Sample Inspection Report of Exchanger
-
Upload
rtrajanmech5408 -
Category
Documents
-
view
80 -
download
6
description
Transcript of Sample Inspection Report of Exchanger
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 1 of 22
INSPECTION TEST REPORT
ITEM TESTED E-2570
INSPECTION DATE 30th January 2013
INSPECT BY Khalid
___________________ __________________________ Signatory of Inspector Signatory of R&I Supt/ Engineer
DESIGN DATA
YEAR MANUFACTURED 2002 DESIGN PRESSURE 15 (S) / 2,5 (T) kg/cm2
CONSTRUCTION MATERIAL CS / SS 304L TEST PRESSURE 22 (S) / 4.8 (T) kg/cm2
CORROSION ALLOWANCE 1.0 (S) / 0 (T) mm PRESSURE TEST DATE 2002
FREQUENCY/ INTERVAL OF INSPECTION
INSPECTION INTERVAL (API)
MAX PERMITTED
120 Month(s)
LAST INSPECTION DATE 30th September 2009
NEXT INSPECTION DATE 30th January 2023
REMAINING LIFE <10 years
REASON FOR INSPECTION
Planned Un-plan Other (Process upset)
TYPE OF EXAMINATION/ TEST PERFORMED
TYPE IF INSPECTION Internal External
INSPECTION METHODS / TESTS USED Visual UTG
HYDROSTATIC TEST Entire Coil
OTHERS (PLEASE SPECIFY)
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 2 of 22
RECOMMENDATION/ ACTION ACTION PARTY DATE
CLOSED
To perform hydrotest for the exchanger as per test pressure. Results passed
Mechanical
3rd Feb 2013
INSPECTION SUMMARY
E-2570 was shutdown for maintenance due to process upset. The exchanger was remove and inspected at Ad-meth workshop before cleaning condition. Inspection findings are as follows: Shell side appeared in good condition No plugging of tubes was observed except for fouling built up on tubesheets Expanded bellow also appeared in good condition Baffle tie rod noted slight bend. No issue Eddy current testing could not be performed due to heavy deposits on the internal side of tubes
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 3 of 22
THICKNESS DATA
Location Current (t) mm Previous (t) mm Design (t) mm Corrosion
Allowance (mm) Condition
Channel plate 11.86 - 12.00 1.00 Thickness within tolerance Shell plate 12.57 - 12.70 1.00 Thickness within tolerance
Shell cone 12.72 - 12.70 1.00 Thickness within tolerance
4” Glycol inlet nozzle(N5) 6.15 - 6.02 1.00 Thickness within tolerance
8” Glycol outlet nozzle(N6) 15.9 - 11.18 1.00 Thickness within tolerance
4” Hot oil inlet nozzle(HOS) 8.12 - 8.56 1.00 Thickness within tolerance 4” Hot oil outlet nozzle(HOR) 8.44 - 8.56 1.00 Thickness within tolerance 1” Drain nozzle(D) 6.20 - 6.35 1.00 Thickness within tolerance 1” Vent nozzle(V1) 3.77 - 3.38 1.00 Thickness within tolerance
1” Vent nozzle(V2) 6.02 - 6.35 1.00 Thickness within tolerance
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 4 of 22
EQUIPMENT GA / LAYOUT
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 5 of 22
INSPECTION PHOTOGRAPHIC RECORD Photo Findings
Overview of E-2570
Exchanger shell overview
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 6 of 22
Internal shell appeared in good condition
Channel head overview
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 7 of 22
Internal channel head condition
Shell cover(cone) overview
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 8 of 22
Internal view condition
Internal view condition
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 9 of 22
Floating tube sheet and tube bundle condition.
Tubesheet observed no plugging however fouling built up was observed
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 10 of 22
Close view of fouling built up
Generally tube bundle appeared in good condition
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 11 of 22
Floating head plate condition
Expansion bellow condition
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 12 of 22
After cleaning condition
Shell internal Close view
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 13 of 22
Close view Shell cover(cone)
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 14 of 22
Internal view Close view
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 15 of 22
Expansion bellow condition Channel head condition
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 16 of 22
Channel head cover Floating head plate condition
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 17 of 22
Tubesheet condition Close view of tubes
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 18 of 22
Close view of tubes Tube bundle. One tie rod noted slight bend. No issue
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 19 of 22
Close view.
