SAP CO-PC Material Cost Estimate_EUG

38
Transaction Code: CK40N Product Costing Cockpit - Material Costing Run Version 1.60.1 (Updated 10/01/2010) 1) Enter C AIO_00x) 2) Enter C date) 3) Click o

Transcript of SAP CO-PC Material Cost Estimate_EUG

Page 1: SAP CO-PC Material Cost Estimate_EUG

Transaction Code: CK40N

Product Costing Cockpit - Material Costing RunVersion 1.60.1 (Updated 10/01/2010)

1) Enter Costing Run id (e.g. AIO_00x)

2) Enter Costing Run Date (today's date)

3) Click on (Create) button

Page 2: SAP CO-PC Material Cost Estimate_EUG
Page 3: SAP CO-PC Material Cost Estimate_EUG
Page 4: SAP CO-PC Material Cost Estimate_EUG
Page 5: SAP CO-PC Material Cost Estimate_EUG

1) Click (Save)

2) Click (Back)

Page 6: SAP CO-PC Material Cost Estimate_EUG
Page 7: SAP CO-PC Material Cost Estimate_EUG
Page 8: SAP CO-PC Material Cost Estimate_EUG
Page 9: SAP CO-PC Material Cost Estimate_EUG
Page 10: SAP CO-PC Material Cost Estimate_EUG
Page 11: SAP CO-PC Material Cost Estimate_EUG

1) Choose (SAP&12)

2) Click (Enter)

1) Click (Save)

2) Click (Back)

Page 12: SAP CO-PC Material Cost Estimate_EUG
Page 13: SAP CO-PC Material Cost Estimate_EUG

1) Click (Save)

Page 14: SAP CO-PC Material Cost Estimate_EUG

2) Click (Save)

3) Click (Back)

1) Untick (Test Run)

Page 15: SAP CO-PC Material Cost Estimate_EUG
Page 16: SAP CO-PC Material Cost Estimate_EUG
Page 17: SAP CO-PC Material Cost Estimate_EUG

2) Click (Save)

3) Click (Back)

1) Untick (Test Run)

Page 18: SAP CO-PC Material Cost Estimate_EUG
Page 19: SAP CO-PC Material Cost Estimate_EUG

Back to client create

Page 20: SAP CO-PC Material Cost Estimate_EUG

Product Costing Cockpit - Material Costing RunVersion 1.60.1 (Updated 10/01/2010)

1) Enter Costing Run id (e.g. AIO_00x)

2) Enter Costing Run Date (today's date)

3) Click on (Create) button

1) Enter description

2) Enter Costing Variant (YPC1)

3) Enter Costing Version (01)

4) Enter Controlling Area (e.g. BP01)

5) Enter Company Code (e.g. BP01)

6) Click (Save)

Page 21: SAP CO-PC Material Cost Estimate_EUG

2) Enter Costing Variant (YPC1)

3) Enter Costing Version (01)

4) Enter Controlling Area (e.g. BP01)

5) Enter Company Code (e.g. BP01)

1) Click on (Dates) tab

2) Change (Costing Date From), (Qty Structure Date), and (Valuation Date) to (today's date).

3) Click on (Enter)

4) Click on (Save)

1) Click (Change Parameter) on (Selection) step

Page 22: SAP CO-PC Material Cost Estimate_EUG

1) Exclude Material Type (PROD)

2) Note: Only select (Select Configured Matls Only) when you are going to cost VC material variants -- for step 8703

3) Click (Save)

4) Click (Back)

1) Click (Execute) on (Selection) step

Page 23: SAP CO-PC Material Cost Estimate_EUG

1) Select (Start Immediately)

2) Click (Check)

3) Click (Confirm)

1) Click (Enter)

1) Click (Refresh) until (Still Open) is 0 or blank

Page 24: SAP CO-PC Material Cost Estimate_EUG

1) Click (Refresh) until (Still Open) is 0 or blank

2) Analize the results, only proceed to the next steps if there is no errors(warning is ok).

1) Click (Change Parameter) on (Struct. Explosion) step

1) Click (Save)

2) Click (Back)

Page 25: SAP CO-PC Material Cost Estimate_EUG

1) Click (Execute)on (Struct. Explosion) step

1) Select (Start Immediately)

2) Click (Check)

3) Click (Confirm)

1) Click (Enter)

Page 26: SAP CO-PC Material Cost Estimate_EUG

1) Click (Enter)

1) Click (Refresh) until (Still Open) is 0 or blank

2) Analize the results, only proceed to the next steps if there is no errors(warning is ok).

Page 27: SAP CO-PC Material Cost Estimate_EUG

1) Click (Change Parameter) on (Costing) step

1) Click (Save)

2) Click (Back)

Page 28: SAP CO-PC Material Cost Estimate_EUG

1) Click (Execute) on (Costing) step

1) Select (Start Immediately)

2) Click (Check)

3) Click (Confirm)

1) Click (Enter)

Page 29: SAP CO-PC Material Cost Estimate_EUG

1) Click (Refresh) until (Still Open) is 0 or blank

2) Analize the results, only proceed to the next steps if there is no errors(warning is ok).

1) Click (Change Parameter) on (Analysis) step

Page 30: SAP CO-PC Material Cost Estimate_EUG

1) Choose (SAP&12)

2) Click (Enter)

1) Click (Save)

2) Click (Back)

Page 31: SAP CO-PC Material Cost Estimate_EUG

1) Click (Execute) on (Analysis) step.

1) Analyze the cost estimate results

2) Click (Back)

Page 32: SAP CO-PC Material Cost Estimate_EUG

1) Click on (Not yet allowed)on (Marking) step.

1) Click on company code to allow marking (e.g. BP01)

1) Click (Save)

2) Click (Back)

Page 33: SAP CO-PC Material Cost Estimate_EUG

1) Click (Save)

2) Click (Back)

1) Click (Change Parameter) on (Marking) step

2) Click (Save)

3) Click (Back)

1) Untick (Test Run)

Page 34: SAP CO-PC Material Cost Estimate_EUG

1) Click (Execute) on (Marking) step

1) Select (Start Immediately)

3) Click (Check)

4) Click (Confirm)

1) Click (Enter)

2) Untick (Change print param.)

Page 35: SAP CO-PC Material Cost Estimate_EUG

1) Click (Refresh) until (Still Open) is 0 or blank

2) Analize the results, only proceed to the next steps if there is no errors(warning is ok).

Page 36: SAP CO-PC Material Cost Estimate_EUG

1) Click (Change Parameter) on (Release) step

2) Click (Save)

3) Click (Back)

1) Untick (Test Run)

1) Click (Execute) on (Release) step

Page 37: SAP CO-PC Material Cost Estimate_EUG

1) Select (Start Immediately)

3) Click (Check)

4) Click (Confirm)

1) Click (Enter)

2) Untick (Change print param.)

1) Click (Refresh) until (Still Open) is 0 or blank

Page 38: SAP CO-PC Material Cost Estimate_EUG

1) Click (Refresh) until (Still Open) is 0 or blank

2) Analize the results, only proceed to the next steps if there is no errors(warning is ok).