School Board Meeting
July 6, 2010
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 2/23
Purpose
• Establish the background for Board discussion
through providing information about 4 options forhousing students from the Blacksburg Strand for
the 2010-2011 school year
• Identify a housing option for the Blacksburg Strandfor the 2010-2011 school year
• Establish the background for Board discussion
about a delay in school start date for the 2010-2011
school year
•Identify the calendar for the 2010-2011 school year
2
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 3/23
Summary of the Four Options• BMS facility houses grades 7-12 and grade 6 remains
at the respective elementary schools
• OCMS facility houses grades 9-12 and becomes thetemporary home for BHS; BMS facility houses
students in grade 6-8
• OCMS facility houses grades 6-8 and becomes the
temporary home for BMS; BMS facility houses grades
9-12 and becomes the temporary home for BHS• CMS facility houses grades 6-8 from Christiansburg
and grades 6 and 7 from Blacksburg; BMS facility
houses grades 8-12 in Blacksburg.3
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 4/23
BMS facility houses grades 7-12 and grade 6
remains at the respective elementary schools
• 47 portables at BMS
• Lose 2 PhysicalEducation and
Community Use Sports
Fields
4
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 5/23
BMS facility houses grades 7-12 and grade 6 remains
at the respective elementary schoolsCriteria Matrix BMS 7-12 6th Grade at Elem. Factor Associate Cost
Safety X √ Total Students 1729
Instructional program (Non Voc.) √- √ Less Capacity 1200
Transportation Cost √ √ Additional Students 529/144%
Transportation Time √ √ # of Mobiles 36-47/11
Food Services Program √ √ Purchase of Mobiles $2,444,000
Library/Media √ √ Lease of Mobiles $978,070
Additional Staffing Needs √ X Facilities Upgrades $25,000
Fine Arts √- √- Parking
Instructional Program (Vocational) √ X Science Labs $25,000
Family Issues √ √ Technology $259,000
Instructional Time √ √ School Nutrition $55,000
Technology √ √- Transportation
Keep Students in Blacksburg √ √ Relocate OCMS Staff Move the least number of students √ √ Moving teachers $103,500
Keep 9-12 and 6-8 together X X Overtime services $40,000
Extracurricular √- √
Traditional High School Schedule √ NA Moving Cost $44,000
Doesn’t disrupt middle school X X
Ready by September 6, 2010 ? √- Total Cost Purchase $2,995,500
Cost to provide option X X Total Cost Lease $1,529,5705
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 6/23
OCMS facility houses grades 9-12 and
becomes the temporary home for BHS; BMS
facility houses students in grade 6-8
• 29 Mobile Units
• Loss of 2 outdoorPhysical Education
fields (all field space)
currently used byschools, parks and
recreation and the
community at large
6
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 7/23
OCMS facility houses grades 9-12; BMS facility
houses students in grades 6-8
Criteria Matrix BHS 9-12 @ OCMS Factor Associate CostSafety X Total Students 1117
Instructional program (Non Voc.) X Less Capacity 775
Transportation Cost X Additional Students 342/144%/74%
Transportation Time X # of Mobiles 29
Food Services Program X Purchase of Mobiles $1,508,000
Library/Media √- Lease of Mobiles $603,490
Additional Staffing Needs √ Facilities Upgrades $250,000
Fine Arts X Parking $100,000
Instructional Program (Vocational) √ Science Labs $100,000
Family Issues X Technology $187,000
Instructional Time √ School Nutrition $450,000
Technology X Transportation $146,910
Keep Students in Blacksburg X Relocate OCMS Staff $34,500
Move the least number of students X Moving teachers $76,500
Keep 9-12 and 6-8 together √ Overtime services $20,000
Extracurricular X
Traditional High School Schedule √ Moving Cost $30,000
Doesn’t disrupt middle school √
Ready by September 6, 2010 X Total Cost Purchase $2,902,910
Cost to provide option X Total Cost Lease $1,998,400
7
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 8/23
OCMS facility houses grades 6-8 and becomes the
temporary home for BMS; BMS facility houses grades
9-12 and becomes the temporary home for BHS.