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 20 of 22
INSPECTION CHECKLISTS RECORD
Pressure Vessel Inspection Checklist
Item Tick relevant boxes
Completed[ ]
Comments
Heat Exchanger (Shell & Tube)
1) Check before and after cleaning
2) Visual check shell, cover, channel cover, floating head cover and nozzles condition
3) Visual check any erosion-corrosion attack on the tube ends
4) Visual check external tube any corrosion or damage condition
5) Perform NDT for tube NA Could not be carried out due to heavy deposits on internal tubes
6) Visual check any disclose grooving of tubes and enlargement of baffle holes.
7) Check anodes condition (if any) NA
8) Inspect the impingement or wear plates for any sign of corrosion or erosion
9) Obtain thickness for shell/ nozzles and dead legs area Thickness within tolerance
10) Check any insulation damage / CUI/ external corrosion
11) Check foundations bolting is double-nutted/ support condition
12) Check platform, ladders, handrails and davis condition NA
13) Check any painting damage
14) Gasket seating surface any damage
15) Hammer test on Lifting lugs
16) Hammer test on Shell small piping connection
17) Kettle-type exchanger check weir condition NA
Furnace (Fire Heater)
1) Check before and after cleaning NA
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 21 of 22
2) Check for porous refractory by hammer test and mark out for repair (if any)
NA
3) Any damage of baffle brick NA
4) Check and damage or crack ferrules NA
5) Check any expose anchor NA
6) Replace feed tube (R1/R2) with correct material construction of Inconel with PMI (for F-8010 only)
NA
7) Vacuum or remove dust on furnace bottom circumference of the refractory brick (for F-8010 only)
NA
8) Fill up the bricks to bricks joints with Ceramic fibre if gap approximately >4mm (if any)
NA
9) Check internal radiant coil thermo bond secured (for Hot Oil Heater only)
NA
10) Check any sign of loose supports securing the radiant coils (for Hot Oil Heater only)
NA
11) Check any ash formation built up / refractory drop out at the crossover fin coils from small doors area (for Hot Oil Heater only)
NA
12) Obtain thickness for shell/ nozzles and dead legs area NA
13) Check any insulation damage / CUI/ external corrosion NA
14) Check foundations/ support condition NA
15) Check platform, ladders, handrails and davis condition NA
16) Check any painting damage NA
17) Check all internal apparatus like thermo well, etc condition NA
Boiler
1) Check before and after cleaning NA
2) Check internal Steam drum and tubes condition NA
3) Check internal water drum condition NA
4) Check internal spacer tubes condition NA
5) Check for porous refractory by hammer test and mark out for repair (if any)
NA
6) Perform require NDT NA
7) Obtain thickness for shell/ nozzles and dead legs area NA
8) Check any insulation damage / CUI/ external corrosion NA
CHEVRON ORONITE PTE LTD
INSPECTION TEST REPORT
Rev.5 / Sept 2011 Page 22 of 22
9) Check foundations/ support condition NA
10) Check platform, ladders, handrails and davis condition NA
11) Check any painting damage NA
12) Check all internal apparatus like thermo well, etc condition
Pressure Vessel (Column/ Vessel/ Reactor)
1) Check before and after cleaning NA
2) Visual check internal wall condition NA
3) Check chimney tray condition NA
4) Check bottom vortex strainer condition NA
5) Check demister pads condition NA
6) Check internal packing for any fouling or plugging in bed NA
7) Inspect the impingement or wear plates for any sign of corrosion or erosion
NA
8) Perform require NDT NA
9) Inspect any loose of U-bolts & sign of cut or erosion between pipe
NA
10) Check spray nozzle condition NA
11) Check any damage or weld shear off support NA
12) Check any bolt/ nuts loose for impeller blade NA
13) Check any sign of lining/ cladding failure NA
14) Obtain thickness for shell/ nozzles and dead legs area NA
15) Check any insulation damage / CUI/ external corrosion NA
16) Check foundations/ support condition NA
17) Check platform, ladders, handrails and davis condition NA
18) Check any painting damage NA
19) Perform hydro test for external/ internal coil NA
20) Check all internal apparatus like thermo well, etc condition NA
Others Comment.