in NRPG system, following a three
phase fault in Kanpur-Ballabgarh 400 kV line (233-239).
Vo
lta
ge
in
p.u
. V
olt
ag
e i
n p
.u.
31 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Similar results found with generator outage.
Simulation Studies without and with SVC- Wind Generators Outage
(a)
1
0.9
0.8
0.7
0.6
0.5
0.4
15 16 17 18 19
Time in s
20 21 22 23
(b) 1
0.9
0.8
0.7
0.6
0.5
0.4
0.3 0 5 10 15 20 25 30 35 40 45
Time in s
Figure : Voltage at Jaipur (Bus 40), following the outages of two wind
generators
Vo
lta
ge
in
p.u
. V
olt
ag
e in
p.u
.
32 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Decentralized Wide Area Damping Controller Considering Load Model Uncertainties
• A decentralized wide area damping controller proposed for the
wind farms and FACTS considering uncertainties in the load parameters through the Monte-Carlo simulations..
• A robust H∞ output feedback controller is, then, designed for the uncertain fuzzy system by satisfying Linear Matrix inequalities (LMIs).
• Practical issues such as input signal latency has been considered in this work.
• Input/output signal selection using joint controllability-observability index and input time delay compensated through state prediction using Extended Kalman Filter (EKF)
• Tested on two test systems.
33 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Figure : A typical decentralized wide area control architecture
Δω Y1 G- PMU-1 +
Y2
Exciter AVR-1
Y
1 +
WADC-1
PMU-2 DFIG WADC-2
POWER
SYSTEM
PMU-K SVC WADC-N
Y K
TDC
TDC
TDC
CPSS-1
34 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Steps in Proposed Methodology
1. Choice of control architecture-Decentralized. 2. Wide area signal selection.
3. System reduction. 4. Controller design. 5. Non-linear simulations.
Input-Output Signals in SRPG System
Table : Critical eigenvalues in the SRPG system and input-output signals for decentralized controllers
S.N0 Eigenvalue Input Signal Output Signal
1 -0.0186+j2.324 P7361−8504 , P7351−7353 Wind Plant at 7408
2 -0.0369+j3.051 P7357−9801 , P7356−8505 TCSC in 7353-7354
3 -0.0539+j2.915 P7358−8509 , P736−921 Wind plant at 8981
4 -0.0947+j3.9458 P7368−8511 , P7408−8643 Wind plant at 9855
5 -0.1070+j3.6820 P7327−9208 , P7551−8522 SVC at 7558
35 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Three Phase Fault
500
400
300
200
100
0
-100
-200
-300 0 5 10 15 20
Time in s
25 30 35 40
Figure : Power flow in tie line following a three-phase fault at a bus in
SRPG system (Similar results observed for most critical line outage)
Real
po
we
r fl
ow
in
tie
lin
e i
n M
W.
CPSS
CPSS+LOCAL PWADTFC
36 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Real Time Validation on RTDS
Satellite
GPS clock
Input Signal
GTNET
PMUs
Workstation
Wide Area Damping
Figure : Software in loop implementation of the proposed controller in RTDS
RTDS
Control Signal
Delayed Signal
Extended Kalman Filter
Based Delay
Compensator
Delay Compensated
Signal
Proposed Decentralized
Controller
37 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Impact of Time Delay Compensation
900
800
700
600
500
400
12 14 16 18 20
Time in s
22 24 26 28 30
Figure : Power flow in line 15-16 following loss of load at bus 21 in NE
39 bus system
Real p
ow
er
flo
w in
lin
e 1
5-1
6 in
MW
Without TDC
With TDC
38 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
Conclusions Future power system expansion will have large deployment of
Distributed Energy Resources containing renewable sources, predominantly solar and wind based generations.
Solar and wind generation intermittency will pose system stability challenges. This may worsen in presence of dynamic induction motor loads.
Apart from flexible generation and ample storage for system power balancing, proper controls such as use of FACTS controllers are required to improve the system stability.
Use of synchrophasor based wide area damping control will help in damping system oscillations under disturbances.
39 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA
40 SC Srivastava/IITK NETRA-Conference on 'Green Power-Challenges and Innovations' 9th June, 2017 NTPC-PMI, NOIDA