    New Double Garage

    for

    Mr Joe BloggsHappy Customer Lane

    BostonLincolnshire

    at:

    Happy Customer LaneBoston

    Lincolnshire

  • 8/12/2019 Sample Quote

    2/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358, Fax: 01205 750358,VAT No: 310927971

    Page 2

    Mr Joe BloggsHappy Customer LaneBostonLincolnshire

    Site address:Happy Customer LaneBostonLincolnshire

    Wednesday, 15 July 2009

    Dear Mr Joe Bloggs,

    Subject: Garage

    Thank you for your valued enquiry and instructions to quote for the above project.

    We are pleased to attach the following estimate as requested. Should you have anyquestions regarding this estimate, please do not hesitate to contact us.

    Considerations:

    This estimate is based on the specification described herein. Any changes to drawingsor specification would be treated as a variation and may be subject to an agreed priceadjustment.

    This estimate is valid for a period of 28 days from date of issue.

    We trust that we have interpreted your requirements correctly as every effort has been

    made to accurately estimate your project.

    We look forward to hearing from you.

    Yours sincerely

    ST Portess & Son

  • 8/12/2019 Sample Quote

    3/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 3

    Commencement

    Preparation of site and commencement of all building works.

    Plant

    GarageSite Strip (Reduce dig)Removal of spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.34 20

    TonneDumper to assist with site clearance 3 Tonne Dumper 1 Week

    Total Cost Excluding VAT 263.93

    Foundations

    Excavate for foundations using mechanical plant (if required) andcast foundations. Please note that the Building Control Officer willinspect the foundation prior to concreting and may require changesto the foundation depth and construction. Variations for additionalexcavation, trench support and concrete etc. will incur additionalcosts.

    Material

    GarageBrick and Block Cavity Wall (Brick and blockwalls)Structural concrete R'mix Concrete GEN 1 50 - 70mm slump 6m3 (Allowance 80) 0.81 m

    Brick and Block Cavity Wall (Brick and blockwall, rear)Structural concrete R'mix Concrete GEN 1 50 - 70mm slump 6m3 (Allowance 80) 0.81 m

    Brick and Block Cavity Wall (brick and blockwall, side)Structural concrete R'mix Concrete GEN 1 50 - 70mm slump 6m3 (Allowance 80) 1.6 m

    Labour

    GarageBrick and Block Cavity Wall (Brick and blockwalls)

    Additional tasks to include Excavate trench,Remove spoil from site, Prepare bottom of trench,Lay structural concrete, Place cavity fill

    Groundworker 3 Hours

    Brick and Block Cavity Wall (Brick and blockwall, rear)

    Additional tasks to include Excavate trench,Remove spoil from site, Prepare bottom of trench,Lay structural concrete, Place cavity fill

    Groundworker 3 Hours

    Brick and Block Cavity Wall (brick and blockwall, side)Excavate trench Groundworker 2 Hours

    Prepare bottom of trench Groundworker 2 HoursPlace cavity fill Groundworker 1 Hours

    Additional tasks to include Remove spoil from site,Lay structural concrete

    Groundworker 2 Hours

  • 8/12/2019 Sample Quote

    4/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 4

    Plant

    GarageBrick and Block Cavity Wall (Brick and blockwalls)Plant to remove excavated spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.34 20

    Tonne

    Brick and Block Cavity Wall (Brick and blockwall, rear)Plant to remove excavated spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.34 20

    Tonne

    Brick and Block Cavity Wall (brick and blockwall, side)Plant for excavation of trench JCB 3CX Excavator & Driver (8hr. day) 0.39 DayPlant to remove excavated spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.68 20

    Tonne

    Total Cost Excluding VAT 913.99

    Footings

    Construct brick and block footings off prepared foundations.

