Safety experience from CNGS

38
CNGS horn exchange procedure (EN/MEF) with input from E. Gschwendtner, Hei. Vincke, M.L. Sentis Safety experience from CNGS EDMS 1148375

description

Safety experience from CNGS. CNGS horn exchange procedure. Ans Pardons (EN/MEF) with input from E. Gschwendtner, Hei . Vincke, M.L. Sentis and . EDMS 1148375. Outline. Introduction to CNGS Introduction to CNGS horns Horn exchange Remote handling Horn electrical connection - PowerPoint PPT Presentation

Transcript of Safety experience from CNGS

Page 1: Safety experience from CNGS

CNGS horn exchange procedure

Ans Pardons (ENMEF) with input from E Gschwendtner Hei Vincke ML Sentis and

Safety experience from CNGS

EDMS 1148375

2

Outline Introduction to CNGS Introduction to CNGS horns Horn exchange

Remote handling Horn electrical connection Exchange procedure RP optimisation Hazard and operability (HAZOP) study

2006 horn repair Summary

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

3Neu2012 27-28 Sept 2010 CERNEdda Gschwendtner CERN 3

CERN

PS

SPS

LHC

CNGS

Lake Geneva

CERN Accelerator Complex

bull From SPS 400 GeVcbull Cycle length 6 sbull 2 Extractions separated by 50msbull Pulse length 105msbull Beam intensity 2x 24 middot 1013 pppbull Beam power (dedicated mode) 500kWbull s ~05mm Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

4ABMB 14 Oct 2008E Gschwendtner ABATB

4

Ans PARDONS1st EuroNU Safety Workshop June 2011

Introduction to CNGS - beamline

5

434m100m

1095m 18m 5m 5m67m

27m

TBID

1 Target unit 13 graphite rods 10cm1 Magazine 1 unit used 4 in situ spares

994m long 245m 1mbar vacuum

100kW

270cm1125cm

Muon detectors2x41 LHC type BLMs

Target chamber 100m

2 HORNS (magnets)7m long 150180kA pulsedWater cooled 18mm inner conductor

Horn1

Horn2

Introduction to CNGS - performance

6

Jul-0

6

Sep-

06

Dec

-06

Feb-

07

May

-07

Aug

-07

Oct

-07

Jan-

08

Apr

-08

Jun-

08

Sep-

08

Nov

-08

Feb-

09

May

-09

Jul-0

9

Oct

-09

Jan-

10

Mar

-10

Jun-

10

Aug

-10

Nov

-10

Feb-

11

Apr

-11

Jul-1

1

Oct

-11

Dec

-11

00E+0050E+1810E+1915E+1920E+1925E+1930E+1935E+1940E+1945E+1950E+1955E+1960E+1965E+1970E+1975E+1980E+1985E+1990E+1995E+1910E+2011E+2011E+2012E+20

inte

grat

ed P

OT

2006008E19 pot

2007008E19 pot

2008 (108 days)178E19 pot

2009 (151 days)352E19 pot

2010 (192 days)404E19 pot

Physics runbullBeam commissioningbullFinishing OPERA

2011

Total Integrated Intensity since CNGS Start in 2006

Start-up Issues

50 of approved nr of protons on target

Ans PARDONS1st EuroNU Safety Workshop June 2011

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 2: Safety experience from CNGS

2

Outline Introduction to CNGS Introduction to CNGS horns Horn exchange

Remote handling Horn electrical connection Exchange procedure RP optimisation Hazard and operability (HAZOP) study

2006 horn repair Summary

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

3Neu2012 27-28 Sept 2010 CERNEdda Gschwendtner CERN 3

CERN

PS

SPS

LHC

CNGS

Lake Geneva

CERN Accelerator Complex

bull From SPS 400 GeVcbull Cycle length 6 sbull 2 Extractions separated by 50msbull Pulse length 105msbull Beam intensity 2x 24 middot 1013 pppbull Beam power (dedicated mode) 500kWbull s ~05mm Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

