S2 DRL B2CDE1 EMITS - emits.sso.esa.intemits.sso.esa.int/emits-doc/S2_DRL_B2CDE1_EMITS.pdf · P....
Transcript of S2 DRL B2CDE1 EMITS - emits.sso.esa.intemits.sso.esa.int/emits-doc/S2_DRL_B2CDE1_EMITS.pdf · P....
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 1 of 42
GMES Sentinel-2
document title/ titre du document
ENTINEL
HASE
OCUMENTS EQUIREMENTS IST
prepared by/préparé par Sentinel-2 Team reference/réference S2-RS-ESA-SY-0002 issue/édition 3 revision/révision 0 date of issue/date d’édition 13/02/2007 status/état Document type/type de document Requirements Specification Distribution/distribution (See page 5)
GMES Sentinel-2
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 2 of 42
GMES Sentinel-2
A P P R O V A L
Title titre
Documents Requirements List issue issue
3 revision revision
Draft
author auteur
Sentinel-2 Team date date
02/01/2007
checked by verifié par
Sentinel-2 Team date date
approved by approuvé par
Francois Spoto (EOP-PU)
date date
13/02/2007
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 3 of 42
GMES Sentinel-2
C H A N G E L O G
reason for change /raison du changement issue/issue revision/revision date/date
S2 Phase B2/C/D/E1 ITT version for EMITS 3 0 13-02-2007
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 4 of 42
GMES Sentinel-2
C H A N G E R E C O R D
Issue: 3 Revision: 0
reason for change/raison du changement page(s)/page(s) paragraph(s)/paragraph(s)
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 5 of 42
GMES Sentinel-2
D I S T R I B U T I O N
ESTEC & ESRIN/EOP ESTEC & HQ/RES Industry V. Liebig D-EOP G. Stjernevi PIO S. Briggs S C. Bayle PIO G. Kohlhammer G E. Pittarelli PC R. Zobl P A. Stader PAN P. Edwards PZ E. Montanari PA F. Spoto PU O. Sy PUS ESTEC /TEC P. Martimort PUM A. Tobias S U. del Bello PUM J. Bosma Q V. Fernandez PUM P. Perol E B. Berruti PV P. Armbruster ED G. Levrini PZ Y. Bordes EDD J. Butu PM D. Temperanza ECC T. Siwitza PM S. Dolce MCT S. Carlier PTQ F. Gascon EEP P. Viau PE L. Winzer QQS R. Meynart PI M. Martinez Fernandez ETC P.L. Silvestrin SF G. Migliorero MMM J. Aschbacher E C. Taylor EDS E. Forcada GS H. Joumier SYC B. Greco GP P. de Maagt EEA O. Arino SEP I. Zayer MME M. Doherty SE R. Vitulli EDP M. Berger SML V. Kirchner MMO A. Ciccolella E K. Buechler PZ H.L. Moeller GP HQ/LAU G. Labruyere PAE L. Bourillet ER S. Delwart PEL G. Ulbrich PIO ESTEC/SCI P. Goryl GQ J. Louet P G.M. Pinna GF L. di Napoli PTA A. Castro GS ESOC/OPS PP. Emanuelli OE P. Bargellini OEA
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 6 of 42
GMES Sentinel-2
T A B L E O F C O N T E N T S
1 INTRODUCTION .................................................................................................................. 7
2 REQUIREMENTS................................................................................................................. 8
2.1 Documents format .................................................................................................................................................... 8
2.2 Sentinel-2 documentation completeness.................................................................................................................. 9
2.3 Sentinel-2 restricted information............................................................................................................................. 9
2.4 Sentinel-2 documents deliveries and classification................................................................................................. 9
3 SENTINEL-2 PROJECT MANAGEMENT.......................................................................... 11
4 SENTINEL-2 SYSTEM ENGINEERING............................................................................. 16
5 SENTINEL-2 SATELLITE ASUMPTIONS FOR THE GROUND SEGMENT ..................... 21
6 SENTINEL-2 SATELLITE ENGINEERING ........................................................................ 22
7 SENTINEL-2 INTERNAL AND EXTERNAL INTERFACES............................................... 26
8 SENTINEL-2 SUPPORT SPECIFICATIONS ..................................................................... 28
9 SENTINEL-2 SATELLITE DRAWINGS ............................................................................. 30
10 SENTINEL-2 MULTISPECTRAL INSTRUMENT ............................................................... 31
11 SENTINEL-2 FIRE INSTRUMENT ..................................................................................... 35
12 SENTINEL-2 AIT................................................................................................................ 36
13 SENTINEL-2 PRODUCT ASSURANCE ............................................................................ 39
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 7 of 42
GMES Sentinel-2
1 INTRODUCTION This Documentation Requirement List forms part of the Sentinel-2 Statement Of Work “S2-SW-ESA-SY-0001” (it constitutes its Appendix B) and specifies a minimal list of Satellite level or key lower level documents to be delivered to the Agency during the Sentinel-2 Phase-B2/C/D/E1. The following information is provided for each document:
• A document mnemonic that can be called upon within other documents, such as in the SoW corpus.
