![Page 1: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/1.jpg)
Sausalito Ferry Landside Improvements Project
Update
SAUSALITO CITY COUNCIL MEETING
SEPTEMBER 24, 2019
![Page 2: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/2.jpg)
BACKGROUND
![Page 3: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/3.jpg)
Phase 1GGBHTD Builds Temp Ferry Landing
Golden Gate Bridge Highway Transportation District Project
Summer 2020 – June, October, November
![Page 4: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/4.jpg)
Phase 2 GGBHTD Rebuilds Existing DockMove Ferry Back to Rebuilt Dock
Golden Gate Bridge Highway Transportation District Project
Summer 2021 – June, October, November
![Page 5: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/5.jpg)
Phase 3Demolition of Temporary Dock
Golden Gate Bridge Highway Transportation District Project
Summer 2022 – June, October, November
![Page 6: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/6.jpg)
![Page 7: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/7.jpg)
City of Sausalito – Ferry Landside Improvements
![Page 8: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/8.jpg)
Study Area – Visioning Phase (Package A
Vision plus Parking Area Improvement Required per the Grant
– Design (Package B)
![Page 9: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/9.jpg)
• $2.4 million Federal Grant Pass through from GGBHTD Grant
• Improvements to access for Citizens of Sausalito and Commuters
• Maintain and Improve experience for tourists and residents
• Parking and Connectivity Improvements
![Page 10: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/10.jpg)
![Page 11: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/11.jpg)
Estimated Timeline (Plaza Design/Construction)
• October 2019 – Award of Professional Service Contract• Summer 2020 - Preferred Alternative Development for Plaza
Improvements• Fall 2020 – Spring 2021 - Federal Approval Process• Fall 2020 – Spring 2021 - Environmental Approval• Spring 2021 - Completion of Design Package• Spring 2021 - December 2021 - Construction
![Page 12: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/12.jpg)
Timeline (Visioning Plan)
• October 2019 – Award of Professional Service Contract• Spring 2020 – Public Outreach Meetings and General Planning • Summer 2020 - Preferred Alternative Development for Plaza
Improvements
![Page 13: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/13.jpg)
Current Status
• City Requested Proposals from Qualified Consultants (June 2019)
• City Received three proposals from qualified firms (July 2019)
• Consultant Interviews held for selecting consultants (September 2019)
![Page 14: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/14.jpg)
Proposal Harris and AssociatesBKF EngineersSWA
• Harris’s Quote• Package A Visioning + 30% Design
$672,113
• Package B Visioning + Full Design $1,428,900
Current BudgetFTA Grant $2,000,000GGBHTD $400,000City Funds $100,000
Total = $2,500,000
![Page 15: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/15.jpg)
Preliminary Cost Estimates
Ferry Landside Construction • Design (12.5%) $230,000• Construction $1,900,000• Contingency (10%) $190,000• Construction Management (~10%) $180,000
Total = $2,500,000
Minimal Improvements within
the Ferry Landing Area
No funding in this case for Visioning Package A
Preliminary – Modification may be needed
![Page 16: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/16.jpg)
Options and Direction
City Council Assistance and Direction
Direct staff to negotiate with Harris to reduce their cost for Package B to be in relative conformance with the budget and proceed with the work.
Rebid this portion of the project.
![Page 17: Sausalito Ferry Landside Improvements Project Update€¦ · Golden Gate Bridge Highway Transportation District Project Summer 2021 – June, October, November. Phase 3 Demolition](https://reader033.fdocuments.us/reader033/viewer/2022060207/5f03d03e7e708231d40ae626/html5/thumbnails/17.jpg)
Questions and Comments