4ABMB 14 Oct 2008E Gschwendtner ABATB

4

Ans PARDONS1st EuroNU Safety Workshop June 2011

Introduction to CNGS - beamline

5

434m100m

1095m 18m 5m 5m67m

27m

TBID

1 Target unit 13 graphite rods 10cm1 Magazine 1 unit used 4 in situ spares

994m long 245m 1mbar vacuum

100kW

270cm1125cm

Muon detectors2x41 LHC type BLMs

Target chamber 100m

2 HORNS (magnets)7m long 150180kA pulsedWater cooled 18mm inner conductor

Horn1

Horn2

Introduction to CNGS - performance

6

Jul-0

6

Sep-

06

Dec

-06

Feb-

07

May

-07

Aug

-07

Oct

-07

Jan-

08

Apr

-08

Jun-

08

Sep-

08

Nov

-08

Feb-

09

May

-09

Jul-0

9

Oct

-09

Jan-

10

Mar

-10

Jun-

10

Aug

-10

Nov

-10

Feb-

11

Apr

-11

Jul-1

1

Oct

-11

Dec

-11

00E+0050E+1810E+1915E+1920E+1925E+1930E+1935E+1940E+1945E+1950E+1955E+1960E+1965E+1970E+1975E+1980E+1985E+1990E+1995E+1910E+2011E+2011E+2012E+20

inte

grat

ed P

OT

2006008E19 pot

2007008E19 pot

2008 (108 days)178E19 pot

2009 (151 days)352E19 pot

2010 (192 days)404E19 pot

Physics runbullBeam commissioningbullFinishing OPERA

2011

Total Integrated Intensity since CNGS Start in 2006

Start-up Issues

50 of approved nr of protons on target

Ans PARDONS1st EuroNU Safety Workshop June 2011

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 3: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

3Neu2012 27-28 Sept 2010 CERNEdda Gschwendtner CERN 3

CERN

PS

SPS

LHC

CNGS

Lake Geneva

CERN Accelerator Complex

bull From SPS 400 GeVcbull Cycle length 6 sbull 2 Extractions separated by 50msbull Pulse length 105msbull Beam intensity 2x 24 middot 1013 pppbull Beam power (dedicated mode) 500kWbull s ~05mm Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

4ABMB 14 Oct 2008E Gschwendtner ABATB

4

Ans PARDONS1st EuroNU Safety Workshop June 2011

Introduction to CNGS - beamline

5

434m100m

1095m 18m 5m 5m67m

27m

TBID

1 Target unit 13 graphite rods 10cm1 Magazine 1 unit used 4 in situ spares

994m long 245m 1mbar vacuum

100kW

270cm1125cm

Muon detectors2x41 LHC type BLMs

Target chamber 100m

2 HORNS (magnets)7m long 150180kA pulsedWater cooled 18mm inner conductor

Horn1

Horn2

Introduction to CNGS - performance

6

Jul-0

6

Sep-

06

Dec

-06

Feb-

07

May

-07

Aug

-07

Oct

-07

Jan-

08

Apr

-08

Jun-

08

Sep-

08

Nov

-08

Feb-

09

May

-09

Jul-0

9

Oct

-09

Jan-

10

Mar

-10

Jun-

10

Aug

-10

Nov

-10

Feb-

11

Apr

-11

Jul-1

1

Oct

-11

Dec

-11

00E+0050E+1810E+1915E+1920E+1925E+1930E+1935E+1940E+1945E+1950E+1955E+1960E+1965E+1970E+1975E+1980E+1985E+1990E+1995E+1910E+2011E+2011E+2012E+20

inte

grat

ed P

OT

2006008E19 pot

2007008E19 pot

2008 (108 days)178E19 pot

2009 (151 days)352E19 pot

2010 (192 days)404E19 pot

Physics runbullBeam commissioningbullFinishing OPERA

2011

Total Integrated Intensity since CNGS Start in 2006

Start-up Issues

50 of approved nr of protons on target

Ans PARDONS1st EuroNU Safety Workshop June 2011

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 4: Safety experience from CNGS

