Sample Inspection Report of Exchanger

22
CHEVRON ORONITE PTE LTD INSPECTION TEST REPORT Rev.5 / Sept 2011 Page 1 of 22 INSPECTION TEST REPORT ITEM TESTED E-2570 INSPECTION DATE 30 th January 2013 INSPECT BY Khalid ___________________ __________________________ Signatory of Inspector Signatory of R&I Supt/ Engineer DESIGN DATA YEAR MANUFACTURED 2002 DESIGN PRESSURE 15 (S) / 2,5 (T) kg/cm2 CONSTRUCTION MATERIAL CS / SS 304L TEST PRESSURE 22 (S) / 4.8 (T) kg/cm2 CORROSION ALLOWANCE 1.0 (S) / 0 (T) mm PRESSURE TEST DATE 2002 FREQUENCY/ INTERVAL OF INSPECTION INSPECTION INTERVAL (API) MAX PERMITTED 120 Month(s) LAST INSPECTION DATE 30 th September 2009 NEXT INSPECTION DATE 30 th January 2023 REMAINING LIFE <10 years REASON FOR INSPECTION Planned Un-plan Other (Process upset) TYPE OF EXAMINATION/ TEST PERFORMED TYPE IF INSPECTION Internal External INSPECTION METHODS / TESTS USED Visual UTG HYDROSTATIC TEST Entire Coil OTHERS (PLEASE SPECIFY)

description

ex

Transcript of Sample Inspection Report of Exchanger

Page 1: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 1 of 22

INSPECTION TEST REPORT

ITEM TESTED E-2570

INSPECTION DATE 30th January 2013

INSPECT BY Khalid

___________________ __________________________ Signatory of Inspector Signatory of R&I Supt/ Engineer

DESIGN DATA

YEAR MANUFACTURED 2002 DESIGN PRESSURE 15 (S) / 2,5 (T) kg/cm2

CONSTRUCTION MATERIAL CS / SS 304L TEST PRESSURE 22 (S) / 4.8 (T) kg/cm2

CORROSION ALLOWANCE 1.0 (S) / 0 (T) mm PRESSURE TEST DATE 2002

FREQUENCY/ INTERVAL OF INSPECTION

INSPECTION INTERVAL (API)

MAX PERMITTED

120 Month(s)

LAST INSPECTION DATE 30th September 2009

NEXT INSPECTION DATE 30th January 2023

REMAINING LIFE <10 years

REASON FOR INSPECTION

Planned Un-plan Other (Process upset)

TYPE OF EXAMINATION/ TEST PERFORMED

TYPE IF INSPECTION Internal External

INSPECTION METHODS / TESTS USED Visual UTG

HYDROSTATIC TEST Entire Coil

OTHERS (PLEASE SPECIFY)

Page 2: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 2 of 22

RECOMMENDATION/ ACTION ACTION PARTY DATE

CLOSED

To perform hydrotest for the exchanger as per test pressure. Results passed

Mechanical

3rd Feb 2013

INSPECTION SUMMARY

E-2570 was shutdown for maintenance due to process upset. The exchanger was remove and inspected at Ad-meth workshop before cleaning condition. Inspection findings are as follows: Shell side appeared in good condition No plugging of tubes was observed except for fouling built up on tubesheets Expanded bellow also appeared in good condition Baffle tie rod noted slight bend. No issue Eddy current testing could not be performed due to heavy deposits on the internal side of tubes

Page 3: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 3 of 22

THICKNESS DATA

Location Current (t) mm Previous (t) mm Design (t) mm Corrosion

Allowance (mm) Condition

Channel plate 11.86 - 12.00 1.00 Thickness within tolerance Shell plate 12.57 - 12.70 1.00 Thickness within tolerance

Shell cone 12.72 - 12.70 1.00 Thickness within tolerance

4” Glycol inlet nozzle(N5) 6.15 - 6.02 1.00 Thickness within tolerance

8” Glycol outlet nozzle(N6) 15.9 - 11.18 1.00 Thickness within tolerance

4” Hot oil inlet nozzle(HOS) 8.12 - 8.56 1.00 Thickness within tolerance 4” Hot oil outlet nozzle(HOR) 8.44 - 8.56 1.00 Thickness within tolerance 1” Drain nozzle(D) 6.20 - 6.35 1.00 Thickness within tolerance 1” Vent nozzle(V1) 3.77 - 3.38 1.00 Thickness within tolerance

1” Vent nozzle(V2) 6.02 - 6.35 1.00 Thickness within tolerance

Page 4: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 4 of 22

EQUIPMENT GA / LAYOUT

Page 5: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 5 of 22

INSPECTION PHOTOGRAPHIC RECORD Photo Findings

Overview of E-2570

Exchanger shell overview

Page 6: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 6 of 22

Internal shell appeared in good condition

Channel head overview

Page 7: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 7 of 22

Internal channel head condition

Shell cover(cone) overview

Page 8: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 8 of 22

Internal view condition

Internal view condition

Page 9: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 9 of 22

Floating tube sheet and tube bundle condition.

