04-0619CA technical archives TRIC Training Log: 06-19-04 Client: Orange Coast Plumbing, Santa Ana, CA Job: Replace 4” C. I. drain line under concrete patio at fire station Pull: 40’ / 4” / SDR17 / Downstream

description

Job: Replace 4” C. I. drain line under concrete patio at fire stationPull: 40’ / 4” / SDR17 / Downstream

Transcript of Santa Ana, CA 6/19/04

Page 1: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

TRIC Training Log: 06-19-04

Client: Orange Coast Plumbing, Santa Ana, CA

Job: Replace 4” C. I. drain line under concrete patio at fire station

Pull: 40’ / 4” / SDR17 / Downstream

Page 2: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

The cast: The able crew of Orange Coast Plumbing in Santa Ana, CA.

Page 3: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

The pull: 40’ under concrete, pulling hole (in foreground) is downstream. Material to be replaced is bell-and-spigot 4” cast iron.

Page 4: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Entry hole: Roughly 2.5’ x 4’ x 3.5’ deep.

Page 5: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Pulling hole: Roughly 4’ x 4” x 5’ deep.

Page 6: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Setup: Snapping out old cast iron cleanout manifold at pulling hole.

Page 7: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Head assembly: Ready to fuse the PE end cap.

Page 8: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Wonder plastic: A word on the durability and versatility of PE pipe.

Page 9: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Head assembly: Using a socket wrench to secure clevis head to PE end cap after fusion.

Page 10: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Securing pipe in jig: Note wood used to level pipe with fusing machine.

Page 11: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

New specimen: A quick explanation of the pipe bursting process.

Page 12: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Fusing: Watch closely, and join ends just enough to see an even bead roll from each facing surface. Going further will weaken the joint by pushing beyond the melted material.

Page 13: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Bead reaming: After each joint has completely cooled, leave pipe in fusion jig for support and alignment during the bead reaming process (required in some areas).

Page 14: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Straight shooting: Lining up reamer with pipe.

Page 15: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

The spin: Use a sturdy right-angle drill with enough torque to do the job.

Page 16: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Reaming: Note shaved bead removed by reamer blade.

Page 17: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Fusion machine: Lining up pipe in the jig.

Page 18: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Alignment: Adjust entire length of pipe from side to side or up and down to match ends as closely as possible before trimming. Some PE pipe may be slightly out of round due to storage or

temperature variations. In this case, rolling the pipe in the jig can help match outside diameters.

Page 19: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Heating: Check mating surfaces again after trimming before inserting heating iron.

Page 20: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Heating iron: Factory set at 450º, here shown set at 500º. Allow a half-hour to warm up.

Page 21: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Fusing logistics: You may elect to fuse head assembly last. Putting the head on one end of the line versus the other can greatly facilitate entry positioning.

Page 22: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Cooling: For most common PE pipe sizes up to 6” diameter, a good rule of thumb is 10 minutes per joint. Pipe should remain undisturbed while cooling. See manufacturer’s

specifications for further details.

Page 23: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

The business end: Trimming the head assembly for fusing.

Page 24: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Before heating: Remove trimmings from jig area, being careful not to touch mating surfaces..

Page 25: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Last joint.

Page 26: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Entry hole: Note relatively tight angle of attack. Here the top of the old pipe in the ground is broken out to ease entry.

Page 27: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Positioning: Hauling pipe into place to connect to cable.

Page 28: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Almost ready: Head assembly is attached to the cable. Note orange spray paint on cable just before clevis sheath (cable terminator). This makes clevis more visible as it approaches the pulley assembly.

Page 29: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Entry: Give the cable enough room to take up any slack before tension occurs. Also be aware of which way the clevis assembly is “hinging” so that it moves in the natural direction of the pull.

Page 30: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Good start: Flexible yet durable PE pipe can negotiate tight angles. Always monitor head upon entry, to begin pull as smoothly as possible.

Page 31: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Progress: After the first few feet, the length of pipe usually needs little attention.

Page 32: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Least resistance: Monitor pipe to ensure that no unnecessary scraping or gouging occurs as line is dragged into the earth. Here the concrete edge of the entry hole was

smooth enough so as not to require protection.

Page 33: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Versatile: TRIC ram can operate at any axial rotation on pulley assembly. Also, note pressure plate against utility line. If other utilities interfere with pull, pressure plate can be

rotated or even removed, and steel poles driven in its place to resist pulley pressure.

Page 34: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Interference: Here another utility line makes using the extender cage precarious.

Page 35: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Remedy: Use extended cribbing instead.

Page 36: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Whatever works: Keep plenty of wood on hand. Thick plywood, 2” x 4” and 4” x 4”lumber makes setup easier, and can even save the day.

Page 37: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Helping hand: Reinserting cable into ram.

Page 38: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Freedom: Bursting head makes a complete exit, as clevis sheath (cable terminator) reaches threshold of pulley housing.

Page 39: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Made it: Mole is removed and line is ready to “bump” from other end.

Page 40: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Excess is good: Always fuse enough pipe to extend beyond entry hole at end of pull. This allows you to trim excess to optimal length for bumping.

Page 41: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Swing away: A 12 to 16-pound sledge hammer is ideal for pipe up to 6” diameter.

Page 42: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Perfect fit: Bumping from the other end to drive pipe right up to coupling. This also helps to relieve any stretching that may have occurred in pipe during longer pulls through bends

and/or difficult ground conditions.

Page 43: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Flex: Relieving curve “memory” in pipe, driving a wedge between top of pipe and earth.

Page 44: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Matching up: Connecting to existing pipe upstream.

Page 45: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Cleanout: Stack reassembly.

Page 46: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Final touch: A standard cast iron to plastic coupling is used to tie into new line.

Page 47: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

Customized: Note extendable bracket attached to power unit’s engine cage, to hang hydraulic hoses.

Page 48: Santa Ana, CA 6/19/04

04-0619CAtechnical archives

It’s a wrap!