Ans PARDONS1st EuroNU Safety Workshop June 2011

4ABMB 14 Oct 2008E Gschwendtner ABATB

4

Ans PARDONS1st EuroNU Safety Workshop June 2011

Introduction to CNGS - beamline

5

434m100m

1095m 18m 5m 5m67m

27m

TBID

1 Target unit 13 graphite rods 10cm1 Magazine 1 unit used 4 in situ spares

994m long 245m 1mbar vacuum

100kW

270cm1125cm

Muon detectors2x41 LHC type BLMs

Target chamber 100m

2 HORNS (magnets)7m long 150180kA pulsedWater cooled 18mm inner conductor

Horn1

Horn2

Introduction to CNGS - performance

6

Jul-0

6

Sep-

06

Dec

-06

Feb-

07

May

-07

Aug

-07

Oct

-07

Jan-

08

Apr

-08

Jun-

08

Sep-

08

Nov

-08

Feb-

09

May

-09

Jul-0

9

Oct

-09

Jan-

10

Mar

-10

Jun-

10

Aug

-10

Nov

-10

Feb-

11

Apr

-11

Jul-1

1

Oct

-11

Dec

-11

00E+0050E+1810E+1915E+1920E+1925E+1930E+1935E+1940E+1945E+1950E+1955E+1960E+1965E+1970E+1975E+1980E+1985E+1990E+1995E+1910E+2011E+2011E+2012E+20

inte

grat

ed P

OT

2006008E19 pot

2007008E19 pot

2008 (108 days)178E19 pot

2009 (151 days)352E19 pot

2010 (192 days)404E19 pot

Physics runbullBeam commissioningbullFinishing OPERA

2011

Total Integrated Intensity since CNGS Start in 2006

Start-up Issues

50 of approved nr of protons on target

Ans PARDONS1st EuroNU Safety Workshop June 2011

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 5: Safety experience from CNGS

Ans PARDONS1st EuroNU Safety Workshop June 2011

Introduction to CNGS - beamline

5

434m100m

1095m 18m 5m 5m67m

27m

TBID

1 Target unit 13 graphite rods 10cm1 Magazine 1 unit used 4 in situ spares

994m long 245m 1mbar vacuum

100kW

270cm1125cm

Muon detectors2x41 LHC type BLMs

Target chamber 100m

2 HORNS (magnets)7m long 150180kA pulsedWater cooled 18mm inner conductor

Horn1

Horn2

Introduction to CNGS - performance

6

Jul-0

6

Sep-

06

Dec

-06

Feb-

07

May

-07

Aug

-07

Oct

-07

Jan-

08

Apr

-08

Jun-

08

Sep-

08

Nov

-08

Feb-

09

May

-09

Jul-0

9

Oct

-09

Jan-

10

Mar

-10

Jun-

10

Aug

-10

Nov

-10

Feb-

11

Apr

-11

Jul-1

1

Oct

-11

Dec

-11

00E+0050E+1810E+1915E+1920E+1925E+1930E+1935E+1940E+1945E+1950E+1955E+1960E+1965E+1970E+1975E+1980E+1985E+1990E+1995E+1910E+2011E+2011E+2012E+20

inte

grat

ed P

OT

2006008E19 pot

2007008E19 pot

2008 (108 days)178E19 pot

2009 (151 days)352E19 pot

2010 (192 days)404E19 pot

Physics runbullBeam commissioningbullFinishing OPERA

2011

Total Integrated Intensity since CNGS Start in 2006

Start-up Issues

50 of approved nr of protons on target

Ans PARDONS1st EuroNU Safety Workshop June 2011

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 6: Safety experience from CNGS

