SAFETY AUDIT
IS 14489 : 1998
DO INSPECTION AUDIT YOURSELF
GROUP 5
-
8/3/2019 Safety Audit Ppt Representation (2)
2/58
INTRODUCTION
Safety Audit is management tool comprisingof a systematic ,periodic and objectiveevaluation of how well the safety
organization, management and equipmentare performing, with the aim of helps tosafeguard a companys assets by facilitatingmanagement control of safety, health and
environmental practices and assessingcompliance with established standards
-
8/3/2019 Safety Audit Ppt Representation (2)
3/58
TYPES OF AUDITS
External : These are conducted by a thirdparty
Internal : Corporate : By headquartersor
personnel from other units of
the same company.
Self :Inhouseby the plant personnelthemselves.
-
8/3/2019 Safety Audit Ppt Representation (2)
4/58
AUDITS OBJECTIVES
Verify compliance with established standards(regulations, internal policies and industry wisestandards of practice )
Identify deviation from designed and plannedoperating and maintenance procedure andstandards
Identify plant condition or operating procedures
that could lead to an accident and significantlosses to life or property
Ensure that the plan and operating andmaintenance procedures match the design intent
and standards
-
8/3/2019 Safety Audit Ppt Representation (2)
5/58
Keep the operating personnel alert to the process
hazards Review operating procedures for necessary
revisions
Seek to identify equipment or process changes
that could have introduced new hazards
Ultimate application of new technology to existing
hazards
Review adequacy of safety inspections Look for major risk situations recommend
measures to improve overall safety performance
of the plant
-
8/3/2019 Safety Audit Ppt Representation (2)
6/58
Methodology in Conducting a Safety Audits
The following activities are carried out in conducting a
safety audit and implementing the audit recommendation
Pre-audit activities
Key on-sites activities
Post-audit activities
-
8/3/2019 Safety Audit Ppt Representation (2)
7/58
Pre-audit Activities
The safety audit process being with the following activities
before the actual onsite audit takes place :
Request by management / identification of industry according to highhazards/high rate of accidents
Scheduling of the audits
Selection of the audit team
Development of an audit plan which includes-Defining the scope of the audit
-Selecting priority topics-Modifying the audit protocols-Allocating audit team resources
Advance visit to the factory to gather background information and data,administering a questionnaire.
-
8/3/2019 Safety Audit Ppt Representation (2)
8/58
Background information to be gathered :
1. List of products2. Brief description of the manufacturing process with
process flow diagram/block diagram
3. Built-up area and site plan/names of departments
4. Number of company employees ( managers, supervisorsand workmen ) and contractors employees
5. Organization structure, including SHE function
6. List of chemicals handled:
- Raw materials- Products
- Intermediates
- By-products
-
8/3/2019 Safety Audit Ppt Representation (2)
9/58
Date to be gathered :
1 Brief description of major accidents in the pastten years
2 Accident statistics for the last five yearstypes/ cause of accidents and analysis
3 Details of fires / explosions / toxic releases inthe last five years
-
8/3/2019 Safety Audit Ppt Representation (2)
10/58
Key On-site Activities
Understanding Management Systems:
First of all a working understanding of the industrys
internal safety management system, i.e. the set of
formal and normal actions taken by the industry is
required to be developed. This step usually includes
developing a understanding of :
Factory processes
Internal controls ( both management and engineering)
-
8/3/2019 Safety Audit Ppt Representation (2)
11/58
Plant organization and responsibilities
Compliance parameters and other applicable requirements
Any current or past problems The picture of internal management systems is usually drawn
from the following sources:
Discussions with management personnel, supervisors andworks
Specially designed internal controls questionnaire Plant visits
In some cases, a limited amount of verification testingconducted to help confirm the auditors initial understanding
The auditor records his or her understanding in a flow chart-
narrative, description, or some combination of the two-inorder to have a written description against which audit is to bedone.
-
8/3/2019 Safety Audit Ppt Representation (2)
12/58
Assessing Strengths and Weaknesses :
In assessing strengths of internal controls,
auditors look for the following indications.