    Material

    GarageBrick and Block Cavity Wall (Brick and blockwalls)Cavity Fill R'mix Concrete GEN 1, 125mm slump 2-3 m3 (Allowance 85) 0.07 mTrench Blocks Trench Block 440 x 215 x 275mm 1.4 mBlockwork to Inner leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 2.7 mBlockwork to outer leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 1.4 mBricks below splash course Facing Bricks - Provisional (Allowance 0.40 each) 27 EachBricks for use in splash course Engineering Brick - Class A Blue 65mm 54 EachSand below dpc in brickwork Building Sand Bulk Bag 0.06 EachSand below dpc in blockwork Building Sand Bulk Bag 0.06 EachSand below dpc in trench blocks Building Sand Bulk Bag 0.04 EachCement below dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 0.66 EachCement below dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 0.63 EachCement below dpc in trench blocks Blue Circle Mastercrete Original Cement 25kg Bag 0.42 Each

    Brick and Block Cavity Wall (Brick and blockwall, rear)Cavity Fill R'mix Concrete GEN 1, 125mm slump 2-3 m3 (Allowance 85) 0.07 m

    Trench Blocks Trench Block 440 x 215 x 275mm 1.4 mBlockwork to Inner leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 2.7 mBlockwork to outer leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 1.4 mBricks below splash course Facing Bricks - Provisional (Allowance 0.40 each) 27 EachBricks for use in splash course Engineering Brick - Class A Blue 65mm 54 EachSand below dpc in brickwork Building Sand Bulk Bag 0.06 EachSand below dpc in blockwork Building Sand Bulk Bag 0.06 EachSand below dpc in trench blocks Building Sand Bulk Bag 0.04 EachCement below dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 0.66 EachCement below dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 0.63 EachCement below dpc in trench blocks Blue Circle Mastercrete Original Cement 25kg Bag 0.42 Each

    Brick and Block Cavity Wall (brick and blockwall, side)Cavity Fill R'mix Concrete GEN 1, 125mm slump 2-3 m3 (Allowance 85) 0.14 mTrench Blocks Trench Block 440 x 215 x 275mm 2.7 mBlockwork to Inner leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 5.4 mBlockwork to outer leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 2.7 mBricks below splash course Facing Bricks - Provisional (Allowance 0.40 each) 54 EachBricks for use in splash course Engineering Brick - Class A Blue 65mm 108 EachSand below dpc in brickwork Building Sand Bulk Bag 0.11 EachSand below dpc in blockwork Building Sand Bulk Bag 0.11 Each

  • 8/12/2019 Sample Quote

    5/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 5

    Sand below dpc in trench blocks Building Sand Bulk Bag 0.07 EachCement below dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 1.3 EachCement below dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 1.3 EachCement below dpc in trench blocks Blue Circle Mastercrete Original Cement 25kg Bag 0.84 Each

    Labour

    GarageBrick and Block Cavity Wall (Brick and blockwalls)Backfill trench Groundworker 2 HoursLay Trench Blocks 2 Bricklayers and Mate 1 HoursLay blockwork to inner leaf below dpc 2 Bricklayers and Mate 1 HoursLay blockwork to outer leaf below dpc 2 Bricklayers and Mate 1 HoursLay bricks for use in splash course 2 Bricklayers and Mate 1 Hours

    Additional tasks to include Lay bricks below splashcourse

    2 Bricklayers and Mate 1 Hours

    Brick and Block Cavity Wall (Brick and blockwall, rear)Backfill trench Groundworker 2 HoursLay Trench Blocks 2 Bricklayers and Mate 1 HoursLay blockwork to inner leaf below dpc 2 Bricklayers and Mate 1 HoursLay blockwork to outer leaf below dpc 2 Bricklayers and Mate 1 HoursLay bricks for use in splash course 2 Bricklayers and Mate 1 Hours

    Additional tasks to include Lay bricks below splash

    course

    2 Bricklayers and Mate 1 Hours

    Brick and Block Cavity Wall (brick and blockwall, side)Backfill trench Groundworker 3 HoursLay Trench Blocks 2 Bricklayers and Mate 1 HoursLay blockwork to inner leaf below dpc 2 Bricklayers and Mate 2 HoursLay blockwork to outer leaf below dpc 2 Bricklayers and Mate 1 HoursLay bricks below splash course 2 Bricklayers and Mate 1 HoursLay bricks for use in splash course 2 Bricklayers and Mate 1 Hours

    Total Cost Excluding VAT 1,246.43

    Oversite and slabbing

    Lay and compact subbase on reduced levels and form concreteslab.

