SAFE-Web Project Status Update for Peralta Community College District March 18, 2010

27
Andrew Nassir Sherri Sanchez Nancy Kelleher

description

SAFE-Web Project Status Update for Peralta Community College District March 18, 2010. Andrew Nassir Sherri Sanchez Nancy Kelleher. Agenda. Restating Peralta Needs Additional Requirements Deliverables General Features and Functionality Product Licenses Services Contract Term - PowerPoint PPT Presentation

Transcript of SAFE-Web Project Status Update for Peralta Community College District March 18, 2010

Page 1: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Andrew Nassir Sherri SanchezNancy Kelleher

Page 2: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Agenda1. Restating Peralta Needs2. Additional Requirements3. Deliverables

General Features and Functionality Product Licenses Services

4. Contract Term 5. Mainframe Safe Deliverables6. Project Breakout

Work Group 1 – Setup Work Group 2 – Student Information Work Group 3 – Processing Setup Work Group 4 – Student Processing Work Group 5 – Batch Processing

7. Project Schedule8. Finishing Up

Page 3: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Restating Peralta’s Needs Desires to have ESI SAFE application moved off mainframe

due to cost considerations It is the only production application currently running on

Peralta mainframe Doesn’t want to rush migration due to previous “bad”

experience Use Peralta data warehouse as an intermediary data

repository for integrated PeopleSoft/SAFE data So that users don’t access production system for

query/reporting requests IT has strong preference that new code not be maintained

in COBOL Prefers that any future Peralta customization/integration work

be done in more “modern” programming language Pre-production/testing will be hosted by ESI remotely

Page 4: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Restating Peralta Needs, con’t Desires to continue printing checks from the custom

PCCD check writing module Requires 7 years of current PCCD SAFE award and

payment history data for record retention/access (within SAFE system, not data mart)

Page 5: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Additional Requirements Wants additional features/functionality (per fit/gap analysis)

and updated web interface implemented with initial conversion/migration effort (not in later phase)

Letter creation/printing, user interface design and other features could affect project costs and warranty – and result in schedule slippages

Page 6: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Deliverables General Features and Functionality

Retain most current EMAS SAFE - mainframe functionality in EMAS SAFE - Web

Store all ISIRs for a given student (currently we only store only one)

Enhance ability to send emails from system Convert and migrate SAFE award and payment history

data Custom software programming for bi-directional

PeopleSoft data bridge with SAFE - Web (via datamart) Integration to the current custom check writing module

(does not include conversion of PCCD programs)

Page 7: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Deliverables, con’t Product Licenses

EMAS Financial Aid Pro (SAFE Web-based) Usage License (2010-11) For all PCCD colleges for use by staff and students Peralta is to start 2010-11 FA award year processing with existing

EMAS SAFE (mainframe-based) 2010-2011 award year version. Implementation of 2010-2011 award year EMAS SAFE (web-based) will start on a mutual agreeable date based on project completion.

EMAS Financial Aid Pro (SAFE Web-based) Usage License (2011-12) ESI will continue to provide support and maintenance

services for the mainframe version to Peralta without additional charge until the software is successfully installed and integrated and capable of being used in production.

Page 8: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Deliverables, con’t Services

ESI EMAS SAFE Managed Services Tier 1: Issue response within 2 hours during normal ESI

business hours ESI EMAS Data Services

Services during normal ESI business hours

Import load of PCCD colleges Federal ISIRs and monitor PeopleSoft import/export operation

Support operation of scheduled PCCD auto-award packaging, and management data reporting

Page 9: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Contract Term

Effective Date Sept 30, 2009 – Sept 29, 2012 (initial

term) Note: contract was signed on November 4,

2009 Services purchased for FA Award Years

2010-11 and 2011-12

Page 10: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Mainframe SAFE Deliverables

FA Year 09-10 (Jan 09 – Oct 1, 2010) Already paid (Nov 09, 2009 – late due to move from Regents) Maintenance and Support Work until Sept ‘10 FISAP – deliverable July/August ’10

FA Year 10-11 (Jan 10 – Oct 1, 2011) Payment for SAFE-Web includes mainframe with turnoff sometime

2011) Initial release planned for mid to late Feb, 2010 COD Reporting – Apr - June 2010 On-going maintenance (turn off TBD)

FA 09-11 Anticipated Changes FAFSA Changes Year Round Pell – additional terms of Pell in award year start Summer

09-10 Direct Loans – new again to Peralta (already at Merritt)

Mandates on District(?) Using FA to increase completion rates (Retention Pro?) Cal Grant future (no funds?)

Page 11: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Project Breakout

Page 12: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 1 – Setup

Setup data will be input by PCCD FAOs, ESI Managed/Data Services or PCCD IT Staff. Another possibility may be to extract existing settings/setup from the current mainframe segments if/when appropriate.

