Santa Cruz County 2014 Regional Transportation Plan ... Cruz County 2014 Regional Transportation...

22
Santa Cruz County 2014 Regional Transportation Plan - Transportation Projects for Hybrid Scenarios RTP_Num Agency Project Total Project Cost (1000s) Projects with dedicated funds or are already programmed. Cost (1000s) Project cost still needed after dedicated funds removed. (Total cost Ded/prog cost) % of project Cost (1000s) % of project Cost (1000s) CT-P09e Caltrans Hwy 9 Operational & Safety Improvements 0.02 0 0.02 0% 0 0% 0 CT-P41 Caltrans Hwy 17 Access Management/Corridor Study 0.02 0 0.02 0% 0 0% 0 CT-P44 Caltrans District 5 Vista Point Interpretive Display 693 0 693 0% 0 0% 0 CT-P45 Caltrans State Highway Preservation (bridge, roadway, roadside) 428000 128000 300000 0% 0 0% 0 CT-P46 Caltrans Collision Reduction & Emergency Projects 592000 163000 429000 0% 0 0% 0 CT-P47 Caltrans Minors 140000 42000 98000 0% 0 0% 0 SV-P08 Caltrans Hwy 17/Granite Creek Interchange Reconstruction 8000 0 8000 0% 0 0% 0 CHP-P01 CHP - California H Hwy 17 Safety Program 2200 2200 0 0% 0 0% 0 CHP-P02 CHP - California H Traffic Management 0.05 0 0.05 0% 0 0% 0 CHP-P03 CHP - California H Hwy 129 Safety Program 500 0 500 0% 0 0% 0 CAP 11 City of Capitola Clares Street Traffic Calming 425 425 0 0% 0 0% 0 CAP 15 City of Capitola Park Avenue Sidewalks 500 500 0 0% 0 0% 0 CAP-P01 City of Capitola Hwy 1/41st Avenue Interchange 0.01 0 0.01 0% 0 0% 0 CAP-P03 City of Capitola Upper Capitola Avenue Improvements 1300 0 1300 100% 1300 100% 1300 CAP-P04b City of Capitola Capitola Village Multimodal Enhancements - Phase 2/3 3000 0 3000 100% 3000 100% 3000 CAP-P05 City of Capitola Cliff Drive Improvements (combine with CAP 31 and 33) 1500 0 1500 0% 0 0% 0 CAP-P06 City of Capitola Citywide General Maintenance and Operations 17600 8800 8800 20% 1760 50% 4400 CAP-P07 City of Capitola Bay Avenue/Hill Street Intersection 200 0 200 0% 0 0% 0 CAP-P07p City of Capitola Stockton Ave Bridge Rehab 2500 0 2500 100% 2500 100% 2500 CAP-P08 City of Capitola Bay Avenue/Capitola Avenue Improvements 400 0 400 0% 0 0% 0 CAP-P09 City of Capitola Park Avenue/Kennedy Drive Improvements 350 0 350 0% 0 0% 0 CAP-P12 City of Capitola Monterey Avenue Multimodal Improvements 350 0 350 100% 350 100% 350 Dedicated not included Hybrid 1 Hybrid 2 Please note that approximately 75% of the transportation funding for Santa Cruz County is dedicated to certain projects or uses. The column titled ‘project cost still needed after dedicated funds removed’ indicates projects that need additional funds. The hybrid scenarios (1 and 2) show different ways to allocate the remaining 25% of the estimated funds over a 22 year timeframe. Many of the projects are similar between the two hybrid scenarios with the greatest difference being more Highway 1 corridor projects are funded in hybrid #1 and more maintenance is funded in hybrid #2. For the complete project list for each of the hybrid scenarios, add the dedicated projects to each of the hybrids.

Transcript of Santa Cruz County 2014 Regional Transportation Plan ... Cruz County 2014 Regional Transportation...

Santa Cruz County 2014 Regional Transportation Plan - Transportation Projects for Hybrid Scenarios

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

CT-P09e CaltransHwy 9 Operational & Safety Improvements 0.02 0 0.02 0% 0 0% 0

CT-P41 CaltransHwy 17 Access Management/Corridor Study 0.02 0 0.02 0% 0 0% 0

CT-P44 CaltransDistrict 5 Vista Point Interpretive Display 693 0 693 0% 0 0% 0

CT-P45 CaltransState Highway Preservation (bridge, roadway, roadside) 428000 128000 300000 0% 0 0% 0

CT-P46 CaltransCollision Reduction & Emergency Projects 592000 163000 429000 0% 0 0% 0

CT-P47 Caltrans Minors 140000 42000 98000 0% 0 0% 0

SV-P08 CaltransHwy 17/Granite Creek Interchange Reconstruction 8000 0 8000 0% 0 0% 0

CHP-P01 CHP - California HHwy 17 Safety Program 2200 2200 0 0% 0 0% 0CHP-P02 CHP - California HTraffic Management 0.05 0 0.05 0% 0 0% 0CHP-P03 CHP - California HHwy 129 Safety Program 500 0 500 0% 0 0% 0CAP 11 City of Capitola Clares Street Traffic Calming 425 425 0 0% 0 0% 0CAP 15 City of Capitola Park Avenue Sidewalks 500 500 0 0% 0 0% 0CAP-P01 City of Capitola Hwy 1/41st Avenue Interchange 0.01 0 0.01 0% 0 0% 0

CAP-P03 City of Capitola Upper Capitola Avenue Improvements 1300 0 1300 100% 1300 100% 1300

CAP-P04b City of CapitolaCapitola Village Multimodal Enhancements - Phase 2/3 3000 0 3000 100% 3000 100% 3000

CAP-P05 City of CapitolaCliff Drive Improvements (combine with CAP 31 and 33) 1500 0 1500 0% 0 0% 0

CAP-P06 City of CapitolaCitywide General Maintenance and Operations 17600 8800 8800 20% 1760 50% 4400

CAP-P07 City of Capitola Bay Avenue/Hill Street Intersection 200 0 200 0% 0 0% 0CAP-P07p City of Capitola Stockton Ave Bridge Rehab 2500 0 2500 100% 2500 100% 2500

CAP-P08 City of CapitolaBay Avenue/Capitola Avenue Improvements 400 0 400 0% 0 0% 0

CAP-P09 City of CapitolaPark Avenue/Kennedy Drive Improvements 350 0 350 0% 0 0% 0

CAP-P12 City of CapitolaMonterey Avenue Multimodal Improvements 350 0 350 100% 350 100% 350

Dedicated not included

Hybrid 1 Hybrid 2

Please note that approximately 75% of the transportation funding for Santa Cruz County is dedicated to certain projects or uses. The column titled ‘project cost still needed after dedicated funds removed’ indicates projects that need additional funds. The hybrid scenarios (1 and 2) show different ways to allocate the remaining 25% of the estimated funds over a 22 year timeframe. Many of the projects are similar between the two hybrid scenarios with the greatest difference being more Highway 1 corridor projects are funded in hybrid #1 and more maintenance is funded in hybrid #2. For the complete project list for each of the hybrid scenarios, add the dedicated projects to each of the hybrids.

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CAP-P15 City of Capitola Capitola Jitney Transit Service 1000 0 1000 0% 0 0% 0

CAP-P16 City of CapitolaClares Street Pedestrian Crossing west of 40th Ave 500 0 500 100% 500 100% 500

CAP-P17 City of Capitola Citywide Traffic Calming 1400 0 1400 0% 0 0% 0CAP-P18 City of Capitola Capitola Intra-City Rail Trolley 14000 0 14000 0% 0 0% 0CAP-P24 City of Capitola Pacific Cove Parking Lot expansion 15000 2000 13000 0% 0 0% 0CAP-P27 City of Capitola Wheelchair Access Ramps 25 0 25 100% 25 100% 25CAP-P28 City of Capitola Monterey Avenue at Depot Hill 250 0 250 0% 0 0% 0

CAP-P29 City of CapitolaBay Avenue Traffic Calming and Bike/Ped Enhancements 400 0 400 100% 400 100% 400

CAP-P30 City of Capitola47th Avenue Traffic Calming and Greenway 100 100 0 0% 0 0% 0

CAP-P32 City of CapitolaBay Avenue/Monterey Avenue Intersection Modification 300 0 300 100% 300 100% 300

CAP-P34 City of CapitolaCapitola Village Enhancements: Capitola Ave 1000 0 1000 100% 1000 100% 1000

CAP-P35 City of CapitolaAuto Plaza Drive Extension to Bay Avenue 10000 0 10000 0% 0 0% 0

CAP-P37 City of Capitola41st Ave/Capitola Road Intersection Improvements 500 0 500 0% 0 0% 0

CAP-P38 City of Capitola40th Ave/Clares St Intersection Improvements 1500 0 1500 0% 0 0% 0

CAP-P40 City of Capitola46th/47th Ave (Clares to Cliff Dr) bike lanes/traffic calming 15 0 15 100% 15 100% 15

CAP-P41 City of Capitola

Brommer/Jade/Topaz St bike lanes/traffic calming (Western City Limit on Brommer to 47thAve) 15 0 15 100% 15 100% 15

CAP-P42 City of CapitolaClares St Bike Lanes/Sharrows (Capitola Rd to 41st Ave) 5 0 5 100% 5 100% 5