• The Document category as defined in the GMES Sentinel-2 Management Requirements (S2-RS-ESA-SY-0007):
o A: To be formally approved by the Agency as a strict condition to authorise the Contractor work associated to this document.
o R: To be reviewed by the Agency. The Agency requests to review these documents such as feedback can be provided to the Contractor to update these documents prior to execute the tasks driven by this document.
• The Document title • The Document delivery/re-deliveries Project milestones • Some remarks relevant to specific documents, as relevant
The content for each DRL document is specified within the “GMES Sentinel-2 Phase B2/CD/E1 Documents Requirements Description” (S2-RS-ESA-SY-0003).
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 8 of 42
GMES Sentinel-2
2 REQUIREMENTS
2.1 Documents format All DRL documents shall be delivered to the Agency in electronically generated and native searchable PDF format (scanned pages only accepted for hand written documents, e.g. minutes of meetings, and in specific cases where no original electronic version of the document is available, like in the case of very old documentation). Furthermore, PDF documents must have their Table Of Content (TOC), where present, available as PDF bookmarks. On Agency’s request (e.g. when portion of documentation needs to be imported in Customer's documentation), the Contractor shall also deliver the native word/excel version of the documents, even though it is understood that the only contractually binding document will remain the pdf version. All drawings shall be generally provided in A3 PDF format, with additional A0 format for very large drawings (e.g. grounding diagrams, command and control synoptics, etc...). In addition, one paper copy shall also be delivered for all drawings. Where mentioned in the DRL, on-line access to real time up-to-date electronic data base or spreadsheet is additionally required (e.g. for NCR’s). The Agency will inform the Contractor at the Phase B2 KO about the address/location to be used for the delivery of all electronic and paper documentation. In case of reviews, the Contractor shall deliver: • For Satellite reviews, 10 paper copies and 50 sets of CD/DVD • For Instrument reviews, 5 paper copies and 30 sets of CD/DVD • For lower level (S/S, equipment) reviews, 2 paper copies and 10 sets of CD/DVD The Review Data package shall be distributed at least two weeks prior to the Review presentation by the Contractor or Sub-Contractor. Any additional specific delivery request is indicated directly within the DRL.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 9 of 42
GMES Sentinel-2
2.2 Sentinel-2 documentation completeness The current list of documents identified by the Agency and called upon within the Statement Of Work shall be reviewed and completed as necessary by the Contractor before the Satellite PDR, this to ensure:
• That all Sentinel-2 Satellite development activities that pertain to the fulfilment of the Agency baseline requirements are properly documented.
• That the final list of documents to be agreed at Sentinel-2 PDR is consistent with the
Contractor Sentinel-2 Specification and Plan Tree (an update of the Agency DRL will be frozen at Sentinel-2 PDR time).
2.3 Sentinel-2 restricted information For Security related documents, generation and delivery within the Sentinel-2 consortium and to the Agency shall be made in accordance with the ESA Security Regulations Part I and Part II, forming part of the reference documents to the Statement of Work. Several documents or part-of are already identified within this DRL as “restricted”. It may be possible that this requirement for classified information has to be enlarged to other documents not yet identified as such within the current version of the DRL. This extension if necessary to meet the Sentinel-2 security concept shall be part of the Contractor baseline work.