Page 13: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 2–Student Information

Student data is supplied by the Department of Education in the form of an ISIR record and is loaded into the system or can be manually entered by FAO’s for students not completing the Free Application for Federal Student Aid (FAFSA)

Page 14: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 2 – Student Information, con’t

Processing can commence. Student data entries can be corrected if errors are present FAOs make the corrections and system functions are used to create the correction file to be sent to the Department of Education

Page 15: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 3 – Student Processing Setup

Setup is completed by FAO, ES Account mgr, PCCD IT, or if appropriate mainframe parameters exported/imported for other student processing functionality to allow for continued student processing for a student or group of students

Page 16: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 3 – Student Processing Setup, con’t

Setup is completed by FAO, ES Account mgr, PCCD IT, or if appropriate mainframe parameters exported/imported for other student processing functionality to allow for continued student processing for a student or group of students

Page 17: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 4 - Student Processing

FAOs verify student information as correct and correct data if incorrect, document requests are made for institution required documents as well as verification required documents. FAOs make the corrections, request the documents be printed/emailed (new) and send the correspondence to students. System functions are used to create the correspondence (as with correction files) and receipt of documents is monitored by FAOs. System updates are made upon receipt of documents (tracking)

Page 18: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 4 – Student Processing, con’t

Continue with other student processing once the correction, verification, and tracking process is completed for a student or group of students. FAOs can complete the functionality on demand or schedule/request batch jobs to be run in off hours. These scheduled jobs use system settings and student information to initiate the process.

Page 19: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 4 - Student Processing, con’t

Continue with other student processing once the correction, verification, and tracking process is completed for a student or group of students. FAOs would perform these tasks or request/schedule the jobs to be run at off times.

Page 20: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 5 – Batch Processing(in Mainframe)

Continue with other student processing once awards are packaged and payments are being made. FAOs or ES Account Manager would request/schedule these jobs to run at an off time (e.g. overnight for example) or run the process on demand. Changes will need to be made to the ISIR load process to provide for storage of all student ISIR transactions and to allow the FAO’s functionality to change the active ISIR in the database.

Page 21: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 5 –Batch Processing(in Mainframe)

Continue with other student processing once awards are packaged and payments are being made. FAOs or ES Account Manager would request/schedule these jobs to run at an off time (e.g. overnight for example) or run the process on demand. Changes will need to be made to the ISIR load process to provide for storage of all student ISIR transactions and to allow the FAO’s functionality to change the active ISIR in the database.

Page 22: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 5 – Batch Processing(in Mainframe)

FAOs or ES Account Manager would request/schedule these jobs to be run in off hours or will be able to process the data on demand.

Page 23: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 5 - Batch Processing(in Mainframe)

Common Origination and Disbursement (COD) system reporting. FAOs or ES Account Manager would request/schedule these jobs to be run in off hours or will be able to process the data on demand.

Page 24: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Workgroup 5 – Batch Processing in Mainframe, con’t

FAOs or ES Account Manager would request/schedule these jobs to be run in off hours or will be able to process the data on demand.

Page 25: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Project ScheduleMilestone DateProject Kick-Off San Diego, Nov 13

Project Status Update Met in Oakland - February 5, 2010

Conversion Methodology/Tool Selection/Resource Staffing

Started - March 5, 2010

Goal to Complete – April 16, 2010

Peralta/ESI Weekly Team Meetings (ongoing) Started - March 11, 2010

Fit/Gap Analysis – Features/functionality Peralta would like to add to requirements

Goal to complete – March 31, 2010

Email Module Requirements Finalized TBD (with Peralta input)

Check Writing Module Requirements Finalized TBD (with Peralta input)

PeopleSoft Integration (Data Mart) Requirements Finalized

TBD (with Peralta input)

WorkGroup 1 – Requirements Definition TBD after Tool/Methodology Chosen

WorkGroup 2 – Requirements Definition TBD after Tool/Methodology Chosen

WorkGroup 3 – Requirements Definition TBD after Tool/Methodology Chosen

Page 26: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Project Schedule, con’tMilestone DateWorkGroup 4 – Requirements Definition TBD after Tool/Methodology Chosen

WorkGroup 5 – Requirements Definition TBD after Tool/Methodology Chosen

WorkGroup 1 - for Peralta Testing TBD after Tool/Methodology Chosen

WorkGroup 2 - for Peralta Testing TBD after Tool/Methodology Chosen

WorkGroup 3 – for Peralta Testing TBD after Tool/Methodology Chosen

WorkGroup 4 – for Peralta Testing TBD after Tool/Methodology Chosen

WorkGroup 5 – for Peralta Testing TBD after Tool/Methodology Chosen

Data Migration TBD after Tool/Methodology Chosen

Training TBD after Tool/Methodology Chosen

Page 27: SAFE-Web Project Status Update for Peralta Community College District  March 18, 2010

Finishing Up Takeaways

Action items