CAP-P43 City of CapitolaClares St/41st Ave bicycle intersection improvement 5 0 5 100% 5 100% 5

CAP-P44 City of CapitolaGross/41st Ave bicycle intersection improvement 15 0 15 100% 15 100% 15

CAP-P45 City of Capitola38th Ave (Capitola Rd to City limit to south)-bike lanes/traffic calming 15 0 15 100% 15 100% 15

CAP-P46 City of Capitola40th Ave (at Deanes Ln)Bike/Ped connection 5 0 5 100% 5 100% 5

CAP-P47 City of Capitola41st Ave (Soquel to Portola) crosswalks 15 0 15 100% 15 100% 15

CAP-P48 City of CapitolaCapitola Mall (Capitola Rd to Clares) bike path 50 0 50 100% 50 100% 50

CAP-P49 City of Capitola41st Ave (Soquel to Brommer) Signal Synchronization 15 0 15 100% 15 100% 15

CAP-P50 City of Capitola Capitola-wide HOV priority 40 0 40 100% 40 100% 40CAP-P51 City of Capitola Citywide Sidewalk Program 1000 0 1000 100% 1000 100% 1000

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CAP-P52 City of Capitola Citywide Bike Projects 1000 0 1000 0% 0 0% 0

SC 07 City of Santa CruzBroadway-Brommer Bike/Ped Path (Arana Gulch Multiuse Trail) 4000 4000 0 0% 0 0% 0

SC 23 City of Santa CruzWest Cliff Path Minor Widening (Lighthouse to Swanton) 500 500 0 0% 0 0% 0

SC 25 City of Santa Cruz Hwy 1/9 Intersection Modifications 6200 4000 2200 100% 2200 100% 2200SC 37 City of Santa Cruz Murray St Bridge Replacement 11070 11070 0 0% 0 0% 0

SC 38 City of Santa CruzHwy 1/San Lorenzo Bridge Replacement 20000 500 19500 0% 0 0% 0

SC 42 City of Santa CruzSoquel Ave at Frederick St Intersection Modifications 300 300 0 0% 0 0% 0

SC 46 City of Santa Cruz Branciforte Creek Bike/Ped Crossing 2650 2650 0 0% 0 0% 0SC-P03 City of Santa Cruz Hwy 1 Sound Wall 500 0 500 0% 0 0% 0

SC-P07 City of Santa Cruz Citywide Operations and Maintenance 158400 66000 92400 20% 18480 50% 46200SC-P09 City of Santa Cruz Sidewalk Program 20000 0 20000 50% 10000 50% 10000

SC-P100 City of Santa CruzSeabright/Murray Traffic Signal Modifications 1000 0 1000 100% 1000 100% 1000

SC-P101 City of Santa CruzSwift/Delaware Intersection Roundabout or Traffic Signal 1000 0 1000 0% 0 0% 0

SC-P104 City of Santa Cruz Measure H Road Projects 37400 37400 0 0% 0 0% 0

SC-P105 City of Santa CruzMarket Street Sidewalks and Bike Lanes 1000 0 1000 100% 1000 100% 1000

SC-P106 City of Santa CruzArana Gulch Bicycle/Pedestrian Connection (at Agnes St) 500 500 0 0% 0 0% 0

SC-P107 City of Santa CruzArroyo Seco Trail (Medar St to Grandview St) 280 0 280 0% 0 0% 0

SC-P108 City of Santa CruzHwy 1 - Harvey West Area Alternative Access 4000 0 4000 0% 0 0% 0

SC-P109 City of Santa Cruz Bay/High Intersection Modification 2000 0 2000 0% 0 0% 0

SC-P110 City of Santa CruzRiver (Rte 9)/Fern Intersection Modification 500 0 500 0% 0 0% 0

SC-P111 City of Santa CruzRiver (Rte 9)/Encinal Intersection Modification 300 0 300 0% 0 0% 0

SC-P112 City of Santa CruzMission (Hwy 1)/Laurel Intersection Modification 100 0 100 0% 0 0% 0

SC-P113 City of Santa CruzMission (Hwy 1)/Swift Intersection Modification 100 0 100 0% 0 0% 0

SC-P114 City of Santa Cruz King/Laurel Intersection Modification 100 0 100 0% 0 0% 0

SC-P115 City of Santa CruzNorth Branciforte/Water Intersection Modification 2000 0 2000 0% 0 0% 0

SC-P116 City of Santa CruzRiverSt/River Street South Intersection Modification 500 0 500 100% 500 100% 500

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

SC-P117 City of Santa CruzWater St (add Branciforte and Center) signal synchronization 200 0 200 100% 200 100% 200

SC-P118 City of Santa CruzMott St (at Hiawatha) bike/ped connections 20 0 20 100% 20 100% 20

SC-P119 City of Santa CruzSoquel/Water (Branciforte to Morrissey) crosswalks 100 0 100 100% 100 100% 100

SC-P12 City of Santa CruzMorrissey/Poplar/Soquel Intersection Modification 2000 0 2000 100% 2000 100% 2000

SC-P120 City of Santa Cruz

Ocean St and San Lorenzo River Levee Bike/Ped Connections (Felker, Kennan, Blain, Barson Streets) 600 0 600 100% 600 100% 600

SC-P121 City of Santa Cruz Riverside Avenue (Barson to Soquel) 200 0 200 100% 200 100% 200

SC-P122 City of Santa CruzOcean Sreet Corridor Multiuse Transit Lane 400 0 400 100% 400 100% 400

SC-P123 City of Santa Cruz

Soquel/Branciforte/Water (San Lorenzo River to Branciforte) bike lane treatments 400 0 400 100% 400 100% 400

SC-P124 City of Santa CruzOcean Street/San Lorenzo River Levee Area Wayfinding 150 0 150 100% 150 100% 150

SC-P13 City of Santa CruzRiverside Ave/Second St Intersection Modification. 75 0 75 0% 0 0% 0

SC-P14 City of Santa Cruz Park & Ride Lots 20000 0 20000 0% 0 0% 0

SC-P21 City of Santa CruzBrookwood Drive Bike and Pedestrian Path 1000 0 1000 100% 1000 100% 1000

SC-P22 City of Santa Cruz Chestnut St. Pathway 550 0 550 100% 550 100% 550SC-P23 City of Santa Cruz Delaware Avenue Bike lanes 50 0 50 100% 50 100% 50SC-P28 City of Santa Cruz Mission Street Extension Pathway 100 0 100 0% 0 0% 0

SC-P29 City of Santa Cruz Morrissey Blvd. Bike Path over Hwy 1 90 0 90 100% 90 100% 90SC-P30 City of Santa Cruz Murray St to Harbor Path Connection 200 0 200 100% 200 100% 200

SC-P31 City of Santa CruzSan Lorenzo River Bike/Ped Path at RR Bridge 3225 0 3225 100% 3225 100% 3225

SC-P35 City of Santa CruzSan Lorenzo River Levee Path Connection 2000 0 2000 100% 2000 100% 2000

SC-P47 City of Santa Cruz Chestnut Street Bike Lanes 550 0 550 100% 550 100% 550

SC-P59 City of Santa Cruz King Street Bike Lanes (entire length) 2000 0 2000 100% 2000 100% 2000

SC-P66 City of Santa CruzOcean Street Widening from Soquel to East Cliff 5000 0 5000 0% 0 0% 0

SC-P69 City of Santa CruzSeabright Avenue Bike Lanes (Pine-Soquel) 2000 0 2000 100% 2000 100% 2000

SC-P73 City of Santa CruzNeighborhood Traffic Management Improvements 2500 0 2500 100% 2500 100% 2500

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

SC-P75 City of Santa Cruz Lump Sum Bike Projects 4000 0 4000 0% 0 0% 0

SC-P76 City of Santa CruzStorey/King Street Intersection Left-Turn Lane 100 0 100 0% 0 0% 0

SC-P77 City of Santa Cruz Bay Street Corridor Modifications 4000 0 4000 100% 4000 100% 4000

SC-P81 City of Santa Cruz

Hwy 1/Mission St at Chestnut/King/Union Intersection Modification 4500 0 4500 0% 0 0% 0

SC-P83 City of Santa Cruz West Cliff/Bay Street Modifications 300 0 300 0% 0 0% 0

SC-P84 City of Santa CruzOcean St Streetscape and Intersection, Water to Soquel 6000 500 5500 100% 5500 100% 5500

SC-P86 City of Santa CruzOcean St Streetscape and Intersection, Plymouth to Water 4000 0 4000 100% 4000 100% 4000

SC-P87 City of Santa CruzSoquel Ave Corridor Widening (Branciforte-Morrissey) 2250 0 2250 0% 0 0% 0

SC-P90 City of Santa CruzHigh St/Moore St Intersection Modification 100 0 100 100% 100 100% 100

SC-P91 City of Santa CruzShaffer Road Widening and Railroad Crossing 500 0 500 0% 0 0% 0

SC-P92 City of Santa Cruz Shaffer Rd/Hwy 1 Signalization 500 0 500 0% 0 0% 0SC-P93 City of Santa Cruz Beach/Cliff Intersection Signalization 200 0 200 100% 200 100% 200

SC-P95 City of Santa CruzBranciforte Creek Pedestrian Path Connections 3250 0 3250 100% 3250 100% 3250