    Material

    GarageGarage Slab (Floor slab)

    Sub-base to concrete slab Sub Base MOT Type 1 Bulk Bag 10 EachSand blinding to slab Building Sand Bulk Bag 1.7 EachConcrete in slab R'mix Concrete RC 30, 50mm slump 6m3 (Allowance 75) 3.8 mDPM to concrete slab Polythene DPM Blue 300mu 4 x 25m PIFA (27.6kg) 0.42 Each

    Labour

    GarageGarage Slab (Floor slab)Place and compact sub-base to slab Groundworker and Labourer 3 HoursLay sand blinding Groundworker and Labourer 2 HoursLay DPM to slab Groundworker and Labourer 1 HoursPlace and compact concrete slab Groundworker and Labourer 3 HoursFloat finish to concrete slab Groundworker and Labourer 3 Hours

    Plant

    GarageGarage Slab (Floor slab)

  • 8/12/2019 Sample Quote

    6/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 6

    Excavator for preparation of slab JCB 3CX Excavator & Driver (8hr. day) 0.5 DayPlant delivery and collection Delivery (10 to 15 Miles) 4 Each

    Total Cost Excluding VAT 1,488.83

    Erect Scaffold

    Erect scaffolding on site to provide access for our contractors. Noallowance has been made to adapt the scaffolding for clients ortheir own contractors' requirements.

    Subcontract Work

    GarageScaffolding (Scaffold)Scaffold budget Scaffolding contractor 525 Unit

    Subcontract Work

    GarageScaffolding (Scaffold)

    Allowance for sundry costs Sundry Costs 50 Each

    Total Cost Excluding VAT 632.50

    Brickwork Shell

    Construct facing brick in sand/cement mortar, leaving all joints withrecessed finish. All openings around windows, doors etc. to beprovided with vertical damp proof courses where required. Internalleaf to be formed in blockwork.

    Material

    GarageDouble Garage Door (Vertical Slat Garage Door)

    Garage Door Frame Softwood Garage Door Frame 4270 x 1981mm 1 EachExternal/Combination lintel Steel Lintel 100mm Cavity 4800mm (Garage) 1 Each

    Garage Pedestrian DoorDoor frame External Softwood Door Frame 838 x 1981 Open in 1 EachExternal/Combination lintel Steel Lintel 50 Cavity x 1200mm 1 Each

    Brick and Block Cavity Wall (Brick and blockwalls)Bricks above dpc less openings Facing Bricks - Provisional (Allowance 0.40 each) 353 EachBlocks above dpc less openings Insulation Block Standard 440 x 215 x 100mm 5.9 mBrick ties Brickwork Tie DD140 Type 4 225mm 26 EachDPC to brickwork Pitch Polymer DPC 100mm x 20m 0.3 EachDPC to blockwork Pitch Polymer DPC 100mm x 20m 0.3 EachSand above dpc in brickwork Building Sand Bulk Bag 0.26 EachSand above dpc in blockwork Building Sand Bulk Bag 0.08 EachCement above dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 1.5 EachCement above dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 0.49 Each

    Brick and Block Cavity Wall (Brick and blockwall, rear)Bricks above dpc less openings Facing Bricks - Provisional (Allowance 0.40 each) 773 Each

  • 8/12/2019 Sample Quote

    7/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 7

    Blocks above dpc less openings Insulation Block Standard 440 x 215 x 100mm 13 mBrick ties Brickwork Tie DD140 Type 4 225mm 47 EachDPC to brickwork Pitch Polymer DPC 100mm x 20m 0.3 EachDPC to blockwork Pitch Polymer DPC 100mm x 20m 0.3 EachSand above dpc in brickwork Building Sand Bulk Bag 0.58 EachSand above dpc in blockwork Building Sand Bulk Bag 0.19 EachCement above dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 3.3 EachCement above dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 1.1 Each

