FORM # G-007 (8/8/22) SHT 1 of 1 SAUDI ARAMCO PRE-COMMISSIONING FORM SUBMERSIBLE PUMPS EQUIPMENT TYPE: USER REFERENCE: EQUIPMENT TAG NO.: DESCRIPTION: BI/JO NO.: PLANT NO. / LOCATION: REF. DRAWINGS & DOCUMENTS: MANUFACTURER: MODEL NO.: SERIAL NO.: COMMISSIONING DATE: 1 PUMPS CHECKED PER DATA SHEET_______ YES____NO____ 2 NAME PLATE DATA CHECKED. YES____NO____ 3 PUMP UNDAMAGED YES____NO____ 4 POSITION & MOUNTING CHECKED PER _____ YES____NO____ 5 CAISSONS INSTALLATION CHECKED PER_____ YES____NO____N/A____ 6 PUMP LEVEL CHECKED YES____NO____ 7 SEAL SYSTEM COMPLETED YES____NO____ 8 SUCTION STRAINER FITTED YES____NO____ 9 MOTOR WINDINGS MEGGER CHECKED YES____NO____ 10 CABLE MEGGER CHECKED YES____NO____ 11 ACCESS TO DISCHARGE VALVE CHECKED YES____NO____ 12 INSTRUMENTATION SYSTEM VERIFIED YES____NO____ 13 ELECTRICAL SYSTEM VERIFIED YES____NO____ 14 VENDOR'S RECOMMENDATIONS FOLLOWED YES____NO____ NOTE: This non-mandatory form may be used as the starting point to assemble a pre-commissioning checklist. Entries should be revised, added and deleted and approvals adjusted to reflect the needs of the Project Acceptance Committee. APPROVALS SAPMT INSPECTION OTHER DEPT. OPERATIONS Signature & Date Copyright©Saudi Aramco 2009. All rights reserved.

description

precom

Transcript of SA-G-007

SUBMESIBLE PUMPS

FORM # G-007 (5/09)SHT 1 of 1SAUDI ARAMCO PRE-COMMISSIONING FORMSUBMERSIBLE PUMPS

EQUIPMENT TYPE:USER REFERENCE:

EQUIPMENT TAG NO.:DESCRIPTION:

BI/JO NO.:PLANT NO. / LOCATION:

REF. DRAWINGS & DOCUMENTS:

MANUFACTURER:

MODEL NO.:SERIAL NO.:

COMMISSIONING DATE:

1PUMPS CHECKED PER DATA SHEET_______YES____NO____ 2NAME PLATE DATA CHECKED.YES____NO____ 3PUMP UNDAMAGEDYES____NO____ 4POSITION & MOUNTING CHECKED PER _____YES____NO____ 5CAISSONS INSTALLATION CHECKED PER_____ YES____NO____N/A____6PUMP LEVEL CHECKEDYES____NO____ 7SEAL SYSTEM COMPLETEDYES____NO____ 8SUCTION STRAINER FITTEDYES____NO____ 9MOTOR WINDINGS MEGGER CHECKEDYES____NO____ 10CABLE MEGGER CHECKEDYES____NO____ 11ACCESS TO DISCHARGE VALVE CHECKEDYES____NO____ 12INSTRUMENTATION SYSTEM VERIFIEDYES____NO____ 13ELECTRICAL SYSTEM VERIFIEDYES____NO____ 14VENDOR'S RECOMMENDATIONS FOLLOWEDYES____NO____

NOTE: This non-mandatory form may be used as the starting point to assemble a pre-commissioning checklist. Entries should be revised, added and deleted and approvals adjusted to reflect the needs of the Project Acceptance Committee.APPROVALSSAPMTINSPECTIONOTHER DEPT.OPERATIONS

Signature & Date