SC-P96 City of Santa Cruz Bay/California Traffic Signals 500 0 500 0% 0 0% 0

SC-P97 City of Santa CruzLaurent/High Intersection Improvements 400 0 400 0% 0 0% 0

SC-P99 City of Santa CruzSeabright/Water Intersection Improvements 100 0 100 0% 0 0% 0

SV-18A City of Scotts ValleGreen Hills Road Bike Lanes 700 0 700 100% 700 100% 700SV-P01 City of Scotts ValleHwy 17/Midtown Interchange 30000 0 30000 0% 0 0% 0SV-P05 City of Scotts ValleCitywide Sidewalk Program 5000 0 5000 25% 1250 25% 1250SV-P06 City of Scotts ValleCitywide Access Ramps 200 0 200 100% 200 100% 200

SV-P09 City of Scotts ValleMt. Hermon Rd. Circulation Master Plan 3500 0 3500 0% 0 0% 0

SV-P10 City of Scotts ValleErba Lane/Terrace View/SV Drive Realignment 500 0 500 0% 0 0% 0

SV-P11 City of Scotts ValleSky Park Commercial Area Circulation 2000 0 2000 0% 0 0% 0

SV-P13 City of Scotts ValleMt Hermon, Lockewood, Springs Lake widening 4000 0 4000 0% 0 0% 0

SV-P14 City of Scotts ValleEl Pueblo Rd Ext . North 1200 0 1200 0% 0 0% 0SV-P15 City of Scotts ValleEl Pueblo Rd Extensions 400 0 400 0% 0 0% 0SV-P16 City of Scotts ValleBean Creek Road Realignment 2750 0 2750 0% 0 0% 0

SV-P21 City of Scotts ValleLockwood Ln Pedestrian Signal near golf course 50 0 50 100% 50 100% 50

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

SV-P22 City of Scotts ValleEmergency Access-Sundridge/Pueblo 400 0 400 0% 0 0% 0

SV-P23 City of Scotts ValleEmergency Access-Bethany/Glenwood 200 0 200 0% 0 0% 0

SV-P24 City of Scotts ValleEmergency Access Granite Creek/Hwy 17 550 0 550 0% 0 0% 0

SV-P25 City of Scotts ValleEmergency Access SV DR/Upper Willis Dr. 1000 0 1000 0% 0 0% 0

SV-P26 City of Scotts ValleEmergency Access Whispering Pines 50 0 50 0% 0 0% 0

SV-P27 City of Scotts ValleCitywide General Maintenance and Operations 14300 7800 6500 20% 1300 50% 3250

SV-P28 City of Scotts ValleNeighborhood Traffic Calming 750 0 750 100% 750 100% 750SV-P29 City of Scotts ValleGlen Canyon Rd. Bike Lanes 1000 0 1000 0% 0 0% 0

SV-P30A City of Scotts ValleMt. Hermon Road Sidewalk Connections 500 0 500 100% 500 100% 500

SV-P32 City of Scotts ValleBluebonnet Lane Bike Lanes 150 0 150 100% 150 100% 150SV-P33 City of Scotts ValleCivic Center Drive Bike Lanes 400 0 400 0% 0 0% 0

SV-P34 City of Scotts ValleN. Navarra Dr-Sucinto Dr Bike Lanes 600 0 600 0% 0 0% 0

SV-P35 City of Scotts ValleBean Creek Road Sidewalks (SVMS to Blue Bonnet) 400 0 400 100% 400 100% 400

SV-P36 City of Scotts ValleEl Rancho Dr. Bike Lanes 325 0 325 0% 0 0% 0SV-P37 City of Scotts ValleLockhart Gulch Rd Bike Lanes 700 0 700 0% 0 0% 0SV-P38 City of Scotts ValleBike Rest Stops in Scotts Valley 225 0 225 0% 0 0% 0SV-P39 City of Scotts ValleGlenwood Dr. Bike Lanes 500 0 500 100% 500 100% 500

SV-P40 City of Scotts ValleLockwood Lane Sidewalk and Bike Lanes 500 0 500 100% 500 100% 500

SV-P41 City of Scotts ValleCitywide Bike Lanes 3000 0 3000 0% 0 0% 0

SV-P42 City of Scotts ValleSynchronize Traffic Signals along Mt. Hermon Road 100 0 100 100% 100 100% 100

SV-P43 City of Scotts Valle

Mt. Hermon Rd./Scotts Valley Dr. Intersection Operations Improvement Project 1000 0 1000 0% 0 0% 0

SV-P44 City of Scotts Valle

Mt. Hermon Rd./Hwy 17 Ramps Intersection Operations Improvement Project 1000 0 1000 0% 0 0% 0

SV-P45 City of Scotts ValleScotts Valley Town Center Bicycle/Pedestrian Facilities 4000 0 4000 50% 2000 50% 2000

SV-P46 City of Scotts ValleMt Hermon/King's Village Rd-Transit Signal priority 75 0 75 100% 75 100% 75

SV-P47 City of Scotts ValleMt Hermon/Scotts Valley - transit queue jump 600 0 600 100% 600 100% 600

SV-P48 City of Scotts ValleScotts Valley-wide - greenway signage 20 0 20 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

SV-P49 City of Scotts ValleMt Hermon Rd and Scotts Valley Drive -crosswalks 1000 0 1000 50% 500 50% 500

SV-P50 City of Scotts ValleMt Hermon/Scotts Valley - intersection improvements for bicycle treatment 10 0 10 100% 10 100% 10

SV-P51 City of Scotts ValleMt. Hermon Road/Town Center Entrance Traffic Signal 250 0 250 100% 250 100% 250

SV-P52 City of Scotts ValleKings Village Rd/Town Center Entrance Traffic Signal 200 0 200 100% 200 100% 200

SV-P53 City of Scotts ValleMt Hermon Rd to El Rancho Drive bike/ped connection 1000 0 1000 0% 0 0% 0

SV-P54 City of Scotts ValleMt Hermon Rd/ Spring Hill Road Pedestrian Intersection Improvements 50 0 50 100% 50 100% 50

CT-P32 City of WatsonvilleRiverside Drive/Hwy 129 Widening (Union-Bridge St) 8000 0 8000 0% 0 0% 0

CT-P33 City of WatsonvilleEast Lake/Hwy 152 Widening (Martinelli-Holohan) 1000 0 1000 0% 0 0% 0

CT-P38 City of WatsonvilleMain/Beach/Lake Ave Bike Facilities 0.002 0 0.002 0% 0 0% 0CT-P39 City of WatsonvilleRiverside Bike Facilities 0.02 0 0.02 0% 0 0% 0

WAT 01 City of WatsonvilleHwy 1/ Harkins Slough Road Interchange 9800 9800 0 0% 0 0% 0

WAT 27a City of WatsonvilleMain St. (Hwy 152)/Freedom Blvd Roundabout 1250 1250 0 0% 0 0% 0

WAT 39 City of WatsonvilleFreedom Blvd Reconstruction (Broadis St to Alta Vista Ave) 3500 3500 0 0% 0 0% 0

WAT-P04 City of WatsonvilleNeighborhood Traffic Plan 100 0 100 100% 100 100% 100

WAT-P06 City of WatsonvilleCitywide General Maintenance and Operations 55000 33000 22000 20% 4400 50% 11000

WAT-P11 City of WatsonvilleFreedom Blvd Improvements (Green Valley Rd to Compton Terrace) 5000 2000 3000 0% 0 0% 0

WAT-P13 City of WatsonvilleNeighborhood Traffic Plan Implementation 400 0 400 100% 400 100% 400

WAT-P15 City of WatsonvilleCitywide Pedestrian Facilities 2000 0 2000 50% 1000 50% 1000WAT-P19 City of WatsonvilleLump Sum Bicycle Projects 5000 0 5000 0% 0 0% 0WAT-P24 City of WatsonvilleCitywide Transportation Projects 24000 0 24000 0% 0 0% 0WAT-P27 City of WatsonvilleWatsonville Shuttle 250 0 250 0% 0 0% 0

WAT-P28 City of WatsonvilleAirport Blvd (Freedom Blvd to City Limits) 1500 950 550 100% 550 100% 550

WAT-P29 City of WatsonvilleCrestview/Wagner Extension 4000 0 4000 0% 0 0% 0

WAT-P30 City of WatsonvilleBuena Vista/Calbasas/Freedom Connection 5000 0 5000 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

WAT-P31 City of WatsonvilleOhlone Parkway Improvements - Phase 2 (UPRR to West Beach) 500 0 500 100% 500 100% 500

WAT-P33 City of WatsonvilleFreedom Blvd Reconstruction - Phase 3 (Alta Vista to Davis) 2500 0 2500 0% 0 0% 0

WAT-P34 City of WatsonvilleAirport Blvd Modifications (Hwy 1 to Ross Ave) 2000 0 2000 0% 0 0% 0

WAT-P35 City of WatsonvilleBridge Maintenance 100 100 0 0% 0 0% 0WAT-P36 City of WatsonvilleAlley Improvements 50 50 0 0% 0 0% 0

WAT-P37 City of WatsonvillePennsylvania Dr/Clifford St Roundabout 250 250 0 0% 0 0% 0

WAT-P38 City of WatsonvilleFreedom Blvd Undergrounding 1230 1230 0 0% 0 0% 0WAT-P39 City of WatsonvilleEast Fifth St (Main St to Lincoln St) 250 250 0 0% 0 0% 0