2.4 Sentinel-2 documents deliveries and classification The milestones and document categories used in this DRL are as follows: BID = Sentinel-2 Phase B2/C/D/E1 Proposal Phase B2 K.O. = Sentinel-2 Phase-B2/C/D/E1 Kick-Off PDR = Sentinel-2 Preliminary Design Review Phase C/D/E1 K.O. = Sentinel-2 Phase C/D/E1 Kick-Off CDR = Sentinel-2 Critical Design Review QR = Sentinel-2 Qualification Review FAR = Sentinel-2 Flight Acceptance Review IOCR = Sentinel-2 In orbit Commissioning Review The Contractor shall issue some Sentinel-2 documents identified in the DRL as an output of a configured and controlled Data Base tool. These documents are marked with the symbol “DB” in the
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S1-RS-ESA-SY-0002
page 10 of 42
GMES Sentinel-2
column “Remark”. The Contractor shall grant remote computer access, such as the Agency is able at any time to access up-to-date information between two formal document releases. The DRL structures the Sentinel-2 documents requested for delivery by the Agency along the following eleven families:
• PM: Sentinel-2 Project Management • SY: Sentinel-2 System Engineering (including verification) • GS: Ground Segment • SA: Sentinel-2 Satellite (including platform and payload module functions, all deliverables
specified in the SoW, exception made for the GSE covered under AIT) • IF: Sentinel-2 Satellite Internal and External Interfaces • SS: Sentinel-2 Satellite Engineering Support Specifications • DR: Sentinel-2 Satellite Drawings • MS: Sentinel-2 MultiSpectral Instrument • FI: Sentinel-2 FIRE Instrument (currently limited to its interface definition – see option in
Special Tender conditions) • AV: Sentinel-2 Satellite AIT (including GSE aspects) • PA: Sentinel-2 Product and Quality Assurance
The Contractor shall respond to the DRL ensuring completeness and consistency of his documentation with the families of documents defined above.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 11 of 42
GMES Sentinel-2
3 SENTINEL-2 PROJECT MANAGEMENT
DRD REF.
CAT PROJECT MANAGEMENT
PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1 K.O.
CDR QR FAR IOCR REMARKS
PM-1 A Sentinel-2 Project Management Plan
X X X X X
PM-2 R (Prime)
I (Subco’s
)
Sentinel-2 Progress Report
6 weekly, from B2 K.O. until PDR, 8 weekly afterwards.
PM-3 R Sentinel-2 Project Meetings Plan
DB. 4 weekly, from B2 K.O. onwards.
PM-4 I Sentinel-2 Minutes of Meetings (to which the Customer has right of attendance)
Issued not later than 1 week following the meeting, signed by all attending parties. Written/issued/configured and controlled by the Contractor from B2 K.O. onwards
PM-5 I Sentinel-2 Project Directory
X X X X X X X Updates as required.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 12 of 42
GMES Sentinel-2
DRD REF.
CAT PROJECT MANAGEMENT
PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1 K.O.
CDR QR FAR IOCR REMARKS
PM-6 A
Sentinel-2 Geographical Distribution of the Work
X X X X X
PM-7 I Sentinel-2 Inventory Record
X X X X X
PM-8 R Sentinel-2 Master Schedule Reporting
X X X X X X X DB. 6 weekly after B2 Kick-Off until PDR, 8 weekly afterwards, together with Progress Report, with lower level inputs
PM-9 A (Prime)
R
Sentinel-2 Contract Change Notice
As required along the programme.
PM-10 R Sentinel-2 Change Status List
DB. 6 weekly from B2 K.O. until PDR, 8 weekly afterwards, together with Progress Report. Data Base updated in real time and accessible to ESA.
PM-11 R Sentinel-2 Action Item List
DB. 6 weekly from B2 K.O. until PDR, 8 weekly afterwards, together with Progress Report.
PM-12 R Sentinel-2 Product Tree
X X X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 13 of 42
GMES Sentinel-2
DRD REF.
CAT PROJECT MANAGEMENT
PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1 K.O.
CDR QR FAR IOCR REMARKS
PM-13 A (Prime level)
R
Sentinel-2 Work Breakdown Structure
X X X X Updates as required.
PM-14 A (Prime level)
R
Sentinel-2 Work Package Description
X X X Updates as required
PM-15 I Sentinel-2 Invoicing and Payments Status Report
DB. 6 weekly from B2 K.O. until PDR, 8 weekly afterwards, together with Progress Report
PM-16 A (Prime level)
R
Sentinel-2 Milestone Payment Plan
X X X X X X Updates as required
PM-17 R Sentinel-2 Cost and Manpower Reports
6 weekly from B2 K.O until PDR, 8 weekly afterwards
PM-18 I List of Acronyms and Abbreviations
X X X X X X X
X Updates as required
PM-19 A Sentinel-2 Risk Management Plan
X X X X X X X Updates as required
PM-20 A Sentinel-2 Contract Structure
X X X Updates as required
PM-21 A Sentinel-2 Configuration Control and Documentation Management Plan
X X X X X Updates as required.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 14 of 42
GMES Sentinel-2
DRD REF.
CAT PROJECT MANAGEMENT
PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1 K.O.
CDR QR FAR IOCR REMARKS
PM-22 A (for
DCNs on CatA docts)
Sentinel-2 Document Change Notice
As required
PM-23 A Sentinel-2 Contract Close-out Data Package
X X Draft at FAR.
PM-24 A (Prime level)
R
Request for Waivers (as built)
X X X X As applicable.
PM-25 A (Prime level)
R
Request for Deviations (as designed)
X X X X As applicable.