    Brick and Block Cavity Wall (brick and blockwall, side)Bricks above dpc less openings Facing Bricks - Provisional (Allowance 0.40 each) 1800 EachBlocks above dpc less openings Insulation Block Standard 440 x 215 x 100mm 30 mBrick ties Brickwork Tie DD140 Type 4 225mm 106 EachDPC to brickwork Pitch Polymer DPC 100mm x 20m 0.6 EachDPC to blockwork Pitch Polymer DPC 100mm x 20m 0.6 EachSand above dpc in brickwork Building Sand Bulk Bag 1.4 EachSand above dpc in blockwork Building Sand Bulk Bag 0.43 EachCement above dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 7.7 EachCement above dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 2.5 Each

    Labour

    GarageDouble Garage Door (Vertical Slat Garage Door)Form opening Bricklayer 2 Hours

    Fix external lintel 2 Bricklayers and Mate 1 HoursMake door frame Joiner 2 Hours

    Additional tasks to include Fix preformed cavitytray

    Bricklayer 1 Hours

    Garage Pedestrian DoorForm opening Bricklayer 1 Hours

    Additional tasks to include Fix external lintel Bricklayer 1 Hours

    Brick and Block Cavity Wall (Brick and blockwalls)Lay bricks above dpc less openings 2 Bricklayers and Mate 3 HoursLay blocks above dpc less openings 2 Bricklayers and Mate 2 Hours

    Brick and Block Cavity Wall (Brick and blockwall, rear)Lay bricks above dpc less openings 2 Bricklayers and Mate 7 HoursLay blocks above dpc less openings 2 Bricklayers and Mate 4 Hours

    Brick and Block Cavity Wall (brick and blockwall, side)Lay bricks above dpc less openings 2 Bricklayers and Mate 15 HoursLay blocks above dpc less openings 2 Bricklayers and Mate 8 Hours

    Total Cost Excluding VAT 5,274.43

  • 8/12/2019 Sample Quote

    8/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 8

    Roof Structure

    Form roof structure including any fascias and bargeboards andassociated guttering as described.

    Material

    GarageApex Truss Roof (Roof)Noggings between roof joists Sawn Softwood Kiln Dried Treated 47.0 x 50mm 33 Metre

    Apex truss roof rafters To be defined 11 UnitTruss Clips Truss Clip 50mm 22 Each

    Apex roof gable Ladder Rafters Sawn Dry Graded Structural Softwood Treated 47.0 x 125mm 36 MetreGable ladder noggings Sawn Softwood Kiln Dried Treated 47.0 x 50mm 11 MetreSoffit carriers Sawn Batten Treated 25.0 x 38mm 6 MetreWall plate Sawn Dry Graded Structural Softwood Treated 75.0 x 100mm 13 Metre

    Diagonal bracing Sawn Dry Graded Structural Softwood Treated 25.0 x 100mm 20 MetreLongitudinal bracing Sawn Dry Graded Structural Softwood Treated 25.0 x 100mm 22 Metre

    Apex bracing Sawn Dry Graded Structural Softwood Treated 25.0 x 100mm 5.5 MetreRoof structure fixings (allowance) Round Wire Nails Bright 100mm x 25kg 0.57 BoxEaves fascia White 175mm Square Fascia x 16mm x 5.0M 2.6 EachBargeboard White 175mm Square Fascia x 16mm x 5.0M 3.6 EachBargeboard fixings White plastic top Nail 40mm - 10G 0.89 EachWallplate straps Lateral Restraint Strap 30 x 5 x 1200mm bent at 150mmm 6 EachGable straps at joist level Lateral Restraint Strap 30 x 5 x 1200mm bent at 150mmm 4 EachGable straps at verge level Lateral Restraint Strap 30 x 5 x 1600mm bent at 100mmm 8 EachGable soffits (side 1) White 400mm PVC Board x 9mm x 5.0M 0.85 EachGable soffits (side 2) White 400mm PVC Board x 9mm x 5.0M 0.85 EachEaves soffitts (side 1) White 400mm PVC Board x 9mm x 5.0M 0.64 EachEaves soffitts (side 2) White 400mm PVC Board x 9mm x 5.0M 0.64 EachSoffit fixings White plastic top Nail 40mm - 10G 1.2 EachGutter Half Round Gutter 4m x 112mm 3.3 EachDown pipe Half Round Downpipe 4m x 68mm 1.3 EachStop ends Half Round Gutter Stop End External 112mm 4 Each