Tubesheet observed no plugging however fouling built up was observed

Page 10: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 10 of 22

Close view of fouling built up

Generally tube bundle appeared in good condition

Page 11: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 11 of 22

Floating head plate condition

Expansion bellow condition

Page 12: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 12 of 22

After cleaning condition

Shell internal Close view

Page 13: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 13 of 22

Close view Shell cover(cone)

Page 14: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 14 of 22

Internal view Close view

Page 15: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 15 of 22

Expansion bellow condition Channel head condition

Page 16: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 16 of 22

Channel head cover Floating head plate condition

Page 17: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 17 of 22

Tubesheet condition Close view of tubes

Page 18: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 18 of 22

Close view of tubes Tube bundle. One tie rod noted slight bend. No issue

Page 19: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 19 of 22

Close view.

Page 20: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 20 of 22

INSPECTION CHECKLISTS RECORD

Pressure Vessel Inspection Checklist

Item Tick relevant boxes

Completed[ ]

Comments

Heat Exchanger (Shell & Tube)

1) Check before and after cleaning

2) Visual check shell, cover, channel cover, floating head cover and nozzles condition

3) Visual check any erosion-corrosion attack on the tube ends

4) Visual check external tube any corrosion or damage condition

5) Perform NDT for tube NA Could not be carried out due to heavy deposits on internal tubes

6) Visual check any disclose grooving of tubes and enlargement of baffle holes.

7) Check anodes condition (if any) NA

8) Inspect the impingement or wear plates for any sign of corrosion or erosion

9) Obtain thickness for shell/ nozzles and dead legs area Thickness within tolerance

10) Check any insulation damage / CUI/ external corrosion

11) Check foundations bolting is double-nutted/ support condition

12) Check platform, ladders, handrails and davis condition NA

13) Check any painting damage

14) Gasket seating surface any damage

15) Hammer test on Lifting lugs

16) Hammer test on Shell small piping connection

17) Kettle-type exchanger check weir condition NA

Furnace (Fire Heater)

1) Check before and after cleaning NA

Page 21: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 21 of 22

2) Check for porous refractory by hammer test and mark out for repair (if any)

NA

3) Any damage of baffle brick NA

4) Check and damage or crack ferrules NA

5) Check any expose anchor NA

6) Replace feed tube (R1/R2) with correct material construction of Inconel with PMI (for F-8010 only)

NA

7) Vacuum or remove dust on furnace bottom circumference of the refractory brick (for F-8010 only)

NA

8) Fill up the bricks to bricks joints with Ceramic fibre if gap approximately >4mm (if any)

NA

9) Check internal radiant coil thermo bond secured (for Hot Oil Heater only)

NA

10) Check any sign of loose supports securing the radiant coils (for Hot Oil Heater only)

NA

11) Check any ash formation built up / refractory drop out at the crossover fin coils from small doors area (for Hot Oil Heater only)

NA

12) Obtain thickness for shell/ nozzles and dead legs area NA

13) Check any insulation damage / CUI/ external corrosion NA

14) Check foundations/ support condition NA

15) Check platform, ladders, handrails and davis condition NA

16) Check any painting damage NA

17) Check all internal apparatus like thermo well, etc condition NA

Boiler

1) Check before and after cleaning NA

2) Check internal Steam drum and tubes condition NA

3) Check internal water drum condition NA

4) Check internal spacer tubes condition NA

5) Check for porous refractory by hammer test and mark out for repair (if any)

NA

6) Perform require NDT NA

7) Obtain thickness for shell/ nozzles and dead legs area NA

8) Check any insulation damage / CUI/ external corrosion NA

Page 22: Sample Inspection Report of Exchanger

CHEVRON ORONITE PTE LTD

INSPECTION TEST REPORT

Rev.5 / Sept 2011 Page 22 of 22

9) Check foundations/ support condition NA

10) Check platform, ladders, handrails and davis condition NA

11) Check any painting damage NA

12) Check all internal apparatus like thermo well, etc condition

Pressure Vessel (Column/ Vessel/ Reactor)

1) Check before and after cleaning NA

2) Visual check internal wall condition NA

3) Check chimney tray condition NA

4) Check bottom vortex strainer condition NA

5) Check demister pads condition NA

6) Check internal packing for any fouling or plugging in bed NA

7) Inspect the impingement or wear plates for any sign of corrosion or erosion

NA

8) Perform require NDT NA

9) Inspect any loose of U-bolts & sign of cut or erosion between pipe

NA

10) Check spray nozzle condition NA

11) Check any damage or weld shear off support NA

12) Check any bolt/ nuts loose for impeller blade NA

13) Check any sign of lining/ cladding failure NA

14) Obtain thickness for shell/ nozzles and dead legs area NA

15) Check any insulation damage / CUI/ external corrosion NA

16) Check foundations/ support condition NA

17) Check platform, ladders, handrails and davis condition NA

18) Check any painting damage NA

19) Perform hydro test for external/ internal coil NA

20) Check all internal apparatus like thermo well, etc condition NA

Others Comment.