Whether factory personnel are trained andexperienced
Whether responsibilities at various levels are clearlydefined and carefully assigned
-
8/3/2019 Safety Audit Ppt Representation (2)
13/58
Whether duties are so divided that these minimize conflicts ofinterest
Whether authorization systems are in existence
Whether internal verification procedures are in place Whether protective measures-security systems and alarms are
taken
Whether procedures and compliance / exception results are inplace
For each of the areas assigned, the auditor should ask himselfthe following questions :
* If the facility is doing everything the way they say ithappens, is that acceptable ?* Is the facility incompliance with applicable requirementsand is the factory adequately protected ?
-
8/3/2019 Safety Audit Ppt Representation (2)
14/58
Collecting Audit Evidence :
Audit evidence forms the basis on which the teamdetermines compliance with laws, regulations,corporate policies and / or other standards.
Suspected weaknesses in the management system areconfirmed in this step. Also management systemsthat appear sound are tested to verify that they workas planned and are consistently effective. Variouswork such as record reviews, examination of
available data, observation and interviews withfactory personnel are used to gather audit evidence.
-
8/3/2019 Safety Audit Ppt Representation (2)
15/58
Completeness and authenticity of records
Purpose and effectiveness of the format and theirsatisfactory filling-up.
Checking of records and show-up action by neverauthorities.
Method of maintaining records
Interview with factory personnel :
The auditor asks questions, both formally andinformally. The following points should be kept inmind while interviewing a person.
-
8/3/2019 Safety Audit Ppt Representation (2)
16/58
Interviewing persons is a difficult matter and should behandled properly.
Sometimes due to various reasons, the person is reluctant to
provide the required information. During interviews, unnecessary / irrelevant questions should
be avoided.
The person being interviewed should be kept at ease
The interviewer should create a feeling of trust in the person
being interviewed. Information should be collected by interviewing, persons at
the appropriate level.
Verify statements by interviewing persons of the same /different levels.
The person should be interviewed at his normal workinglocation.
Proper judgments should be used to select a sample of thework force for the interview.
-
8/3/2019 Safety Audit Ppt Representation (2)
17/58
Observation :
Plant visit, observation is a significant aspect of safety
audit. The auditor collect evidence through what can be
seen, heard, touched or smell. The following points
should be kept in mind during a plant visit :
Visit to the plant must be during the normal working
condition.
Observation on relevant audit elements should berecorded on the spot.
The auditor should develop skills ( keep eyes open ) to
make observation of several elements at each location.
-
8/3/2019 Safety Audit Ppt Representation (2)
18/58
Once sufficient deficiencies relating to a particularitem are detected, checking of that item at other
locations may be stopped. When sufficient observations ( particularly about
acceptable systems ) are made on a particularelement during plant visit the auditor should spent
less time in document verification of that item. Safe operating procedures should also be checked.
The auditor should try to visit some locations undershut down maintenance, construction, etc.
The auditor must make one visit during second shift/ holiday to assess conditions and functioning ofsystems apart from in the general shift.
The auditor must check the availability of operatingprocedures in the plant.
-
8/3/2019 Safety Audit Ppt Representation (2)
19/58
Evaluating audit evidence :
After the evidence is gathered, the audit findings
and observations are evaluated. The audit team
sets aside a few hours at the end of the audit to
discuss, evaluate and finalize the tentative audit
findings. The team confirms if there is sufficient
evidence to support all findings. Findings that
may be more significant than individualdeficiencies are identified and each finding is
summarized in a way that most clearly conveys
its significance.
-
8/3/2019 Safety Audit Ppt Representation (2)
20/58
-
8/3/2019 Safety Audit Ppt Representation (2)
21/58
Post-audit Activities
The final audit report is issued to the chiefexecutive of the company. Some companies also
distribute the report to various levels of the operatingand line management communication and distributedto those with a need to know. A formal procedure forresponding to the audit report is established. Theaction planning process is initiated as audit findingsare identified. If assigns responsibilities for correctiveaction, determines potential solutions and preparesrecommendations to correct any deficienciesmentioned in the audit report, and establishes time
tables. Companies may also incorporates the actionplan in the final report. Action plans are monitoredand followed either by the operating management,the safety department. Or the auditors. The follow-upinvolves a written or oral inquiry to the status of the
planned action.
