 Purpose Splitting structure determine how and what selected activity-independent costs from a cost center are divided between the activity types. This applies to both plan and actual costs.  A s plitting structure consists of one or more assignments, which define the connection between the cost element(s) or cost element group to be split and the splitting rule used to divide the costs. Each splitting rule is based on a splitting method; for example, splitting costs based on statistical key figures. Trigger N.A. Prerequisites  After you define a splitting structure, you must assign it to the cost centers on which you want to split costs according to the given rules. You can assign a structure to:  All cost centers  All cost centers in a given group  All cost centers in a given interval The structure can apply to a single version or to all versions in a controlling area for a fiscal year Menu Path Path :- SPRO  Controlling  Cost Center Accounting  Actual Posting  Period   End Closing   Activity Allocation  Splitting  Define Splitting Structure Initial screen Click on New entries Maintain Split structure OKES

Transcript of SAP OKES - Splitting Structure

Page 1: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 1/9

Purpose

Splitting structure determine how and what selected activity-independent costs from a cost center aredivided between the activity types. This applies to both plan and actual costs.

A splitting structure consists of one or more assignments, which define the connection between the costelement(s) or cost element group to be split and the splitting rule used to divide the costs.

Each splitting rule is based on a splitting method; for example, splitting costs based on statistical keyfigures.

Trigger

N.A.

Prerequisites

After you define a splitting structure, you must assign it to the cost centers on which you want to splitcosts according to the given rules. You can assign a structure to:

All cost centers All cost centers in a given group All cost centers in a given interval

The structure can apply to a single version or to all versions in a controlling area for a fiscal year

Menu PathPath :- SPRO Controlling Cost Center Accounting Actual Posting Period – End Closing

Activity Allocation Splitting Define Splitting Structure

Initial screen

Click on New entries

Maintain Split structure OKES

Page 2: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 2/9

Page 3: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 3/9

Click on

Click on

Select

Double click on

Page 4: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 4/9

Purpose

If you want to split costs in the cost center to the activity types, you must assign a splitting structure to this

cost center.

The SAP System splits costs per the rules that you set in the splitting structure.

Menu Path

Path :- SPRO Controlling Cost Center Accounting Actual Posting Period – End Closing Activity Allocation Splitting Assign Split structure to Cost Center

Initial screen

Initial Screen

Click on save button.

Assign Split structure to Cost Center OKEW

Page 5: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 5/9

Purpose

You need to create Splitting Structure and Splitting rule. The splitting rule shall be based on activityquantity. Then this structure should be assigned to the selected cost centers. In addition, you need tomodify the master data of Activity type by selecting 5 against the Act Price Indicator. Then you also needto select either one of the options available price calculation tab 'settings for each fiscal year' as pastedbelow.

Trigger

Revaluation at Actual Prices Indicator determining whether actual activities in a version are valuatedwith actual prices and how the valuation is performed

All actual activities valuated with the plan price 1 Revaluation in separate transaction All actual activitiesvaluated with the actual price; original allocation unchanged The differences between allocations valuatedwith plan and actual prices are posted under a separate transaction (actual price calculation). 2

Revaluation in original transaction All actual activities revaluated with the actual price; original allocationchanged The differences between allocations valuated with actual and plan prices are not shown with thisoption

Prerequisites

N.a.

Menu Path

SAP Easy Access Accounting Controlling Cost Center Accounting Period – End Closing Single Functions KSS2 - Splitting

Initial screen

Maintain Splitting KSS2

Page 6: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 6/9

Click on execute

Click on back

Remove the test run

Page 7: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 7/9

Click on execute

Page 8: SAP OKES - Splitting Structure

8/9/2019 SAP OKES - Splitting Structure

http://slidepdf.com/reader/full/sap-okes-splitting-structure 8/9

Purpose

Price calculation , which you can carry out during planning, is based on planned costs and activity. The

resulting prices are used to valuate actual activity.

After running actual price calculation, you can choose to recalculate actual activity at actual prices. Thisrevaluates the activity using the difference between plan and actual prices. By revaluing the actual activitywith actual prices, you can fully balance sender cost centers and sender business processes.

Trigger

If you are working with transfer prices (parallel value flows) actual price calculation and recalculation arepossible in all valuations. In the output list of the price calculation, you can choose to display the prices inall valuations.

Prerequisites

Recalculation in a special business transaction

The R/3 System posts the difference between the plan and actual allocation valuations using a separatebusiness transaction (actual price calculation). This makes it easier to track variances between valuationsusing actual and plan prices.

Recalculation in the original transaction

The R/3 System posts the recalculation in the original transaction. The variances between calculations atactual and plan prices can then no longer be tracked. Use this option if you do not have plan prices,meaning the original allocation was not valuated

Menu Path

SAP Easy Access Accounting Controlling Cost Center Accounting Period – End Closing Single Functions KSII – Price Calculation