PM-26 R Sentinel-2 short term schedule reporting
DB. Weekly update for next 3 weeks. Reporting on daily activities
PM-27 R Sentinel-2 Public Relation leaflet
X X X Presentation/content to be mutually agreed with the Agency during phase B2/C.
PM-28 R Sentinel-2 sub-Contractor’s contracts
X Delivered after signature
PM-29 R Sentinel-2 Project Management Requirements Specification
X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 15 of 42
GMES Sentinel-2
DRD REF.
CAT PROJECT MANAGEMENT
PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1 K.O.
CDR QR FAR IOCR REMARKS
PM-30 A Sentinel-2 Project Organization Breakdown Structure
X X X X
PM-31 A Sentinel-2 Industrial Procurement plan
X X X X
PM-32 R Sentinel-2 Document Status List
PM-33 R Sentinel-2 Configuration Item Data List
X X X X X X X X
PM-34 R Sentinel-2 Risks Assessment Plan
X X X
PM-35 R Sentinel-2 Risks Assessment Report
X X X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 16 of 42
GMES Sentinel-2
4 SENTINEL-2 SYSTEM ENGINEERING
DRD REF.
CAT SENTINEL-2 SYSTEM PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SY-1 A Sentinel-2 System Verification Plan
X X X X X X X Covers the full Satellite including its external interfaces. Covers software verification, validation, and as relevant independent verification and validation activities. Covers on ground characterization.
SY-2 R Sentinel-2 System Security Concept and Implementation Document
X X X X Restricted access.
SY-3 A Sentinel-2 System Security Requirements Specification
X X X X X Restricted access.
SY-4 A Sentinel-2 System Security Verification Plan
X X X X X Restricted access.
SY-5 A Sentinel-2 System Specification, Interface Control Document and Plan Tree
X X X X X For the full Sentinel-2 Work Breakdown Structure
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 17 of 42
GMES Sentinel-2
DRD REF.
CAT SENTINEL-2 SYSTEM PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SY-6
R
Sentinel-2 Mission Analysis Report
X X
X
X X X
SY-7 R Sentinel-2 Mission Operations Concept Document
X X X X X
SY-8 R Sentinel-2 LEOP Operations Timeline
X X Draft for CDR
SY-9 A Sentinel-2 In Flight Verification Plan
X X Draft for CDR. Covers in orbit Characterisation and Calibration
SY-10 R Sentinel-2 L0/1a/1b/1c Ground Prototype Processor Design, Development and verification plan
X X X X
SY-11 A Sentinel-2 L0/1a/1b/1c Ground Prototype Processor Requirements Specification
X X X Issued in time for GPP procurement K.O. as part of B2 phase.
SY-12 R Sentinel-2 L1a/1b/1c Ground Prototype Processor Installation, Description and User Manual
X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 18 of 42
GMES Sentinel-2
DRD REF.
CAT SENTINEL-2 SYSTEM PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SY-13 R Sentinel-2 System Performance Simulator Design, Development and Verification Plan
X X X X Includes the MultiSpectral Instrument Level 2 simplified processing functionality.
SY-14 A Sentinel-2 System Performance Simulator Requirements Specification
X X X Issued in time for procurement K.O. as part of B2 phase. Includes the MultiSpectral Instrument Level 2 simplified processing functionality.
SY-15 R Sentinel-2 System Performance Simulator Installation, Description and User Manual
X X X
SY-16 R Sentinel-2 Test data description and delivery plan
X X X X X
SY-17 R Sentinel-2 LEOP and In Orbit Verification report
X Singled out from the overall Sentinel-2 reports in view of its importance for the Mission. Covers in orbit characterization and calibration.
SY-18 R Sentinel-2 Launchers Survey Document
X X X
SY-19 A Sentinel-2 Satellite Reference Data Base Specification
X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 19 of 42
GMES Sentinel-2
DRD REF.
CAT SENTINEL-2 SYSTEM PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SY-20 A Sentinel-2 Satellite Characterisation and Calibration Data Base Specification
X X X X X
SY-21 A (Structure
only)
Sentinel-2 Satellite Flight Operations Manual
X X X X X Structure of the document to be agreed at PDR (reflecting all Satellite elements)
SY-22 R Sentinel-2 Satellite Autonomy and Failure Detection, Isolation and Recovery Concept Document
X X Document will be relayed after concept approval by dedicated specifications and overall Satellite design documentation.
SY-23 R Sentinel-2 GPP Test Scripts Definition and Test Output Files
X X X X
SY-24 R Sentinel-2 Level 0/1a/1b/1c Product Format Definition
X X X X X X To be iterated with the Agency during Phase B2. Consistency required with RD14 of the SoW.