WAT-P40 City of WatsonvilleMain St Modifications (500 Block: Fifth St to East Lake Ave) 600 400 200 100% 200 100% 200

WAT-P41 City of WatsonvilleWest Lake Ave Modifications (Main St to Rodriguez St) 200 0 200 0% 0 0% 0

WAT-P42 City of WatsonvillePajaro Valley High School Connector Trail 600 0 600 100% 600 100% 600

WAT-P43 City of WatsonvilleUpper Watsonville Slough Trail 650 0 650 100% 650 100% 650

WAT-P44 City of WatsonvilleGreen Valley Rd Modifications (Struve Slough to Freedom Blvd) 1400 0 1400 100% 1400 100% 1400

WAT-P45 City of WatsonvilleGreen Valley Rd Modifications (Freedom Blvd to City Limit) 1750 0 1750 100% 1750 100% 1750

WAT-P46 City of WatsonvilleLower Watsonville Slough Trail 650 0 650 100% 650 100% 650

WAT-P47 City of WatsonvilleMain St Modifications (City Limit to Lake Ave) 1400 0 1400 100% 1400 100% 1400

WAT-P48 City of WatsonvilleWalker St Modifications (Beach St to Watsonville Slough) 2700 0 2700 0% 0 0% 0

WAT-P49 City of Watsonville2nd/Maple Ave (Lincoln to Walker) Traffic Calming and Greenway 15 0 15 100% 15 100% 15

WAT-P50 City of Watsonville5th St (Lincoln to Walker) - Traffic calming and Greenway 15 0 15 100% 15 100% 15

WAT-P51 City of WatsonvilleRodriguez St (Main St to Riverside)- buffered bike lane 10 0 10 100% 10 100% 10

WAT-P52 City of WatsonvilleUnion/Brennan (Freedom to Riverside) -sharrows 5 0 5 100% 5 100% 5

WAT-P53 City of WatsonvilleKearney/Rodriguez - ped crossing 25 0 25 100% 25 100% 25WAT-P54 City of WatsonvilleMain St - 3 HAWK signals 750 0 750 100% 750 100% 750

WAT-P55 City of WatsonvilleMain/Rodriguez/Union/Brennan (Freedom to Riverside) - crosswalks 100 0 100 100% 100 100% 100

WAT-P56 City of WatsonvilleWatsonville-wide HOV priority 50 0 50 100% 50 100% 50WAT-P57 City of WatsonvilleEast Lake/Madison - ped crossing 250 0 250 100% 250 100% 250

WAT-P58 City of WatsonvilleMain St (Freedom to Riverside) Ped/Bike Enhancements 750 0 750 100% 750 100% 750

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

WAT-P59 City of WatsonvilleDowntown Watsonville Universal Streets 500 0 500 100% 500 100% 500

WAT-P61 City of Watsonville

Freedom Blvd (Green Valley Rd to Lincoln) Bicycle and Pedestrian Improvements 2000 0 2000 100% 2000 100% 2000

WAT-P62 City of WatsonvilleFreedom Blvd Pedestrian Crossings (Airport to Lincoln) 500 0 500 100% 500 100% 500

WAT-P63 City of WatsonvillePajaro Lane to Freedom Blvd Ped/Bike Connection 300 0 300 0% 0 0% 0

WAT-P64 City of Watsonville

Freedom to Green Valley (at Hillside Avenue, Davis Avenue, Blanca Lane, Clifford Avenue, Mariposa Av 1500 0 1500 0% 0 0% 0

WAT-P60 City of WatsonvillleHillside Ave to Freedom Blvd Ped/Bike Connection 300 0 300 0% 0 0% 0

CTSA-P01 Consolidated TranCountywide Specialized Transportation 55000 34000 21000 50% 10500 50% 10500

CTSA-P02 Consolidated TranLift Line Maintenance/Operations Center 15000 0 15000 0% 0 0% 0

CTSA-P03 Consolidated TranNon-ADA Paratransit Service Expansion 21000 0 21000 0% 0 0% 0

CTSA-P04 Consolidated TranMedically Fragile Specialized Transportation 13000 0 13000 0% 0 0% 0

CTSA-P05 Consolidated TranAgricultural Worker Transportation Program 2550 0 2550 100% 2550 100% 2550

CO 50 County Health SerSanta Cruz County Health Service Agency - traffic safety education 6250 375 5875 100% 5875 100% 5875

VAR 01 County Health SerSanta Cruz County Open Streets 2000 0 2000 50% 1000 50% 1000

CO 16b County of Santa CWilder Ranch Bike/Pedestrian Path: Phase 2 4000 0 4000 0% 0 0% 0

CO 42b County of Santa CGreen Valley Rd Pedestrian Safety Project 375 375 0 0% 0 0% 0

CO 51 County of Santa CCorralitos Rd Left Turn Ln (Bradley Elementary School) 1000 1000 0 0% 0 0% 0

CO 62 County of Santa CNelson Rd PM 2.0 Storm Damage Repair 1500 1500 0 0% 0 0% 0

CO 64 County of Santa CAptos Village Plan Improvements 3377 3377 0 0% 0 0% 0

CO 65 County of Santa C17th Ave Cape Seal (Brommer to East Cliff) 363 363 0 0% 0 0% 0

CO 66 County of Santa CEast Cliff Drive Cape Seal (12th-17th) 222 222 0 0% 0 0% 0

CO 67 County of Santa CEmpire Grade Chip Seal: City of SC limits to 130' N of Heller Drive 328 328 0 0% 0 0% 0

CO 68 County of Santa CGreen Valley Rd Chip Seal: Devon Ln to Melody Ln (0.58 mi) 260 260 0 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO 69 County of Santa CMt. Hermon Rd Overlay: Graham Hill to 1000' N of Locatelli Ln 836 836 0 0% 0 0% 0

CO 70 County of Santa CPorter Street Overlay: Capitola Limits to 288' N/O Soquel Dr 341 341 0 0% 0 0% 0

CO-P02 County of Santa CAirport Blvd Improvements (City limits to Green Valley Rd) 1200 0 1200 100% 1200 100% 1200

CO-P03 County of Santa CAmesti Road Multimodal Improvements (Green Valley to Brown Valley Rd) 6000 0 6000 0% 0 0% 0

CO-P04 County of Santa CBear Creek Road Improvements (Hwy 9 to Hwy 35) 4600 0 4600 0% 0 0% 0

CO-P08 County of Santa C

Corralitos Road Rehab and Improvements (Freedom Blvd to Hames Rd) 600 0 600 100% 600 100% 600

CO-P09 County of Santa CEast Cliff Drive Improvements (32nd Ave to Harbor) 4600 0 4600 100% 4600 100% 4600

CO-P10 County of Santa CEmpire Grade Improvements 4600 0 4600 0% 0 0% 0

CO-P11 County of Santa C

Freedom Blvd Multimodal Improvements (Bonita Dr to City of Watsonville) 3000 0 3000 0% 0 0% 0

CO-P12 County of Santa CGraham Hill Road Multimodal Improvements (City of SC to Hwy 9) 6800 0 6800 0% 0 0% 0

CO-P13 County of Santa CGreen Valley Road Improvements 4000 0 4000 0% 0 0% 0

CO-P14 County of Santa CLa Madrona Dr Improvements (El Rancho Dr to City of Scotts Valley) 3500 0 3500 0% 0 0% 0

CO-P15 County of Santa CLakeview Road Improvements 1200 0 1200 0% 0 0% 0

CO-P16 County of Santa CRobertson Street Improvements (Soquel Wharf Rd to Soquel Dr.) 3500 0 3500 0% 0 0% 0

CO-P17 County of Santa CSims Road Improvements (Graham Hill Rd to La Madrona Dr) 1700 0 1700 0% 0 0% 0

CO-P18 County of Santa CSoquel Ave Improvements (City of SC to Gross Rd) 3200 0 3200 100% 3200 100% 3200

CO-P19 County of Santa CSoquel Dr Improvements (Soquel Ave to Freedom Blvd) 7300 0 7300 100% 7300 100% 7300

CO-P20 County of Santa CState Park Drive Improvements Phase 2 1300 0 1300 0% 0 0% 0

CO-P22 County of Santa CPaul Sweet Road Improvements (Soquel Dr to end) 1200 0 1200 100% 1200 100% 1200

CO-P23 County of Santa CCollege Road Improvements (Hwy 152 to Lakeview Rd) 1700 0 1700 0% 0 0% 0

CO-P24 County of Santa CLockwood Lane Improvements (Graham Hill Rd to SV limits) 850 0 850 0% 0 0% 0

CO-P26a County of Santa C41st Ave Improvements Phase 2 (Hwy 1 Interchange to Soquel Dr) 1200 0 1200 100% 1200 100% 1200

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO-P26b County of Santa CBeach Road Improvements (City limits to Pajaro Dunes) 1200 0 1200 0% 0 0% 0

CO-P26c County of Santa CBonny Doon Rd Improvements (State Hwy 1 to Smith Grade Rd) 2300 0 2300 0% 0 0% 0

CO-P26d County of Santa CBrown Valley Rd Improvements (Corralitos Rd to Redwood Rd) 1200 0 1200 0% 0 0% 0

