Agendag
• AWWA M28 Liner ClassificationsAWWA M28 Liner Classifications• Class IV C.I.P.P. Case Study: Omaha, NE• Class IV Swagelining Case Study: Amarillo TxClass IV Swagelining Case Study: Amarillo, Tx
• Q&A
P Li Cl ifi tiPressure Liner Classifications• Two categories of pressure
pipe liners– Independent – liner isIndependent liner is
designed for all applicable loads independent of the host pipe INDEPENDENTp p
– Interactive – semi-structural liner relies on radial support from host pipe to handle
loose-fitting and close-fitting
p pinternal loads without failing
INTERACTIVE
Design Liner Classification (AWWA M 28 Manual)
Class I Linings Non Structural
Class II Linings Semi Structural
Class III Linings Semi Structuralg
Class IV Linings*
Fully Structural or Structurally Independent
AQUA-PIPESwageliningg g
1. A long term (50- year) internal burst strength , when tested independently from the host pipe, equal to or greater than the MAOP of the pipe to be rehabilitated
2 The ability to survive any dynamic loading or other short term 2. The ability to survive any dynamic loading or other short- term effects associated with sudden failure of the host pipe due to internal pressure loads
Class IV CIPP Water Main Renewal
1. Locate the pipe2. Excavate access pits3 Cl th i3. Clean the pipe4. CCTV inspection5. Install the liner6. Hydrostatic pressure test7. Reconnection & civil work8 Disinfect the pipe8. Disinfect the pipe9. Site restoration
Water Main RenewalLiner installation
Polyester woven liner impregnated with Epoxy resin Cured with hot water @ 65°C (150°F)
Water Main Renewal Pressure Test
Carried out before Carried out before reinstatement of service connections
As per ASTM F1743 section 8.3
Questions to ask before selecting a technology
A i lt fitti i d t• Are specialty fittings required to:– Pass a pressure test– Terminate the CIPP pipe– Add a new connection
• Are specialty tools required to:– Add a service connection– Repair the pipe
•
SwageliningWater Main Renewal
1. Locate the pipep p2. Excavate access pits3. Clean the pipe4 CCTV inspection4. CCTV inspection5. Install the liner6. Hydrostatic pressure test7. Reconnection & civil work8. Disinfect the pipe9. Site restoration
Swagelining™ Process –P ti f H t PiPreparation of Host Pipe
• Camera inspection• Camera inspection• Cleaning
Swagelining™ Process –Butt Fusion
• Sections of HDPE pipe are butt fused togetherE t l b d• External bead removed
Swagelining™ Process –HDPE enters receiving pit
• Pulling force• Pulling force removed
• Natural relaxation of HDPE
• 90% of reversion occurs in 2 hoursoccurs in 2 hours
• Remaining reversion occurs overnight
Swagelining™ Process –Results
No gaps - all ann al space is annual space is eliminated
Fully structural ypipe