1-) The Agile Manifesto states which of the following values:

A-) People are more important than contracts

B-) Working software should have priority over comprehensive documentation

C-) Plans should have priority over ability to respond

D-) Contracts should be negotiated which allow control over the people

Sample Agile Scrum Certification

Exam Questions

1-) The Agile Manifesto states which of the following values:

A-) People are more important than contracts

B-) Working software should have priority over comprehensive documentation

C-) Plans should have priority over ability to respond

D-) Contracts should be negotiated which allow control over the people

Explanation: The 4 main pillars of Agile manifesto are:1. Individuals and interactions over processes and tools2. Working software over comprehensive documentation3. Customer collaboration over contract negotiation4. Responding to change over following a plan

Sample Agile Scrum Certification

Exam Questions

2-) What does Scrum advise a team to do with the product backlog items it chooses to bring into the sprint?

A-) The team should break each product backlog item into tasks and estimate each task in terms of

effort.

B-) The product owner assigns each product backlog item to the specialist best suited to carry the work.

C-) The team asks the ScrumMaster to research the product backlog items and decide who should work

on each one.

D-) The team doesn't do anything with the product backlog items. Scrum doesn,t use tasks or task lists.

Visit: http://masterofproject.com/courses/agile-project-management-scrum-framework-certification-prep forfull Agile Scrum Certification course

Sample Agile Scrum Certification

Exam Questions

2-) What does Scrum advise a team to do with the product backlog items it chooses to bring into the sprint?

A-) The team should break each product backlog item into tasks and estimate each task in terms of

effort.

B-) The product owner assigns each product backlog item to the specialist best suited to carry the work.

C-) The team asks the ScrumMaster to research the product backlog items and decide who should work

on each one.

D-) The team doesn't do anything with the product backlog items. Scrum doesn,t use tasks or task lists.

Explanation: When the Scrum team has selected and committed to deliver a set of top priority features from the

product backlog, the ScrumMaster leads the team in a planning session to break down product backlog features

into sprint tasks..... At the end of the meeting, the team will have produced a list of all the tasks with estimates

(typically in hours or fractions of a day)

Sample Agile Scrum Certification

Exam Questions

3-) The leadership style of a ScrumMaster is .....

A-) Directive

B-) Assertive

C-) Facilitative

D-) Feature-based

Visit: http://masterofproject.com/courses/agile-project-management-scrum-framework-certification-prep forfull Agile Scrum Certification course

Sample Agile Scrum Certification

Exam Questions

3-) The leadership style of a ScrumMaster is .....

A-) Directive

B-) Assertive

C-) Facilitative

D-) Feature-based

Explanation: The Scrum Master is a facilitative leader, as he should facilitate all the Scrum meetings (events), and also a facilitator in the sense of removing all the team’s impediments for them to continue their work effectively, and meet the Sprint goal at the end of the sprint.

Sample Agile Scrum Certification

Exam Questions

4-) In order to communicate well, the Agile project should ...

A-) Keep team-size large, to avoid stakeholders feeling left out

B-) Break the project into small, mixed-skill, self-organizing teams

C-) Operate with one team of less than 10 people

D-) Operate with separate customer, developer and test teams

Visit: http://masterofproject.com/courses/agile-project-management-scrum-framework-certification-prep forfull Agile Scrum Certification course

Sample Agile Scrum Certification

Exam Questions

4-) In order to communicate well, the Agile project should ...

A-) Keep team-size large, to avoid stakeholders feeling left out

B-) Break the project into small, mixed-skill, self-organizing teams

C-) Operate with one team of less than 10 people

D-) Operate with separate customer, developer and test teams

Explanation: One of the main benefits of Agile is the multiple communication channels it provides to accomplish the product as required. The self-organized team is committed to the product & the backlog they acquire, and as a fruit of the communication & the self-organized teams is the continuous improvement.

Sample Agile Scrum Certification

Exam Questions

5-) How could maintainability of the developing product be improved in a development team?

A-) Apply standard design patterns

B-) Make refactoring a common practice

C-) All of these

D-) Ensure unit testing is included in the developments

Visit: http://masterofproject.com/courses/agile-project-management-scrum-framework-certification-prep forfull Agile Scrum Certification course

Sample Agile Scrum Certification

Exam Questions

5-) How could maintainability of the developing product be improved in a development team?

A-) Apply standard design patterns

B-) Make refactoring a common practice

C-) All of these

D-) Ensure unit testing is included in the developments

Explanation: All the mentioned methods are encouraged by Scrum framework as best engineering practice within the project.