Introduction to CNGS - performance

6

Jul-0

6

Sep-

06

Dec

-06

Feb-

07

May

-07

Aug

-07

Oct

-07

Jan-

08

Apr

-08

Jun-

08

Sep-

08

Nov

-08

Feb-

09

May

-09

Jul-0

9

Oct

-09

Jan-

10

Mar

-10

Jun-

10

Aug

-10

Nov

-10

Feb-

11

Apr

-11

Jul-1

1

Oct

-11

Dec

-11

00E+0050E+1810E+1915E+1920E+1925E+1930E+1935E+1940E+1945E+1950E+1955E+1960E+1965E+1970E+1975E+1980E+1985E+1990E+1995E+1910E+2011E+2011E+2012E+20

inte

grat

ed P

OT

2006008E19 pot

2007008E19 pot

2008 (108 days)178E19 pot

2009 (151 days)352E19 pot

2010 (192 days)404E19 pot

Physics runbullBeam commissioningbullFinishing OPERA

2011

Total Integrated Intensity since CNGS Start in 2006

Start-up Issues

50 of approved nr of protons on target

Ans PARDONS1st EuroNU Safety Workshop June 2011

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 7: Safety experience from CNGS

7

Target chamber lay-out and dose rate

1 Protected service tunnel

2 Upstream part of target hall (crane storage)

3 Target area4 Horn area

mSvh

One year continuous operation at 3xnominal

intensity then one day cool-down

beam

1

32 4

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 8: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

8

Length 7 meters weight1500kg Water cooled at 15 bar Powered at 150180kA via striplines from service gallery In shielding castle 2 cradles for remote handling with overhead crane Electric Fast Coupling (manual) amp water connection

(automatic)

CNGS horns

Ans PARDONS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 9: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

9

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange

Ans PARDONS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 10: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

10

Remote handling Design of shielding and beamline elements

optimised for remote handling followed by extensive handling tests

Overhead crane with coordinate system and cameras

beam

Ans PARDONS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 11: Safety experience from CNGS

11 1st EuroNU Safety Workshop June 2011

CNGS horns electrical connection1 Disconnect fast

coupling (through shielding block)

2 Remove section of stripline (in trench)

3 Slide disconnected section downstream (in trench)

13

2

Custom-made shieldingSliding section

Screws to disconnectSection fixed to

horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 12: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

12

CNGS horns electrical connection In pictures

Ans PARDONS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 13: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

13

bull Disconnect Fast Coupling

bull Take out Stripline Link

bull Move stripline part 1(open)

bull Remove shielding (roof amp passage

side wall)

Horn Exchange procedure

Exchange Horn

bull Build up shieldingbull Move stripline part 1

(close) bull Put Stripline Link

backbull Connect Fast

CouplingAns PARDONS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 14: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

14

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 15: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

15

RP optimisation FLUKA simulations

Dose rate (microSvh) for different cool-down times

mSvhAns PARDONS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 16: Safety experience from CNGS

16 Ans PARDONS1st EuroNU Safety Workshop June 2011

I ntervention StepDuration (min) Location 1 day 1 week 1 month 2 months 4 months 6 months

I nstall lights 1 2 1573 48 31 26 19 17

Open f ast coupling connection 4 3 6461 236 148 122 91 77Remove stripline link section in trench 14 1 5716 178 134 118 103 92

Slide stripline downstream 3 1 1224 38 28 25 22 19

Slide stripline upstream 6 1 2449 76 57 50 44 39

Close f ast coupling connection 6 3 9691 354 222 184 137 116

Take dimensions of new stripline link section 2 1 816 25 19 16 14 13

I nstall stripline link section in trench 20 1 8166 255 192 169 147 132

Remove lights 1 2 1573 48 31 26 19 17TOTAL (μSv ) 37700 1260 870 740 600 530

Accumulated dose (μSv )

RP optimisation accumulated dose Most penalizing steps identified optimization

(design or tools) Minimum cool-down time indication (though in-situ

RAMSES measurements have the last word)

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 17: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

17

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested

Updated procedure = script for exchange exercise

Horn exchange procedure

Ans PARDONS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 18: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

18

HAZOP study (from HAZOP report) Scopehellip The proposed sequence of horn exchange

operations was examined using HAZOPs a systematic team-based hazard identification method This resulted in the identification of potential hazards and operability problems which could then be addressed in the development of the detailed method statements which would be produced should replacement of the Horn be needed This would give confidence that these method statements would incorporate adequate safety and that operator doses arising from their implementation would be As Low As Reasonably Achievable (ALARA) hellip