    Gutter unions Half Round Gutter Union Bracket 112mm 4 EachGutter clips Half Round Gutter Support Bracket 112mm 14 EachGutter outlet Half Round Gutter Running Outlet 112mm 2 EachDown pipe unions Half Round Downpipe Connector 68mm 2 EachDown pipe clips Half Round Downpipe Saddle Bracket 68mm 6 EachSwan necks Half Round Downpipe Bend 67.5 deg 68mm 4 EachPrimer for bargeboard and fascia Undercoat White 5 Litre 0.15 EachPrimer for soffits Undercoat White 5 Litre 0.18 Each

    Labour

    GarageApex Truss Roof (Roof)Fix noggings between roof joists Joiner 5 HoursFix apex roof truss rafters Joiner + Mate 5 HoursFix apex roof gable ladder rafters Joiner + Mate 3 HoursFix gable ladder noggings Joiner 2 Hours

    Fix soffit carriers Joiner 1 HoursFix wall plate Joiner 2 HoursFix diagonal bracing Joiner + Mate 2 HoursFix longitudinal bracing Joiner + Mate 2 HoursFix eaves fascia Joiner + Mate 2 HoursFix bargeboard Joiner + Mate 2 HoursFix wallplate straps Joiner 1 HoursFix gable straps at joist level Joiner 1 HoursFix gable straps at verge level Joiner 2 HoursFix gutter Joiner 3 HoursFix down Pipe Joiner 1 HoursFix gable soffits (side1 ) Joiner 2 HoursFix gable soffits (side 2) Joiner 2 HoursFix eaves soffitts (side 1) Joiner 1 HoursFix eaves soffitts (side 2) Joiner 1 HoursPrepare bargeboard and fascia for painting Joiner 2 HoursPrime bargeboard and fascia Joiner 2 HoursPrime soffits Joiner 2 Hours

    Additional tasks to include Fix apex bracing Joiner + Mate 1 Hours

  • 8/12/2019 Sample Quote

    9/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 9

    Total Cost Excluding VAT 2,135.12

    Roof Tiling

    Lay roof covering.

    Material

    GarageApex Truss Roof (Roof)Lathe Sawn Batten Treated 25.0 x 38mm 603 MetreLathe nails Round Wire Nails Galvanised 65mm x 25kg 0.42 BoxRoofing felt Breather Membrane 700 1.5 x 50 m 0.84 EachTiles Plain Clay Tile (60 per m2) (Allowance 0.70 each) 3412 EachTile Nails Round Wire Nails Galvanised 65mm x 25kg 0.09 BoxRidge tile Half Round Clay Ridge (300mm) (Allowance 12 each) 22 EachEaves tiles Clay Eaves Tile (Allowance 0.90) 87 EachTop tiles Clay Eaves Tile (Allowance 0.90) 87 EachVerge tiles Clay Tile & Half (Allowance 1.40 each) 87 EachTile undercloak 1 Cement Soffit Strip 2400 x 150 x 4.5mm 3.6 EachTile undercloak 2 Cement Soffit Strip 2400 x 150 x 4.5mm 3.6 EachSand pointing/bedding to ridge Building Sand Bulk Bag 0.07 EachSand pointing/bedding to verge Building Sand Bulk Bag 0.17 EachCement in pointing/bedding to ridge Blue Circle Mastercrete Original Cement 25kg Bag 0.75 EachCement pointing/bedding to verge Blue Circle Mastercrete Original Cement 25kg Bag 2 Each

    Labour

    GarageApex Truss Roof (Roof)Fix tiles, felt and lathe. 3 Roof tilers + mate 21 HoursFix top tiles Roof tiler 1 HoursFix verge tiles Roof tiler 1 HoursFix ridge tile Roof tiler + mate 1 Hours

    Additional tasks to include Fix eaves tiles, Fix tileundercloak 1, Fix tile undercloak 2

    Roof tiler 2 Hours

    Total Cost Excluding VAT 5,385.95

    Joinery 1st Fix

    Form carcassing and first fix timbers.