CO-P26e County of Santa CBuena Vista Rd Improvements (San Andreas to Freedom Blvd) 2900 0 2900 0% 0 0% 0

CO-P26g County of Santa CCasserly Rd Improvements (Hwy 152 to Green Valley Rd) 750 0 750 0% 0 0% 0

CO-P26h County of Santa CCenter Ave/Seacliff Dr Improvements (Broadway to Aptos Beach Dr) 1200 0 1200 0% 0 0% 0

CO-P26i County of Santa CChanticleer Ave Improvements (Hwy 1 to Soquel Dr) 1200 0 1200 0% 0 0% 0

CO-P26j County of Santa CEast Zayante Rd Improvements (Lompico Rd to just before Summit Rd) 1700 0 1700 0% 0 0% 0

CO-P26k County of Santa CEl Rancho Dr Improvements (Mt. Hermon/Hwy 17 to SC city limits) 2300 0 2300 100% 2300 100% 2300

CO-P26l County of Santa CEureka Canyon Rd Improvements (Hames Rd to Buzzard Lagoon Rd) 2300 0 2300 0% 0 0% 0

CO-P26m County of Santa CGlen Canyon Rd Improvements (Branciforte Dr to City of Scotts Valley) 5800 0 5800 0% 0 0% 0

CO-P26n County of Santa CGlenwood Dr. Improvements (Scotts Valley city limits to State Hwy 17) 2900 0 2900 0% 0 0% 0

CO-P26p County of Santa CMattison Ln Improvements (Chanticleer Ave to Soquel Ave) 1400 0 1400 0% 0 0% 0

CO-P26q County of Santa CMt. Hermon Rd. Improvements (Lockhart Gulch to Graham Hill Rd) 2900 0 2900 100% 2900 100% 2900

CO-P26r County of Santa CPorter St Improvements (Soquel Dr to Paper Mill Rd) 1200 0 1200 0% 0 0% 0

CO-P26s County of Santa CSeascape Blvd Improvements (Sumner Ave to San Andreas Rd) 600 0 600 0% 0 0% 0

CO-P26u County of Santa CSummit Rd Improvements 5400 0 5400 0% 0 0% 0

CO-P27a County of Santa C

37th/38th Ave (Brommer to Eastcliff) Multimodal Circulation Improvements and Greenway 2000 0 2000 0% 0 0% 0

CO-P27b County of Santa CAptos Beach Dr Improvements (Esplande to Rio Del Mar Blvd) 1200 0 1200 0% 0 0% 0

CO-P27c County of Santa CCorcoran Ave Improvements (Alice St to Felt St) 600 0 600 0% 0 0% 0

CO-P27e County of Santa CMain St Improvements (Porter St to Cherryvale Ave) 1700 0 1700 100% 1700 100% 1700

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO-P27f County of Santa CMill St Improvements (entire length) 350 0 350 0% 0 0% 0

CO-P27g County of Santa CMountain View Rd Improvements (Branciforte Dr to Rodeo Gulch Rd) 1200 0 1200 0% 0 0% 0

CO-P27h County of Santa CPaulsen Rd Improvements (Green Valley Rd to Whiting Rd) 1200 0 1200 0% 0 0% 0

CO-P27i County of Santa CPinehurst Dr Improvements (entire length) 850 0 850 0% 0 0% 0

CO-P27j County of Santa CSeacliff Dr Improvements (entire length) 1700 0 1700 0% 0 0% 0

CO-P27k County of Santa CSpreckels Dr Improvements (Soquel Dr to Aptos Beach Dr) 1200 0 1200 0% 0 0% 0

CO-P27l County of Santa CWinkle Ave Improvements (entire length from Soquel Dr) 2300 0 2300 0% 0 0% 0

CO-P28a County of Santa CBean Creek Rd Improvements (Scotts Valley City Limits to Glenwood Dr) 1700 0 1700 0% 0 0% 0

CO-P28c County of Santa CCommercial Way Improvements (Mission Dr. to Soquel Dr.) 600 0 600 0% 0 0% 0

CO-P28d County of Santa CFelton Empire Road Improvements (entire length to State Hwy 9) 2300 0 2300 0% 0 0% 0

CO-P28f County of Santa CPine Flat Rd Improvements (Bonny Doon Rd to Empire Grade Rd) 2300 0 2300 0% 0 0% 0

CO-P28g County of Santa CSoquel-Wharf Rd Improvements (Robertson St to Porter St) 1000 0 1000 100% 1000 100% 1000

CO-P28h County of Santa CThurber Ln Improvements (entire length) 1700 0 1700 0% 0 0% 0

CO-P28i County of Santa CVarni Rd Improvements (Corralitos Rd to Amesti Rd) 1200 0 1200 0% 0 0% 0

CO-P29b County of Santa CBonita Dr Improvements (entire length) 1200 0 1200 0% 0 0% 0

CO-P29c County of Santa CCliff Dr. Improvements (Rio Del Mar to Railroad Crossing) 600 0 600 0% 0 0% 0

CO-P29e County of Santa CMaciel Ave. Improvements (Capitola Rd to Mattison Ln) 1400 0 1400 0% 0 0% 0

CO-P29f County of Santa CPaul Minnie Ave. Improvements (Rodriguez St to Soquel Ave) 1200 0 1200 0% 0 0% 0

CO-P29g County of Santa CPolo Dr. Improvements (Soquel Dr to end) 1400 0 1400 0% 0 0% 0

CO-P29h County of Santa CWebster St Improvements (Jose Ave to 16th St) 1200 0 1200 0% 0 0% 0

CO-P30b County of Santa CAlba Rd Improvements (Empire Grade to State Hwy 9) 1700 0 1700 0% 0 0% 0

CO-P30c County of Santa CBranciforte Dr. Improvements (City of Santa Cruz to Vine Hill Rd) 1700 0 1700 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO-P30d County of Santa CCabrillo College Dr. Improvements (Park Ave to Twin Lakes Church) 1200 0 1200 0% 0 0% 0

CO-P30f County of Santa CGlen Arbor Rd. Improvements (State Hwy 9 to State Hwy 9) 1200 0 1200 0% 0 0% 0

CO-P30h County of Santa CGranite Creek Rd. Improvements (Branciforte Dr to City of Scotts Valley) 1700 0 1700 0% 0 0% 0

CO-P30i County of Santa CLarkin Valley Rd. Improvements (San Andreas Rd to Buena Vista Dr) 600 0 600 0% 0 0% 0

CO-P30j County of Santa C

Laurel Glen Rd. Improvements (Soquel-San Jose Rd to Mt. View/Rodeo Gulch Rd) 1200 0 1200 0% 0 0% 0

CO-P30k County of Santa CLompico Rd. Improvements (E Zayante Rd. to end) 600 0 600 0% 0 0% 0

CO-P30l County of Santa CMar Monte Ave. Improvements (San Andreas Rd to State Hwy 1) 600 0 600 0% 0 0% 0

CO-P30n County of Santa CRio Del Mar Blvd. Improvements (Esplanade to Soquel Dr) 2900 0 2900 100% 2900 100% 2900

CO-P30p County of Santa CTrout Gulch Rd. Improvements (Soquel Dr. to end) 2900 0 2900 0% 0 0% 0

CO-P30q County of Santa C

Vine Hill Rd. Improvements (Branciforte/Mt. View Rd to State Hwy 17) 1400 0 1400 0% 0 0% 0

CO-P31a County of Santa C26th Ave Improvements (entire length-Portola Dr to end) 2500 0 2500 0% 0 0% 0

CO-P31b County of Santa CCapitola Rd. Ext Improvements (Capitola Rd to Soquel Ave) 1200 0 1200 0% 0 0% 0

CO-P31c County of Santa CDay Valley Rd. Improvements (entire length-Freedom Blvd to Valencia Rd) 1200 0 1200 0% 0 0% 0

CO-P31d County of Santa CLedyard Way Improvements (entire length-Soquel Dr to Soquel Dr) 600 0 600 0% 0 0% 0

CO-P31e County of Santa CLockhart Gulch Improvements (Scotts Valley City limits to end) 1200 0 1200 0% 0 0% 0

CO-P31f County of Santa CMesa Dr. Improvements (Vienna Drive to Ledyard Way) 1200 0 1200 0% 0 0% 0

CO-P31g County of Santa COpal Cliff Dr. Improvements (41st Av to Captiola City Limits) 1200 0 1200 100% 1200 100% 1200

CO-P31h County of Santa CPioneer Rd. Improvements (Amesti Rd to Green Valley Rd) 850 0 850 0% 0 0% 0

CO-P31i County of Santa C

Rodeo Gulch Rd. Improvements (So & North: Mt. View/Laurel Glen Rd to Hwy 1) 1700 0 1700 0% 0 0% 0

CO-P31j County of Santa CRoland Dr. Improvements (30th to 35th) 850 0 850 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO-P32a County of Santa CClubhouse Drive Improvements (Sumner Av to Rio Del Mar Blvd) 1400 0 1400 0% 0 0% 0

CO-P32b County of Santa CHames Rd Improvements (entire length-Freedom Blvd to Eureka Canyon Rd) 3500 0 3500 0% 0 0% 0

CO-P32c County of Santa C

Harkins Slough Rd. Improvements (entire length-Buena Vista Dr to State Hwy 1) 1700 0 1700 0% 0 0% 0