-
8/3/2019 Safety Audit Ppt Representation (2)
22/58
Audit ElementsThe detailed scope of the audit is listed as a series of
audit elements in two broad categories :
1 Management Systems , and
2 Technical / Hardware Aspects .
Under each element a number of sub- elements have
been listed. There may be many instances,particularly in small or medium sized plants, whereall elements need not be used. Further, for eachtype of industry (e.g. fertilizer petrochemical,pesticide ) detailed listings /checklists would need tobe prepared. Therefore selection of elements andsub-elements should be done using the professional
judgment of the auditor, based on the type and sizeof the industry and other aspects.
-
8/3/2019 Safety Audit Ppt Representation (2)
23/58
Management SystemThe essential elements of safety management system
to be audited are given below :
1 Safety, Health & Environment ( SHE ) Policyi ) Managements commitment to SHEii ) Accountability and Responsibility
iii ) Implementationiv ) Policy review
2 Safety and Health Organizational Set-upi ) Safety Department
- Structure- Responsibilitiesii ) Occupational Health Servicesiii ) Safety Committee
-
8/3/2019 Safety Audit Ppt Representation (2)
24/58
3 Education and Training
i ) Induction training for new employees-Category-Topics-Duration
-Feedback-Methodology
ii ) Periodic Training
-Category
-Topics-Duration-Periodicity-Feedback-Methodology
-
8/3/2019 Safety Audit Ppt Representation (2)
25/58
4 ) Communication / Motivation /Promotion in Safetyi) Safety suggestion schemeii) Safety competitions- Safety performance- Housekeeping
- Safety essay, slogan and posteriii) Display Board informationiv) Safety publicationsv) Safety week / Day celebrations
5 ) Safety Inspectionsi) Periodic inspectionii) Routine inspectioniii) Special inspection
-
8/3/2019 Safety Audit Ppt Representation (2)
26/58
6) Accident Reporting, Investigation and
Implementation of Recommendations
i) Reportable- Fatal- Serious- Othersii) Non-Reportable
iii) Dangerous occurrences / Near misses7) Maintenance of Accident Statistics and its
Utilization
i) Accident rate per 1000 workers employedii) Frequency rateiii) Severity- Type-wise and cause-wise analysis ofaccidents
-
8/3/2019 Safety Audit Ppt Representation (2)
27/58
8) Safety Audits
i) External auditsii) Internal audits
- Self
- Corporate
9) Personal Protective
Equipmentsi) Types and selection
ii) Training and motivationiii) Enforcement
iv) Maintenance
v) Testing
P / Pl M difi i P d
-
8/3/2019 Safety Audit Ppt Representation (2)
28/58
10) Process / Plant Modification Procedure
( including Technology Change )
11) Safe Operating Procedurei) Implementationii) Review
12) Work Permit System
i) Line breakingii) Confined space entry
iii) Hot workiv) Electrical lockout and tag systemv) Excavationvi) Working at heightvii) Working on fragile
-
8/3/2019 Safety Audit Ppt Representation (2)
29/58
13) Fire Fighting System
i) Selection of fire fighting equipment
ii) Fire fighting proceduresiii) Fire fighting teamiv) Communication systemv) Drillsvi) Inspection and maintenance of fire fighting
equipments14) Health and Safety Improvement Plan /
Targets
i) Accident / Incident rate reduction
ii) Improvement in environmental standards
-
8/3/2019 Safety Audit Ppt Representation (2)
30/58
15 Prevention of Occupational Diseasesi) Identification of areas with potential for occupationaldiseasesii) Engineering control measuresiii) Administrative control measures
16) Work Environment Monitoring System
i) In-plant facilitiesii) Assistance from outside organizations
17) Medical Examinationi) Pre-employmentii) Periodical
-
8/3/2019 Safety Audit Ppt Representation (2)
31/58
18) Material Safety Data Sheetsi) Preparation
ii) Updates
iii) Dissemination
19) Emergency Preparedness Plan ( On-site / off-
site )
i) Emergency response systemii) Emergency alarm system
iii) Mock drills
iv) Co-ordination with the local authorities
v) Education of general publicvi) Communication with the public
-
8/3/2019 Safety Audit Ppt Representation (2)
32/58
20) Hazardous Waste Treatment and
Disposal
i) Incineration of solid waste
ii) Efficient treatment
iii) Disposal
iii) Air pollution control measures
21) Transportation of Hazardous Materialsi) Provision of informationii) Emergency response
-
8/3/2019 Safety Audit Ppt Representation (2)
33/58
22) Hazard Identification
i) Checklist
ii) What if ? review of operations
iii) Hazard and operability study ( Hazop )
iv) Fault Tree Analysisv) Mond and Dow index
23) Contractor Safety Systems
24) New Equipment Review / Inspection
-
8/3/2019 Safety Audit Ppt Representation (2)
34/58
Technical Aspects
The essential elements of a technical safety audit are
based on the scope of the audit. These may be actedin a particular plant / operation / aspect or mayextend to technical safety aspects of the entire
factory.