SY-25 R Sentinel-2 End-to-End Mission, Satellite and Payload Performance Budgets Document
X X X X X Based on methodology defined in SY-28.
SY-26 R Sentinel-2 System Cleanliness and Contamination Analysis
X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 20 of 42
GMES Sentinel-2
DRD REF.
CAT SENTINEL-2 SYSTEM PHASE-B2/C/D/E1
BID
B2 K.O.
PDR C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SY-27 R Sentinel-2 Customisation of the Packet Utilisation Standard
X X X X X
SY-28 R Sentinel-2 End-to-End Mission, Satellite and Payload Performance Budgets Methodology Documents
X X Budgets are compiled within SY-25.
SY-29 R Sentinel-2 Packet Utilisation Standard Customization Document
X X
SY-30 R Sentinel-2 SPS Test Scripts Definition and Test Output Files
X X X X X Based on simplified SPS for PDR.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 21 of 42
GMES Sentinel-2
5 SENTINEL-2 SATELLITE ASUMPTIONS FOR THE GROUND SEGMENT
DRD REF.
CAT SATELLITE PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
GS-1 R Sentinel-2 Satellite Assumptions for the Ground Segment
X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 22 of 42
GMES Sentinel-2
6 SENTINEL-2 SATELLITE ENGINEERING
DRD REF.
CAT SATELLITE PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SA-1 R Sentinel-2 Satellite Technical Description
X X X X X X X Security covered within SY-2. Covers flight and non flight deliverables
SA-2 A Sentinel-2 Satellite Requirements Specification
X X X X X X X Security covered within SY-3. Excludes GSE covered in AV documentation.
SA-3 A Sentinel-2 Satellite Engineering Budgets Methodology Documents
X X X X Covers only engineering budgets. Performance budgets covered by SY-25.
SA-4 R Sentinel-2 Engineering Budgets Document
X X X X X X X Covers only engineering budgets. Performance covered by SY-28.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 23 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SA-5 R Sentinel-2 Satellite Design Justification Document
X X X X X Including description of trade-offs for all Satellite elements and for non-flight deliverables.
SA-6 R Sentinel-2 Satellite Software Design, Development and Verification Plan
X
SA-7 R Sentinel-2 Satellite EMC/RFC Requirements and Control Plan
X X X X
SA-8 A Sentinel-2 Satellite Design and Development Plan
X X X X X Includes all Sentinel-2 flight and non flight deliverables, covers hardware and software, and excludes GSE covered under AV documents.
SA-9 A Sentinel-2 Software Requirements Specification
X X X X X X Flight and non flight Software
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 24 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SA-10 R Sentinel-2 Satellite Frequency Plan
X X X X X
SA-11 R Sentinel-2 Satellite Alignment Requirements and Control Plan
X X X X X
SA-12 A Sentinel-2 Satellite Review Data Package
X X X X X
SA-13 A (Prime)
R
Sentinel-2 MultiSpectral Instrument Review Data Package
X X X X DP Consistent with Contractor DP Requirements
SA-14 A (Prime)
R
Sentinel-2 Instruments, Sub-systems and equipments Data Packages
X X X X DP Consistent with Contractor Requirements for flight and non flight deliverables
SA-15 R Sentinel-2 Technical Notes and analysis reports
X X X X X X As required for flight and non-flight deliverable activities, and for service support activities
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 25 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SA-16 R Sentinel-2 Satellite Sub-Systems and Equipments Requirements Specifications
X X X X X X X Consistent with S2 Product Tree for flight and non flight deliverables
SA-17 R Sentinel-2 Software Development and Validation Environment Specification
X X X X X X
SA-18 A Sentinel-2 Fracture Control Plan
X X
SA-19 R Sentinel-2 Software Development and Verification Environment Installation, description and User Manual
X X X
SA-20 R Sentinel-2 Mission Data Base specification
SA-21 R Sentinel-2 Manufacturing File
X X X
SA-22 R Sentinel-2 Thermal, Mechanical and Geometrical mathematical models description
X X X X
SA-23 R Sentinel-2 Satellite Housekeeping Telemetry Data Definition document
X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 26 of 42
GMES Sentinel-2
7 SENTINEL-2 INTERNAL AND EXTERNAL INTERFACES
DRD REF.
CAT SATELLITE INTERFACES
PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
IF-1 A Sentinel-2 Satellite to Ground Segment Interface Control Document
X X X X X X X X A specific classified section may be requested to cover Satellite security aspects impacting the ground Segment.
IF-2 A Sentinel-2 Satellite to Launcher Interface Control Document
X X X X X X X Takes into account VEGA and a backup launcher as per SoW.