CO-P32d County of Santa CHuntington Dr. Improvements (Monroe Ave to Valencia Rd.) 2300 0 2300 0% 0 0% 0

CO-P32e County of Santa CJamison Cr. Rd Improvements (entire length-Empire Grade to Hwy 236) 600 0 600 0% 0 0% 0

CO-P32f County of Santa CQuail Hollow Rd Improvements (entire length- East Zayante to Glen Arbor Rd) 800 0 800 0% 0 0% 0

CO-P32g County of Santa C

Smith Grade Improvements (entire length-Empire Grade to Bonny Doon Rd) 2300 0 2300 0% 0 0% 0

CO-P32h County of Santa C

Sumner Ave. Improvements (entire length-Rio Del Mar Blvd to end [just past via Novella]) 1400 0 1400 0% 0 0% 0

CO-P32j County of Santa CValencia Rd. Improvements (Trout Gulch Rd to Valencia School Rd) 1700 0 1700 0% 0 0% 0

CO-P33a County of Santa C

Bowker Rd. Improvements (entire length-Buena Vista Dr to Freedom Blvd) 600 0 600 0% 0 0% 0

CO-P33b County of Santa CCathedral Dr. Improvements (entire length) 600 0 600 0% 0 0% 0

CO-P33c County of Santa C

Esplanade Improvements (entire loop: Aptos Beach Dr to Moosehead/Aptos Beach Dr) 1200 0 1200 0% 0 0% 0

CO-P33d County of Santa CHarper St Improvements (entire length-El Dorado Ave to ECM) 1200 0 1200 0% 0 0% 0

CO-P33e County of Santa C

Manfre Rd. Improvements (entire length-Larkin Valley Rd to Buena Vista Dr) 600 0 600 0% 0 0% 0

CO-P33f County of Santa C

Mar Vista Drive Improvements (entire length-just before Seacliff Dr to Soquel Dr) 290 0 290 0% 0 0% 0

CO-P33g County of Santa CMcGregor Dr. Improvements (Capitola city limits to Searidge Rd) 1200 0 1200 0% 0 0% 0

CO-P33h County of Santa CThompson Ave. Improvements (entire length-Capitola Rd to end) 1200 0 1200 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO-P33i County of Santa CWallace Ave. Improvements (entire length-Huntington Dr to end) 850 0 850 0% 0 0% 0

CO-P35 County of Santa CCountywide General Road Maintenance and Operations 473000 165000 308000 20% 61600 40% 123200

CO-P36 County of Santa CSoquel-San Jose Rd Improvements (Paper Mill Rd to Summit Rd) 2500 0 2500 100% 2500 100% 2500

CO-P37 County of Santa CCountywide Access Ramps 1200 0 1200 50% 600 50% 600CO-P38 County of Santa CPajaro River Bike Path System 9200 0 9200 100% 9200 100% 9200CO-P39 County of Santa CMurphy Crossing Improvements 1200 0 1200 0% 0 0% 0

CO-P40 County of Santa CGlen Coolidge Drive/Hwy 9 Bike Path 2300 0 2300 0% 0 0% 0CO-P41 County of Santa CCountywide Sidewalks 70000 0 70000 20% 14000 20% 14000

CO-P42 County of Santa CSpreckels Dr/Treasure Island Dr Improvements 600 0 600 0% 0 0% 0

CO-P43 County of Santa CBonny Doon Road Improvements 8000 0 8000 0% 0 0% 0CO-P46 County of Santa CSan Lorenzo River Valley Trail 25000 0 25000 0% 0 0% 0

CO-P46a County of Santa C

San Lorenzo Valley Trail: Hwy 9 - Downtown Felton Bike Lanes & Sidewalks 2200 0 2200 100% 2200 100% 2200

CO-P46b County of Santa CSan Lorenzo Valley Trail: Hwy 9 - North Felton Bike Lanes & Sidewalks 7400 0 7400 100% 7400 100% 7400

CO-P49 County of Santa CCarol Way/Lompico Creek Bridge Replacement 1200 0 1200 0% 0 0% 0

CO-P50 County of Santa CEast Cliff Drive Pedestrian Pathway (5th-7th Ave) 1700 1700 0 0% 0 0% 0

CO-P51 County of Santa CRedwood Lodge Rd (Entire Length) 3000 0 3000 0% 0 0% 0

CO-P56 County of Santa CCarlton Rd Traffic Improvements for Trucks (Lakeview Intersection) 750 0 750 0% 0 0% 0

CO-P58 County of Santa CSoquel Dr Traffic Signal and Left Turn Lane (Robertson St) 500 0 500 0% 0 0% 0

CO-P61 County of Santa C

Glenwood Cutoff General Improvements (Glenwood Dr to Hwy 17) 3000 0 3000 0% 0 0% 0

CO-P62 County of Santa CSoquel Dr Road Improvements (Robertson St to Daubenbiss) 400 0 400 100% 400 100% 400

CO-P65 County of Santa CBulb Ave Road Improvements (Garden St to Capitola City Limits) 750 0 750 0% 0 0% 0

CO-P67 County of Santa CEl Dorado Ave Road Improvements (Capitola Rd to RR) 1750 0 1750 0% 0 0% 0

CO-P68 County of Santa CThurwachter Road Bike Lanes 50 0 50 0% 0 0% 0CO-P71 County of Santa CCountywide Bike Projects 4000 0 4000 0% 0 0% 0

CO-P72 County of Santa CMar Vista to State Park Dr New Ped/Bike Connection 500 0 500 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

CO-P73 County of Santa CSeacliff Dr/North Avenue Bike/Ped Connection to MBSST 300 0 300 0% 0 0% 0

CO-P74 County of Santa CSearidge Drive (Mar Vista to State Park) Bike Improvements 100 0 100 100% 100 100% 100

CO-P75 County of Santa CRancho Del Mar Shopping Center (Rail Line to State Park) bike/ped path 300 0 300 100% 300 100% 300

CO-P76 County of Santa C35th to 41st (at Roland Way) New Ped/Bike Connection 500 0 500 0% 0 0% 0

CO-P77 County of Santa CEast Cliff (26th to Moran Way) Sidewalk Improvement 400 0 400 0% 0 0% 0

CO-P78 County of Santa C26th to 30th (at Lode/Quartz) Bike/Ped Connection 500 0 500 0% 0 0% 0

CO-P79 County of Santa C41st Ave (Portola to Eastcliff) Bike/Ped Enhancement 200 0 200 100% 200 100% 200

CO-P80 County of Santa CPortola Ave (26th to 41st) Bike/Ped Enhancement 300 0 300 100% 300 100% 300

CO-P81 County of Santa C

Brommer and Portola Bike/Ped Connection (atThompson and Vanessa Ln) 300 0 300 100% 300 100% 300

RTC 17 Ecology ActionEcology Action Transportation Employer Membership Program 2250 435 1815 100% 1815 100% 1815

RTC 26 Ecology Action Bike To Work/School Program 3500 1100 2400 100% 2400 100% 2400

RTC 01 SCCRTCFreeway Service Patrol (FSP) on Hwy 1 and Hwy 17 9200 4500 4700 100% 4700 100% 4700

RTC 02 SCCRTCCommute Solutions Rideshare Program 6250 1750 4500 100% 4500 100% 4500

RTC 04 SCCRTCPlanning, Programming & Monitoring (PPM) - SB45 4600 4600 0 0% 0 0% 0

RTC 15 SCCRTC Vanpool Incentive Program 625 0 625 100% 625 100% 625RTC 16 SCCRTC Bike Parking Subsidy Program 700 0 700 100% 700 100% 700RTC 25 SCCRTC Recreational Rail Infrastructure 5000 0 5000 100% 5000 100% 5000

RTC 27a SCCRTC

Monterey Bay Sanctuary Scenic Trail Network - Design, Environmental Clearance, and Construction 86000 7000 79000 50% 39500 50% 39500

RTC 27b SCCRTCMonterey Bay Sanctuary Scenic Trail Network - Maintenance 4000 0 4000 50% 2000 50% 2000

RTC 27c SCCRTCMonterey Bay Sanctuary Scenic Trail Network - Trail Management Program 1000 0 1000 100% 1000 100% 1000

RTC 32 SCCRTC Bicycle Route Signage Countywide 500 100 400 100% 400 100% 400RTC-P01 SCCRTC SAFE: Call Box System Along Hwys 5390 5390 0 0% 0 0% 0

RTC-P02 SCCRTCRail Transit: Watsonville-Santa Cruz Corridor 82500 0 82500 50% 24750 100% 82500

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

RTC-P03 SCCRTC Rail Line Management 3500 3500 0 0% 0 0% 0RTC-P07 SCCRTC SCCRTC Administration (TDA) 14000 14000 0 0% 0 0% 0RTC-P08 SCCRTC SCCRTC Planning 19500 19500 0 0% 0 0% 0RTC-P34 SCCRTC 511 Travel Information System 2200 0 2200 100% 2200 100% 2200RTC-P41 SCCRTC Rail Line: Freight Service Upgrades 20000 0 20000 100% 20000 100% 20000RTC-P49 SCCRTC RTC Bikeway Map 300 0 300 100% 300 100% 300

RTC-P50 SCCRTCCounty-wide bicycle, pedestrian and vehicle occupancy counts 400 0 400 100% 400 100% 400

