SATR-S-4001

2
Page 1 of 2 SAUDI ARAMCO ID/PID - 6/30/2008 - REV 3 (Standards Cutoff - June 2008) REV 3 30-Jun-08 SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER Sanitary Sewers Gravity Test SATR-S-4001 15-Dec-09 PL PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT SAUDI ARAMCO USE SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A A. TEST PROCEDURE AND CHECKLIST A1 A2 A3 A4 B. TEST RESULTS C. CONCLUSIONS TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A C1 N/A REFERENCE DOCUMENTS: 2-SAES-S-070 -- Installation of Utility Piping Systems, 13 November 2007 Contractor / Third-Party Saudi Aramco Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed QC Inspector PID Representative Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed QC Supervisor Proponent and Others Name, Sign and Date: Quality Record Approved: T&I Witnessed QC Record Reviewed *Person Responsible for Implementation of Test and Analysis of Results Y = YES N ITEM No. Sanitary sewer lines shall be hydrotested with potable water, well water or seawater. SAES-S-070 Para 18.2 Gravity Sanitary Sewers shall be tested from manhole to manhole, or Manhole to sump inlet. The Upstream Manhole may be tested at the same time. SAES-S-070 Para 18.7 Gravity Sanitary Sewer Pipe if tested separately shall be pressure tested at column of water equivalent to the rim elevation of the upstream manhole. SAES-S-070 Para 18.8 e. The required test pressure shall be maintained for 24 hours for lines whose joints have backfilled and 4 hours for lines whose joints have not been backfilled or are above grounds SAES-S-070 Para 18.8 Head of water recorded at the start of the test _____________ft Head of water recorded at the end of the test _____________ft ITEM No. Test results are acceptable (no leak detected) and in accordance with Saudi Aramco Engineering Standards and contractual requirements. REMARKS: Technician Performing Test* PMT Representative Name, Title, Department, Company, Initials and Date: Name, Initials and Date: Name, Initials and Date: Name, Initials and Date: Name, Organization, Initials and Date:

description

SATR-S-4001

Transcript of SATR-S-4001

Single Page SATRSAUDI ARAMCO ID/PID - 6/30/2008 - REV 3 (Standards Cutoff - June 2008)REV 330-Jun-08SAUDI ARAMCO TEST REPORTSATR NUMBERDATE APPROVEDQR NUMBERSanitary Sewers Gravity TestSATR-S-400115-Dec-09PLUMBPROJECT TITLEWBS / BI / JO NUMBERCONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S)EQUIPMENT DESCRIPTIONEQPT CODESYSTEM ID.PLANT NO.

LAYOUT DRAWING NUMBERREV. NO.PURCHASE ORDER NUMBEREC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIMEACTUAL TEST DATE & TIMEQUANTITY INSP.MH's SPENTTRAVEL TIMESAUDI ARAMCO USE ONLYSAUDI ARAMCO TIP NUMBERSAUDI ARAMCO ACTIVITY NUMBERWORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVELCONTRACTOR INSPECTION LEVEL

ITEM No.TEST PROCEDURE ACCEPTANCE CRITERIAREFERENCEPASSFAILN/ARE-TEST DATE

A. TEST PROCEDURE AND CHECKLISTA1Sanitary sewer lines shall be hydrotested with potable water, well water or seawater.SAES-S-070 Para 18.2A2Gravity Sanitary Sewers shall be tested from manhole to manhole, or Manhole to sump inlet. The Upstream Manhole may be tested at the same time.SAES-S-070 Para 18.7A3Gravity Sanitary Sewer Pipe if tested separately shall be pressure tested at column of water equivalent to the rim elevation of the upstream manhole. SAES-S-070 Para 18.8 e.A4The required test pressure shall be maintained for 24 hours for lines whose joints have backfilled and 4 hours for lines whose joints have not been backfilled or are above grounds SAES-S-070 Para 18.8 B. TEST RESULTSHead of water recorded at the start of the test _____________ft

Head of water recorded at the end of the test _____________ft C. CONCLUSIONSITEM No.TEST RESULTS ACCEPTANCE CRITERIAREFERENCEPASSFAILN/ARE-TEST DATE

C1Test results are acceptable (no leak detected) and in accordance with Saudi Aramco Engineering Standards and contractual requirements.N/A

REMARKS:

REFERENCE DOCUMENTS:2-SAES-S-070 -- Installation of Utility Piping Systems, 13 November 2007

Contractor / Third-PartySaudi AramcoTechnician Performing Test* PMT Representative

Name, Title, Department,Company, Initials and Date:Test Performed Successfully and Results are Acceptable:Name, Initials and Date:T&I WitnessedQC Record ReviewedWork Verified

QC InspectorPID RepresentativeName, Initials and Date:Witnessed TestWork / Rework May ProceedName, Initials and Date:T&I WitnessedQC Record ReviewedWork Verified

QC SupervisorProponent and OthersName, Sign and Date: Quality Record Approved:Name, Organization,Initials and Date:T&I WitnessedQC Record ReviewedWork Verified

*Person Responsible for Implementation of Test and Analysis of ResultsY = YES N = NO F = FAILED