The following technical aspects are to be looked into in detail while carrying out the safety audit.1) Building and Structuresi) Location and lay-out
ii) Conforming to standards
iii) Stability certificateiv) Escape routes and exitsv) Fire-proof constructionvi) Lighting arrestor
-
8/3/2019 Safety Audit Ppt Representation (2)
35/58
2) Operational Safety and Procedures
i) Availability and compliance of operating andsafety manualsii) Control of operating parametersiii) Start-up and shut-down procedures
iv) Venting / Scrubbing systemsv) Running of emergency equipmentduring power failurevi) Cleaning and tank entry procedures
vii) Work permit systemsviii) Precautions against endothermic /exothermic run-away reactions
-
8/3/2019 Safety Audit Ppt Representation (2)
36/58
3) Chemical Process Safetyi) Plant lay out
- Separation and isolation, - Drainage,- Enclosed spacesii) Material compatibilityiii) Contamination control
iv) Physical facilitiesv) Inspection and maintenancevi) General containment and controlsvii) Instrumentation
viii) Piping systemsix) Protective systems ( not quality control)x) Electrical equipmentxi) Pressure vessels
ii) P d
-
8/3/2019 Safety Audit Ppt Representation (2)
37/58
xii) Pumps and compressorsxiii) Reactionsxiv) Venting
xv) Interlock devices for critical operationsand equipmentsxvi) Over-pressure: relief devicesxvii) Continuous operation of neutralizationsystem and connecting it with diesel generating setin case of power failurexviii) Connecting critical equipment with dieselgenerating set in case of total power failurexix) Alarm warning system in case of emergency
xx) Indication and alarm system for processparameters controlxxi) Installation of fail-safe instruments
-
8/3/2019 Safety Audit Ppt Representation (2)
38/58
4 Handling and Storage of Chemicalsi) Site selection
-Storage area away from buildings or
structures , - Distances as per the statutory
regulations , - Well ventilated area , - Easy
access from the control room
ii) Alarm and indications
- High level alarm , - High pressure & high
temperature alarms , - Isolation of the tank ,-Remote control valve
iii) Fencing
iv) Distance between two tank
-
8/3/2019 Safety Audit Ppt Representation (2)
39/58
v) Dyke walls with drainage systemvi) Display of caution notice
vii) Support for above ground tanksviii) Ventingix) Valvesx) Level measurementxi) Pumpsxii) Sources of ignitionxiii) Lighting
xiv) Marking of tanks , connections andfittingsxv) Gas leakages and control
-
8/3/2019 Safety Audit Ppt Representation (2)
40/58
xvi) Safety valves discharge connection tothe neutralization system / flarexvii) Flame proof fittingsxviii) Electrical grounding of the vesselsand pipe linesxix) Diesel generating set connected to the
emergency power supplyxx) Minimizing of inventoryxxi) Storage of chemicals under lowpressure
xxii) House keepingxxiii) Fire fighting arrangement andprovision of static water
-
8/3/2019 Safety Audit Ppt Representation (2)
41/58
xxiv) Extension of liquid inlet line to avoid static
charge
xxv) Personal protective equipments
xxvi) Hydraulic testing and inspection of
pipelines
xxvii) Material safety data sheetxxviii) Trem (Transit Emergency ) card
xxix) Emergency information panel
xxx) Labeling of packaging material
xxxi) Loading and unloading procedurexxxii) Transport emergency preparedness
xxxiii) Emergency kit / fire fighting equipment
-
8/3/2019 Safety Audit Ppt Representation (2)
42/58
(5) Fire and Explosion hazards