RTC-P51 SCCRTC Performance Monitoring 1600 0 1600 100% 1600 100% 1600

RTC-P54 SCCRTC School-based mobility/TDM programs 2500 0 2500 100% 2500 100% 2500RTC-P55 SCCRTC Rail Line Planning 500 0 500 100% 500 100% 500

RTC-P56 SCCRTCTransportation Demand Management Ordinance and User Guide 250 0 250 100% 250 100% 250

RTC-P57 SCCRTC Shared Parking Program 150 0 150 100% 150 100% 150RTC-P58 SCCRTC Real-Time Transit Info 500 0 500 100% 500 100% 500

CT-P01 SCCRTC/CaltransHwy 1 Ramp Metering: Southern Sections 20000 0 20000 0% 0 0% 0

RTC 24 SCCRTC/Caltrans91 - Hwy 1: HOV Lanes from Morrissey to San Andreas Rd 0.05 0 0.05 0% 0 0% 0

RTC 24a SCCRTC/Caltrans

8 - Hwy 1: Reconstruct Remaining Interchanges, Auxiliary Lanes and Install Ramp Metering 250000 0 250000 0% 0 0% 0

RTC 24e SCCRTC/Caltrans3 - Hwy 1: Park Avenue to Bay/Porter Auxiliary Lanes 23000 0 23000 100% 23000 0% 0

RTC 24f SCCRTC/Caltrans2 - Hwy 1: 41st to Soquel Av Auxiliary Lanes and Chanticleer Bike/Ped Bridge 27000 27000 0 0% 0 0% 0

RTC 24g SCCRTC/Caltrans4 - Hwy 1: State Park Dr. to Park Ave. Auxiliary Lanes 34250 0 34250 100% 34250 0% 0

RTC 24h SCCRTC/Caltrans5 - Hwy 1: Reconstruct Morrissey Interchange 35300 0 35300 100% 35300 0% 0

RTC 24i SCCRTC/Caltrans6 - Hwy 1: Reconstruct Soquel Avenue Interchange 63300 0 63300 100% 63300 0% 0

RTC 24j SCCRTC/Caltrans7 - Hwy 1: Reconstruct Bay/Porter and 41st Avenue Interchange 107500 0 107500 0% 0 0% 0

RTC 24k SCCRTC/Caltrans1 - Hwy 1 Corridor Investment Program 0.005 0 0.005 0% 0 0% 0

RTC 24m SCCRTC/Caltrans9 - Hwy 1: Construction of HOV Lanes from Morrissey to San Andreas Rd 60000 0 60000 0% 0 0% 0

RTC 24n SCCRTC/Caltrans92 - Hwy 1: TSM Project from Morrissey to San Andreas Rd. 0.005 0 0.005 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

RTC 30 SCCRTC/CaltransHwy 1 Bicycle/Ped Overcrossing at Mar Vista 7550 7550 0 0% 0 0% 0

MTD 02 SCMTD ADA Paratransit Bus Replacements 13000 600 12400 20% 2480 30% 3720

MTD 13 SCMTDSanta Cruz Metro Center/Pacific Station Renovation 12000 2100 9900 0% 0 0% 0

MTD 18 SCMTD Replacement Transit Fareboxes 9100 100 9000 0% 0 0% 0MTD-P04 SCMTD Metro Bus Replacements 125500 2500 123000 20% 24600 33% 40590

MTD-P06 SCMTD Transit Technological Improvements 7350 0 7350 0% 0 0% 0MTD-P09 SCMTD Bus Stop Upgrades 8100 100 8000 50% 4000 50% 4000

MTD-P10 SCMTDLocal Transit - Continuation of Existing Service Levels 2010-2035 773000 773000 0 0% 0 0% 0

MTD-P10B SCMTDHwy 17 Express Service - Cont. of Existing Service Levels 53000 53000 0 0% 0 0% 0

MTD-P10C SCMTDADA Paratransit Service - Continuation of Existing Service 101000 101000 0 0% 0 0% 0

MTD-P11 SCMTD ADA Service Expansion 3500 0 3500 100% 3500 100% 3500MTD-P12 SCMTD Hwy 17 Express Service Expansion 4500 0 4500 100% 4500 100% 4500MTD-P13 SCMTD UCSC Bus Service Expansion 14000 0 14000 90% 12600 0% 0

MTD-P14 SCMTDLocal Transit Service Restoration and Expansion 177000 0 177000 0% 0 0% 0

MTD-P15 SCMTD Bus Rapid Transit 25920 0 25920 100% 25920 60% 15552

MTD-P18 SCMTD Commuter/Subscription Bus Program 2000 0 2000 0% 0 0% 0

MTD-P19 SCMTDTransit Mobility Training Program Expansion 1200 0 1200 100% 1200 100% 1200

MTD-P20 SCMTD Bikes on Buses Expansion 1500 0 1500 100% 1500 100% 1500

MTD-P21 SCMTD Signal Priority/Pre-Emption for Buses 2000 0 2000 100% 2000 100% 2000MTD-P23 SCMTD Bike Station at Capitola Mall 1000 0 1000 0% 0 0% 0MTD-P24 SCMTD Small Bus Fleet 0.01 0 0.01 0% 0 0% 0MTD-P27 SCMTD Hwy 1 Express Buses 6000 0 6000 20% 1200 50% 3000MTD-P28 SCMTD ParaCruz Operating Facility 12000 0 12000 0% 0 0% 0MTD-P29 SCMTD Solar Panels for MetroBase 6000 0 6000 0% 0 0% 0

MTD-P30 SCMTDParaCruz Mobile Data Terminals; Radios 732 732 0 0% 0 0% 0

MTD-P31 SCMTD Bus Rebuild and Maintenance 2500 0 2500 100% 2500 100% 2500MTD-P32 SCMTD Non-Revenue Vehicles 1200 0 1200 0% 0 0% 0

MTD-P33 SCMTDTransit Security and Surveillance Systems 1100 860 240 100% 240 100% 240

MTD-P34 SCMTD Disaster Response Mobile Command 500 0 500 0% 0 0% 0

MTD-P35 SCMTDTransit System Technology Improvements 5310 980 4330 0% 0 0% 0

MTD-P36 SCMTD Metro facilities repair/upgrades 3785 155 3630 100% 3630 100% 3630

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

MTD-P38 SCMTD MetroBase Phase II 15000 0 15000 0% 0 0% 0MTD-P39 SCMTD Parking Structure 4000 0 4000 0% 0 0% 0MTD-P40 SCMTD Water Harvesting for River St. 1500 0 1500 0% 0 0% 0

MTD-P42 SCMTDSenior/Disabled/Low-Income Fixed-Route Transit Incentives 3125 0 3125 100% 3125 100% 3125

MTD-P43 SCMTD Deviated Fixed-Route Pilot Program 100 0 100 0% 0 0% 0MTD-P44 SCMTD Inter-County Paratransit Connection 1250 0 1250 100% 1250 100% 1250

MTD-P45 SCMTDTransit/Paratransit Driver Emergency Training 250 0 250 100% 250 100% 250

MTD-P46 SCMTDWatsonville Transit Center Improvements 1000 1000 0 0% 0 0% 0

MTD-P47 SCMTD Electric Non-Fleet Vehicles 560 560 0 0% 0 0% 0MTD-P48 SCMTD EV Fast Charging Stations 1000 1000 0 0% 0 0% 0MTD-P49 SCMTD Pacific Station- Bike Station 400 0 400 100% 400 100% 400

RTC-P43 Seniors CouncilSenior Employment Ride Reimbursement 1600 0 1600 100% 1600 100% 1600

UC-P01 UCSC UCSC Main Entrance Improvements 2000 0 2000 0% 0 0% 0UC-P02 UCSC West Gate Improvements 500 0 500 0% 0 0% 0

UC-P03 UCSCSteinhart Way Multimodal Improvements 500 0 500 0% 0 0% 0

UC-P04 UCSCMeyer Drive Extension/Jordan Gulch Bridges 20000 0 20000 0% 0 0% 0

UC-P07 UCSC Northern Loop Roadway 18000 0 18000 0% 0 0% 0UC-P08 UCSC Northern Entrance 10000 0 10000 0% 0 0% 0

UC-P10 UCSCHagar/McLaughlin Intersection Improvements 500 0 500 0% 0 0% 0

UC-P14 UCSCHagar/Steinhart Intersection Improvements 1000 0 1000 0% 0 0% 0

UC-P19 UCSCTransit Pullouts and Shelters Enhancements 1500 0 1500 0% 0 0% 0

UC-P22 UCSCAlternative Fuel/Electric shuttle vehicles 10000 0 10000 0% 0 0% 0

UC-P23 UCSC Transit Vehicles (ongoing) 5000 5000 0 0% 0 0% 0

UC-P30 UCSCMcLaughlin Drive Bike Lanes/Pedestrian Enhancements 2500 0 2500 0% 0 0% 0

UC-P32 UCSC UCSC Bike Showers/Storage Lockers 600 0 600 0% 0 0% 0

UC-P33 UCSC UCSC Bicycle Parking Improvements 500 0 500 100% 500 100% 500UC-P34 UCSC Spring Street Bikeway 300 0 300 0% 0 0% 0