• 12 mobile units
• Loss of ½ of one majoroutdoor playing field
8
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 9/23
OCMS facility houses grades 6-8;
BMS facility houses grades 9-12Criteria Matrix BMS @OCMS Factor Associate Cost
BHS 9-12 @BMS BMS @ OCMSSafety √- Total Students 1117 883
Instructional program (Non Voc.) √ Less Capacity 1200 775
Transportation Cost X Additional Students 0 108/114%/93%
Transportation Time X # of Mobiles 4 10-12
Food Services Program X Purchase of Mobiles $208,000 $520,000
Library/Media √- Lease of Mobiles $83,240 $208,100
Additional Staffing Needs √ Facilities Upgrades $150,000
Fine Arts √ Parking $130,000
Instructional Program (Vocational) √ Science Labs $25,000
Family Issues X Technology $100,000
Instructional Time √ School Nutrition $450,000
Technology X Transportation $146,910
Keep Students in Blacksburg X Relocate OCMS Staff $34,500Move the least number of students X Moving teachers $76,500 $54,000
Keep 9-12 and 6-8 together √ Overtime services $5,000 $15,000
Extracurricular √-
Traditional High School Schedule √ Moving Cost $24,000 $24,000
Doesn’t disrupt middle school √-
Ready by September 6, 2010 √- Total Purchase Cost $1,962,910
Cost to provide option X Total Lease Cost $1,526,250
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 10/23
CMS facility houses grades 6-8 from Christiansburg
and grades 6-7 from Blacksburg,
BMS facility houses grades 8-12 in Blacksburg
12 mobile units at CMS
No field space lost
10
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 11/23
CMS facility houses grades 6-8 from Christiansburg
and grades 6-7 from Blacksburg,
BMS facility houses grades 8-12 in Blacksburg
12 mobile units at BMS
No field space lost
11
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 12/23
CMS facility houses grades 6-8 from Christiansburg and grades
6-7 from Blacksburg, BMS facility houses 8-12 in BlacksburgCriteria Matrix BHS 8-12/CMS 6-7 Factor Associate Costs
BHS 8-12 @BMS BMS 6-7 @CMS
Safety √ Total Students 1412 1410
Instructional program (Non Voc.) √ Less Capacity 1200 1200
Transportation Cost X Additional Students 212/118% 210/118%
Transportation Time X # of Mobiles 12-14 12-14
Food Services Program √ Purchase of Mobiles $624,000 $624,000
Library/Media √ Lease of Mobiles $249,720 $249,720
Additional Staffing Needs √ Facilities Upgrades
Fine Arts √ Parking $130,000
Instructional Program (Vocational) √ Science Labs $25,000
Family Issues X Technology $43,000 $43,000
Instructional Time √ School Nutrition
Technology √ Transportation $146,910
Keep Students in Blacksburg X Relocate OCMS Staff
Move the least number of students √ Moving teachers $85,500 $45,000
Keep 9-12 and 6-8 together X Overtime services $5,000 $5,000
Extracurricular √-
Traditional High School Schedule √ Moving Cost $30,000 $20,000
Doesn’t disrupt middle school X
Ready by September 6, 2010 √ Total Purchase Cost $1,826,410
Cost to provide option √ Total Lease Cost $1,077,85012
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 13/23
Data Related to Moving OCMS Programs
• Number of students to relocate:
Phoenix- maximum of 12
Independent Secondary- 70
Rivendell- 39 (includes 4 students in pregnant teens program)
• Number of staff to relocate:
Phoenix- 2
ISS- 10Rivendell- 11
• Minimum number of rooms needed:
Phoenix-2
ISS- 6 (includes office area)Rivendell- 6 (includes office area) plus CTE space for Culinary Arts kitchen and Building Trades
• Challenges to relocating Phoenix, ISS and Rivendell:
Transportation
Family Issues
CTE space for Culinary Arts and Building Trades13
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 14/23
Relocation of Additional Staff and Community
Programs Currently Housed at OCMS• Office space needed for 29 MCPS staff currently
located at OCMS
• Additional MCPS Programs to relocate:
Weight room for CHS football
GED classroom spaceRobotics
Student Records
• Community programs currently using OCMS:Safe Haven
Sweet Adelines
14
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 15/23
15
Enrollments
SCHOOLGRADE
6
GRADE
7
GRADE
8
GRADE
9
GRADE
10
GRADE
11
GRADE
12 TOTAL
BMS
(capacity
1200) 271 317 295 883
BHS(capacity
1216) 330 284 246 257 1117
CMS
(capacity1200) 256 279 287 822
OCMS
(capacity
775) 106
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 16/23
Summary of Criteria MatrixCriteria Matrix BMS 7-12 6th at Elem. OCMS 9-12 OCMS 6-8/9-12 BMS CMS 6-8/BMS 8-12
Safety X √ X √- √
Instructional program (Non Voc.) √- √ X √ √
Transportation Cost √ √ X X X
Transportation Time √ √ X X X
Food Services Program √ √ X X √
Library/Media √ √ √- √- √
Additional Staffing Needs √ X √ √ √
Fine Arts √- √- X √ √
Instructional Program
(Vocational)
√ X √ √ √
Family Issues √ √ X X X
Instructional Time √ √ √ √ √
Technology √ √- X X √
Keep Students in Blacksburg √ √ X X X
Move the least # of students √ √ X X √
Keep 9-12 and 6-8 together X X √ √ X
Extracurricular √- √ X √- √-
Traditional H. S. Schedule √ NA √ √ √
Doesn’t disrupt middle school X X √ √- X
Ready by September 6, 2010 ? √- X √- √
Cost to provide option X X X X √16
S f C i
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 17/23
Summary of Cost Estimates
17
OPTION 1 OPTION 2 OPTION 3 OPTION 4
DESCRIPTIONBHS 7-12 @
BMSBMS Grade6 @ Elem.