IF-3 R Sentinel-2 Satellite to Test Facilities Interface control Document
X X X X X X
IF-4 A Sentinel-2 Satellite Command & Control Protocol and Interface Specification
X X X X X X Including all Relevant Protocols for Satellite onboard command and housekeeping telemetry handling.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 27 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE INTERFACES
PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
IF-5 A Sentinel-2 Mission Data Protocol and Interface Specification
X X X X X Specifies the generation, formatting and transfer of Mission data within the Satellite
IF-6 R Sentinel-2 Satellite Engineering Interface Control Documents
X X X X X One document per Satellite engineering discipline, including also onboard software and SRDB.
IF-7 R Sentinel-2 Satellite to MultiSpectral Instrument Interface Requirements Specification
X X Covers all Satellite to MultiSpectral Instrument interfaces for flight and non flight elements.
IF-8 R Sentinel-2 Satellite to GSE Interface Control Document
X X
IF-9 A Sentinel-2 Satellite Characterisation and Calibration Data Base ICD
X X X X X Compatibility of the SCCDB with GPP, SPS and FOCC is required.
IF-10 A Sentinel-2 SRDB ICD X X X X X IF-11 A Sentinel-2 On-Board
Software ICD X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 28 of 42
GMES Sentinel-2
8 SENTINEL-2 SUPPORT SPECIFICATIONS
DRD REF.
CAT SATELLITE SUPPORT SPECIFICATIONS
PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SS-1 R Sentinel-2 Satellite Electrical Design Requirements Specification
X X X X X X For Satellite and GSE
SS-2 R Sentinel-2 Satellite Mechanical and Thermal Design Requirements Specification
X X X X X X
SS-3 R Sentinel-2 Satellite Environment and Test Requirements Specification
X X X X X X
SS-4 R Sentinel-2 Satellite EMC Requirements Specification
X X X X X X
SS-5 R Sentinel-2 Satellite RFC Requirements Specification
X X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 29 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE SUPPORT SPECIFICATIONS
PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
SS-6 R Sentinel-2 Software Engineering Support Specification
X X X X X X Covers onboard and on-ground software
SS-7 R Sentinel-2 Satellite Electro-Explosive Device and Pyrotechnics requirements specification
X X X X X X
SS-8 R Sentinel-2 Satellite Finite Element Model requirements specification
X X X X X X
SS-9 R Sentinel-2 Satellite Thermal Model requirements specification
X X X X X X
SS-10 R Sentinel-2 Mechanisms Design and performance requirements specification
X X X X X X
SS-11 R Sentinel-2 generic GSE support specification
X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 30 of 42
GMES Sentinel-2
9 SENTINEL-2 SATELLITE DRAWINGS DRD REF.
CAT DRAWINGS PHASE-B2/C/D/E1
BID
PHASE B2 K.O.
PDR PHASE C/D/E1
K.O
CDR QR FAR IOCR REMARKS
DR-1 R Sentinel-2 Satellite Overall Assembly and Accommodation Drawings
X X X X X X X
DR-2 R Sentinel-2 Satellite Mechanical and Thermal Interface Drawings
X X X X X Down to equipment level
DR-3 R Sentinel-2 Satellite Electrical Drawings
X X X X X Down to equipment level
DR-4 R Sentinel-2 Satellite Equipment Circuit Diagrams
X X DB. Down to equipment level
DR-5 R Sentinel-2 switching diagrams and command/control synoptics
Appended to the FOM. Down to equipment level
DR-6 R Sentinel-2 Electrical Grounding Diagrams
X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 31 of 42
GMES Sentinel-2
10 SENTINEL-2 MULTISPECTRAL INSTRUMENT In view of the prominent function of the MultiSpectral Instrument within the Sentinel-2 mission, the DRL identifies key documents to be produced by the responsible Contractor. The reviews indicated refer to the MultiSpectral Instrument level. These documents shall however be made available to the Agency at the time of corresponding Satellite level reviews, for reference of for review as relevant.
DRD REF.
CAT INSTRUMENT PHASE-B2/C/D/E1
BID
KO PDR PHASE C/D/E1
K.O
CDR QR FAR IOCR REMARKS
MS-1 R Sentinel-2 MultiSpectral Instrument Technical Description
X X X X X X X
MS-2 A (Prime)
R
Sentinel-2 MultiSpectral Instrument Requirements Specification
X X X X X X X Including software
MS-3 R Sentinel-2 MultiSpectral Instrument Sub-System/Equipments Requirements Specifications
X X X X X X Including software
MS-4 R Sentinel-2 MultiSpectral Instrument to Satellite Interface Control Document
X X X X X
MS-5 A Sentinel-2 MultiSpectral Instrument In Flight Characterization and Calibration Plan
X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 32 of 42
GMES Sentinel-2
DRD REF.