UC-P36 UCSCPorter/Performing Arts Pedestrian Bridge 1000 0 1000 0% 0 0% 0

UC-P37 UCSCCollege Nine/Crown College Pedestrian Bridge 1500 0 1500 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

UC-P38 UCSCPedestrian Directional Map/Wayfinding System 500 500 0 0% 0 0% 0

UC-P39 UCSCCollege Nine/Communications Pedestrian Bridge 1000 0 1000 0% 0 0% 0

UC-P40 UCSCScience Hill/North Academic Core Pedestrian Bridge 1000 0 1000 0% 0 0% 0

UC-P42 UCSC Coolidge Overlook 600 0 600 0% 0 0% 0UC-P44 UCSC UCSC Pedestrian/Transit Zone 1000 0 1000 0% 0 0% 0UC-P46 UCSC East Collector Transit Hub 5000 0 5000 0% 0 0% 0

UC-P47 UCSC

Hagar-Coolidge Connector Road/Hagar/East Remote Intersection Improvements 3000 0 3000 0% 0 0% 0

UC-P48 UCSCUCSC - Metro Station Bus Rapid Transit Improvements 5000 0 5000 0% 0 0% 0

UC-P49a UCSCCoastal Marine Campus Roadway and Transit Improvements 7000 4000 3000 0% 0 0% 0

UC-P49b UCSCCoastal Marine Campus Bike Improvements 300 300 0 0% 0 0% 0

UC-P49c UCSCCoastal Marine Campus Pedestrian Improvements 2000 2000 0 0% 0 0% 0

UC-P50 UCSC Sidewalk/pedestrian Improvements 5000 0 5000 0% 0 0% 0UC-P51 UCSC Bike Shuttle Vehicle Acquisition 500 0 500 0% 0 0% 0UC-P52 UCSC UCSC Bike Loan Program 1000 0 1000 0% 0 0% 0UC-P55 UCSC UCSC Bicycle Facilities 1000 0 1000 0% 0 0% 0

UC-P56 UCSCHeller Drive Bicycle Lanes (Empire Grade to Porter College) 800 0 800 0% 0 0% 0

UC-P57 UCSCKresge/Core West Pedestrian Bridge: ADA Upgrades 3000 0 3000 0% 0 0% 0

UC-P58 UCSC UCSC Traffic Control 2500 2500 0 0% 0 0% 0

UC-P59 UCSCUCSC Lump Sum Roadway Maintenance 10000 0 10000 20% 2000 30% 3000

UC-P60 UCSCGreat Meadow Bike Path Safety Improvements 3000 0 3000 30% 900 30% 900

UC-P61 UCSCTraveller Safety Education/Information Programs 100 100 0 0% 0 0% 0

UC-P62 UCSCBus Tracking and AVL Transit Programs 250 250 0 0% 0 0% 0

UC-P63 UCSC UCSC Vanpool Program 8400 8400 0 0% 0 0% 0UC-P64 UCSC Alternative Fuel Fleet Vehicles 3000 0 3000 0% 0 0% 0UC-P65 UCSC Electric Vehicle Charging Stations 300 300 0 0% 0 0% 0

UC-P66 UCSCTransportation-Related Stormwater Management Projects 1000 1000 0 0% 0 0% 0

UC-P67 UCSCZimride Emergency Preparedness Database 300 0 300 0% 0 0% 0

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

UC-P68 UCSCParking Management Technology Improvements 400 400 0 0% 0 0% 0

UC-P69 UCSC UCSC Commute Counseling Program 3000 3000 0 0% 0 0% 0

UC-P70 UCSC UCSC Commuter Incentive Programs 1500 1500 0 0% 0 0% 0UC-P71 UCSC Solar PVs on Campus Parking Lots 0.001 0 0.001 0% 0 0% 0

UC-P72 UCSCKerr/Porter Rd Pedestrian Bridge ADA Upgrades 3000 0 3000 0% 0 0% 0

UC-P73 UCSCUCSC Parking Operations & Maintenance 68200 68200 0 0% 0 0% 0

UC-P74 UCSC UCSC Transit Service 60060 60060 0 0% 0 0% 0UC-P75 UCSC Disability Van Service 5280 5280 0 0% 0 0% 0

CT-P07a Various AgenciesHwy 1 Bike/Ped Bridge (Cabrillo-New Brighton) 8000 0 8000 0% 0 0% 0

RTC 33 Various Agencies Cabrillo College TDM Programs 1515 75 1440 100% 1440 100% 1440

RTC-P25 Various AgenciesTransit Oriented Development Grant Program 5000 0 5000 100% 5000 100% 5000

RTC-P26 Various AgenciesCountywide Pedestrian Signal Upgrades 2000 0 2000 100% 2000 100% 2000

RTC-P32 Various Agencies Countywide Pedestrian Planning Grant 300 0 300 100% 300 100% 300

RTC-P48 Various AgenciesClimate Action Transportation Programs 2500 0 2500 100% 2500 100% 2500

RTC-P53 Various AgenciesTDM individualized employer/multiunit housing program 4500 0 4500 100% 4500 100% 4500

VAR-P03 Various Agencies Bicycle Sharrows 500 0 500 50% 250 50% 250VAR-P04 Various Agencies Mobility Management Center 7500 0 7500 0% 0 0% 0

VAR-P05 Various Agencies Bike-Activated Traffic Signal Program 1000 0 1000 100% 1000 100% 1000VAR-P06 Various Agencies Carsharing Program 2500 0 2500 0% 0 0% 0

VAR-P07 Various Agencies Transportation System Electrification 50000 0 50000 0% 0 0% 0VAR-P08 Various Agencies Safe Paths of Travel 3000 0 3000 100% 3000 100% 3000VAR-P10 Various Agencies Safe Routes to Schools Studies 200 0 200 100% 200 100% 200VAR-P11 Various Agencies Local Arterial ITS Infrastructure 600 0 600 0% 0 0% 0VAR-P14 Various Agencies Lump Sum Bridge Preservation 69500 69500 0 0% 0 0% 0

VAR-P15 Various Agencies Transportation for Low Income Youth 2500 0 2500 0% 0 0% 0VAR-P16 Various Agencies Bike Share 5000 0 5000 0% 0 0% 0

VAR-P17 Various AgenciesEco-Tourism - Sustainable Transportation 1000 0 1000 100% 1000 100% 1000

VAR-P18 Various AgenciesMission St/Hwy 1 Bike/Truck Safety Campaign 500 0 500 100% 500 100% 500

VAR-P19 Various Agencies School Safety Programs 3700 0 3700 100% 3700 100% 3700

RTP_Num Agency ProjectTotal Project Cost (1000s)

Projects with dedicated funds or are already programmed. Cost

(1000s)

Project cost still needed after

dedicated funds removed. (Total cost -

Ded/prog cost)% of

projectCost

(1000s)% of

projectCost

(1000s)

Hybrid 1 Hybrid 2

VAR-P20 Various Agencies Public Transit Marketing 1500 0 1500 100% 1500 100% 1500

VAR-P21 Various AgenciesPlugin Electric Vehicle Access, Education & Promotion 800 0 800 0% 0 0% 0

VAR-P22 Various AgenciesMonterey Bay Electric Vehicle Alliance (MBEVA) 400 0 400 0% 0 0% 0

VAR-P23 Various Agencies Coolidge Drive Reconstruction 3000 0 3000 0% 0 0% 0VAR-P24 Various Agencies Countywide Senior Driving Training 80 0 80 100% 80 100% 80

VAR-P25 Various AgenciesPlanning for Transit Oriented Development for Seniors 75 0 75 100% 75 100% 75

VAR-P26 Various Agencies Park and Ride Lot Development 8000 0 8000 0% 0 0% 0VAR-P27 Various Agencies Complete Streets Implementation 10000 0 10000 0% 0 0% 0VAR-P28 Various Agencies Complete Streets Area Plan 2000 0 2000 100% 2000 100% 2000

VAR-P29 Various AgenciesPublic/Private Partnership Bicycle and Pedestrian Connection Plan 150 0 150 100% 150 100% 150

VAR-P30 Various AgenciesPublic/Private Partnership Transit Stops and Pull Outs Plan 150 0 150 100% 150 100% 150

VAR-P31 Various AgenciesUncontrolled Pedestrain Crossing Improvements 5000 0 5000 0% 0 0% 0

VAR-P32 Various AgenciesBicycle Treatments for intersection improvements (ADD) 5000 0 5000 100% 5000 100% 5000

VAR-P33 Various Agencies Neighborhood Greenways 5000 0 5000 0% 0 0% 0VAR-P34 Various Agencies Transit Priority 5000 0 5000 100% 5000 100% 5000VAR-P35 Various Agencies School Complete Streets Projects 10000 0 10000 0% 0 0% 0

VC-P1 Volunteer CenterVolunteer Center Transportation Program 3750 0 3750 100% 3750 100% 3750

AIR-P01 Watsonville AirporLump Sum Watsonville Airport Capital Projects 26500 12188 14312 0% 0 0% 0

AIR-P02 Watsonville Airpor Watsonville Airport Operations 44000 44000 0 0% 0 0% 05660102.193 2067367 3592735.193 674405 673877Total Need Total ded/prog

Discretionary/Semi-flexible

funds 674,000 Total funds estimated to be available if half cent sales tax measure and

vehicle registration fee is passed 2,740,000