Ans PARDONS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 19: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

19

HAZOP study (from HAZOP report)The HAZOP technique The HAZOP technique is a structured systematic and comprehensive

examination process of the proposed sequence of operations in order to identify potential hazards and operability problems The process is carried out by a suitably qualified team of experts familiar with all aspects of the operations undergoing study This team is led by a team leader qualified in the application of the technique usually a safety professional Discussions conclusions recommendations and actions are formally recorded by a technical secretary

The HAZOP technique is used worldwide throughout the nuclear and chemical process industries as a powerful tool to aid safe design of processes (and operations) and to minimise operability problems associated with the design of a particular process or sequence of operations

The HAZOP uses a set of keywords which are essentially potential hazards which direct the teamrsquos thinking

Each keyword was considered separately in succession and any potential hazards or operability problems recorded

The keyword list is presented to the team and agreed before commencement of the study

Ans PARDONS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 20: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

20

HAZOP study Performed by specialized company in close collaboration with CERN

experts (radiation protection safety handling horn horn handling + project leader)

1 Preparation- agree on sequences in horn exchange procedure- agree on keywords (applicable hazards)

2 HAZOP meeting (25 days) 15-17 June 2005- visit of tunnels- detailed work-through of all the procedure steps applying

each keywordhazard to each step (see next slide)3 Follow-up

1 approve minutes2 follow-up on ldquoactionsrdquo3 review actions (phone conference)4 presentation of HAZOP report 2 Sept 2005

Ans PARDONS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 21: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

21

HAZOP study keywords and procedure steps (from report)

Preparation Manned entry to the target chamber to set up the lighting disconnect the Fast Coupling Connection and physically disconnect the stripline

Shielding Removal Using the overhead crane remotely remove the top and side shielding Removal and Storage of the old Horn Using the overhead crane remotely remove the old Horn

from the target chamber support frame and place on motorised trailer The motorised trailer is then guided remotely to a chamber where the horn is stored behind shielding

Installation of the new Horn The new Horn having been brought into the access chamber is picked up by the overhead crane and remotely placed on the target chamber support frame

Shielding Replacement Using the overhead crane remotely replace the top and side shielding Horn Reconnection Via manned entry physically re-install the stripline and reconnect the FCC Conclusion Via manned entry tidy up target chamber and remove lighting

Ans PARDONS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 22: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

22

Extract from minutes (from report)

(no

actio

n ne

eded

)

Ans PARDONS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 23: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

23

HAZOP study conclusion (from report) A number of hazards and operability concerns were identified

together with existing safety measures Where additional safety measures or other measures to address operability concerns were required they were addressed through actions raised on team members Action responses were discussed at an action review meeting actions were accepted and cleared one recommendation was made This recommendation is now the subject of a design study

As part of pre-active commissioning work the CNGS project intend to carry out a full trial of the Horn Exchange procedure This will take account of issues raised at this study and will result in a complete set of operating instructions for the procedure In this way the adequacy of safety measures and the potential for operability problems can be tested and depending on the results additional measures put in place prior to the procedure being used during the life of the experiment

Ans PARDONS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 24: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

24

HAZOP study our conclusionWas it worth it Yes

Frequently Asked Questions amp RemarksldquoYou could have done this yourselvesrdquo Yes but would we have taken the time to do it in enough detail Would we have done in an officially recognized traceable manner An external pair of eyes sheds a new light on ldquoourrdquo topic

ldquoDid you really learn something newrdquo (Eh yes we did (at least I did)) Even if this could be true for some very experienced persons having

some items pointed out in a clear manner and documented allows no ldquoescaperdquo when it comes to action

Would we do it againYes this structured exercise is very useful for other more frequent interventions in ldquohotrdquo areas at CERN

Ans PARDONS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 25: Safety experience from CNGS