BHS 6-8 @BMS
BHS 9-12 @OCMS
BHS 9-12 @BMS
BMS 6 -8 @OCMS
BHS 8-12@ BMS
BMS 6& 7@ CMS
Total Students 1729 271 883 1117 1117 883 1412 1410
Less: Capacity 1200 1200 775 1200 775 1200 1200
=Additional Students 529 0 342 0 108 212 210
Percent of Capacity 144% 74% 144% 93% 144% 118% 118%
# of Mobiles 36-42 11 29 4 10-12 12-14 12-14
Purchase of Mobiles $1,872,000 $572,000 $0 $1,508,000 $208,000 $520,000 $624,000 $624,000
Lease Cost of Mobiles $749,160 $228,910 $603,490 $83,240 $208,100 $249,720 $249,720
Facilities Upgrades $25,000 $250,000 $150,000
Parking $100,000 $130,000 $130,000
Science Labs $25,000 $100,000 $25,000 $25,000
Technology $226,000 $33,000 $187,000 $100,000 $43,000 $43,000
School Nutrition $45,000 $10,000 $450,000 $450,000
Transportation $146,910 $146,910 $146,910
Relocate OCMSStaff $34,500 $34,500
Moving Teachers $94,000 $9,000 $76,500 $76,500 $54,000 $85,500 $45,000
Overtime Costs $20,000 $20,000 $20,000 $5,000 $15,000 $5,000 $5,000
Moving Costs $24,000 $20,000 $30,000 $24,000 $24,000 $30,000 $20,000
Total Purchase Cost $2,995,500 $2,902,910 $1,962,910 $1,826,410
Total Lease Cost $1,529,570 $1,998,400 $1,526,250 $1,077,850
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 18/23
Recommendation(s) – Housing option(s)
for students in the
Blacksburg strand
18
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 19/23
Calendar : September 7th as the first
day for students
19
• No negative impact on academic progression
• Change in employee start date from August 11, 2010 - August 30, 2010
• Change in school start date from August 18, 2010 – September 7, 2010
• Reduction of winter break from 10 days to 7 days
• Reduction in semester break:
•From: 1 Holiday coupled with 2 Professional Dev. days
•To: 1 Professional Dev. Day at the end of the semester
• Change in last day of school from May 27, 2011 to June 10, 2011 (without any
inclement weather days)
• Change in number of Work/Staff Dev. days from 1 day to 2 days after the end of
school
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 20/23
August 30th as the
first day for students• No negative impact on academic progression
• Change in employee start date from August 11, 2010 - August 23, 2010
• Change in school start date from August 18, 2010 – August 30, 2010
• Reduction of winter break from 10 days to 7 days
• Reduction of spring break from 3 days (Thu, Fri, & Mon) to 2 days (Fri & Mon)
• Reduction in semester break:
• From: 1 Holiday coupled with 2 Professional Dev. days
• To: 1 Professional Dev. Day after the end of the semester
• Change in last day of school from May 27, 2011 to June 2, 2011 (without any inclement
weather days)
• Change in number of Work/Staff Dev. days from 1 day to 2 days after the end of school
20
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 21/23
Calendar: August 23rd as the first
day for students• No negative impact on academic progression
•
Change in employee start date from August 11, 2010 - August 18, 2010
• Change in school start date from August 18, 2010 – August 25, 2010
• Reduction of winter break from 10 days to 7 days
• Reduction in semester break:
• From: 1 Holiday coupled with 2 Professional Dev. days
•To: 1 Professional Dev. Day after end of the semester
• Addition of 1 Professional Dev. Day during Parent Teacher conference week in
April
• Change in last day of school from May 27, 2011 to June 1, 2011 (without anyinclement weather days)
21
8/7/2019 SB Update Power Point) July 6 2010 (2)
http://slidepdf.com/reader/full/sb-update-power-point-july-6-2010-2 22/23
Next Steps
• Press Release
• Advise all impacted communities, students,parents and staff of changes in student
housing assignment• Advise all stakeholders of any change in the
school calendar for 2010-2011
• Begin implementation of housing for
Blacksburg strand