1 Fire prevention- No smoking restricted area-Periodic checking & continuity of ear thing-Prevention of spillages
-Accumulation of waste and combustible inprocess areas-Water sprinklers-Fire alarms-Lightning arrestor-Flame proof fittings-Flame arrestor-Static charge
-Fire exits
-
8/3/2019 Safety Audit Ppt Representation (2)
43/58
2- Fire Protection-Location and capacity of fire hydrant pump-Booster pump and standby pump
-Hydrant pump starting system and procedure-Static water quantityLayout of linesSpace between the hydrantsWater jet monitorsHydrant boxesFoam requirement
3- Fire extinguishers :
Testing and certification by competent authorities
Fire siren systemFire fighting team
Fire fighting training
Mutual aid scheme
-
8/3/2019 Safety Audit Ppt Representation (2)
44/58
(6) Material Handling
i) Manual handling :
Procedures-Handling aids-Condition of material handling areas
ii) Lifting machinery and tackles :
-Selection-Design criteria-Inspection and testing-Compliance with standards
-Periodic checking and maintenance-Storages-Safe working load, identification, markings etc.-Slinging practices
-
8/3/2019 Safety Audit Ppt Representation (2)
45/58
iii) Material Handling procedures :
-Stacking and restacking procedures :-Compliance with standards-Load bearing capacity
-Stacking stability-Safe handling procedure for chemicals andexplosives-Storage facilities ( adequacy & suitability )
including pallets-Clearance and passages-Provision of aisles
-
8/3/2019 Safety Audit Ppt Representation (2)
46/58
7) Machine Guardingi) Types of guards
ii) Guarding materialsiii) Maintenance of guardsiv) Periodic inspection
8) Pumps and Compressorsi) Pressure design of casing
ii) Rating of in stream pipingiii) Check valves / Control valvesiv) Suction piping and over pressurev) Isolation valvevi) Speed control
vii) Design temperature controlviii) Leakagesix) Lubricationx) Reverse flow / rotationxi) Vibration / Alignment
-
8/3/2019 Safety Audit Ppt Representation (2)
47/58
9) Inspection & Testing of Pressure Vessels
i) Schedule and inspection and testingii) Testing and inspection reportsiii) Compliance with standardsiv) Inspection and testing of pressure relief valves andrupture discs
10 Personal Protective Equipments
- Selection and suitabilityi) Proper useii) Display
iii) Inspection and testingiv) Maintenancev) Proper storage
-
8/3/2019 Safety Audit Ppt Representation (2)
48/58
11) Electrical Hazards
i) Area classification
ii) Selection and use of electrical appliances
iii) Overload and short-circuit devices
iv) Power isolation procedures
v) Electrical fire-fighting devices
vi) Flame proof fittings
vii) Lightning arrestorviii) Ear thing / Earth leakage circuit breaker
ix) Lock out and tagging procedures
-
8/3/2019 Safety Audit Ppt Representation (2)
49/58
12) Instrumentation
i) Provision and suitability of instrument in
process / equipmentii) Instrument calibration proceduresiii) Tripping devices for control of processparameters
iv) Fail-safe instrumentation proceduresv) Periodic maintenance proceduresvi) Testing and inspection proceduresvii) Checking against response time
viii) Effects of humidity and temperature oninstrumentsix) Back-up proceduresx) Checking of air ( quality, pressure, etc )
-
8/3/2019 Safety Audit Ppt Representation (2)
50/58
13) Preventive Maintenance
i) Schedule
ii) Maintenance checklist / reportsiii) Equipment change-over schedule
iv) Review of equipment failures
14) Pollution Systemi) Effluent treatment plant