    Material

    GarageDouble Garage Door (Vertical Slat Garage Door)Door frame fixings to sides Hammer in Fixing 8mm x 100mm (12 Bag) 0.5 PackDoor frame fixings to top and bottom Wood Screws Steel CSK Twin Thread 10 x 3 inch (100 box) 0.14 Box

    Garage Pedestrian Door

    Door frame fixings to sides Hammer in Fixing 8mm x 100mm (12 Bag) 0.5 Pack

  • 8/12/2019 Sample Quote

    10/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 10

    Labour

    GarageDouble Garage Door (Vertical Slat Garage Door)Fix door frame Joiner 2 Hours

    Garage Pedestrian DoorAdditional tasks to include Fix door frame Joiner 1 Hours

    Total Cost Excluding VAT 42.04

    Internal Decoration

    Apply decoration. (Note that a basic paint specification has beenused for the purposes of estimating the building works. However,colours and finishes may be changed by agreement in writing.)

    Material

    GarageDouble Garage Door (Vertical Slat Garage Door)Primer for door frame internally Undercoat White 5 Litre 0.04 EachUndercoat for door frame internally Undercoat White 5 Litre 0.04 EachPaint for door frame internally Gloss Brilliant White 5 Litre 0.04 Each

    Garage Pedestrian DoorPrimer for door frame internally Undercoat White 5 Litre 0.03 EachUndercoat for door frame internally Undercoat White 5 Litre 0.03 EachPaint for door frame internally Gloss Brilliant White 5 Litre 0.03 EachPrimer for door internally Undercoat White 5 Litre 0.05 EachUndercoat for door internally Undercoat White 5 Litre 0.05 EachPaint for door internally Gloss Brilliant White 5 Litre 0.05 Each

    Labour

    GarageDouble Garage Door (Vertical Slat Garage Door)

    Additional tasks to include Prepare interior of doorframe for decoration, Apply primer to door frameinternally, Apply undercoat to door frame internally,

    Apply paint to door frame internally

    Decorator 3 Hours

    Garage Pedestrian DoorAdditional tasks to include Prepare interior of doorframe for decoration, Apply primer to door frameinternally, Apply undercoat to door frame internally,

    Apply paint to door frame internally, Prepare int. ofdoor for primer or paint, Apply primer to interior ofdoor, Apply undercoat to interior of door, Applygloss to interior of door

    Decorator 3 Hours

    Total Cost Excluding VAT 89.50

    External Decoration

    Apply decoration. (Note that a basic paint specification has beenused for the purposes of estimating the building works. However,colours and finishes may be changed by agreement in writing.)

  • 8/12/2019 Sample Quote

    11/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 11

    Material

    GarageDouble Garage Door (Vertical Slat Garage Door)Sealant Silicone Sealant White 0.31 Litre 0.39 EachPrimer for door frame externally Undercoat White 5 Litre 0.04 EachUndercoat for door frame externally Undercoat White 5 Litre 0.04 EachPaint for door frame externally Gloss Brilliant White 5 Litre 0.04 EachUndercoat for door externally Undercoat White 5 Litre 0.27 EachPaint for door externally Gloss Brilliant White 5 Litre 0.27 Each

    Garage Pedestrian DoorSealant Silicone Sealant White 0.31 Litre 0.18 EachPrimer for door frame externally Undercoat White 5 Litre 0.03 EachUndercoat for door frame externally Undercoat White 5 Litre 0.03 EachPaint for door frame externally Gloss Brilliant White 5 Litre 0.03 EachPrimer for door externally Undercoat White 5 Litre 0.05 EachUndercoat for door externally Undercoat White 5 Litre 0.05 EachPaint for door externally Gloss Brilliant White 5 Litre 0.05 EachPrimer for external cill Outdoor Varnish Clear Gloss 750ml 0.02 EachUndercoat/varnish for external cill Outdoor Varnish Clear Gloss 750ml 0.02 EachPaint/varnish for external cill Outdoor Varnish Clear Gloss 750ml 0.02 Each