CAT INSTRUMENT PHASE-B2/C/D/E1
BID
KO PDR PHASE C/D/E1
K.O
CDR QR FAR IOCR REMARKS
MS-6 A (If
procured from
Prime) R
Sentinel-2 MultiSpectral Instrument Verification Plan
X X X X X X X Pre launch activities.
MS-7 A (If
procured from
Prime) R
Sentinel-2 MultiSpectral Instrument Design and Development Plan
X X X X X X X Including software
MS-8 A (If
procured from
Prime) R
Sentinel-2 MultiSpectral Instrument AIT Plan
X X X X X X X Includes on ground characterization and alignment
MS-9 R Sentinel-2 MultiSpectral Instrument Technical Budgets Report
X X X X X X Includes engineering, performance and on ground characterization as input to Satellite level budget documentation. Budget control methodology as per MS-20.
MS-10 R Sentinel-2 MultiSpectral Instrument L1a/1b/1c Theoretical Basis Document
X X X X Allowing a prototype processor specification to be generated. Input to SY-11.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 33 of 42
GMES Sentinel-2
DRD REF.
CAT INSTRUMENT PHASE-B2/C/D/E1
BID
KO PDR PHASE C/D/E1
K.O
CDR QR FAR IOCR REMARKS
MS-11 R Sentinel-2 MultiSpectral Instrument Reference Data Base Specification
X X X X To be used as input to SY-19.
MS-12 R Sentinel-2 MultiSpectral Instrument on Ground Characterization and Calibration Specification
MS-13 R Sentinel-2 MultiSpectral Instrument Flight Operations Manual
X X X X Outline to be delivered at PDR. To be integrated as a section of SY-21.
MS-14 R Sentinel-2 MultiSpectral Instrument Technical Notes and Analysis Reports
As required
MS-15 Deleted MS-16 R Sentinel-2 MultiSpectral
Instrument Design Justification Document
X X
MS-17 R Sentinel-2 MultiSpectral Instrument GSE Specifications
X X
MS-18 R Sentinel-2 MultiSpectral Instrument GSE Design Description
X
MS-19 R Sentinel-2 MultiSpectral Instrument Performance and Calibration Analysis
X X X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 34 of 42
GMES Sentinel-2
DRD REF.
CAT INSTRUMENT PHASE-B2/C/D/E1
BID
KO PDR PHASE C/D/E1
K.O
CDR QR FAR IOCR REMARKS
MS-20 R Sentinel-2 MultiSpectral Instrument Budgets Methodology Document
X X Engineering and Performance Budgets compiled within MS-9.
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 35 of 42
GMES Sentinel-2
11 SENTINEL-2 FIRE INSTRUMENT
DRD REF.
CAT FIRE INSTRUMENT
PHASE-B2/C/D/E1
BID
PHASE B2 KO
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
FI-1 R Sentinel-2 FIRE Instrument Interface control Document
X X X X X Response to the Agency FIRE Interface Specification.
FI-2 R Sentinel-2 FIRE Accommodation analysis
X X Preliminary input in the bid as an answer to the ITT
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 36 of 42
GMES Sentinel-2
12 SENTINEL-2 AIT
DRD REF.
CAT SATELLITE AIT PHASE-B2/C/D/
E1 BID
PHASE B2
K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
AV-1 A (Satellite
) R
Sentinel-2 System Verification Control Documents (verification matrices verification reports)
X X X X X X X DB. Applicable to the full Sentinel-2 technical baseline requirements. Evolving from verification matrix with open traces at PDR, to verification reports at FAR. (VCD can used for statements of compliance. Indication of verification method only until PDR.
AV-2 A Sentinel-2 Satellite AIT Plan X X X X X X X Covers also on ground characterization
AV-3 R Sentinel-2 GSE Design and Development Plan
X X X X X Covers only GSE and all non flight deliverables.
