SACRED HEART CATHOLIC PARISH AND SCHOOL Heart Parish...• Replace door hardware at all rooms doors...

1
SACRED HEART CATHOLIC PARISH AND SCHOOL CHURCH INTERIOR Interior Walls & Ceiling Nave: Repair wall at North entry that has undergone significant water damage. Locate and repair the source of the water damage prior to completing the repair of the interior wall. - $1,075 Restroom: Repair East wall that has undergone significant water damage. Locate and repair the source of the water damage prior to completing the repair of the interior wall. - $26913. Doors & Hardware Replace door hardware at all rooms doors with ADA complaint hardware except where there is existing panic hardware or levers. (ADA requirement for public use) - $13,659 Mechanical  / Plumbing Replace all furnace and split system equipment. The equipment is well beyond life expectancy. - $184,575 Introduce outside ventilation air through the HVAC system to all spaces in order to meet building code requirements.Included above Provide adequate combustion air to the large gas fired twinned furnaces in the basement in order to meet building code requirements.Included above Replace old gas fired equipment. At a minimum, examine the heat exchangers for leakage prior to the heating season. - $738 CHURCH TOTAL$200,316 SCHOOL EXTERIOR Exterior Envelope Tuckpoint brick mortar joints to prevent additional moisture damage. Re‐grout and seal around scupper openings. - $78,260 Replace all windows. - $110,745 SCHOOL INTERIOR Vertical Circulation Add ADA and IBC compliant handrails on both sides of the main stair. (ADA requirement for public use) - $2,240 Remove the double‐doors at the bottom of the main stair. The stair is required to have a bottom landing, which is in conflict with the double‐doors. Provide a bottom landing that is compliant with ADA and IBC. - $81,316 . Doors & Hardware Replace door hardware at all rooms doors with ADA complaint hardware except where there is existing panic hardware or levers. (ADA requirement for public use) - $33,224 . Mechanical  / Plumbing Provide adequate combustion air in the basement to meet building code requirements. - $6,153 Replace and insulate steam piping from boiler to radiators. - $61,525 . Electrical Replace the main floor panel because it utilizes screw in fuses and cloth insulation on the branch circuits. - $3,692 Upgrade all receptacles in the restrooms to GFCI. - $738 Update exit and emergency lighting to meet building code requirements. - $1,384 Upgrade fire alarm system to a new addressable, ADA compliant system. - $19,613 SCHOOL TOTAL$318,386 PARISH HALL EXTERIOR Exterior Envelope Remove and replace existing roof system. - $116,622 Refinish or replace the metal paneling above the gymnasium to avoid additional deterioration. - $5,537 PARISH HALL INTERIOR Doors & Hardware Replace door hardware at required egress doors with ADA complaint hardware except where there is existing panic hardware or levers. (ADA requirement for public use) - $20,000 Mechanical  / Plumbing Replace all furnace and split system equipment. The equipment is well beyond life expectancy. - $116,898 Introduce outside ventilation air through the HVAC system to all spaces in order to meet building code requirements. Included Above Upgrade or replace the mechanical room furnaces that will have adequate combustion air to meet building code requirements. - $86,135 Replace old gas fired equipment. At a minimum, examine the heat exchangers for leakage prior to the - $738 PARISH HALL TOTAL$345,930 RECTORY INTERIOR Mechanical  / Plumbing Provide adequate combustion air for fuel fired appliances.$123 Extend the combustion air intake up through the roof. Relocate the furnace vent through the roof in lieu of its current termination point just outside the back‐door porch.$923 RECTORY TOTAL$1,046 TOTAL OF ALL PHASE ONE PROJECTS $865,678 Potential Improvements and Projected Costs

Transcript of SACRED HEART CATHOLIC PARISH AND SCHOOL Heart Parish...• Replace door hardware at all rooms doors...

Page 1: SACRED HEART CATHOLIC PARISH AND SCHOOL Heart Parish...• Replace door hardware at all rooms doors with ADA complaint hardware except where there is existing panic hardware or levers.

SACRED HEART CATHOLIC PARISH AND SCHOOL

CHURCH INTERIOR  Interior Walls & Ceiling

•Nave: Repair wall at North entry that has undergone significant water damage. Locate and repair the source of the water damage prior to completing the repair of the interior wall. - $1,075•Restroom: Repair East wall that has undergone significant water damage. Locate and repair the source of the water damage prior to completing the repair of the interior wall. - $26913. 

Doors & Hardware•Replace door hardware at all rooms doors with ADA complaint hardware except where there is existing panic hardware or levers. (ADA requirement for public use) - $13,659

Mechanical  / Plumbing•Replace all furnace and split system equipment. The equipment is well beyond life expectancy. - $184,575•Introduce outside ventilation air through the HVAC system to all spaces in order to meet building code requirements.Included above •Provide adequate combustion air to the large gas fired twinned furnaces in the basement in order to meet building code requirements.Included above•Replace old gas fired equipment. At a minimum, examine the heat exchangers for leakage prior to the heating season. - $738

CHURCH TOTAL$200,316

SCHOOL EXTERIOR Exterior Envelope

•Tuckpoint brick mortar joints to prevent additional moisture damage. Re‐grout and seal around scupper openings. - $78,260•Replace all windows. - $110,745

SCHOOL INTERIOR Vertical Circulation

•Add ADA and IBC compliant handrails on both sides of the main stair. (ADA requirement for public use) - $2,240•Remove the double‐doors at the bottom of the main stair. The stair is required to have a bottom landing, which is in conflict with the double‐doors. Provide a bottom landing that is  compliant with ADA and IBC. - $81,316.

Doors & Hardware•Replace door hardware at all rooms doors with ADA complaint hardware except where there is existing panic hardware or levers. (ADA requirement for public use) - $33,224.

Mechanical  / Plumbing•Provide adequate combustion air in the basement to meet building code requirements. - $6,153•Replace and insulate steam piping from boiler to radiators. - $61,525.

Electrical •Replace the main floor panel because it utilizes screw in fuses and cloth insulation on the branch circuits. - $3,692•Upgrade all receptacles in the restrooms to GFCI. - $738•Update exit and emergency lighting to meet building code requirements. - $1,384•Upgrade fire alarm system to a new addressable, ADA compliant system. - $19,613

SCHOOL TOTAL$318,386

PARISH HALL EXTERIOR Exterior Envelope

•Remove and replace existing roof system. - $116,622•Refinish or replace the metal paneling above the gymnasium to avoid additional deterioration. - $5,537

PARISH HALL INTERIOR Doors & Hardware

•Replace door hardware at required egress doors with ADA complaint hardware except where there is existing panic hardware or levers. (ADA requirement for public use) - $20,000 Mechanical  / Plumbing

•Replace all furnace and split system equipment. The equipment is well beyond life expectancy. - $116,898•Introduce outside ventilation air through the HVAC system to all spaces in order to meet building code requirements. Included Above•Upgrade or replace the mechanical room furnaces that will have adequate combustion air to meet building code requirements. - $86,135•Replace old gas fired equipment. At a minimum, examine the heat exchangers for leakage prior to the  - $738

PARISH HALL TOTAL$345,930

RECTORY INTERIOR Mechanical  / Plumbing

•Provide adequate combustion air for fuel fired appliances.$123•Extend the combustion air intake up through the roof. Relocate the furnace vent through the roof in lieu of its current termination point just outside the back‐door porch.$923

RECTORY TOTAL$1,046

TOTAL OF ALL PHASE ONE PROJECTS $865,678