    Apex Truss Roof (Roof)Undercoat for bargeboard and fascia Undercoat White 5 Litre 0.15 Each

    Paint for bargeboard and fascia Gloss Brilliant White 5 Litre 0.15 EachUndercoat for soffits Undercoat White 5 Litre 0.18 EachPaint for soffits Gloss Brilliant White 5 Litre 0.18 Each

    Labour

    GarageDouble Garage Door (Vertical Slat Garage Door)Prepare exterior of door for painting Decorator 2 Hours

    Apply undercoat to exterior of door Decorator 2 HoursApply gloss to exterior of door Decorator 2 HoursAdditional tasks to include Apply sealant Joiner 1 HoursAdditional tasks to include Prepare exterior of doorframe for decoration, Apply primer to door frameexternally, Apply undercoat to door frameexternally, Apply paint to door frame externally

    Decorator 3 Hours

    Garage Pedestrian DoorAdditional tasks to include Apply sealant Joiner 1 HoursAdditional tasks to include Prepare exterior of doorframe for decoration, Apply primer to door frameexternally, Apply undercoat to door frameexternally, Apply paint to door frame externally,Prepare exterior of door for painting, Apply primerto exterior of door, Apply undercoat to exterior ofdoor, Apply gloss to exterior of door, Prepareexternal cill for decoration, Apply primer toexternal cill, Apply undercoat/varnish to externalcill, Apply paint/varnish to external cill

    Decorator 3 Hours

    Apex Truss Roof (Roof)Undercoat bargeboard and fascia Decorator 2 HoursPaint bargeboard and fascia Decorator 2 HoursPrepare soffits for painting Joiner 2 HoursUndercoat soffits Decorator 2 HoursPaint soffits Decorator 2 Hours

    Total Cost Excluding VAT 362.82

    Joinery 2nd Fix

    Fix doors and windows, fixtures and fittings.

  • 8/12/2019 Sample Quote

    12/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 12

    Material

    GarageDouble Garage Door (Vertical Slat Garage Door)Garage Door Double Garage Door 4267 x 1981mm (Allowance 1350) 1 Each

    Garage Pedestrian DoorDoor KXT Back Door Softwood 3 Panel 6 Pane D&G 838 x 1981mm 1 EachDoor furniture Georgian Brass 5 Lever BS Exterior Door Pack 1 EachHinges Butt Hinge Brassed 102mm 1.5 PairSafety Glass Toughened Sealed Units for KXT Door 1 Each

    Labour

    GarageDouble Garage Door (Vertical Slat Garage Door)Hang door Joiner 6 Hours

    Garage Pedestrian DoorHang door Joiner 3 HoursFix door furniture Joiner 2 HoursFix glazing Joiner 1 Hours

    Total Cost Excluding VAT 2,241.67

    Completion

    Completion of all building works.

    Labour

    GarageGarage Pedestrian DoorReturn to ease door Joiner 1 Hours

    Total Cost Excluding VAT 18.70

    Total Cost Excluding VAT 20,095.92Total VAT 3,014.39Total Cost Including VAT 23,110.31

  • 8/12/2019 Sample Quote

    13/14

    ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971

    Page 13

    Acceptance of Estimate/Variation

    Reference: Garage (Estimate dated Wednesday, 15 July 2009)

    Mr Joe Bloggs

    Happy Customer LaneBostonLincolnshire

    Site address:Happy Customer LaneBostonLincolnshire

    Please carry out the building works itemised in the Estimate defined above, datedWednesday, 15 July 2009 to the value of:

    Total Cost Excluding VAT 20,095.92Total VAT 3,014.39Total Cost Including VAT 23,110.31

    Signed Mr Joe Bloggs .

    Date //20..

    Signed on behalf of ST Portess & Son .

    Date //20..