AV-4 R Sentinel-2 Test Facilities utilisation and Satellite Transportation Plan
X X X X X X X Including storage (if applicable)
AV-5 R Sentinel-2 Hardware/Software Matrix
X X X X X X X Covers Satellite and GSE
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 37 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE AIT PHASE-B2/C/D/
E1 BID
PHASE B2
K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
AV-6 R Sentinel-2 GSE Requirements Specifications
X X X X X Several distinct specifications to procure EGSE, MGSE, OGSE, and FGSE
AV-7 A (Satellite, MSI)
R
Sentinel-2 Satellite/MSI/ Sub-systems/Equipments Test Plans and Specifications
X X X X X Draft issue at PDR
AV-8 R
Sentinel-2 Satellite/MSI/Sub-systems/Equipments Test Procedures
X X X
AV-9 A Sentinel-2 Launch Site Operations and logistics Plan
X X X X X Applicable to VEGA and to the backup Launcher. Draft at PDR
AV-10 R Sentinel-2 Launch Site Operations Procedures
X X X Applicable to VEGA and to the backup Launcher services
AV-11 A Sentinel-2 S band R/F Suitcase Specification
X X X X X
AV-12 R Sentinel-2 S band R/F Suitcase Description and User Manual
X X
AV-13 A Sentinel-2 X band RF Suitcase Specification
X X X X X
AV-14 R Sentinel-2 X band RF Suitcase Description and User Manual
X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 38 of 42
GMES Sentinel-2
DRD REF.
CAT SATELLITE AIT PHASE-B2/C/D/
E1 BID
PHASE B2
K.O.
PDR PHASE C/D/E1
K.O.
CDR QR FAR IOCR REMARKS
AV-15 A (verificat
ion reports)
R
Sentinel-2 Satellite Acceptance, Qualification Tests & Verification and Engineering Analysis Reports
X X X AV-15 covers a variety of different reports applicable to the Satellite and to the non-flight deliverables such as the GPP or the SPS. Specific reports are already specified within the SoW.
AV-16 A Sentinel-2 Security Test and Verification Plan
X X X X X Draft at PDR. Restricted access.
AV-17 A Satellite Ground Operations Handling Constraints
X X X X X
AV-18 Sentinel-2 GSE Test & Calibration Report
X
AV-19 R Sentinel-2 Critical Onboard Software Independent Verification and Validation Report
X X X
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 39 of 42
GMES Sentinel-2
13 SENTINEL-2 PRODUCT ASSURANCE
DRD REF. CAT SATELLITE PA
PHASE-B2/C/D/E1
BID
PHASE B2 KO PDR
PHASE C/D/E1
KO CDR QR FAR IOCR REMARKS
Product Assurance
PA-1 A Product Assurance & Safety Plan x x x
PA-2 A Subcontractor PA Requirement x x x
Quality Assurance
PA-3 R Audit Programme x x x
PA-4 R Audit Checklists and Reports As available
PA-5 R Critical Items List x x x x x
PA-6 A/R Non Conformance Reports x x x To be available on-line
on the NCTS TOOL
PA-7 R Non Conformance Status Report x x x
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 40 of 42
GMES Sentinel-2
DRD REF. CAT SATELLITE PA
PHASE-B2/C/D/E1
BID
PHASE B2 KO PDR
PHASE C/D/E1
KO CDR QR FAR IOCR REMARKS
PA-8 R Qualification Status Report x x x x
PA-9 R MIP/KIP List x x
PA-11 R Alert Status List x x x x
PA-11 R End Item Data Packages (ADP) x x
PA-12 R Long lead Items List x x x
PA-13 A Cleanliness and Contamination Control Plan
x x x
PA-14 A Cleanliness Requirement Specification
x x x
Reliability and Safety
PA-15 R Reliability and Availability Prediction Report
x x x x
PA-16 R FMEA x x x
PA-17 R Safety Data Package x x x
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 41 of 42
GMES Sentinel-2
DRD REF. CAT SATELLITE PA
PHASE-B2/C/D/E1
BID
PHASE B2 KO PDR
PHASE C/D/E1
KO CDR QR FAR IOCR REMARKS
PA-18 R FDIR Implementation Report X X X
PA-19 R Worst case Analysis reports x x
EEE Parts Procurement
PA-20 A Parts Approval Document (PAD) As required
PA-21 R Declared Components List x x x x
PA-22 R Radiation Analysis Report x x x
PA-23 R Parts Derating Analysis Reports x x
Materials and Processes
PA-24 A Request For Approval As required
PA-25 R Declared Mechanical Parts List (DMPL) x x x x
PA-26 R Declared Material List (DML) x x x x
GMES Sentinel-2 Documents Requirements List
Issue 3 Rev 0 S2-RS-ESA-SY-0002
page 42 of 42
GMES Sentinel-2
DRD REF. CAT SATELLITE PA
PHASE-B2/C/D/E1
BID
PHASE B2 KO PDR
PHASE C/D/E1
KO CDR QR FAR IOCR REMARKS
PA-27 R Declared Process List (DPL) x x x x
Software PA
PA-28 R Software Maintenance File x x x
PA-29 R Software Criticality Analysis Report x x x x
PA-30 R Software Product Assurance Report x x x x