25

Design phase Optimization with respect to dose rate (material choice) and intervention time (remote connections etc)

+ Experience from past First draft of procedure = Input to RP minimum waiting time amp

optimisation of intervention steps Second draft of procedure

= Input to HAZOP study main remaining risks identified modifications proposed and

integrated New version written with input from study amp experts

(radioprotection handling transport hellip) Tools designed produced amp tested Third draft = script for exchange exercise (before

start-up) From lessons learnt Final version of procedure

Final version of procedure = script for future horn exchange

Horn exchange procedure

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 26: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

26

When reality kicks in Horn Water LeakOctober 2006 Leak in water outlet of cooling circuit of reflector after 4105 pulses

1hour40

60Observation bull High refill rate of closed water circuit of reflector cooling systembull Increased water levels in sumpsReasonbullInadequate design of water outlet connectors (machining brazing)

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 27: Safety experience from CNGS

Ans PARDONS1st EuroNU Safety Workshop June 2011

27

Improvement

Improved design replace brazed connections by connectors under pressure

Stress in ceramic strongly reducedbull No brazingbull No machined internal edgesbull Ceramic under compression only

(10 times stronger)

Water amp air tightbull Soft graphitesteel seal

(5MPa pre-stress)bull Self-locking nuts

Thorough technical studybull Detailed validationcalculations

of the new design bull Additional features optimized

new new

old

old

Water Outlets Water Inlets

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 28: Safety experience from CNGS

Ans PARDONS1st EuroNU Safety Workshop June 2011

28

2006 Horn RepairWork executed in upstream part

of target hall Repair includes the removal amp

reinstallation of both horns according to horn exchange procedure

Dose to personnel minimised thanks to Detailed documentation available on

ldquohorn exchangerdquo and additional radiation dose planning and minimization for the rest

Experience from ldquohorn exchangerdquo available (same team) and practice of the repair work on spare horn

Each work step executed by up to 4 persons to reduce individual dose

Additional local shielding total integrated dose 16mSv

(repair plus ldquohorn exchangerdquo)Shielded cabin

Mobile lead shield

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 29: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

29

Summary Guidelines for ldquosmoothrdquo interventions Include remote handling from the early design stage on Involve RP in the early design stage (many iterations do

the trick) Invest in an adapted (remote) and reliable lifting device Horn exchange procedure received

Mechanical input (experience in deign for remote handling) RP input (FLUKA calculations very helpful completed with on-

site monitoring) General safety input (HAZOP + CERN safety team)

Practise the procedure on mock-up or on ldquocleanrdquo objects (several weeks and several iterations) and complete documentation with pictures films coordinate sheets

Ans PARDONS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 30: Safety experience from CNGS

For info in next slides

Photos of the horn exchange procedure

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 31: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

31

Remove old horn

100 Remote

from target chamberto radioactive storage

Horn vs lower frame

Ans PARDONS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 32: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

32

Install new horn

50 Remote New laquo clean raquo horn

Ans PARDONS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 33: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

33

Build up shielding

Coordinates recorded during exercise

before after

Storage blocks

100 Remote

Ans PARDONS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 34: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

34Edda Gschwendtner CERN 34

Beam parameters Nominal CNGS beam Nominal PSNF beamProton beam delivered from SPS PS

Nominal proton energy 400 GeVc 20 GeVcCycle length 6 s 12 s extractions per cycle 2 separated by 50 ms 1Intensity per cycle 48 1013 3 1013

Extraction length 105 ms 21ms (dedicated) 184ms (parasitic)

Beam power 500 kW 80 kW

Approved total protons on target 225 1019 25 1019

Beam Parameters CNGS - PSNF

Ans PARDONS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 35: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

35Edda Gschwendtner CERN 35

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- due to high energy hadron fluence)

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

targetmagnetic

horns

decay tunnel

hadron absorber

muon detector 1

muon detector 2

CNGS no surface building above CNGS target area

large fraction of electronics in tunnel area

Failure in ventilation system installed in the CNGS Service gallery due to radiation effects in electronics (SEU ndash Single Event Upsets- from high energy hadron fluence)

ventilationunits

(2007-2008)CNGS Radiation Issues I

Ans PARDONS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 36: Safety experience from CNGS