ii) Air pollution control and monitoring
iii) Hazardous wastes disposal
iv) Noise pollution
-
8/3/2019 Safety Audit Ppt Representation (2)
51/58
15) Emergency Preparedness
i) Organization
ii) Emergency planningiii) Emergency control centeriv) Escape routesv) Assembly pointsvi) Evacuation proceduresvii) Communication within the plantviii) Identification of hazardous areasix) Key personnelx) Emergency response equipments
xi) First aid and medical facilityxii) Communication ( authorities and public )xiii) Dispersion modelsxiv) Training and drills
-
8/3/2019 Safety Audit Ppt Representation (2)
52/58
16) Boilers / Furnaces
i) Compliance with statutory requirements
ii) Feed water piping
iii) Steam outlet piping
iv) Quality of waterv) Drum water level
vi) Maintenance of instrument
vii) Gas burner control
viii) Interlocks
-
8/3/2019 Safety Audit Ppt Representation (2)
53/58
viii) Interlocksix) Shut-off valvesx) Dampers
xi) Low pressure, high pressure alarmsxii) Pressure and vacuum relief valvesxiii) Flame arrestor on discharge of relief valvesxiv) Stack height
xv) Emergency relief devicexvi) Monitoring of stack emissionxvii) Economizer and super heaterxviii) Access to control valvesxix) Inspection of furnace liningxx) Explosion hazardsxxi) Fuel controlxxii) Insulationsxxiii) Measurement of heat stress
17) H d T l d P t bl P T l
-
8/3/2019 Safety Audit Ppt Representation (2)
54/58
17) Hand Tools and Portable Power Tools
i) Selection
ii) Maintenance
iii) Quality
iv) Storage
v) Guarding
vi) Ear thing of portable power tools
18) Lighting / illumination
i) Type of lighting
ii) Illumination levelsiii) Compliance with standards
iv) Ratio of contrast
v) Glare
vi) Maintenance of fixtures and fittings
19) H k i
-
8/3/2019 Safety Audit Ppt Representation (2)
55/58
19) House-keeping
i) Floor surface
ii) Cleanliness and tidinessiii) Disposal binsiv) Fencing of dangerous spots andditches
v) Covering of trenches and pitsvi) Steps, ladders, staircases, ramps,walkwaysvii) Passages
viii) Drainageix) Work platformsx) Left over materialsxi) Stacking
-
8/3/2019 Safety Audit Ppt Representation (2)
56/58
IMPORTANT ASPECT FOR ACCIDENT
PREVENTATION
TO
PREVENT
ACCIDENT
HAZARD IDENTIFICATION
-HAZOP
-HAZAN-FAULT TREE ANALYSIS
-EVENT TREE ANALYSIS
-DOW INDEX
-SAFETY AUDIT
-SAFETY INSPECTION
WORK PERMIT SYSTEM-MECH. MAINTENANCE PERMIT
-ELEC. MAINTENANCE PERMIT
-HOT WORK PERMIT
-COLD WORK PERMIT
-VESSEL ENTRY PERMIT
-WORK AT HEIGHT PERMIT
-ESCAVATION PERMIT
-E.T.C. PERMIT
JOB SAFETY ANALYSIS
I
SAFE OPERATING PRACTICE
I
TRAINING
-
8/3/2019 Safety Audit Ppt Representation (2)
57/58
170 How is the medical emergency communication with localbodies and other organizations ensured ? Give details.
171 Is any alternate power source identified ? Give details.172 What is the medical emergency response system ? Give
details.
173 Are you a member of any MUTUAL-AID-SCHEME of yourarea ? If so give details.
174 How many emergency alarm system (s) is / are available ?Give details.
22) PLANT LAYOUT AND AREACLASSIFICATION
175 What is the system of classification of hazardous zones in the plant for
electrical installations ? Please specify.176 Whether periodic inspection and preventive maintenance of electrical
installations is done by a qualified person and record is maintained ?
177 Whether plant layout with area classification has been displayed atappropriate place (s) ?
-
8/3/2019 Safety Audit Ppt Representation (2)
58/58
THANKS