Ans PARDONS1st EuroNU Safety Workshop June 2011

36

CNGS Radiation Issues II

106 hcm2yr2008++

Modifications during shutdown 200708 Move most of the electronics out of

CNGS tunnel area Create radiation safe area for

electronics which needs to stay in CNGS Add shielding 53m3 concrete up to

6m3 thick shielding walls

200607

109 hcm2yr

p-beam target chamber p-beam target chamber

ventilationunits

High-energy (gt20MeV) hadrons fluence (hcm2) for 45E19 pots

(2007-2008)

SBNW11 12 ndash 14 May 2011 FermilabEdda Gschwendtner CERN 36

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 37: Safety experience from CNGS

37

CNGS Sump and Ventilation SystemAfter 1st year of high intensity CNGS physics run Modification needed for Sump system in the CNGS area

avoid contamination of the drain water by tritium produced in the target chamber Try to remove drain water before reaches the target areas and gets in contact with the air Construction of two new sumps and piping work

Ventilation system configuration and operation Keep target chamber under under-pressure with respect to all other areas Do not propagate the tritiated air into other areas and being in contact with the drain water

Add 2 new small sumps (1m3) pump out water immediately

Target chamber

(2009-2010)

Ans PARDONS1st EuroNU Safety Workshop June 2011

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System
Page 38: Safety experience from CNGS

1st EuroNU Safety Workshop June 2011

38

Continuous Surveillance and Interlock System

shielding

shielding

horn

ionization chamber

ionization chamber

target TBIDcollimator

BPM

beam

Intensity on TBID vs BPM

BPM [mm]

14mm collimator opening

5mm target

Intensity on Ionization Chambers vs BPM

BPM [mm]

5mm target

0

2

4

6

8

10

12

14

16

18

20

719

00

0

719

10

5

719

21

1

719

31

6

719

42

2

719

52

7

719

63

3

719

73

8

719

84

4

719

94

9

719

10

55

719

12

00

719

13

06

719

14

11

date

mul

tiplic

ity

10E-01

12E-01

14E-01

16E-01

18E-01

20E-01

22E-01

24E-01

char

ges

pot

TBID Detector

Ionization Chamber

TBID break-down Protons on TargetExtrTemp downstream HornHorn water conductivityTemp Horn cooling water

45deg

60deg

2

11mScm

13deg

20deg22E13

Beam trajectory tolerance on target 05mm

Horiz 50mm rms

Edda Gschwendtner CERN 38Ans PARDONS

  • Safety experience from CNGS
  • Outline
  • Slide 3
  • Slide 4
  • Introduction to CNGS - beamline
  • Introduction to CNGS - performance
  • Target chamber lay-out and dose rate
  • CNGS horns
  • Horn exchange
  • Remote handling
  • CNGS horns electrical connection
  • CNGS horns electrical connection (2)
  • Horn Exchange procedure
  • Horn exchange procedure
  • RP optimisation FLUKA simulations
  • RP optimisation accumulated dose
  • Horn exchange procedure (2)
  • HAZOP study (from HAZOP report)
  • HAZOP study (from HAZOP report) (2)
  • HAZOP study
  • HAZOP study keywords and procedure steps (from report)
  • Extract from minutes (from report)
  • HAZOP study conclusion (from report)
  • HAZOP study our conclusion
  • Horn exchange procedure (3)
  • When reality kicks in Horn Water Leak
  • Improvement
  • 2006 Horn Repair
  • Summary Guidelines for ldquosmoothrdquo interventions
  • For info in next slides
  • Remove old horn
  • Install new horn
  • Build up shielding
  • Beam Parameters CNGS - PSNF
  • CNGS Radiation Issues I
  • CNGS Radiation Issues II
  • CNGS Sump and Ventilation System
  • Continuous Surveillance and Interlock System